Scope of subpart.
This subpart contains foreign product restrictions that are based on policies designed to protect the defense industrial base.
225.7101
Definitions.
“Domestic manufacture” is defined in the clause at 252.225-7025, Restriction on Acquisition of Forgings.
225.7102
Forgings.
225.7102-1
Policy.
When acquiring the following forging items, whether as end items or components, acquire items that are of domestic manufacture to the maximum extent practicable:
ITEMS |
CATEGORIES |
|
|
Ship propulsion shafts |
Excludes service and landing craft shafts |
Periscope tubes |
All |
Ring forgings for bull gears |
All greater than 120 inches in diameter |
225.7102-2 Exceptions.
The policy in 225.7102-1 does not apply to acquisitions—
(a) Using simplified acquisition procedures, unless the restricted item is the end item being purchased;
(b) Overseas for overseas use; or
(c) When the quantity acquired exceeds the amount
needed to maintain the
225.7102-3
Waiver.
Upon request from a contractor, the contracting officer may waive the requirement for domestic manufacture of the items listed in 225.7102-1.
225.7102-4
Contract clause.
Use the clause at 252.225-7025, Restriction on Acquisition of Forgings, in solicitations and contracts, unless—
(a) The supplies being acquired do not contain any of the items listed in 225.7102-1; or
(b) An exception in 225.7102-2 applies. If an exception applies to only a portion of the acquisition, specify the excepted portion in the solicitation and contract.
225.7103 Polyacrylonitrile (PAN) carbon fiber.
225.7103-1 Policy.
DoD has imposed restrictions on the acquisition of PAN
carbon fiber from foreign sources. DoD is phasing out the restrictions over the 5-year period
ending
225.7103-2 Waivers.
With
the approval of the chief of the contracting office, the contracting officer
may waive, in whole or in part, the requirement of the clause at
252.225-7022. For example, a waiver may
be justified if a qualified
225.7103-3 Contract clause.
Use the clause at 252.225-7022, Restriction on Acquisition of Polyacrylonitrile (PAN) Carbon Fiber, in solicitations and contracts for major systems as follows:
(a) In solicitations and contracts issued on or
before
(1) The system is not yet in production (milestone C as defined in DoDI 5000.2, Operation of the Defense Acquisition System); or
(2) The clause was used in prior program contracts.
(b)
In solicitations and contracts issued during the period beginning