[Federal Register: May 8, 2001 (Volume 66, Number 89)]
[Notices]               
[Page 23245-23246]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr08my01-58]                         

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. ES01-31-000, et al.]

 
American Transmission Company LLC, et al.; Electric Rate and 
Corporate Regulation Filings

May 1, 2001.
    Take notice that the following filings have been made with the 
Commission:

1. American Transmission Company LLC

[Docket No. ES01-31-000]

    Take notice that on April 23, 2001, American Transmission Company 
LLC (American Transmission) submitted an application pursuant to 
section 204 of the Federal Power Act requests authorization to issue 
ownership interests totaling approximately 8.62% of its total ownership 
shares. American Transmission also requests authorization to issue 
additional ownership interests in an amount not to exceed 3% of 
American Transmission's total ownership per transaction over a two-year 
period. Alternatively, American Transmission requests authorization no 
more than an additional 5% of its cumulative ownership interests over a 
two-year period.
    American Transmission also requests a waiver of the Commission's 
competitive bidding and negotiated placement requirements at 18 CFR 
34.2.
    Comment date: May 21, 2001, in accordance with Standard Paragraph E 
at the end of this notice.

2. Southern California Edison Company

[Docket No. ER01-1874-000]

    Take notice that on April 26, 2001, Southern California Edison 
Company (SCE) tendered for filing a Service Agreement For Wholesale 
Distribution Service under SCE's Wholesale Distribution Access Tariff 
and an Interconnection Facilities Agreement (Agreements) between SCE 
and Alta Mesa Power Partners, LLC (AMPP).
    These Agreements specify the terms and conditions under which SCE 
will interconnect AMPP's generating facility to its electrical system 
and provide Distribution Service for up to 40 MW of power produced by 
the generating facility.
    Copies of this filing were served upon the Public Utilities 
Commission of the State of California and AMPP.
    Comment date: May 17, 2001, in accordance with Standard Paragraph E 
at the end of this notice.

3. Southern Company Services, Inc.

[Docket No. ER01-1868-000]

    Take notice that on April 25, 2001, Southern Company Services, Inc. 
(SCS) acting on behalf of Alabama Power Company, Georgia Power Company, 
Gulf Power Company, Mississippi Power Company (MPC), and Savannah 
Electric and Power Company (collectively referred to as Southern 
Company), tendered for filing two (2) service agreements for Network 
Integration Transmission Service between Southern Companies and Energy 
Marketing, a department of SCS, as agent for MPC, under the Open Access 
Transmission Tariff of Southern Companies (FERC Electric Tariff, Fourth 
Revised Volume No. 5). Under these two (2) agreements, power will be 
respectively delivered to (i) Singing River EPA's North Lucedale 
Delivery Point and (ii) Singing River EPA's Joe Batt Road Delivery 
Point. These agreements are being filed in conjunction with a power 
sale by SCS, as agent for MPC, to South Mississippi Electric Power 
Association under Southern Companies' Market-Based Rate Power Sales 
Tariff.
    Comment date: May 16, 2001, in accordance with Standard Paragraph E 
at the end of this notice.

4. Mirant Delta, LLC, Mirant Potrero, LLC

[Docket No. ER01-1876-000]

    Take notice that, on April 26, 2001, Mirant Delta, LLC (Mirant 
Delta) and Mirant Potrero, LLC (Mirant Potrero) tendered for filing 
certain revised tariff sheets to the Must-Run Service Agreements 
between Mirant Delta, Mirant Potrero, and the California Independent 
System Operator Corporation in order to (1) revise the agreements to 
reflect the January 19, 2001 name changes of the Mirant Parties from 
Southern Energy Delta, L.L.C. and Southern Energy Potrero, L.L.C. to 
Mirant Delta, LLC and Mirant Potrero, LLC, respectively, and (2) change 
the persons identified in Schedule J of the RMR Agreements to receive 
notices on behalf of the Mirant Parties.
    Comment date: May 17, 2001, in accordance with Standard Paragraph E 
at the end of this notice.

5. San Diego Gas & Electric Company

[Docket No. ER01-1878-000]

    Take notice that on April 26, 2001, San Diego Gas & Electric 
Company (SDG&E) tendered for filing as service agreements to its FERC 
Electric Tariff, First Revised Volume No. 6, two interconnection 
agreements. Both agreements relate to the interconnection of a new 
generation plant to be owned by RAMCO, Inc. (RAMCO). The plant, with a 
capacity of approximately 49.5 megawatts, is being constructed on an 
expedited basis to meet potential shortfalls this summer in the Western 
states' electricity supplies. It will be located in Escondido, San 
Diego County, California and is expected to begin service on or about 
July 8, 2001.
    Service Agreement No. 5 is an Expedited Interconnection Facilities 
Agreement dated April 26, 2001 between SDG&E and RAMCO, under which 
SDG&E will construct, operate, and maintain the proposed 
interconnection facilities. Service Agreement No. 6, the 
Interconnection Agreement between SDG&E and RAMCO dated April 12, 2001, 
establishes interconnection and

[[Page 23246]]

operating responsibilities and associated communications procedures 
between the parties. SDG&E requests an effective date of April 26, 2001 
for both agreements.
    SDG&E states that copies of the filing have been served on RAMCO 
and on the California Public Utilities Commission.
    Comment date: May 17, 2001, in accordance with Standard Paragraph E 
at the end of this notice.

6. Dominion Nuclear Connecticut, Inc.

[Docket No. ER01-1879-000]

    Take notice that on April 26, 2001 Dominion Nuclear Connecticut, 
Inc. (DNC) tendered for filing an agreement for the sale of electric 
energy and capacity by DNC to Dominion Nuclear Marketing, I, Inc., 
Dominion Nuclear Marketing II, Inc. and Dominion Nuclear Marketing III, 
L.L.C., dated March 30, 2001.
    Comment date: May 17, 2001, in accordance with Standard Paragraph E 
at the end of this notice.

Standard Paragraph

    E. Any person desiring to be heard or to protest such filing should 
file a motion to intervene or protest with the Federal Energy 
Regulatory Commission, 888 First Street, NE., Washington, DC 20426, in 
accordance with Rules 211 and 214 of the Commission's Rules of Practice 
and Procedure (18 CFR 385.211 and 385.214). All such motions or 
protests should be filed on or before the comment date. Protests will 
be considered by the Commission in determining the appropriate action 
to be taken, but will not serve to make protestants parties to the 
proceeding. Any person wishing to become a party must file a motion to 
intervene. Copies of these filings are on file with the Commission and 
are available for public inspection. This filing may also be viewed on 
the Internet at http://www.ferc.fed.us/online/rims.htm (call 202-208-
2222 for assistance). Comments, protests, and interventions may be 
filed electronically via the internet in lieu of paper. See, 18 CFR 
385.2001(a)(1)(iii) and the instructions on the Commission's web site 
at http://www.ferc.fed.us/efi/doorbell.htm.

David P. Boergers,
Secretary.
[FR Doc. 01-11484 Filed 5-7-01; 8:45 am]
BILLING CODE 6717-01-M