Environmental Document Roster FY 2005 The following is a list of documents which have been completed or are planned for the Eagle Lake Field Office in fiscal year 2005. If you need more information, please call the Project Leader at the number listed. |
NEPA Level /Number | Project Name / Description | Location | Project Leader | Status |
EA 2005-01 | Edward Koch - Right of Way | Willow Creek (CA) | Susan Wannebo 530 252-5303 | Signed 9-8-05 |
CX 2005-02 | Magee Riparian Enclosure | T.25N, R.16E, Sec. 20,21 (CA) | Michael Kuyper 530 252-5306 | In Progress |
CX 2005-03 | Temporary Impoundment Corrals | T.28N, R.16E, Sec. 10,11 | Michael Kuyper 530 252-5306 | Signed |
EA 2005-04 | 2005 Lassen Motorcycle Club Event | T.28N., R.18E., (NV) | Duane Jackson 530 252-5312 | Signed 3-31-05 |
CX 2005-05 | 2005 Never Sweats Endurance Horse Event | T.29,30,31N., R.15,16E., (CA) | Duane Jackson 530 252-5312 | Signed 5-2-05 |
EA 2005-06 | Bosco Stewardship | T.35N, R.10E, Sec.13,14,23,24 T.35N. R.11E. Sec. 16,17 (CA) | Don Dockery 530 252-5313 | Signed 7-5-05 |
EA 2005-07 | Crum/Dodson Spring Development | T.31,32N., R.13E., (CA) | Ralph Mauck 530 252-5307 | Signed 8-25-05 |
CX 2002-08 | FY 2006 OHMURD Grant WSA - LE Project | All of WSA's (CA) | Duane Jackson 530 252-5312 | Signed 5-20-05 |
CX 2005-09 | Forgay Point Hazard Tree Removal | (CA) | Don Dockery 530 252-5313 | Signed 5-20-05 |
CX 2005-10 | FY 2006 OHMURD Grant Fort Sage Projects | T.26N., R.17E., (CA) | Duane Jackson 530 252-5312 | Signed 5-20-05 |
EA 2005-11 | Belfast Native Plant Re-introduction | T.30 N., R.13 E. Sec. 7, (CA) | Carolyn Gibbs | |
CX 2005-12 | Bizz Johnson Tours For The Disabled | Bizz Johnson Trail (CA) | Stan Bales | Signed 6-9-05 |
CX 2005-13 | CMS Generation | Shaffer Mtn. (CA) | Susan Wannebo 530 252-5303 | Signed 8-15-05 |
CX 2005-14 | Cramer Family Trust | Cleghorn (CA) | Susan Wannebo 530 252-5303 | Signed 8-11-05 |
EA 2005-15 | Laird Spring Fence | T.29N., R.19E., Sec. 20,23 | Michael Kuyper 530 252-5306 | In Progress |
CX 2005-16 | Ferdonyer Aspen Restoration Project | T.33N.,R.12E. Sec 14,23 (CA) | Wade Salverson 530 252-5313 | Signed 3-02-05 |
EA 2005-17 | 2005 Bizz Johnson Trail Stabilization Project | T.29N., R.11E. Sec. 5 (CA) | Stan Bales 530 252-5311 | In Progress |
CX 2005-18 | Rails to Trails Festival | Bizz Johnson Trail (CA) | Stan Bales 530 252-5311 | Signed 9-21-05 |
CX 2005-19 | Sea Kayaking Course | Eagle Lake (CA) | Stan Bales 530 252-5311 | Signed 9-21-05 |
CX 2005-20 | Bizz Johnson Marathon - SUP CA-350-06-01 | Bizz Johnson Trail (CA) | Stan Bales 530 252-5311 | Signed |
EA 2005-21 | Opening East Tunnel for Marathon | Bizz Johnson Trail (CA) | Dayne Barron 530 252-5374 | Signed 9-29-05 |
EA 2005-22 | Spencer Rx 2005 | (CA) | Don Armentrout 530 252-5319 | Signed |
EA 2005-23 | 2005 Smoke Creek Road and Little Mud Flat | (CA) | Don Armentrout 530 252-5319 | Signed |