[Federal Register: March 23, 2001 (Volume 66, Number 57)]
[Notices]
[Page 16218-16219]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr23mr01-58]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP01-103-000]
Transcontinental Gas Pipe Line Corporation; Notice of Application
March 19, 2001.
Take notice that on March 12, 2001, Transcontinental Gas Pipe Line
Corporation (Transco), Post Office Box 1396, Houston, Texas 42301, in
Docket No. CP01-103-000 filed an application pursuant to section 7(b)
of the Natural Gas Act for permission and approval for Transco to
abandon certain pipeline facilities, located largely in offshore Texas
and Louisiana, which are portions of the North High Island/West Cameron
Gathering System by transfer to Williams Gas Processing-Gulf Coast
Company, L.P. (WGP), an affiliate of Transco, all as more fully set
forth in the application which is on file with the Commission and open
to public inspection. This filing may be viewed on the web at http://
www.ferc.fed.us/online/rims.htm (call 202-208-2222 for assistance).
Transco proposes to abandon (1) 217.128 miles of 4-to-30-inch
pipeline, (2) the Johnson Bayou Plant, consisting of Station 44
separation and dehydration facilities and 1,200 horsepower of
compression, located in Cameron Parish, Louisiana, (3) Station 44
Compression, consisting of three 3,830 horsepower Solar Centaur Engines
for a total of 11,490 horsepower, also located in Cameron Parish,
Louisiana, and (4) minor compression owned on Shell's High Island Block
179-L, Offshore Texas. Transco advises that the facilities will be
transferred at net book value, which has been calculated at $21,180,514
as of December 31, 2000.
Transco also requests authorization to abandon its Rate Schedules
X-143 (service with ANR Pipeline Company) and X-249 (service with
Columbia Gulf Transmission Company), as well as receipt points included
on a firm transportation agreement with Motiva Enterprises, LLC. It is
indicated that Transco will amend the affected service agreements and
file the necessary conforming changes to its FERC Gas Tariff.
WGP has concurrently filed a petition for a declaratory order in
Docket No. CP01-104-000, requesting that the Commission determine that
WGP's acquisition, ownership, and operation of the facilities at issue
not subject WGP or any portion of WGP's facilities, rates, or services
to the jurisdiction of the Commission under the Natural Gas Act.
Any questions regarding the application should be directed to
Randall R. Conklin, Vice President and General Counsel, and Gisela
Cherches, Senior Attorney at (713) 215-2000, Transcontinental Gas Pipe
Line Corporation, P.O. Box 1396, Houston, Texas 77251.
There are two ways to become involved in the Commission's review of
this project. First, any person wishing to obtain legal status by
becoming a party to the proceedings for this project should, on or
before April 9, 2001, file with the Federal Energy Regulatory
Commission, 888 First Street, NE., Washington, DC 20426, a motion to
intervene in accordance with the requirements of the Commission's Rules
of Practice and Procedure (18 CFR 385.214 or 385.211) and the
Regulations under the NGA (18 CFR 157.10). A person obtaining party
status will be placed on the service list maintained by the Secretary
of the Commission and will receive copies of all documents filed by the
applicant and by all other parties. A party must submit 14 copies of
filings made with the Commission and must mail a copy to the applicant
and to every other party in the proceeding.
Only parties to the proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to intervene in order to have
comments considered. The second way to participate is by filing with
the Secretary of the Commission, as soon as possible, an original and
two copies of comments in support of or in opposition to this project.
The Commission will consider these comments in determining the
appropriate action to be taken, but the filing of a comment alone will
not serve to make the filer a party to the proceeding. The Commission's
rules require that persons filing comments in opposition to the project
provide copies of their protests only to the party or parties directly
involved in the protest.
Persons who wish to comment only on the environmental review of
this project should submit an original and two copies of their comments
to the Secretary of the Commission. Environmental commenters will be
placed on the Commission's environmental mailing list, will receive
copies of the environmental documents, and will be notified of meetings
associated with the Commission's environmental review process.
Environmental commenters will not be required to serve copies of filed
documents on all other parties. However, the non-party commenters will
not receive copies of all documents filed by other parties or issued by
the Commission (except for the mailing of environmental documents
issued by the Commission) and will not have the right to seek court
review of the Commission's final order.
The Commission may issue a preliminary determination on non-
environmental issues prior to the completion of its review of the
environmental aspects of the project. This preliminary determination
typically considers such issues as the need for the project and its
economic effect on existing customers of the applicant, on other
pipelines in the area, and on landowners and communities. For example,
the Commission considers
[[Page 16219]]
the extent to which the applicant may need to exercise eminent domain
to obtain rights-of-way for the proposed project and balances that
against the non-environmental benefits to be provided by the project.
Therefore, if a person has comments on community and landowner impacts
from this proposal, it is important either to file comments or to
intervene as early in the process as possible.
Also, comments protests, and interventions may be filed
electronically via the internet in lieu of paper. See, 18 CFR
385.2001(a)(1)(iii) and the instructions on the Commission's web site
at http://www.ferc.fed.us/efi/doorbell.htm.
If the Commission decides to set the application for a formal
hearing before an Administrative Law Judge, the Commission will issue
another notice describing that process. At the end of the Commission's
review process, a final Commission order approving or denying a
certificate will be issued.
David P. Boergers,
Secretary.
[FR Doc. 01-7277 Filed 3-22-01; 8:45 am]