This is the accessible text file for GAO report number GAO-06-404 
entitled 'Homeland Security: Contract Management and Oversight for 
Visitor and Immigrant Status Program Need to Be Strengthened' which was 
released on July 10, 2006. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Report to Congressional Requesters: 

United States Government Accountability Office: 

GAO: 

June 2006: 

Homeland Security: 

Contract Management and Oversight for Visitor and Immigrant Status 
Program Need to Be Strengthened: 

US-VISIT Contract Management: 

GAO-06-404: 

GAO Highlights: 

Highlights of GAO-06-404, a report to congressional requesters 

Why GAO Did This Study: 

The Department of Homeland Security (DHS) has established a 
multibillion-dollar program—U.S. Visitor and Immigrant Status Indicator 
Technology (US-VISIT)—to control and monitor the pre-entry, entry, visa 
status, and exit of foreign visitors. To deliver system and other 
program capabilities, the program relies extensively on contractors, 
some of whom are managed directly by US-VISIT and some by other 
agencies (including both DHS agencies, such as Customs and Border 
Protection, and non-DHS agencies, such as the General Services 
Administration). Because of US-VISIT’s heavy reliance on contractors to 
deliver program capabilities, GAO was asked to determine whether DHS 
has established and implemented effective controls for managing and 
overseeing US-VISIT–related contracts. 

What GAO Found: 

US-VISIT–related contracts have not been effectively managed and 
overseen. The US-VISIT program office established and implemented 
certain nonfinancial controls for those contracts that it managed 
directly, such as verifying that contractor deliverables satisfied 
established requirements. However, it did not implement effective 
controls for overseeing its contracts managed by other DHS agencies and 
by non-DHS agencies. Moreover, effective financial controls were not in 
place on any contracts that GAO reviewed (see table for agencies 
managing these contracts). 

* The program office did not know the full extent of US-VISIT–related 
contract actions, and it had not performed key nonfinancial practices 
associated with understanding contractor performance in meeting the 
terms of these contracts. This oversight gap was exacerbated by the 
fact that the other agencies had not always established and implemented 
effective controls for managing their respective contracts. These other 
agencies directly managed more than half (56 percent) of the total US-
VISIT–related contract obligations reported to GAO. 

* The program office and other agencies did not implement effective 
financial controls. Without these controls, some agencies were unable 
to reliably report US-VISIT contracting expenditures. Further, the 
program office and these other agencies improperly paid and accounted 
for related invoices, including making duplicate payments and payments 
for non-US-VISIT services with funds designated for US-VISIT. 

According to the US-VISIT program official responsible for contract 
matters, the program office has focused on contracts that it manages 
directly and decided to rely on the responsible agencies to manage the 
other contracts. Further, it has decided to use other agencies to 
properly manage financial matters for their respective contracts, and 
it also decided to rely on another agency for its own financial 
management services. Without effective contract management and 
oversight controls, the program office does not know that required 
program deliverables and mission results will be produced on time and 
within budget, and that proper payments are made. 

Table: Agencies Managing US-VISIT-Related Contracts: 

Managing Organization: US-VISIT Acquisition and Program Management 
Office; Purpose of Contract actions managed: Support all aspects of US-
VISIT. 

Managing Organization: Architect Engineering Resource Center (Army 
Corps of Engineer); Purpose of Contract actions managed: On-site 
program management at ports of entry and economic impact assessment of 
US-VISIT implementation on northern and southern borders. 

Managing Organization: General Services Administration; Purpose of 
Contract actions managed: Facilities services related to US-VISIT work 
at ports of entry. 

Managing Organization: Customs and Border Protection (DHS); Purpose of 
Contract actions managed: Systems development; hardware deployment. 

Managing Organization: Immigration and Customs Enforcement (DHS); 
Purpose of Contract actions managed: Systems engineering; IT support. 

Managing Organization: Transportation Security Administration (DHS); 
Purpose of Contract actions managed: Systems development. 

Source: GAO analysis. 

[End of Table] 

What GAO Recommends: 

GAO is making recommendations to the Secretary of Homeland Security to 
ensure that effective contract management and financial controls are 
established and implemented both for contracts managed by the US-VISIT 
program office and for those managed by other agencies. In written 
comments on a draft of this report, DHS concurred with the 
recommendations. In oral comments, officials from other agencies 
provided comments aimed at clarifying selected GAO statements. 

[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-06-404]. 

To view the full product, including the scope and methodology, click on 
the link above. For more information, contact Randolph C. Hite at (202) 
512-3439 or McCoy Williams at (202) 512-9095. 

[End of Section] 

Contents: 

Letter: 

Results in Brief: 

Background: 

US-VISIT Established and Implemented Key Controls for Contracts That It 
Managed Directly, but It Did Not Have Controls for Overseeing Contracts 
Managed by Others or for Effective Financial Management: 

Conclusions: 

Recommendations for Executive Action: 

Agency Comments and Our Evaluation: 

Appendix I: Objective, Scope, and Methodology: 

Appendix II: Comments from the Department of Homeland Security: 

Appendix III: Detailed Agency Evaluations: 

Appendix IV: GAO Contacts and Staff Acknowledgments: 

Tables: 

Table 1: Relationships between Servicing Agencies Managing US-VISIT- 
Related Contracts and US-VISIT Program: 

Table 2: APMO's Establishment and Implementation of Key Contractor 
Management Practices: 

Table 3: Status of Critical Contractor Management Practices at US-VISIT 
Contract Management Agencies: 

Table 4: Acceptance Reports for One Contract Deliverable: 

Table 5: Contract Actions Related to US-VISIT That Were Examined in 
This Review: 

Table 6: Evaluation of US-VISIT Acquisition and Program Management 
Office: 

Table 7: Evaluation of General Services Administration: 

Table 8: Evaluation of Army Corps of Engineers Architect-Engineer 
Resource Center: 

Table 9: Evaluation of Customs and Border Protection: 

Table 10: Evaluation of Transportation Security Administration: 

Table 11: Evaluation of Immigration and Customs Enforcement: 

Figures: 

Figure 1: Organizational Structure of DHS: 

Figure 2: Organizational Structure of US-VISIT Program Office and 
Functional Responsibilities: 

Figure 3: Changes in US-VISIT System Ownership and Management, July 
2003-March 2005: 

Figure 4: Distribution of $347 Million US-VISIT Obligated Contracting 
Dollars between March 2002 and March 2005: 

Abbreviations: 

ADIS: Arrival Departure Information System: 

AERC: Architect-Engineering Resource Center: 

APMO: Acquisition and Program Management Office: 

CBP: Customs and Border Protection: 

CMMI: Capability Maturity Model Integration: 

COR: contracting officer's representative: 

COTR: contracting officer's technical representative: 

DHS: Department of Homeland Security: 

FAR: Federal Acquisition Regulation: 

GSA: General Services Administration: 

IAA: inter-or intra-agency agreement: 

ICE: Immigration and Customs Enforcement: 

IDENT: Automated Biometric Identification System: 

INS: Immigration and Naturalization Service: 

IPAC: Intra-governmental Payment and Collection: 

OMB: Office of Management and Budget: 

SEI: Software Engineering Institute: 

TECS: Treasury Enforcement Communications Systems: 

TSA: Transportation Security Administration: 

US-VISIT: U.S. Visitor and Immigrant Status Indicator Technology: 

United States Government Accountability Office: 
Washington, DC 20548: 

June 9, 2006: 

Congressional Requesters: 

The U.S. Visitor and Immigrant Status Indicator Technology (US-VISIT) 
program of the Department of Homeland Security (DHS) is a 
governmentwide program for controlling and monitoring the pre-entry, 
entry, visa status, and exit of foreign visitors. The department is 
taking an incremental approach to acquiring and implementing US-VISIT, 
with the initial increments focused on enhancing existing systems, 
modifying facilities, and augmenting program office staff. In doing so, 
DHS has relied heavily on contractor support, obtained through multiple 
existing contracts managed by several DHS and non-DHS agencies. Because 
of the importance of effective contractor management and oversight to 
this program, you asked us to determine whether the department has 
established and implemented effective controls for managing and 
overseeing US-VISIT-related contractors. 

To achieve this objective, we reviewed the contracting policies and 
procedures of DHS and non-DHS agencies responsible for US-VISIT-related 
contracts.[Footnote 1] We also reviewed a set of contracting actions 
(contract awards and task orders) that were performed between March 
2002 and March 2005. We could not ensure that the selected contracting 
actions were statistically representative of all US-VISIT-related 
contracting actions because DHS did not have a complete inventory of 
such actions. Instead, we used a judgmental selection, focusing on 
service contracts from fiscal years 2002 to 2005.[Footnote 2] 

We conducted our review from March 2005 through April 2006 in 
accordance with generally accepted government auditing standards. 
Further details of our objective, scope, and methodology, including the 
basis for our judgmental selection, are included in appendix I. 

Results in Brief: 

Although the success of the US-VISIT program depends heavily on the 
work performed by contractors, important US-VISIT-related contract 
activities have not been effectively managed and overseen. For those 
contracts that it directly managed, the program office established and 
implemented nonfinancial management controls (such as assigning 
contractor management responsibilities and authorities, training key 
contract management personnel, and verifying that contractor 
deliverables satisfied established requirements), but it fell short in 
other key areas. In particular: 

* The program office did not establish and implement effective 
nonfinancial management controls for overseeing US-VISIT-related 
contract work performed on its behalf by other DHS agencies, such as 
Customs and Border Protection (CBP), and by two non-DHS agencies--the 
Army Corps of Engineers Architect-Engineering Resource Center 
(AERC)[Footnote 3] and the General Services Administration (GSA). These 
agencies did not always establish and implement the full range of 
nonfinancial controls needed to effectively manage their respective 
contracts. For example, the program office did not know what US-VISIT- 
related contract actions these other agencies had under way and had 
completed, and the other agencies generally did not establish and 
implement controls for ensuring that contractor deliverables satisfied 
contract requirements, which is significant given that these DHS and 
non-DHS agencies directly managed more than half (56 percent) of the 
total obligations reported to us for US-VISIT-related contract work 
during the period of our review. 

* The program office and other DHS and non-DHS agencies doing work on 
its behalf also did not implement effective US-VISIT-related financial 
management controls. In the absence of these controls, several agencies 
were unable to reliably report US-VISIT contracting expenditures. 
Further, the program office and the other agencies improperly paid and 
accounted for related invoices, including making duplicate payments and 
making payments for non-US-VISIT services using funds designated for US-
VISIT purposes. 

According to the US-VISIT program official responsible for contract 
matters, the program office has focused on contracts that it manages 
directly and decided to rely on other agencies to manage the other US- 
VISIT contracts. Further, it decided to rely on these other agencies to 
properly manage financial matters for their respective contracts, and 
on another agency for its own financial management support. Without 
effective controls over all US-VISIT-related contracts and related 
financial management matters, the program office does not know whether 
required program deliverables and associated mission results will be 
produced on time and within budget, and that proper payments are made 
and accounted for. 

We are making recommendations to the Secretary of Homeland Security to 
ensure that effective contract management and financial controls are 
established and implemented both for contracts managed by the US-VISIT 
program office and for those managed by other agencies. For example, we 
are recommending that the program office develop and implement 
practices for overseeing contractor work managed by other agencies on 
the program office's behalf, including (among other things) having 
current, reliable, and timely information on the full scope of contract 
actions and activities. In addition, we are recommending that the 
program office strengthen financial management by (among other things) 
ensuring that agencies managing contracts on its behalf record amounts 
being billed and expended on US-VISIT-related work so that these can be 
tracked and reported separately from amounts not for US-VISIT purposes. 

In written comments on a draft of this report, DHS stated that although 
it disagreed with some of our assessment, it agreed with many areas of 
the report and concurred with our recommendations and the need for 
improvements in US-VISIT contract management and oversight. In 
particular, DHS described as misleading our characterization of US- 
VISIT's dependency on other agencies for financial management support. 
DHS noted that the decision to use other agencies was based on the 
nature of the services that were required, which it said were outside 
the scope of the program office's areas of expertise. We understand the 
rationale for the decision to use other agencies, and the statement in 
question was not intended to suggest anything more than that such a 
decision was made. The department also provided clarifying information 
about invoice discrepancies and improper payments cited in the report, 
including reasons why they occurred. We do not question the 
department's reasons for the discrepancies; however, they do not change 
our findings about the fact that these discrepancies did indeed occur. 
We have modified the report, where appropriate. DHS's comments, along 
with our responses, are discussed in detail in the Agency Comments and 
Our Evaluation section of this report. The comments are also reprinted 
in their entirety in appendix II. 

Officials from AERC and GSA provided oral comments aimed at clarifying 
some of our statements and findings. We have made revisions as 
appropriate. These comments and our responses are also discussed in the 
Agency Comments and Our Evaluation section of the report. 

Background: 

In response to legislation,[Footnote 4] the Immigration and 
Naturalization Service (INS) established in 2002 an Entry/Exit Program 
to strengthen management of the pre-entry, entry, visa status, and exit 
of foreign nationals who travel to the United States. With the creation 
of DHS in March 2003 and the inclusion of INS as part of the new 
department, this initiative was renamed US-VISIT. The goals of US-VISIT 
are to: 

* enhance the security of U.S. citizens and visitors, 

* facilitate legitimate travel and trade, 

* ensure the integrity of the U.S. immigration system, and: 

* protect the privacy of our visitors. 

To achieve these goals, US-VISIT is to collect, maintain, and share 
information on certain foreign nationals who enter and exit the United 
States; detect fraudulent travel documents, verify traveler identity, 
and determine traveler admissibility through the use of biometrics; and 
facilitate information sharing and coordination within the border 
management community. 

As of October 2005, about $1.4 billion has been appropriated for the 
program, and according to program officials, about $962 million has 
been obligated. 

Acquisition and Implementation Approach: 

DHS plans to deliver US-VISIT capability in four increments: Increments 
1 through 3 are interim, or temporary, solutions that were to fulfill 
legislative mandates to deploy an entry/exit system by specified dates; 
Increment 4 is to implement a long-term vision that is to incorporate 
improved business processes, new technology, and information sharing to 
create an integrated border management system for the future. For 
Increments 1 through 3, the program is building interfaces among 
existing ("legacy") systems; enhancing the capabilities of these 
systems; deploying these capabilities to air, sea, and land ports of 
entry; and modifying ports of entry facilities. These increments are to 
be largely acquired and implemented through task orders placed against 
existing contracts.[Footnote 5] 

* Increment 1 concentrates on establishing capabilities at air and sea 
ports of entry and is divided into two parts--1 and 1B. Increment 1 
(air and sea entry) includes the electronic capture and matching of 
biographic and biometric information (two digital index fingerscans and 
a digital photograph) for selected foreign nationals, including those 
from visa waiver countries.[Footnote 6] Increment 1 was deployed on 
January 5, 2004, at 115 airports and 14 seaports. Increment 1B (air and 
sea exit) collects biometric exit data for select foreign nationals; it 
is currently deployed at 14 airports and seaports. 

* Increment 2 focuses primarily on extending US-VISIT to land ports of 
entry. It is divided into three parts--2A, 2B, and 2C. 

* Increment 2A includes the capability to biometrically compare and 
authenticate valid machine-readable visas and other travel and entry 
documents issued by the Department of State and DHS to foreign 
nationals at all ports of entry (air, sea, and land ports of entry). 
Increment 2A was deployed on October 23, 2005, according to program 
officials. It is also to include the deployment by October 26, 2006, of 
technology to read biometrically enabled passports from visa waiver 
countries. 

* Increment 2B redesigned the Increment 1 entry solution and expanded 
it to the 50 busiest U.S. land border ports of entry with certain 
modifications to facilities. This increment was deployed to these 50 
ports of entry as of December 29, 2004. 

* Increment 2C is to provide the capability to automatically, 
passively, and remotely record the entry and exit of covered 
individuals using radio frequency technology tags at primary inspection 
and exit lanes.[Footnote 7] In August 2005, the program office deployed 
the technology to five border crossings (at three ports of entry) to 
verify the feasibility of using passive radio frequency technology to 
record traveler entries and exits via a unique identification number 
embedded within government-issued travel documentation. The program 
office reported the evaluation results in January 2006, and according 
to the Increment 2C project manager, the program is planning to move 
forward with the second phase of this increment. 

* Increment 3 extended Increment 2B entry capabilities to 104 of the 
remaining 105 land ports of entry as of December 19, 2005.[Footnote 8] 

* Increment 4 is to define, design, build, and implement more strategic 
US-VISIT program capability, which program officials stated will likely 
consist of a further series of incremental releases or mission 
capability enhancements that will support business outcomes. 

The first three increments of US-VISIT include the interfacing of 
existing systems, the modification of facilities, and the augmentation 
of program staff. Key existing systems include the following: 

* The Arrival Departure Information System (ADIS) is a database that 
stores noncitizen traveler arrival and departure data received from air 
and sea carrier manifests and that provides query and reporting 
functions. 

* The Treasury Enforcement Communications Systems (TECS) is a system 
that maintains lookout (i.e., watch list) data, interfaces with other 
agencies' databases, and is currently used by inspectors at ports of 
entry to verify traveler information and update traveler data. 

* TECS includes the Advance Passenger Information System (APIS), a 
system that captures arrival and departure manifest information 
provided by air and sea carriers. 

* The Automated Biometric Identification System (IDENT) is a system 
that collects and stores biometric data about foreign visitors. 

In May 2004, DHS awarded an indefinite-delivery/indefinite- 
quantity[Footnote 9] prime contract to Accenture, which has partnered 
with a number of other vendors.[Footnote 10] According to the contract, 
the prime contractor will develop an approach to produce the strategic 
solution. In addition, it is to help support the integration and 
consolidation of processes, functionality, and data, and is to assist 
the program office in leveraging existing systems and contractors in 
deploying and implementing the interim solutions. 

Organizational Structure and Responsibilities: 

In July 2003, DHS established the US-VISIT program office, which is 
responsible for managing the acquisition, deployment, and operation of 
the US-VISIT system and supporting people, processes, and facilities. 
Accordingly, the program office's responsibilities include, among other 
things, 

* delivering program and system capabilities on time and within budget 
and: 

* ensuring that program goals, mission outcomes, and program results 
are achieved. 

Within DHS, the US-VISIT program organizationally reports directly to 
the Deputy Secretary for Homeland Security, as seen in figure 1. 

Figure 1: Organizational Structure of DHS: 

[See PDF for image] 

Source: GAO analysis of DHA data. 

[End of figure] 

The program office is composed of a number of functional groups. Among 
these groups, three deal with contractor management. These are the 
Acquisition and Program Management Office (APMO), the Office of 
Facilities and Engineering Management, and the Office of Budget and 
Financial Management. As seen in figure 2, all three groups report 
directly to the US-VISIT Program Director. 

Figure 2: Organizational Structure of US-VISIT Program Office and 
Functional Responsibilities: 

[See PDF for image] 

Source: US-VISIT. 

[End of figure] 

APMO is to manage execution of the program's acquisition and program 
management policies, plans, processes, and procedures. APMO is also 
charged with ensuring effective selection, management, oversight, and 
control of vendors providing services and solutions. 

The Office of Facilities and Engineering Management is to implement the 
program's physical mission environment through, for example, developing 
and implementing physical facility requirements and developing 
cooperative relationships and partnering arrangements with appropriate 
agencies and activities. 

The Office of Budget and Finance is to develop executable budgets to 
contribute to cost-effective performance of the US-VISIT program and 
mission; ensure full accountability and control over program financial 
assets; and provide timely, accurate, and useful financial information 
for decision support. 

US-VISIT Relationships with Other DHS and Non-DHS Agencies: 

Since its inception, US-VISIT has relied extensively on contractors to 
deliver system and other program capabilities; these contractors 
include both contractors managed directly by the program office and 
those managed by other DHS and non-DHS agencies. Within the program 
office, APMO manages the prime contract mentioned earlier, as well as 
other program management-related contracts. All other contracts were 
awarded and managed either by other DHS agencies or by two non-DHS 
agencies, GSA and AERC. For the contracts managed by other DHS 
agencies, the program office has entered into agreements[Footnote 11] 
with these agencies. These agreements allow the program to use 
previously awarded contracts to further develop and enhance the 
existing systems that now are part of US-VISIT. By entering into 
agreements with the various owners of these systems, the program office 
has agreed to fund US-VISIT-related work performed on the systems by 
these agencies, which include: 

* CBP, which owns and manages TECS; 

* Immigration and Customs Enforcement (ICE), which owned and managed 
IDENT (until 2004) and ADIS (until 2005), and still provides some 
information technology support services;[Footnote 12] and: 

* the Transportation Security Administration (TSA), which in 2003 
managed the development of the air/sea exit pilot program. 

In addition, through its Office of Facilities and Engineering 
Management, the program office has established an interagency agreement 
with AERC and has established reimbursable work authorizations with 
GSA.[Footnote 13] The agreements with GSA and AERC generally provide 
for management services in support of US-VISIT deployment. 

When the US-VISIT program office was created in July 2003, the program 
did not own or manage any of the key systems described earlier. Rather, 
all systems were owned and managed by other DHS agencies (see fig. 3). 
As of March 2005, the program office had assumed ownership and 
management responsibility for IDENT, which was originally managed by 
ICE; assumed management responsibility for the air/sea exit project, 
which was originally managed by TSA; and shares responsibility for 
ADIS, which was initially owned and managed by ICE. US-VISIT owns ADIS, 
but CBP is responsible for managing the system. These relationships are 
shown in figure 3. 

Figure 3: Changes in US-VISIT System Ownership and Management, July 
2003-March 2005: 

[See PDF for image] 

Source: GAO analysis of DHS data. 

[End of figure] 

IAAs establish a means for US-VISIT to transfer funds to other DHS and 
non-DHS agencies for work done on its behalf. The IAAs first give the 
servicing agencies (that is, the agencies performing the work for US- 
VISIT) obligation authority to contract for US-VISIT work. Once the 
work has been performed, the servicing agencies pay their vendors 
according to the terms of their respective contracts and then request 
reimbursement of the vendor payment from US-VISIT via the Intra- 
governmental Payment and Collection (IPAC) system.[Footnote 14] In 
addition, the servicing agencies also receive IPAC payments for the 
services they themselves provided for US-VISIT--essentially a fee for 
the cost of managing contracts on the program's behalf. 

Table 1 lists the various agencies currently managing US-VISIT-related 
contracts and summarizes their respective relationships with the 
program office and the purpose of the contract actions that we 
reviewed. 

Table 1: Relationships between Servicing Agencies Managing US-VISIT- 
Related Contracts and US-VISIT Program: 

Managing organization: US-VISIT Acquisition and Program Management 
Office; 
Relationship to US-VISIT: N/A; 
Purpose of contract actions managed: Support for all aspects of US-
VISIT. 

Managing organization: Architect Engineering Resource Center (Army 
Corps of Engineers); 
Relationship to US-VISIT: Interagency agreement/ Reimbursable work 
authorization; 
Purpose of contract actions managed: On-site program management at 
ports of entry and economic impact assessment of US-VISIT 
implementation on northern and southern borders. 

Managing organization: General Services Administration; 
Relationship to US-VISIT: Reimbursable work authorization; 
Purpose of contract actions managed: Facilities services related to US-
VISIT work at ports of entry. 

Managing organization: Customs and Border Protection (DHS); 
Relationship to US-VISIT: Intra-agency agreement; 
Purpose of contract actions managed: Work related to TECS and ADIS. 

Managing organization: Immigration and Customs Enforcement (DHS); 
Relationship to US-VISIT: Intra-agency agreement; 
Purpose of contract actions managed: Work related to IDENT and ADIS; IT 
support services. 

Managing organization: Transportation Security Administration (DHS); 
Relationship to US-VISIT: Intra-agency agreement; 
Purpose of contract actions managed: Work related to air/sea exit pilot 
(which interfaces with IDENT). 

Source: GAO analysis. 

[End of table] 

Summary of DHS Reported Obligations for US-VISIT Contracts: 

Documentation provided by the agencies responsible for managing US- 
VISIT-related contracts shows that between March 2002 and March 31, 
2005, they obligated about $347 million for US-VISIT-related contract 
work.[Footnote 15] As shown in figure 4, about $152 million, or less 
than half (44 percent), of the $347 million in obligations reported to 
us was for contracts managed directly by the US-VISIT program office. 
The remaining $195 million, or 56 percent, was managed by other DHS and 
non-DHS agencies. Specifically, $156 million, or 45 percent of the $347 
million in obligations reported to us for contracts, was managed by 
other DHS agencies (TSA and CBP); $39 million, 11 percent, was managed 
by non-DHS agencies (GSA and AERC). 

Figure 4: Distribution of $347 Million US-VISIT Obligated Contracting 
Dollars between March 2002 and March 2005: 

[See PDF for image] 

Source: GAO analysis of DHS data. 

[End of figure] 

From the inception of the US-VISIT program office through September 30, 
2005, the program reports that it transferred about $96.7 million to 
other agencies via the IPAC system for direct reimbursement of contract 
costs and for the agencies' own costs.[Footnote 16] 

Prior Reviews Related to DHS Contractor Oversight and Management: 

In January 2005, we observed[Footnote 17] the increased use of 
interagency contracting by the federal government and noted the factors 
that can make interagency contract vehicles high risk in certain 
circumstances. One of these factors was that the use of such 
contracting vehicles contributes to a much more complex environment in 
which accountability had not always been clearly established, including 
designation of responsibility for such critical functions as describing 
requirements and conducting oversight. We concluded that interagency 
contracting should be designated a high-risk area because of the 
challenges associated with such contracts, problems related to their 
management, and the need to ensure oversight. 

In March 2005, we also reported[Footnote 18] on challenges facing DHS's 
efforts to integrate its acquisition functions. One significant 
challenge was a lack of sufficient staff in the Office of the Chief 
Procurement Officer to ensure compliance with the department's 
acquisition regulations and policies. Another challenge was that the 
department's Office of Procurement Operations, which was formed to 
support DHS agencies that lacked their own procurement support (such as 
US-VISIT), did not yet have sufficient staff and relied heavily on 
interagency contracting. Further, the office had not implemented 
management controls to oversee procurement activity, including ensuring 
that proper contractor management and oversight had been performed. We 
concluded that unless these challenges were addressed, the department 
was at risk of continuing with a fragmented acquisition organization 
that provided only stop-gap, ad hoc solutions. 

Importance of Contractor Management Controls: 

Organizational policies and procedures are important management 
controls to help program and financial managers achieve results and 
safeguard the integrity of their programs. Agency management is 
responsible for establishing and implementing financial and 
nonfinancial controls, which serve as the first line of defense in 
ensuring contractor performance, safeguarding assets, and preventing 
and detecting errors and fraud. 

Pursuant to 31 U.S.C. °Þ 3512 (c),(d), the Comptroller General has 
promulgated standards that provide an overall framework for 
establishing and maintaining internal controls in the federal 
government.[Footnote 19] Policy and guidance on internal control in 
executive branch agencies are provided by the Office of Management and 
Budget (OMB) in Circular A-123,[Footnote 20] which defines management's 
fundamental responsibility to develop and maintain effective internal 
controls. Specifically, management is responsible for implementing 
appropriate internal controls; assessing the adequacy of internal 
controls, including those over financial reporting; identifying needed 
improvements and taking corrective action; and reporting annually on 
internal controls.

The five general standards in our framework for internal control are 
summarized below. 

* Control environment. Management and employees should establish and 
maintain an environment throughout the organization that sets a 
positive and supportive attitude toward internal control and 
conscientious management. A key factor relevant to contractor 
management is having clearly defined areas of authority and 
responsibility and appropriate lines of reporting. 

* Risk assessment. Internal control should provide for an assessment of 
the risks the agency faces from both external and internal sources. 

* Control activities. Internal control activities help ensure that 
management's directives are carried out. The control activities should 
be effective and efficient in accomplishing the agency's control 
objectives. Key control activities associated with contract management 
include: 

* appropriate documentation of transactions, 

* accurate and timely recording of transactions and events, 

* controls over information processing, 

* reviews by appropriate management in the organization, and: 

* segregation of duties. 

* Information and communications. Information should be recorded and 
communicated to management (and others who need it) in a form, and 
within a time frame, that enables them to carry out their internal 
control and other responsibilities. Key contract management activities 
include: 

* identifying, capturing, and distributing information in a form and 
time frame that allows people to perform their duties efficiently; and: 

* ensuring that information flows throughout the organization and to 
external users as needed. 

* Monitoring. Internal control monitoring should assess the quality of 
performance over time and ensure that the findings of audits and other 
reviews are promptly resolved. 

To complement the standards, we developed a tool to help managers and 
evaluators determine how well an agency's internal controls are 
designed and functioning and what, where, and how improvements may be 
implemented.[Footnote 21] This tool is intended to be used concurrently 
with the standards described above and with OMB Circular A-123. The 
tool associates each standard with a list of major factors to be 
considered when users review the controls for that standard, as well as 
points to be considered that may indicate the degree to which the 
controls are functioning. 

Relevant acquisition regulations and IT acquisition management guidance 
also provide criteria for effectively managing contractor activities. 
The Federal Acquisition Regulation (FAR)[Footnote 22] requires that 
government agencies ensure that the contractor performs the 
requirements of the contract, and the government receives the service 
intended. However, the FAR does not prescribe specific methods for 
doing so. 

Other such methods or practices can be found in other acquisition 
management guidance. In particular, the Capability Maturity Model 
Integration model,[Footnote 23] developed by the Software Engineering 
Institute (SEI) of Carnegie Mellon University, explicitly defines 
process management controls that are recognized hallmarks for 
successful organizations and that, if implemented effectively, can 
greatly increase the chances of successfully acquiring software and 
systems. These controls define a number of practices and subpractices 
relevant to managing and overseeing contracts. These practices are 
summarized below. 

* Establish written policies and procedures for performing contractor 
management. Polices establish the organization's expectations for 
performing contractor management activities. Procedures provide the 
"how to" or method to be followed in implementing the policies. 

* Establish and maintain a plan for performing the contract oversight 
process. The plan should include, among other things, a contractor 
management and oversight process description, requirements for work 
products, an assignment of responsibility for performing the process, 
and the evaluations and reviews to be conducted with the contractor. 

* Assign responsibility and authority for performing the specific 
contractor management activities. Responsibility should be assigned for 
performing the specific tasks of the contractor management process. 

* Train the people performing or supporting the contractor management 
process. Personnel participating in the contract oversight process 
should be adequately trained and certified, as appropriate, to fulfill 
their assigned roles. 

* Document the contract. This documentation should include, among other 
things, a list of agreed-upon deliverables, a schedule and budget, 
deliverable acceptance criteria, and types of reviews that will be 
conducted with the contractor. 

* Verify and accept the deliverables. Procedures for accepting 
deliverables should be defined; those accepting the deliverables should 
verify that they meet requirements; the results of acceptance reviews 
or tests should be documented; action plans should be developed for any 
products that do not pass their review or test; and action items should 
be identified, documented, and tracked to closure. 

* Monitor risks involving the contractor and take corrective actions as 
necessary. Risks should be identified and categorized (e.g., risk 
likelihood or risk consequence) and then analyzed according to these 
assigned categories. 

* Conduct technical reviews with the contractor. Reviews should ensure 
that technical commitments are being met in a timely manner and should 
verify that the contractor's interpretation and implementation of the 
requirements are consistent with the project's interpretation. 

* Conduct management reviews. Reviews should address critical 
dependencies, project risks involving the contractor, and the contract 
schedule and budget. 

US-VISIT Established and Implemented Key Controls for Contracts That It 
Managed Directly, but It Did Not Have Controls for Overseeing Contracts 
Managed by Others or for Effective Financial Management: 

Given the US-VISIT program's dependence on contracting, it is extremely 
important for the program office to effectively manage and oversee its 
contracts via the establishment and implementation of key contractor 
management and oversight controls. To its credit, the program office 
established and implemented most of the key practices associated with 
effectively managing nonfinancial contractor activities for those 
contracts that it directly manages. In particular, it established 
policies and procedures for implementing all but one of the key 
practices that we reviewed, and it implemented many of these practices-
-including assigning responsibilities and training key personnel 
involved in contractor management activities, verifying that contractor 
deliverables satisfied established requirements, and monitoring the 
contractor's cost and schedule performance for the task orders that we 
reviewed. In doing so, the program has increased the chances that 
program deliverables and associated mission results will be produced on 
time and within budget. 

However, the program office did not effectively oversee US-VISIT- 
related contract work performed on its behalf by other DHS and non-DHS 
agencies, and these agencies did not always establish and implement the 
full range of controls associated with effective management of their 
respective contractor activities. Without effective oversight, the 
program office cannot adequately ensure that program deliverables and 
associated mission results will be produced on time and within budget. 

Further, the program office and other agencies did not implement 
effective financial controls. The program office and other agencies 
managing US-VISIT-related work were unable to reliably report the scope 
of contracting expenditures. In addition, some agencies improperly paid 
and accounted for related invoices, including making a duplicate 
payment and making payments for non-US-VISIT services from funds 
designated for US-VISIT. Without effective financial controls, DHS 
cannot reasonably ensure that payments made for work performed by 
contractors are a proper and efficient use of resources. 

According to the US-VISIT program official responsible for contract 
matters, the program office has initially focused on contracts that it 
manages directly. For US-VISIT contracts managed by other agencies, the 
program office has decided to rely on those agencies to manage the 
contracts and associated financial matters. In addition, it has decided 
to rely on another agency for financial management support of the 
program office. 

Program Office Established and Implemented Key Contractor Management 
Practices: 

The US-VISIT program office is responsible and accountable for meeting 
program goals and ensuring that taxpayer dollars are expended 
effectively, efficiently, and properly. Within the program office, APMO 
is responsible for establishing and maintaining disciplined acquisition 
and program management processes to ensure the efficient support, 
oversight, and control of US-VISIT program activities. Accordingly, it 
is important that APMO establish and implement effective contractor 
management controls. 

As mentioned previously, federal regulations and acquisition management 
guidance[Footnote 24] identify effective contractor management as a key 
activity and describe a number of practices associated with this 
activity, including (among other things) establishing policies and 
procedures for contractor management, defining responsibilities and 
authorities, providing training, verifying and accepting deliverables, 
and monitoring contractor performance. These general practices often 
consist of more detailed subpractices. Appendix III lists the practices 
and associated subpractices, as well as the extent to which they were 
performed on each of the contract actions that we reviewed. 

For contracts that it directly managed, APMO established policies and 
procedures for all but one of the key nonfinancial practices associated 
with effective contractor management. For example, it established 
policies and procedures for performing almost all contractor management 
activities (practices) through its Contract Administration and 
Management Plan. This programwide plan, in conjunction with its 
Acquisition Procedures Guide Deskbook, defines the methodology and 
approach for performing contractor management for all contracts and 
task orders managed by APMO. However, it neither established polices 
and procedures for having a plan for overseeing individual contract 
actions, nor actually developed such a plan. Instead, APMO relied on 
its programwide polices and procedures for performing contract 
management activities and to define what and how it actually 
implemented them. However, without a plan for specific contracting 
actions, the program office cannot be assured that contract management 
activities will be implemented for each contracting action. 

Table 2 shows the extent to which APMO, in its documented policies and 
procedures, requires that the critical contractor management practices 
be performed; this is shown under the heading "practice established?" 
Under "practice implemented?" the table also shows the extent to which 
APMO had actually implemented such practices for those contracting 
actions that we reviewed, regardless of any documented requirement. 

Table 2: APMO's Establishment and Implementation of Key Contractor 
Management Practices: 

Practice: Establish and maintain a plan for performing the contractor 
oversight process; 
Practice Established: [Empty]; 
Practice Implemented: [Empty].  

Practice: Assign responsibility and authority for performing the 
contractor oversight process; 
Practice Established: check; 
Practice Implemented: check. 

Practice: Train the people performing or supporting the contractor 
oversight process as needed; 
Practice Established: check; 
Practice Implemented: check. 

Practice: Document the contract; 
Practice Established: check; 
Practice Implemented: check.  

Practice: Verify and accept the deliverables; 
Practice Established: check; 
Practice Implemented: check.  

Practice: Monitor risks involving the contractor and take corrective 
actions as necessary; 
Practice Established: check; 
Practice Implemented: check. 

Practice: Conduct technical reviews with the contractor; 
Practice Established: check; 
Practice Implemented: check.  

Practice: Conduct management reviews with the contractor; 
Practice Established: check; 
Practice Implemented: check.  

Legend: 

Filled in = Established/implemented: 
Not filled in = Not established/implemented: 

Sources: SEI, GAO analysis of agency data. 

Note: We determined whether the requirement for a practice was 
established or not established on the basis of documented policies and 
procedures addressing the practice and, where applicable, all, some, or 
none of the subpractices. We determined whether a practice was 
implemented or not implemented on the basis of documentation 
demonstrating that all, some, or none of the subpractices, where 
applicable, had been implemented for the task orders that we reviewed. 

[End of Table] 

APMO also implemented the aforementioned policies and procedures that 
it established for each of the contracting actions that we reviewed. 
For example, APMO implemented all of the key subpractices associated 
with verifying and accepting contract deliverables. Specifically, APMO 
defined acceptance procedures, verified that deliverables satisfied 
their requirements, documented the results of the review, developed a 
plan for addressing deliverable deficiencies, and tracked those issues 
to closure. With respect to one program support task order, for 
example, a designated US-VISIT team reviewed a project plan delivered 
by the contractor and returned it with a "conditionally acceptable" 
letter; this letter stated that the comments included were to be 
incorporated into the plan and assigned a date that the revised plan 
was due back. The contractor resubmitted the plan by the assigned date, 
and the contracting officer's technical representative (COTR) accepted 
it. Throughout the process, APMO tracked the status of this deliverable 
by means of a database designed to track and update the status of 
deliverables owed to US-VISIT by its contractors. The database included 
such information as current document status and when the revised 
document was due back to the program office. 

APMO also implemented all critical subpractices associated with 
contractor technical and management review activities. For example, 
APMO required that the prime contactor provide monthly cost performance 
reports that compared actual with budgeted cost and addressed critical 
dependencies. For example, one report noted that schedule and costs 
were impacted by a change in resources. In the report, the contractor 
proposed a corrective action and resolution date. APMO staff analyzed 
these reports and, according to APMO officials, distributed the 
analysis results to program office management for informational 
purposes (the results focused on the causes of and planned corrective 
actions for the most noteworthy cost and schedule variances). The 
information contained in the monthly reports was also discussed at 
quarterly programwide management reviews, which included contractor 
personnel. In addition to management issues, these reviews addressed 
technical issues such as deliverable status and requirements. 

The quarterly reviews were also used to evaluate the contractor's 
overall performance, as well as the contractor's performance on each 
task order active during that reporting period. The task orders that we 
examined were among those reviewed in this way. For each task order, 
the quarterly reviews included an assessment of schedule, cost and 
funding, technical performance, staffing, and risks. For example, the 
information presented on one task order that we reviewed reported that 
all of these categories were on track and were forecast to remain on 
track.[Footnote 25] During these reviews, technical requirements for 
each of the task orders were discussed among stakeholders, contractor 
personnel, and management to ensure a common understanding of those 
requirements and the status of their implementation. The results of 
these reviews were documented, and key discussion topics and a list and 
status of action items were identified. The action items were assigned 
due dates and were assigned to US-VISIT, the contractor, or specific 
individuals. In some cases, an action item identified a specific task 
order, such as a request to restructure a staffing report on a program 
management task order (in order to more accurately portray the level of 
contractor staffing). In the case of the staffing report, it was 
assigned to a contractor for action. Updated status of open items was 
also provided. 

According to APMO's acquisition policy, the office established and 
implemented these contractor management practices to establish a 
standard approach for conducting contract activities and to ensure that 
US-VISIT contracts continue to be managed in accordance with relevant 
laws, regulations, policies, and acquisition requirements. In doing so, 
the program has increased the chances that program deliverables and 
associated mission results will be produced on time and within budget. 

The Program Office Did Not Effectively Oversee US-VISIT-Related 
Contracts Managed by Other Agencies: 

The US-VISIT program office's APMO is responsible for the program's 
contract-related matters. That means that APMO should, among other 
things, effectively oversee contracts being managed by others on the 
program's behalf. However, the program office did not establish and 
implement effective controls for overseeing US-VISIT-related contracts 
being managed by others. Specifically, the program office did not know 
the full range of US-VISIT-related contract actions that had been 
completed and were under way, and it had not performed key practices 
associated with gaining visibility into and understanding of contractor 
performance in meeting the terms of these contracts. This oversight gap 
is exacerbated by the fact that the other agencies did not always 
establish and implement the full range of controls associated with 
effective management of their contractor activities. For example, these 
agencies did not always implement effective controls for ensuring that 
contractor deliverables satisfy established requirements. Without 
effective oversight of all US-VISIT-related contracts, the program 
office is increasing the risk that program goals and outcomes will not 
be accomplished on time and within budget. 

US-VISIT's Oversight of Other Agencies' Contracting Activities Has Been 
Informal and Inconsistent: 

To effectively oversee program-related contracts being managed by 
others, it is important for a program office to, at a minimum, 
depending on the nature of the contract, (1) define the roles and 
responsibilities for both itself and the entities it relies on to 
manage the contracts, (2) know the full range of such contract work 
that has been completed and is under way, and (3) define and implement 
the steps it will take to obtain visibility into the degree to which 
contract deliverables meet program needs and requirements, which 
underpin the program goals and outcomes. 

However, the US-VISIT program office did not effectively perform the 
following oversight activities for contracts that are being managed by 
other agencies: 

Defining roles and responsibilities. The program office did not define 
and document program office roles and responsibilities for overseeing 
the contractor work managed by other agencies and did not define the 
roles and responsibilities of the agencies managing US-VISIT-related 
contracts. According to the APMO Director, the roles and 
responsibilities were defined in IAAs between these agencies and the 
program office. However, the IAAs generally did not define roles and 
responsibilities. For example, US-VISIT provided us with 12 agreements 
for the agencies that we reviewed,[Footnote 26] and only one of them 
described roles and responsibilities for either APMO or the agency 
managing the contract work. Although responsibilities were identified, 
they were at a high level and the same for both the program office and 
the agency managing the contractor. Specifically, the IAA states that 
the US-VISIT COTR or point of contact and the servicing agency program 
office are responsible for technical oversight of the specified product 
or service identified in the statement of work. However, the IAA does 
not identify any specific contract oversight practices to be performed. 
According to the APMO Director, the program office did not define roles 
and responsibilities because the office is relatively new, and most 
efforts have been focused on developing policies and procedures for 
managing contracts that it directly controls. 

As noted earlier, we have previously reported that the use of IAAs is a 
high-risk approach to contracting.[Footnote 27] Although these contract 
vehicles can offer benefits of improved efficiency and timeliness, 
effective management of IAAs is challenging. Accordingly, we concluded 
that the use of IAAs requires, among other things, that the issuing 
agency clearly define roles and responsibilities for conducting 
contractor management and oversight. 

Knowing the full range of contract work. The program office was not 
able to provide us with a complete list of US-VISIT-related contract 
actions. Instead, US-VISIT told us that we needed to obtain a list of 
actions from each of the DHS and non-DHS agencies that managed the 
contract work. Once we compiled the list of contracting actions 
provided to us by the other agencies, the Director told us that no one 
in the program office could verify that the list was complete and 
correct. The Director further stated that APMO is not responsible for 
overseeing contracts managed outside the program office. 

Defining and implementing the steps to verify that deliverables meet 
requirements. According to DHS's directive on IAAs,[Footnote 28] the 
issuing agency (US-VISIT, in this case) is to, among other things, 
monitor the performance of the servicing agency and/or contractor; the 
directive also assigns responsibility for monitoring performance to the 
program office (or program point of contact) and the contracting 
officer. The contracting officer responsible for US-VISIT's IAAs told 
us that he relied on the program office's designated points of contact 
to conduct oversight of those IAAs. However, the program office did not 
define any specific performance monitoring activities. As a result, 
oversight activities performed have been informal and inconsistent. For 
example, on the AERC contracts, the Facilities and Engineering Budget 
Officer held weekly teleconferences with AERC to discuss project 
progress and contract issues, and concerns on an exception basis. 
However, these meetings were not documented; in other words, any follow-
up on open issues and tracking to closure was handled informally. On 
the CBP contract actions, the US-VISIT Deputy Chief Information Officer 
(or one of his representatives) attended most, but not all, of the 
system development-milestone progress reviews related to US-VISIT work, 
and held ad hoc discussions with a CBP program manager to discuss 
funding and work status. On air/sea exit,[Footnote 29] the US-VISIT 
Director of Implementation relied on weekly meetings with TSA and the 
contractor to keep apprised of project status. However, he relied on a 
representative from US-VISIT Mission Operations to certify that testing 
on air/sea exit was completed in a satisfactory manner, and neither he 
nor a member of his team reviewed the results themselves. According to 
the Director of APMO, specific activities to monitor contracts managed 
by other agencies have not been established because the program 
office's efforts to date have focused on developing policies and 
procedures for contracts that the program office manages directly. 

Without clearly defined roles and responsibilities, as well as defined 
oversight activities for ensuring successful completion of the work 
across all US-VISIT-related contract activities, the program office 
cannot be adequately assured that required tasks are being 
satisfactorily completed. 

Agencies Managing US-VISIT-Related Contractors Did Not Establish and 
Implement Key Contractor Management Practices: 

As mentioned previously, acquisition management guidance[Footnote 30] 
identifies effective contractor management as a key activity and 
describes a number of practices associated with this activity, 
including (among other things) establishing policies and procedures for 
contractor management, defining responsibilities and authorities, 
providing training, verifying and accepting deliverables, and 
monitoring contractor performance. As mentioned earlier, these 
practices often consist of more detailed subpractices; appendix III 
provides further details on the practices, subpractices, and agency 
performance of these on each of the contract actions we reviewed. 

Table 3 shows the extent to which agencies, in their documented 
policies or procedures, require that the critical contractor management 
practices be performed (see columns under "practice established?"); it 
also shows (under "practice implemented?") the extent to which agencies 
had actually implemented such practices for the contracting actions 
that we reviewed, regardless of any documented requirement. 

Table 3: Status of Critical Contractor Management Practices at US-VISIT 
Contract Management Agencies: 

Practice: Establish and maintain a plan for performing the contract 
oversight process; 
Practice Established?[A]: GSA: No; 
Practice Established?[A]: AERC: No; 
Practice Established?[A]: CBP: Partially; 
Practice Established?[A]: TSA: Partially; 
Practice Established?[A]: ICE[B]: Partially; 
Practice Implemented?[A]: GSA: No; 
Practice Implemented?[A]: AERC: No; 
Practice Implemented?[A]: CBP: Partially; 
Practice Implemented?[A]: TSA: Partially.  
 
Practice: Assign responsibility and authority for performing the 
contractor oversight process; 
Practice Established?[A]: GSA: Yes; 
Practice Established?[A]: AERC: Yes; 
Practice Established?[A]: CBP: Yes; 
Practice Established?[A]: TSA: Partially; 
Practice Established?[A]: ICE[B]: Yes; 
Practice Implemented?[A]: GSA: Yes; 
Practice Implemented?[A]: AERC: Yes; 
Practice Implemented?[A]: CBP: Yes; 
Practice Implemented?[A]: TSA: Yes.  

Practice: Train the people performing or supporting the contract 
oversight process; 
Practice Established?[A]: GSA: Yes; 
Practice Established?[A]: AERC: Yes; 
Practice Established?[A]: CBP: Yes; 
Practice Established?[A]: TSA: Partially; 
Practice Established?[A]: ICE[B]: Yes; 
Practice Implemented?[A]: GSA: Yes; 
Practice Implemented?[A]: AERC: Yes; 
Practice Implemented?[A]: CBP: Partially; 
Practice Implemented?[A]: TSA: No. 

Practice: Document the contract; 
Practice Established?[A]: GSA: Partially; 
Practice Established?[A]: AERC: Partially; 
Practice Established?[A]: CBP: Partially; 
Practice Established?[A]: TSA: Partially; 
Practice Established?[A]: ICE[B]: Partially; 
Practice Implemented?[A]: GSA: Partially; 
Practice Implemented?[A]: AERC: Partially; 
Practice Implemented?[A]: CBP: Partially; 
Practice Implemented?[A]: TSA: Partially.  

Practice: Verify and accept the deliverables; 
Practice Established?[A]: GSA: Partially; 
Practice Established?[A]: AERC: Partially; 
Practice Established?[A]: CBP: Partially; 
Practice Established?[A]: TSA: Partially; 
Practice Established?[A]: ICE[B]: Partially; 
Practice Implemented?[A]: GSA: Partially; 
Practice Implemented?[A]: AERC: Partially; 
Practice Implemented?[A]: CBP: Partially; 
Practice Implemented?[A]: TSA: Partially. 

Practice: Monitor risks involving the contractor and take corrective 
actions as necessary; 
Practice Established?[A]: GSA: Partially; 
Practice Established?[A]: AERC: No; 
Practice Established?[A]: CBP: Yes; 
Practice Established?[A]: TSA: Yes; 
Practice Established?[A]: ICE[B]: Partially; 
Practice Implemented?[A]: GSA: No; 
Practice Implemented?[A]: AERC: No; 
Practice Implemented?[A]: CBP: Partially; 
Practice Implemented?[A]: TSA: Partially.  

Practice: Conduct technical reviews with the contractor; 
Practice Established?[A]: GSA: No; 
Practice Established?[A]: AERC: No; 
Practice Established?[A]: CBP: Yes; 
Practice Established?[A]: TSA: No; 
Practice Established?[A]: ICE[B]: Partially; 
Practice Implemented?[A]: GSA: Partially; 
Practice Implemented?[A]: AERC: No; 
Practice Implemented?[A]: CBP: Partially; 
Practice Implemented?[A]: TSA: No. 

Practice: Conduct management reviews with the contractor; 
Practice Established?[A]: GSA: No; 
Practice Established?[A]: AERC: No; 
Practice Established?[A]: CBP: Partially; 
Practice Established?[A]: TSA: No; 
Practice Established?[A]: ICE[B]: No; 
Practice Implemented?[A]: GSA: Partially; 
Practice Implemented?[A]: AERC: No; 
Practice Implemented?[A]: CBP: Partially; 
Practice Implemented?[A]: TSA: Partially.  

Legend: 

Filled in = Established/implemented: 

Half filled in = Partially established/implemented: 

Empty = Not established/implemented: 

Sources: SEI, GAO analysis of agency data. 

[A] We determined whether the requirement for a practice was 
established, partially established, or not established on the basis of 
documented policies and procedures addressing the practice and, where 
applicable, all, some, or none of the subpractices. We determined 
whether a practice was implemented, partially implemented, or not 
implemented on the basis of documentation demonstrating that all, some, 
or none of the subpractices, where applicable, had been implemented for 
the task orders that we reviewed. 

[B] No results are provided for ICE regarding implementation of best 
practices because we were unable to obtain contract documentation in 
time for analysis. 

[End of table] 

As table 3 shows, agencies' establishment and implementation of the key 
contractor management practices for US-VISIT-related contracts have 
been uneven. 

* All of the agencies had established policies or procedures for 
performing some of the key contractor management practices. Only CBP, 
however, had established policies and procedures for some aspect of all 
the key practices, while GSA and AERC had established procedures for 
about half of the key practices. 

* Nevertheless, most of the agencies at least partially implemented 
most of the practices, even though they did not establish written 
procedures for doing so. For example, although three of the 
agencies[Footnote 31] did not establish documented policies or 
procedures for conducting technical and management reviews with the 
contractor, two of them implemented some aspects of the practice. 

All Agencies Established Some Policies and Procedures for Contractor 
Management Activities: 

Contractor management policies and procedures define the organization's 
expectations and practices for managing contractor activities. All of 
the agencies (DHS and non-DHS) had established polices or procedures 
for governing some key contractor management practices. For example, 
CBP's Systems Development Life Cycle, augmented by its Office of 
Information Technology Project Manager's Guidebook, defines policies 
and procedures for assigning responsibilities and authorities for key 
contracting personnel and training those people responsible for 
implementing contractor management activities. Among other things, 
these documents provide descriptions of the duties of the contracting 
officer, the project manager, and COTR.[Footnote 32] The documents also 
require all affected agencies to train the members of their groups in 
the objectives, procedures, and methods for performing contractor 
management activities. CBP guidance also addresses contractor 
management procedures, including verifying and accepting deliverables, 
monitoring contract risk and taking corrective action, and conducting 
various reviews with the contractor. 

Other agencies, such as GSA and AERC, have established fewer procedures 
for contractor management. For example, GSA had not established 
procedures for three practices: (1) establishing and maintaining a plan 
for performing contractor oversight, (2) conducting technical reviews 
with the contractor, and (3) conducting management reviews with the 
contractor. According to GSA officials, they have not documented their 
oversight process in order to allow for as much flexibility as possible 
in performing the process. Further, they said they relied on the 
professional expertise of the contracting officer's representative 
(COR) and/or COTR to ensure the technical accuracy of work produced by 
a contractor. 

Without established policies and procedures for contractor management, 
the organizations responsible for managing US-VISIT-related contracts 
cannot adequately ensure that these vital contractor management 
activities are performed. 

Agencies' Implementation of Key Practices Was Uneven: 

Implementation of key practices in the contracting actions that we 
reviewed was uneven. As table 3 shows, one practice--assigning 
responsibilities and authorities--was implemented by all agencies. 
Other key practices were only partially implemented or not implemented 
by all agencies. The following discussion provides selected examples. 

Most agencies implemented training of contractor management personnel. 
Training the personnel performing or supporting contractor management 
activities helps to ensure that these individuals have the necessary 
skills and expertise to adequately perform their responsibilities. 

Most of the agencies had trained some of the key contracting officials 
responsible for the contracting actions that we reviewed and were able 
to produce documentation of that training.[Footnote 33] For example, 
CBP relied on a DHS-mandated training program to train its key contract 
personnel. However, that program was not established until March 2004 
for contracting officers and December 2004 for COTRs, and so it did not 
apply to all the contracting actions that we reviewed. Before these 
programs were established, CBP relied on the previously existing 
qualifications of its contracting personnel. However, it provided 
training documentation for only some of the key contracting personnel 
for the contracting actions that we reviewed. 

With respect to non-DHS agencies, AERC and GSA records showed that 
contracting personnel had completed contracting-related training for 
the contracting actions that we reviewed. 

Most agencies did not implement all key practices for verifying and 
accepting contract deliverables. Verifying that contract deliverables 
satisfy specified requirements provides an objective basis to support a 
decision to accept the product. Verification depends on the nature of 
the deliverable and can occur through various means, such as reviewing 
a document or testing software. Effectively verifying and accepting 
contract deliverables includes, among other things, (1) defining 
procedures for accepting deliverables; (2) conducting deliverable 
reviews or tests in order to ensure that the acquired product satisfies 
requirements; (3) documenting the results of the acceptance review or 
test; (4) establishing an action plan for any deliverables that do not 
pass the acceptance review or test; and (5) identifying, documenting, 
and tracking action items to closure. 

All agencies implemented some (but not all) of the key practices 
associated with verifying and accepting contract deliverables. The 
following two examples from CBP and TSA illustrate this. 

* CBP implemented most of the subpractices associated with this 
practice. For one contracting action reviewed (software development for 
Increment 2B functionality), CBP defined acceptance (testing) 
procedures, conducted the tests to verify that the deliverables 
satisfied the requirements, and documented the results. However, it did 
not develop an action plan to identify, document, and track unresolved 
action items to closure. Further, CBP accepted the deliverable before 
verifying that it had satisfied the requirements. Specifically, test 
results were presented at a production readiness review (one of the 
progress reviews called for in CBP's system development life cycle) on 
November 4, 2004. The review meeting included a US-VISIT stakeholder 
representative who signed off on the test results, indicating that US- 
VISIT accepted the deliverable and concurred that it was ready to 
operate in a production environment. However, the test analysis report 
highlighted several issues that called this conclusion into question. 
For example, the report stated that testing continued after the review 
(through November 8, 2004), and the report identified 67 issues at 
severity level 2, which CBP defines as a function that does not work 
and whose failure severely impacts or degrades the system. The report 
further stated that some test cases were delayed and subject to further 
testing. CBP could not provide any documentation that these open issues 
were resolved or that the test cases were executed. Further, the COTR 
told us that CBP did not define specific acceptance standards, such as 
the number and severity of defects permissible for acceptance. Instead, 
acceptance of the deliverable was subjectively based on the COTR's 
assessment of whether the software could provide critical 
functionality. 

For another contract action (Increment 1 hardware and software 
installation at ports of entry), CBP did not verify that the equipment 
was installed according to contract requirements. We were told by both 
the CBP Director of Passenger Systems (who was involved with much of 
the US-VISIT work) and the contract task monitor that the formal 
process for verifying and accepting contract deliverables consisted of 
a site-specific deployment checklist that recorded acceptance of 
deployment at each port. Acceptance required a signature from a 
government employee, a date, and an indication of deployment status 
(the two options for this status were (1) that the equipment was 
installed and operational or (2) that it was not installed, along with 
a description of reasons why it was not). However, as shown in table 4, 
not all checklists that we reviewed were signed or indicated that the 
equipment was installed and operational, and CBP could not provide 
documentation on how the identified issues were resolved. Further, 
although the deliverable was deployed to 119 sites, CBP provided 
checklists for 102 sites and was unable to provide them for the other 
17 sites. 

Table 4: Acceptance Reports for One Contract Deliverable: 

Reports: 47; 
Signed?: Yes; 
Status Verified: Operational: Completed; 
Status Verified: Not installed: Not completed; 
No Status provided: Not completed.  

Reports: 37; 
Signed?: Yes; 
Status Verified: Operational: Not Completed; 
Status Verified: Not installed: Completed; 
No Status provided: Not completed.  

Reports: 3; 
Signed?: Yes; 
Status Verified: Operational: Not Completed; 
Status Verified: Not installed: Not completed; 
No Status provided: Completed. 

Reports: 2; 
Signed?: No; 
Status Verified: Operational: Completed; 
Status Verified: Not installed: Not completed; 
No Status provided: Not Completed. 
 
Reports: 13; 
Signed?: No; 
Status Verified: Operational: Not Completed; 
Status Verified: Not installed: Not completed; 
No Status provided: Completed. 

Reports: Total: 102;  

Legend: 

X = Checklist elements completed: 

-- = Checklist elements not completed: 

Source: GAO analysis of CBP documentation. 

[End of table] 

* TSA implemented three of the practices associated with verifying and 
accepting deliverables--defining acceptance procedures, verifying that 
deliverables satisfy requirements, and documenting the results of the 
tests. Specifically, TSA tested the air/sea exit software and hardware, 
and developed a test plan that included test procedures and a 
traceability matrix. It also documented the test results in a test 
analysis report that noted that the software was ready for deployment 
because of the low severity of identified deficiencies. The report 
included, among other things, a list of system deficiencies identified 
during testing.[Footnote 34] The report also included copies of 
documents provided to a US-VISIT technical representative: a test 
problem report, a summary of testing defects, and a document indicating 
that the contractor had approved the test analysis. However, TSA did 
not provide evidence that the deficiencies were managed and tracked to 
closure. TSA officials told us that open issues were tracked informally 
via twice-weekly meetings with a US-VISIT representative, TSA 
personnel, and contactor staff. Although these meetings were 
documented, the minutes did not provide any evidence of testing issues 
being discussed. According to program officials, this was due to the 
short development time frame (about 4 months) and the need to bypass 
traditional TSA milestone reviews in order to ensure that the product 
was delivered on time. 

Without adequately verifying that contract deliverables satisfy 
requirements before acceptance, an organization cannot adequately know 
whether the contractor satisfied the obligations of the contract and 
whether the organization is getting what it has paid for. 

Most agencies performed contractor technical and management reviews. 
Monitoring contractor performance is essential for understanding the 
contractor's progress and taking appropriate corrective actions when 
the contractor's performance deviates from plans. Such monitoring 
allows the acquiring organization to ensure that the contractor is 
meeting schedule, effort, cost, and technical performance requirements. 
Effective monitoring activities include conducting reviews in which 
budget, schedule, and critical dependencies are assessed and 
documented, and the contractor's implementation and interpretation of 
technical requirements are discussed and confirmed. 

Three of the four agencies implemented some contractor review 
activities, including, among other things, addressing technical 
requirements progress against schedule and costs through regular 
meetings with the contractor. For example, TSA conducted weekly reviews 
with the contractor to discuss the status of contract performance; 
material prepared for some of these weekly meetings indicated that 
topics discussed were "actual dollars expended" versus "budget at 
project completion," projected and actual schedule versus baseline, 
anticipated product delivery dates against planned due dates, and 
issues and risks. As another example, CBP held weekly documented 
meetings with its contractor to discuss open issues, the status of the 
project, and the current stage of the systems development life cycle. 
Additionally, CBP milestone reviews addressed project schedule, budget, 
and risk, some of which could be traced to specific contracts. 

In contrast, AERC did not document the monitoring of contractor 
performance during the performance period of the contract. Instead, to 
document contractor performance, it relied solely on end-of-contract 
evaluations required by the FAR. 

Program Office and Other Agencies' Contract Management Was Impaired by 
Financial Management Weaknesses: 

Financial management weaknesses at both the program office and the 
other agencies impaired their ability to adequately manage and oversee 
US-VISIT-related contracting activities. Specifically, well- 
documented, severe financial management problems at DHS (and at ICE in 
particular) affected the reliability and effectiveness of accounting 
for the US-VISIT program. Accordingly, the program office and the other 
DHS agencies were unable to provide accurate, reliable, and timely 
accounts for billings and expenditures made for contracts related to US-
VISIT. In addition, a number of invoice payments were improperly paid 
and accounted for. 

Serious DHS Financial Management Problems Affected the Quality of 
Financial Data for US-VISIT Contracts: 

DHS's financial management problems are well-documented. When the 
department began operations in 2003, one of the challenges we 
reported[Footnote 35]was integrating a myriad of redundant financial 
management systems and addressing the existing financial management 
weaknesses inherited by the department. Since that time, DHS has 
undergone three financial statement audits and has been unable to 
produce fully auditable financial statements for any of the 
audits.[Footnote 36] In its most recent audit report, auditors 
reported[Footnote 37] 10 material weaknesses and 2 reportable 
conditions.[Footnote 38] 

Among the factors contributing to DHS's inability to obtain clean audit 
opinions were serious financial management challenges at ICE, which 
provides accounting services for several other DHS agencies, including 
the US-VISIT program. For fiscal years 2004 and 2005, auditors reported 
that financial management and oversight at ICE was a material weakness, 
principally because its financial systems, processes, and control 
activities were inadequate to provide accounting services for itself 
and other DHS agencies.[Footnote 39] According to the auditors, ICE did 
not adequately maintain its own accounting records or the accounting 
records of other DHS agencies, including US-VISIT. The records that 
were not maintained included intradepartmental agreements and 
transactions, costs, and budgetary transactions. These and other 
accounts required extensive reconciliation and adjustment at year-end, 
which ICE was unable to complete. In addition, in fiscal year 2005, ICE 
was unable to establish adequate internal controls that reasonably 
ensured the integrity of financial data and that adhered to our 
Standards for Internal Control in the Federal Government;[Footnote 40] 
the Chief Financial Officer of ICE also issued a statement of "no 
assurance" on internal control over financial reporting. 

These systemic financial challenges impaired the US-VISIT program's 
contract management and oversight. As the accounting service provider 
for the US-VISIT program, ICE is responsible for processing and 
recording invoice payments both for contractors working directly for 
the program and for the work ICE procures on the program's behalf. 
However, because of its financial problems, the reliability of the 
financial information processed by ICE as the accounting-services 
provider for the program office was limited. Further, ICE was unable to 
produce detailed, reliable financial information regarding the 
contracts it managed on behalf of US-VISIT. 

Program Office and Other DHS Agencies Did Not Adequately Track Billings 
and Expenditures: 

Of the DHS agencies we reviewed, the program office and two others 
managing US-VISIT-related contracts on the program's behalf did not 
track contract billings and expenditures in a way that was accurate, 
reliable, and useful for contract oversight and decision making. 
Specifically, the amounts reportedly billed were not always reliable, 
and expenditures for US-VISIT were not always separately tracked. 

Our Standards for Internal Control in the Federal Government identifies 
accurate recording of transactions and events as an important control 
activity. In addition, the standards state that pertinent financial 
information should be identified, captured, and distributed in a form 
that permits people to perform their duties effectively. In order for 
people to perform their duties effectively, they need access to 
information that is accurate, complete, reliable, and useful for 
oversight and decision making. In the case of US-VISIT, expenditures 
and billings made for US-VISIT-related contracts should be tracked by 
the program office and the agencies managing the contracts on the 
program office's behalf, and controls should be in place to ensure that 
the information is reliable, complete, and accurate. Furthermore, in 
order for the information to be useful for oversight and decision 
making, billings and expenditures made for US-VISIT work should be 
separately tracked and readily identifiable from other billings and 
expenditures. Separately accounting for program funds is an important 
budgeting and management tool, especially when those funds are 
reimbursed by another agency for a program-specific purpose, as was the 
case for US-VISIT. Finally, according to our internal control standards 
and more specifically, our Internal Control Management and Evaluation 
Tool,[Footnote 41] information should be available on a timely basis 
for effective monitoring of events, activities, and transactions. 

The Amounts Reportedly Billed on US-VISIT-Related Contracts Are Nor 
Reliable: 

Because effective internal controls were not in place, the reliability 
of US-VISIT-related billings by DHS agencies was questionable. First, 
the program office could not verify the scope of completed and ongoing 
contracting actions. Second, for the contracting actions that were 
reported, not all agencies provided billing information that was 
reliable. 

The program office did not track all contracting activity and thus 
could not provide a complete list of contracting actions. In the 
absence of a comprehensive list, we assembled a list of contracting 
actions from the program office and from each of the five agencies 
responsible for contracting for US-VISIT work. However, the APMO 
Director did not know whether the list of contracting actions was 
valid. 

In addition, to varying degrees, other DHS agencies could not reliably 
report to us what had been invoiced on the US-VISIT-related contracts 
they managed. In particular, ICE's substantial financial management 
challenges precluded it from providing reliable information on amounts 
invoiced against its contracts. Its inability to provide us with key 
financial documents for US-VISIT-related contracts illustrated its 
challenges. Over a period of 9 months, we repeatedly requested that ICE 
provide various financial documents, including expenditure listings, 
invoice documentation, and a list of all contracting actions managed on 
behalf of US-VISIT. However, it did not provide complete documentation 
in time to be included in this report. In particular, ICE was not able 
to provide complete and reliable expenditures to date. It did provide a 
list of US-VISIT-related contracting actions, but it did not include 
the amounts invoiced on those contracting actions, and program office 
staff noted several problems with ICE's list, including several 
contracts that were likely omitted. A comparable list provided by the 
DHS Office of the Chief Procurement Officer showed ICE's invoiced 
amounts, but the contracting actions on this list differed from those 
provided by ICE. Without accurate tracking of financial information 
related to US-VISIT contracts, the full scope of contracting and 
spending on the program cannot be known with reasonable certainty. This 
limitation introduces the increased possibility of inefficiencies in 
spending, improper payments, and poor management of limited financial 
resources. 

For CBP, a list of contacting actions provided by program officials 
included discrepancies that raised questions about the accuracy both of 
the list and of the invoiced amounts. First, the task order number of a 
2002 contracting action changed during our period of review, and CBP 
initially reported the task order as two different contracting actions-
-one issued in 2002 and another issued in 2004. Second, the task order 
was for services performed bureauwide, not just for US-VISIT, and from 
the contract documentation it was not discernable which work was 
specific to US-VISIT. Such discrepancies suggest that the amount 
invoiced specifically to US-VISIT was not accurate. Finally, our 
summation of all the invoices, through March 31, 2005, on this 
contracting action totaled about $8.8 million, which was about $1.3 
million more than the total invoiced amount that CBP had 
reported.[Footnote 42] This discrepancy indicated that CBP was not 
adequately tracking funds spent for US-VISIT on this contracting 
action, which increased the risk that the program was improperly 
reimbursing CBP on this contract. No such discrepancy existed between 
reported and actual invoiced amounts on the 2003 and 2004 CBP 
contracting actions we reviewed. 

TSA was able to provide accurate billing information on the one US- 
VISIT-related contracting action that it managed, but delays in 
invoicing on this contracting action increase the risk of future 
problems. As of February 2005, development on the TSA contract action 
was finished, and the contract had expired. However, from April 2005 
through February 2006 (the latest date available), TSA reported that it 
continued to receive and process about $5 million in invoices, and that 
the contractor can still bill TSA for prior work performed for up to 5 
years after expiration of the contract. According to TSA, the 
contractor estimated (as of February 2006) that it would be sending TSA 
an additional $2 million in invoices to pay for work already completed. 
TSA officials could not explain this delay in invoicing. Such a 
significant lag between the time in which work is completed and when it 
is billed can present a challenge to the proper review of invoices. 

DHS Agencies Did Not Always Separately Track Expenditures Made to 
Contractors for US-VISIT Work: 

ICE did not track expenditures made to contractors for US-VISIT work 
separately from other expenditures, and CBP experienced challenges in 
its efforts to do so. Reliable, separate tracking of such expenditures 
is an important internal control for ensuring that funds are being 
properly budgeted and that the program office is reimbursing agencies 
only for work performed in support of the program. 

In the case of ICE, its financial management system did not include 
unique codes or any other means to reliably track expenditures made for 
US-VISIT-related contracts separately from non-US-VISIT expenditures. 
As a result, ICE did not have reliable information on what it spent for 
the program, which means that it could have requested improper 
reimbursements from the program office. More specifically, the most 
detailed list ICE could provide of its US-VISIT-related payments was by 
querying its financial management system by contract number, which 
provided all payments under the contract number. However, each 
contract's scope of work is generally broad and includes work 
throughout ICE, not just for US-VISIT. Thus, this method would not give 
an accurate picture of what expenditures ICE had made for US-VISIT- 
related work. 

In the case of CBP, it began using coding in its financial management 
system to separately track US-VISIT obligations and expenditures 
beginning in fiscal year 2003, when CBP first received funding for US- 
VISIT. At that time, CBP tracked all US-VISIT expenditures under a 
single project code. However, between fiscal years 2003 and 2004, CBP 
underwent a system conversion that interrupted its tracking of US- 
VISIT-related funds, which made it challenging to separately report US- 
VISIT-related expenditures. During this time, several changes were made 
to the codes used to track US-VISIT information. When we requested a 
listing of the US-VISIT-related expenditures by CBP, it took several 
weeks for CBP finance center staff to document the financial management 
system coding changes and produce a reasonably complete listing of the 
US-VISIT-related expenditures that CBP made during the system 
conversion. In fiscal years 2004 and 2005, CBP again began tracking all 
US-VISIT-related expenditures separately under a single budget code. 
Thus, in the future, the tracking and reporting of US-VISIT 
expenditures by CBP should be more timely and reliable. 

Several Payments to Contractors for US-VISIT Work Were Improperly Paid 
and Accounted for: 

Although the program office and the agencies--both DHS and others-- 
doing work on its behalf usually documented approval of contractor 
invoices before payment, a number of invoices were improperly paid and 
accounted for, resulting in a potential loss of funds control and, in 
one case, a duplicate payment on an invoice of over $3 million. Our 
Internal Control Management and Evaluation Tool states that 
transactions and events need to be appropriately classified and that 
pertinent information is to be identified and captured in the right 
form.[Footnote 43] 

Overpayments occurred as a result of two kinds of errors: on one 
occasion a duplicate payment was made, and on several other occasions 
incorrect balances were paid. 

* A duplicate payment was made on an invoice for over $3 million. APMO 
had sent an authorization for payment in full on the invoice to its 
finance center. Then, 1 month later, APMO sent another authorization 
for payment in full on the same invoice. The second payment was later 
noticed, and the contractor refunded the amount.[Footnote 44] 

* The other set of overpayments, although small in dollar value, 
exemplify a significant breakdown in internal control. Invoices billed 
to AERC on a fiscal year 2005 contract listed the current amount billed 
on the invoice, as well as a cumulative balance; the cumulative balance 
included invoice payments that AERC had already made, but that had not 
been recorded by the contractor when the next invoice was generated. On 
several of the invoices, AERC mistakenly paid the higher cumulative 
balance when the current amount should have been paid. As a result, 
AERC overpaid the vendor by about $26,600. Moreover, it was the 
contractor that first reported this overpayment in September 2005 and 
refunded the overpayment amount to AERC. According to DHS officials, 
the US-VISIT program office had independently identified the 
overpayment in November 2005 and requested clarification from AERC the 
following day. 

Also at APMO, two questionable payments were made that arose from the 
overriding of controls created for the prime US-VISIT contract. The 
prime contract has been implemented through 12 task orders with 
multiple modifications that either increased funding or made other 
changes to the contract terms. To account for the obligations made on 
each task order, the program's Office of Budget and Finance created 
separate tracking codes in the financial system for each task order and 
sometimes for each modification of a task order. The separate tracking 
of each obligation is a good control for tracking and controlling 
spending against task order funds. However, APMO overrode this control 
when it instructed the finance center to pay two invoices--one for 
about $742,000 and one for about $101,000--out of the wrong account: 
that is, with funds for task orders other than those for which the 
invoices were billed. APMO did not provide any justification for 
payment with funds from the improper account. Our Internal Control 
Management and Evaluation Tool states that any intervention or 
overriding of internal controls should be fully documented as to the 
reasons and specific actions taken.[Footnote 45] 

CBP also inappropriately paid for work unrelated to US-VISIT out of 
funds designated for US-VISIT. For a 2003 contracting action that we 
reviewed, invoices included a significant amount in travel billings. 
However, several travel vouchers that accompanied these invoices were 
for work unrelated to US-VISIT. For example, terms like "Legacy ag/ 
legacy Customs unification," "Agriculture Notes Installation," and 
"Agriculture AQI" were indicated on the vouchers. CBP confirmed that 
these vouchers were billed to US-VISIT in error. Additionally, other 
vouchers included descriptions that were vague and not clearly related 
to any specific program (e.g., emergency hardware replacement), and 
thus it was not clear that the work being billed was related to the 
program. Along with the travel expenses, the labor hours associated 
with the above vouchers were also being billed to the program. This 
circumstance calls into question not only whether or not the travel 
charges were inappropriately classified as US-VISIT work, but also 
whether the time that these employees were charging was inappropriately 
classified, and thus improperly paid. 

On one CBP contracting action, some charges that were not related to US-
VISIT may have been reimbursed by the program office. The contracting 
action in question was a 2002 action for CBP-wide disaster recovery 
services, and thus not all charges were directly related to the US-
VISIT program. On this task order, CBP expended about $1.28 million 
from program-designated funds on items that were not clearly specified 
as US-VISIT work on the invoices. Of that amount, about $43,000 could 
be attributed to a contract modification specific to the program. 
However, CBP stated that one invoice for about $490,000 included in 
this $1.28 million was paid from the program's funds to correct two 
payments for earlier US-VISIT invoices that were erroneously made from 
nonprogram funds. We also found about $771,000 of invoice dollars that 
were specified as US-VISIT work, but that were not on the CBP-provided 
expenditure reports for program funds. 

As a result of these various discrepancies, the US-VISIT program may 
have reimbursed CBP for work that was not done on its behalf. Also, the 
program official responsible, under DHS policy,[Footnote 46] for 
monitoring the CBP contracts related to US-VISIT told us that he had 
not been reviewing invoices on IPAC reimbursement requests from CBP, 
even though such reviews are required by DHS policy. 

In addition, on the 2003 CBP contracting action that we reviewed, many 
of the travel vouchers included first-class flights taken by contract 
personnel, although (with few exceptions) purchase of first-class 
travel is not allowed for travel on cost-reimbursable type contracts. 
However, travel documentation indicated first-class travel on numerous 
instances with no explanation or justification of the first-class 
travel or documentation to indicate that CBP had requested any 
explanation. CBP officials noted that some frequent fliers are 
automatically upgraded when purchasing a full-fare flight. Although 
this is a reasonable explanation, CBP provided no documentation showing 
that it completed any inquiry or research at the time it was invoiced 
to determine if first-class travel was being purchased or if upgrades 
were being given, and invoice documentation did not clarify this. 
Further, in several instances, complete documentation was not provided 
for the costs of all airline travel expenses. 

A final concern regarding payments to contractors is raised by the fact 
that several of the agencies made late payments on invoices. Under the 
Prompt Payment Act,[Footnote 47] the government must pay interest on 
invoices it takes over 30 days to pay. Not only do these interest 
payments deplete funds available for US-VISIT, but excessive late 
invoice payments are also a signal that the contract payment oversight 
process is not being effectively managed. CBP and TSA experienced 
agencywide increases in contract prompt-payment interest. CBP reported 
that in fiscal year 2004, the year that it converted to a new 
accounting system, prompt pay interest accounted for 7.66 percent of 
all payments, a sharp increase from the prior year's frequency rate of 
1.74 percent. In fiscal year 2005, the rate of interest payments at CBP 
receded to 1.80 percent of total payments. 

APMO also paid substantial amounts in prompt payment interest. 
According to DHS's auditors, ICE, which provides US-VISIT payment 
services, had not established internal controls to ensure that invoices 
were paid in a timely manner.[Footnote 48] For the invoices that we 
reviewed, prompt-payment interest was paid on approximately 26 percent 
of the prime contract invoices that we reviewed, representing over 
$27,000 in payments. In addition, we could not verify that the proper 
amount of interest was paid because information in the ICE financial 
management system was incorrect. For example, in many instances, 
important dates used for determining prompt-pay interest were entered 
incorrectly, or the dates in the system could not be validated based on 
invoice documentation provided. A program official told us that certain 
program staff have recently been granted read-only access to ICE's 
financial management system to monitor invoice payments. If the program 
office effectively uses this increased oversight ability, it could 
reduce the number of prompt-payment violations as well as reduce other 
improper contract payments made by the program office. 

Conclusions: 

Contractors have played, and will continue to play, a major role in 
delivering US-VISIT capabilities, including technology, facilities, and 
people. Therefore, the success of the program depends largely on how 
well DHS manages and oversees its US-VISIT-related contracts. 
Establishing and implementing effective contractor management and 
oversight controls, including financial management controls, can 
greatly increase the department's ability to manage and oversee US- 
VISIT-related contracts. However, the department's management and 
oversight of US-VISIT-related contracts are not yet at the level that 
they need to be to adequately ensure, for example, that contract 
deliverables satisfy program requirements, that cost and schedule 
commitments are met, that program outcomes are achieved, that funds are 
not overspent and improperly reimbursed, and that payments are made in 
a proper and timely manner. 

Although the program office has generally established and implemented 
key contractor management controls on those contracts that it manages 
directly, it has not adequately overseen US-VISIT-related contracts 
that were managed by other DHS and non-DHS agencies. According to 
program office officials, this is because they have initially focused 
on those contracts that they manage directly. However, this narrow 
focus raises concerns because the agencies managing contracts on the 
program office's behalf have not implemented the full range of 
management controls needed to have a full, accurate, reliable, and 
useful understanding of the scope of contract activities and 
performance. 

Moreover, none of the US-VISIT contracts that we reviewed have been 
subject to important financial management controls. As previous audits 
have shown, DHS suffers from numerous material weaknesses in financial 
management, some of which are directly related to ICE (the DHS 
component that provides financial management services to the program 
office). These weaknesses have contributed to the program's inability 
to know the full scope of contract activities and fully account for 
expenditures, among other things. By impairing the reliability and 
effectiveness of accounting for US-VISIT contracts, these weaknesses 
have diminished the program's ability to effectively manage and oversee 
work performed by contractors--work that is essential for the program 
to achieve its goals. 

Until DHS addresses these contract management and oversight weaknesses, 
the US-VISIT program will remain at risk of not delivering required 
capabilities and promised benefits on time and within budget, and it 
will be vulnerable to financial mismanagement. 

Recommendations for Executive Action: 

Given the US-VISIT program's mission importance, size, and heavy 
reliance on contractor assistance, we recommend that the Secretary of 
Homeland Security direct the US-VISIT Program Director to take the 
following five actions to strengthen contract management and oversight, 
including financial management: 

* For each US-VISIT contract action that the program manages directly, 
establish and maintain a plan for performing the contractor oversight 
process, as appropriate. 

* Develop and implement practices for overseeing contractor work 
managed by other agencies on the program office's behalf, including (1) 
clearly defining roles and responsibilities for both the program office 
and all agencies managing US-VISIT-related contracts; (2) having 
current, reliable, and timely information on the full scope of contract 
actions and activities; and (3) defining and implementing steps to 
verify that deliverables meet requirements. 

* Require, through agreements, that agencies managing contract actions 
on the program office's behalf implement effective contract management 
practices consistent with acquisition guidance for all US-VISIT 
contract actions, including, at a minimum, (1) establishing and 
maintaining a plan for performing contract management activities; (2) 
assigning responsibility and authority for performing contract 
oversight; (3) training the people performing contract oversight; (4) 
documenting the contract; (5) verifying that deliverables satisfy 
requirements; (6) monitoring contractor-related risk; and (7) 
monitoring contractor performance to ensure that the contractor is 
meeting schedule, effort, cost, and technical performance requirements. 

* Require DHS and non-DHS agencies that manage contracts on behalf of 
the program to (1) clearly define and delineate US-VISIT work from non- 
US-VISIT work as performed by contractors; (2) record, at the contract 
level, amounts being billed and expended on US-VISIT-related work so 
that these can be tracked and reported separately from amounts not for 
US-VISIT purposes; and (3) determine if they have received 
reimbursement from the program for payments not related to US-VISIT 
work by contractors, and if so, refund to the program any amount 
received in error. 

* Ensure that payments to contractors are timely and in accordance with 
the Prompt Payment Act. 

Agency Comments and Our Evaluation: 

We received written comments on a draft of this report from DHS, which 
were signed by the Director, Departmental GAO/IG Liaison Office, and 
are reprinted in appendix II. We also received comments from the 
Director of AERC and the Assistant Commissioner for Organizational 
Resources, Public Buildings Service, GSA. Both the Department of 
Defense audit liaison and the GSA audit liaison requested that we 
characterize these as oral comments. 

In its written comments, DHS stated that although it disagreed with 
some of our assessment, it agreed with many areas of the report and 
concurred with our recommendations and the need for improvements in US- 
VISIT contract management and oversight. The department disagreed with 
certain statements and provided additional information about three 
examples of financial management weaknesses in the report. Summaries of 
DHS's comments and our response to each are provided below. 

* The department characterized as misleading our statements that US- 
VISIT (1) depended on other agencies to manage financial matters for 
their respective contracts and (2) relied on another agency for US- 
VISIT's own financial management support. With respect to the former, 
DHS noted that the decision to use other agencies was based on the 
nature of the services that were required, which it said were outside 
the scope of the program office's areas of expertise. We understand the 
rationale for the decision to use other agencies, and the statement in 
question was not intended to suggest anything more than that such a 
decision was made. We have slightly modified the wording to avoid any 
misunderstanding. 

With respect to its own financial management, DHS said that for us to 
declare that US-VISIT depended on another agency for financial 
management support without identifying the agency and the system, in 
combination with our acknowledging that we did not examine the 
effectiveness of this unidentified system, implies that our report's 
scope is broader than what our congressional clients asked us to 
review. We do not agree. First, our report does identify ICE as the 
agency that the program office relies on for financial management 
support. Second, although we did not identify by name the ICE financial 
management system, we did describe in detail the serious financial 
management challenges at ICE, which have been reported repeatedly by 
the department's financial statement auditors and which have 
contributed to the department's inability to obtain a clean audit 
opinion. Moreover, we fully attributed these statements about these 
serious challenges to the auditors. 

* The department said that our statement regarding the purpose of the 
contracts managed by AERC needed to be clarified, stating that our 
report reflects the scope of the two contract actions reviewed and not 
the broader scope of services under the interagency agreement. We agree 
that the description of AERC services in our report is confined to the 
scope of the two contract actions that we reviewed. This is intentional 
on our part since the scope of our review did not extend to the other 
services. We have modified the report to clarify this. 

* The department provided additional information about three examples 
of invoice discrepancies and improper payments cited in the report, 
including reasons why they occurred. Specifically, the department said 
that the reason that CBP reported a 2002 contracting action as also a 
2004 contracting action was because of the concurrent merger of CBP 
within DHS and the implementation of CBP's new financial system. It 
further stated that the reason that US-VISIT made a duplicate payment 
to the prime contractor was, at least partially, due to poor 
communication between US-VISIT and its finance center. Regarding two 
other duplicate payments, DHS stated that while the cause of the 
duplicate payments is not completely clear from the available evidence, 
both are almost certainly errors resulting from processes with 
significant manual components, as opposed to deliberate control 
overrides, since adequate funds were available in the correct accounts 
for each case. The department also noted that communications may have 
also contributed to one of these two duplicate payments. We do not 
question the department's reasons or the additional information 
provided for the other payments, but neither changes our findings about 
the invoice discrepancies and improper payments. 

* The department stated that although the contractor initially 
identified the AERC overpayment on September 13, 2005, the US-VISIT 
program office independently identified the billing discrepancy on 
November 1, 2005, and requested clarification from AERC the following 
day. The department further stated that because we describe the 
overpayment example in the report as being a small dollar value, we 
should have performed a materiality test in accordance with accounting 
principles in deciding whether the overpayment should be disclosed in a 
public report. We do not dispute whether the US-VISIT program 
independently identified the overpayment in question. Our point is that 
an invoice overpayment occurred because adequate controls were not in 
place. In addition, while we agree that materiality is relevant to 
determining whether to cite an example of an improper payment, another 
relevant consideration to significance is the frequency of the error. 
Our decision to disclose this particular overpayment was based on our 
judgment regarding the significance of the error as defined in 
generally accepted government auditing standards. It is our 
professional judgment that this overpayment is significant because of 
the frequency with which it occurred. Specifically, of the eight 
invoices that we reviewed, four were improperly paid. 

In oral comments, the Director of AERC questioned the applicability of 
the criteria we used to evaluate AERC contract management practices and 
our assessment of its process for verifying and accepting deliverables. 
Despite these disagreements, he described planned corrective actions to 
respond to our findings. 

* The Director stated in general that the Capability Maturity Model 
Integration (CMMI)® model was not applicable to the contracts issued by 
the Corps of Engineers, and in particular that a contract oversight 
plan was not applicable to the two contract actions that we reviewed. 
In addition, the Director commented that AERC's practices were adequate 
to deal appropriately with contractor performance issues had these been 
raised. Nonetheless, to address this issue, the Director stated that 
AERC would require the US-VISIT program office to submit an oversight 
plan describing the project's complexity, milestones, risks, and other 
relevant information, and it would appoint qualified CORs or COTRs to 
implement the plans and monitor contractor performance. 

We disagree with AERC's comments on the applicability of our criteria. 
Although the CMMI model was established to manage IT software and 
systems, the model's practices are generic and therefore applicable to 
the acquisition of any good or service. Specifically, the contractor 
management oversight practices discussed in this report are intended to 
ensure that the contractor performs the requirements of the contract, 
and the government receives the services and/or products intended 
within cost and schedule. We also do not agree that the contract 
actions in question did not warrant oversight plans. Although the 
content of oversight plans may vary (depending on the type, complexity, 
and risk of the acquisition), each acquisition should have a plan that, 
at a minimum, describes the oversight process, defines 
responsibilities, and identifies the contractor evaluations and reviews 
to be conducted. Since the chances of effective oversight occurring are 
diminished without documented plans, we support the program manager's 
commitment to require these plans in the future. 

* Regarding an overpayment discussed in our report, the Director 
indicated that this problem was resolved as described in DHS's 
comments, and that in addition, AERC has procedures and controls to 
prevent the government from paying funds in excess on a firm-fixed 
price contract such as the one in question. Nonetheless, the Director 
described plans for strengthening controls over contract progress 
payments and invoices, including having trained analysts review all 
invoices and ensuring that a program/project manager has reviewed the 
invoices and submitted written authorization to pay them. The Director 
also stated that AERC has an established process for controlling and 
paying invoices, which provides for verifying and accepting 
deliverables. We do not consider that the AERC process was established 
because although AERC officials described it to us, it was neither 
documented nor consistently followed. For example, one contracting 
action that we reviewed had three invoices that did not have a 
signature or other documentation of approval, even though such 
approval, according to AERC, is a required part of the process. 

In oral comments, the GSA Assistant Commissioner disagreed with the 
applicability of certain of the criteria that we used in our 
assessment, as well as with our assessment that these and other 
criteria had not been met. For example, the Assistant Commissioner 
stated that regulations or policies do not require GSA to establish and 
maintain a plan for performing the contract oversight process, that its 
current practices and documents (such as the contract statement of work 
and COR/COTR delegation letters) in effect establish and maintain such 
a plan, that GSA documented the oversight process and results to the 
extent necessary to ensure contractor performance, and that GSA had 
established a requirement to conduct contractor reviews. Although, as 
we state in our report, GSA policies do not include a requirement for 
an oversight plan, we still believe that it is appropriate to evaluate 
GSA against this practice (which is consistent with sound business 
practices and applies to any acquisition), and that GSA's processes and 
activities did not meet the criteria for this practice and ensure 
effective oversight of the contracts. We did not find that the 
delegation letters and contract statements of work were sufficient 
substitutes for such plans, because, for example, they do not 
consistently describe the contractor oversight process or contractor 
reviews. Further, the inclusion of a requirement for contractor reviews 
in some contracts/statements of work does not constitute agencywide 
policies and procedures for performing reviews on all contracts. 

GSA also provided further descriptions of its financial management 
controls and oversight processes and activities, but these descriptions 
did not change our assessment of GSA's financial management controls or 
the extent to which the oversight processes and activities satisfy the 
practices that we said were not established[Footnote 49] or not 
consistently implemented. Among these descriptions was information on 
an automated tool that GSA provided its contracting officers; however, 
this tool was not used during the period under review. GSA also 
provided certain technical comments, which we have incorporated in our 
report, as appropriate. 

As agreed with your offices, unless you publicly announce the contents 
of this report earlier, we plan no further distribution until 30 days 
from the report date. At that time, we will send copies of this report 
to the Chairmen and Ranking Minority Members of the Senate and House 
Appropriations Committees, as well as to the Chairs and Ranking 
Minority Members of other Senate and House committees that have 
authorization and oversight responsibility for homeland security. We 
will also send copies to the Secretary of Homeland Security, the 
Secretary of Defense, the Administrator of GSA, and the Director of 
OMB. Copies of this report will also be available at no charge on our 
Web site at [Hyperlink, http://www.gao.gov]. 

Should your offices have any questions on matters discussed in this 
report, please contact Randolph C. Hite at (202) 512-3439 or at 
hiter@gao.gov, or McCoy Williams at (202) 512-9095 or at 
williamsm1@gao.gov. Contact points for our Offices of Congressional 
Relations and Public Affairs may be found on the last page of this 
report. Key contributors to this report are listed in appendix IV. 

Signed by: 

Randolph C. Hite: 
Director, Information Technology Architecture and Systems Issues: 

Signed by: 

McCoy Williams: 
Director, Financial Management and Assurance: 

List of Requesters: 

The Honorable Peter T. King: 
Chairman: 
The Honorable Bennie G. Thompson: 
Ranking Minority Member: 
Committee on Homeland Security: 
House of Representatives: 

The Honorable Bob Filner: 
House of Representatives: 

The Honorable Raul Grijalva: 
House of Representatives: 

The Honorable Ruben Hinojosa:
 House of Representatives: 

The Honorable Solomon Ortiz: 
House of Representatives: 

The Honorable Silvestre Reyes: 
House of Representatives: 

[End of section] 

Appendix I: Objective, Scope, and Methodology: 

Our objective was to determine whether the Department of Homeland 
Security (DHS) has established and implemented effective controls for 
managing and overseeing contracts related to the U.S. Visitor and 
Immigrant Status Indicator Technology (US-VISIT) program. To address 
our objective, we assessed the implementation of key contractor 
management controls at the program office and at other DHS and non-DHS 
agencies responsible for managing US-VISIT-related contracts. We also 
evaluated the program office's oversight of US-VISIT-related contracts 
managed by these other organizations. Finally, we reviewed internal 
control processes and procedures in place over contract financial 
management. 

Besides the US-VISIT program office, the organizations within DHS that 
we identified as having responsibility for managing US-VISIT-related 
contracts were: 

* Customs and Border Protection (CBP), 

* the Transportation Security Agency (TSA), and: 

* Immigration and Customs Enforcement (ICE). 

The non-DHS agencies performing work in support of US-VISIT were: 

* the General Services Administration (GSA) and: 

* the Army Corps of Engineers Architect-Engineer Resource Center 
(AERC). 

Contract management controls: To assess key contract management 
controls and implementation of those controls at US-VISIT and other 
agencies responsible for managing US-VISIT-related contracts, we 
identified leading public and private sector practices on contract 
management, such as those prescribed by the Federal Acquisition 
Regulation (FAR)[Footnote 50] and Carnegie Mellon University's Software 
Engineering Institute, which publishes the Capability Maturity Model 
Integration.[Footnote 51] US-VISIT officials identified the contracts 
being managed by the program, all within the Acquisition Program 
Management Office (APMO). To evaluate the management of the program's 
contracts, we assessed APMO's and other agencies' documented policies 
against the leading practices that we identified. We also determined 
the extent to which those policies were applied to specific contracting 
actions and determined the extent to which, if any, other formal or 
otherwise established practices were used to manage or oversee the 
specific contract actions. We also discussed any variances with agency 
officials to determine the reasons why those variances existed. 

In determining the extent to which practices/subpractices were judged 
to be established/implemented, we categorized them into one of the 
following: 

* established/implemented, 

* partially established/implemented, or: 

* not established/implemented. 

We judged whether the practice was established, partially established, 
or not established depending on whether the agency had documented 
policies and procedures addressing the practice and all, some, or none 
of the subpractices (where applicable). We judged whether a practice 
was implemented, partially implemented, or not implemented on the basis 
of documentation demonstrating that the practice and all, some, or none 
of the subpractices (where applicable) had been implemented for the 
contracting actions that we reviewed. 

We judged that an agency had "partially established" the requirement 
for a practice or subpractice if the agency relied only on the FAR 
requirement to perform this activity, but did not establish a process 
(i.e., documented procedures) for how the FAR requirement was to be 
met. 

We judged that an agency had "partially implemented" a practice or 
subpractice if it had implemented some, but not all, facets of the 
practice (including its own related requirements for that practice). 

To select specific contracting actions for review, we analyzed 
documentation provided by the program and by the DHS and non-DHS 
agencies responsible for managing US-VISIT-related contracts, to 
identify all contracting work performed in support of the program. 

Program officials were unable to validate the accuracy, reliability, 
and completeness of the list of contracting actions. Therefore, we did 
not perform a statistical sampling of the identified contracting 
actions. Rather, we judgmentally selected from each agency one 
contracting action for US-VISIT-related work awarded in each fiscal 
year from March 1, 2002, through March 31, 2005, focusing on service- 
based contracts. Thus, fiscal years 2002 through 2005 were each 
reviewed to some extent. Not all organizations awarded contracting 
actions in every fiscal year covered under our review, in which case an 
action was not selected for that fiscal year for that organization. The 
contracting actions selected from ICE were excluded in our analysis of 
the implementation of management and financial controls because of 
delays in receiving contract-specific documentation. One program 
management contract that was reported to us by US-VISIT was transferred 
to the program from ICE shortly before the end of our review period, 
and so we were unable to determine, because of the issues with ICE 
identified above, what management activities were performed on the 
contract. 

For each selected contracting action, we reviewed contract 
documentation, including statements of work, project plans, deliverable 
reviews, and other contract artifacts, such as contractor performance 
evaluations. We then compared documentary evidence of contract 
management activity to leading practices and documented policies, 
plans, and practices. Finally, we determined what, if any, formal or 
established oversight practices were in existence at the contract 
level. 

Table 5 shows the judgmental selection of contract actions that were 
reviewed for each agency, including APMO. 

Table 5: Contract Actions Related to US-VISIT That Were Examined in 
This Review: 

Services acquired: Program level management; 
Contract manager: US- VISIT; 
Relationship to US-VISIT: Managed within program office; 
Fiscal year: 2004[A]; 
Contract type: Cost plus award fee; 
Description of services provided by contracting action reviewed: 
Providing program planning, cost and schedule estimation methodology, 
program control methodology, a risk management program, a configuration 
management plan and repository, a quality management plan, a process 
improvement program, a communications management plan and program 
support, a support collaboration tool and integrated portal solution, 
and additional program-level activities. 

Services acquired: US-VISIT strategic plan development; 
Contract manager: US-VISIT; 
Relationship to US-VISIT: Managed within program office; 
Fiscal year: 2005; 
Contract type: Firm fixed price; 
Description of services provided by contracting action reviewed: 
Providing, among other things, an as-is assessment, a business 
functionality vision, an information technology strategic plan, a 
facilities strategic plan, a strategic plan, a data management 
strategic plan, and a business case and implementation plan. 

Services acquired: Pre-award and post-award acquisition services; 
Contract manager: GSA; 
Relationship to US-VISIT: Reimbursable work authorization; 
Fiscal year: 2002; 
Contract type: Firm fixed price; 
Description of services provided by contracting action reviewed: 
Providing pre-award and post-award functions involving the acquisition 
of services to carry out the overall program of the Public Buildings 
Service including the US-VISIT program. 

Services acquired: Planning and mobilization for feasibility studies; 
Contract manager: GSA; 
Relationship to US-VISIT: Reimbursable work authorization; 
Fiscal year: 2003; 
Contract type: Firm fixed price; 
Description of services provided by contracting action reviewed: 
Providing, among other things, mobilization of planning efforts for 
several ports of entry and providing the management of feasibility 
studies for 51 separate ports of entry. 

Services acquired: Program management of US-VISIT at ports of entry; 
Contract manager: GSA; 
Relationship to US-VISIT: Reimbursable work authorization; 
Fiscal year: 2004, 2005[B]; 
Contract type: Firm fixed price; 
Description of services provided by contracting action reviewed: Among 
other things, directing and managing the implementation of the US-VISIT 
program at ports of entry and providing a single point of interface and 
accountability for program implementation efforts. 

Services acquired: On-site program management at ports of entry; 
Contract manager: AERC; 
Relationship to US-VISIT: Reimbursable work authorization; 
Fiscal year: 2003; 
Contract type: Firm fixed price; 
Description of services provided by contracting action reviewed: 
Providing internal US-VISIT management support and coordination for US- 
VISIT initiatives, managing and providing direction to GSA and its 
contractors, coordinating project information and details with CBP, and 
facilitating communication between the various government groups 
involved in port of entry projects. 

Services acquired: Economic impact assessment; 
Contract manager: AERC; 
Relationship to US-VISIT: Interagency agreement; 
Fiscal year: 2005[C]; 
Contract type: Firm fixed price; 
Description of services provided by contracting action reviewed: 
Analyzing and assessing the overall life cycle benefits and costs of 
the US-VISIT program implementation along the northern and southern 
borders of the United States. 

Services acquired: Commercial recovery services; 
Contract manager: CBP; 
Relationship to US-VISIT: Intra-agency agreement; 
Fiscal year: 2002; 
Contract type: Firm fixed price; 
Description of services provided by contracting action reviewed: 
Providing, through a subscription, an adequately equipped primary and 
secondary recovery facility in order to ensure data replication, 
disaster recovery services, extended recovery services, and disaster 
declaration. 

Services acquired: Infrastructure upgrades at ports of entry; 
Contract manager: CBP; 
Relationship to US-VISIT: Intra-agency agreement; 
Fiscal year: 2003; 
Contract type: Labor hour with other direct costs; 
Description of services provided by contracting action reviewed: 
Providing technical support and a comprehensive and integrated 
management approach for infrastructure upgrades at various airports and 
seaports for US-VISIT. 

Services acquired: Systems software maintenance and development 
support; 
Contract manager: CBP; 
Relationship to US-VISIT: Intra-agency agreement; 
Fiscal year: 2004; 
Contract type: Time and materials; 
Description of services provided by contracting action reviewed: 
Providing, among other things, requirements analysis, system 
development and enhancements, and maintenance in support of Increment 
2B. 

Services acquired: Air/sea exit; 
Contract manager: TSA; 
Relationship to US-VISIT: Intra-agency agreement; 
Fiscal year: 2003; 
Contract type: Firm fixed price/Time and materials; 
Description of services provided by contracting action reviewed: 
Providing self-service and attended workstations to guide nonimmigrant 
visa holders through the presentation of their travel documents and 
submission of two fingerprints each. 

Source: GAO analysis of agency data. 

[A] US-VISIT did not manage any contracts before fiscal year 2004. 

[B] In fiscal years 2004 and 2005, GSA issued two task orders under the 
same contract for similar types of work. Both of these task orders were 
selected for our review. 

[C] AERC did not issue new US-VISIT-related work in fiscal year 2004. 

[End of table] 

Contract oversight controls: To assess the program's oversight of 
program-related contracts, we used DHS guidance pertaining to intra-and 
intergovernmental contracting relationships,[Footnote 52] as well as 
practices for oversight developed by us.We met with program office 
officials to determine the extent to which the program office oversaw 
the performance of US-VISIT-related contracts and identified the 
organizations performing work in support of the program (as listed 
earlier). We met with these organizations to determine the extent to 
which the program office interacted with them in an oversight capacity. 

Financial management controls: To assess internal control processes and 
procedures in place over contract financial management, we reviewed 
authoritative guidance on contract management found in the following: 

* the FAR; 

* our Policy and Procedures Manual for Guidance of Federal Agencies, 
Title 7--Fiscal Guidance; 

* Office of Management and Budget (OMB) Revised Circular A-123, 
Management's Responsibility for Internal Control; and: 

* OMB Revised Circular A-76, Performance of Commercial Activities. 

We also reviewed DHS's performance and accountability reports for 
fiscal years 2003, 2004, and 2005, including the financial statements 
and the accompanying independent auditor's reports, and we reviewed 
other relevant audit reports issued by us and Inspectors General. We 
interviewed staff of the independent public accounting firm responsible 
for auditing ICE and the DHS bureaus for which ICE provides accounting 
services (including US-VISIT). 

We obtained the congressionally approved budgets for US-VISIT work and 
other relevant financial information. For each of the contracting 
actions selected for review, listed above, at US-VISIT, AERC, GSA, CBP, 
and TSA, we obtained copies of available invoices and related review 
and approval documentation. We reviewed the invoice documentation for 
evidence of compliance with our Standards for Internal Control in the 
Federal Government and Internal Control Management and Evaluation 
Tool.[Footnote 53]Specifically, we reviewed the invoices for evidence 
of the performance of certain control activities, including the 
following: review and approval before payment by a contracting officer, 
contracting officer's technical representative, and other cognizant 
officials; reasonableness of expenses billed (including travel) and 
their propriety in relation to US-VISIT; payment of the invoice in the 
proper amount and to the correct vendor; payment of the invoice from a 
proper funding source; and payment of the invoice within 30 days as 
specified by the Prompt Payment Act. We also reviewed the invoices for 
compliance with requirements of the specific contract provisions for 
which they were billed. We did not review invoice documentation for the 
selected contracting actions managed by ICE, because ICE did not 
provide us with invoice documentation for all requested contracts in 
time to meet fieldwork deadlines. 

We also obtained copies of invoices paid through July 2005 and 
available payment review and approval documentation on the prime 
contract from the ICE finance center. We reviewed this documentation 
for evidence of execution of internal controls over payment approval 
and processing. In addition, we performed data mining procedures on the 
list of payments from APMO for unusual or unexpected transactions. 
Based on this analysis, we chose a judgemental selection of payments 
and reviewed their related invoice and payment approval documentation. 

We interviewed agency officials involved with budgeting, financial 
management, contract oversight, and program management at the program 
office, ICE, CBP, TSA, AERC, and GSA. We obtained and reviewed DHS and 
US-VISIT policies, including: 

* the DHS Acquisition Manual; 

* US-VISIT Contract Management and Administration Plan; 

* US-VISIT Acquisition Procedures Guide (APG-14)--Procedures for 
Invoice Review and Approval; 

* DHS Management Directive 0710.1 (Reimbursable Agreements); and: 

* CBP and ICE's standard operating procedures regarding financial 
activities. 

We also interviewed representatives from the prime contractor to 
determine how they track certain cost information and invoice the 
program. In addition, we observed how requisitions and obligations are 
set up in the financial management system used by the program. 

We observed invoice processing and payment procedures at the CBP and 
ICE finance centers, the two major finance centers responsible for 
processing payments for program-related work. From the CBP finance 
center, we obtained data on expenditures for US-VISIT-related work made 
by CBP from fiscal year 2003 through fiscal year 2005. From the ICE 
finance center, which processes payments for the program office, we 
obtained a list of payments made by US-VISIT from August 2004 through 
July 2005. We did not obtain this level of detail for expenditures at 
AERC and GSA because these agencies are external to DHS; therefore we 
do not report on the reliability of expenditure reporting by either 
agency. 

From ICE's finance center, we also obtained and reviewed a list of 
Intra-governmental Payment and Collection system transactions paid by 
the US-VISIT program office to its federal trading partners through 
September 30, 2005. We requested a list of expenditures on program- 
related contracts managed by ICE; however, ICE was unable to provide a 
complete, reliable list. Officials at ICE's Debt Management Center, 
however, did provide a list of ICE's interagency agreements related to 
US-VISIT. 

In assessing data reliability, we determined that the available data 
for this engagement were not sufficiently reliable for us to conduct 
statistical sampling or to base our conclusions solely on the data 
systems used by the program and other agencies managing US-VISIT- 
related contracts. Specifically, the contracting actions managed by the 
program office and these agencies were self-reported and could not be 
independently validated. Further, recent audit reports found that the 
financial system used by the program office and ICE was unreliable, and 
because of the system, among other reasons, the auditors could not 
issue an opinion on DHS's fiscal year 2004 and 2005 financial 
statements. Our conclusions, therefore, are based primarily on 
documentary reviews of individual contracting actions and events, and 
our findings cannot be projected in dollar terms to the whole program. 

We conducted our work at: 

* DHS finance centers in Dallas, Texas and Indianapolis, Indiana; 

* CBP facilities in Washington, D.C., and Newington, Virginia; 

* ICE facilities in Washington, D.C; 

* TSA facilities in Arlington, Virginia; 

* the US-VISIT program offices in Rosslyn, Virginia; and: 

* GSA and AERC facilities in Ft. Worth, Texas. 

Our work was conducted from March 2005 through April 2006, in 
accordance with generally accepted government auditing standards. 

[End of section] 

Appendix II: Comments from the Department of Homeland Security: 

U.S. Department of Homeland Security: 
Washington, DC 20528: 

May 19, 2006: 

Randolph C. Hite: 
Director, Information Technology Architecture and Systems Issues: 
U.S. Government Accountability Office: 
Washington, D.C. 20548: 

Dear Mr. Hite: 

Thank you for the opportunity to review the draft report, Homeland 
Security: Contract Management and Oversight for Visitor and Immigrant 
Status Program Need to Be Strengthened (GAO-06-404). As with prior 
reports that your office has issued regarding US-VISIT, there are many 
areas with which we agree, and the recommendations have made US-VISIT a 
stronger program. However, as with those past reports, the Department 
of Homeland Security (DHS) has certain areas of disagreement. They 
appear in our comments, which follow. 

While we disagree with some of GAO's assessment of US-VISIT's contract 
management and oversight, we concur with the report's recommendations 
and the need for improvement. Overall, the report's findings will help 
US-VISIT to continue making its already highly successful and valuable 
contributions to the enhanced security of the United States. 

On page 6 of the draft report, GAO states: "Further, it [US-VISIT] has 
depended on the other agencies to properly manage financial matters for 
their respective contracts, and it also depended on another agency for 
its own financial management support. " 

This is a misleading statement. To declare that US-VISIT depended on 
another agency for its own financial management support without 
identifying that agency/system, and disclosing that the current 
engagement did not examine the effectiveness of that financial 
management system, implies that the scope of this report is broader 
than Congress directed. The reference to "another agency" should be 
deleted or the statement should clarify that financial management 
controls were examined and not the financial management systems 
themselves. 

Furthermore, the decision to use other agencies to manage US-VISIT 
contracts is based on the nature of the facilities and infrastructure 
services required at the ports of entry. Procurement of architectural 
and engineering services and property management services are outside 
the information technology systems scope of the core US-VISIT mission. 
Rather than establish that capability in-house, the Director of US- 
VISIT decided to utilize the existing expertise at the Architect 
Engineering Resource Center/Army Corps of Engineers (AERC) and the 
General Services Administration (GSA). 

When authority to manage facilities and infrastructure contracts was 
granted to AERC and GSA, US-VISIT also delegated to those agencies the 
authority to manage financial matters under those contracts. Each 
agency provides turnkey procurement services, including contract 
management and financial management. These two functions cannot be 
easily separated since each agency maintains systems of records for 
contracts issued and disbursements made under those contracts. 

* In Table 1 on page 15, GAO states that the purpose of the contracts 
managed for AERC is "On-site program management at ports of entry and 
economic impact assessment of US-VISIT implementation on northern and 
southern borders. " 

This statement needs clarification. The AERC provides facilities 
services for US-VISIT reporting primarily on-site. Services encompass 
program and project management, planning, and environmental studies. 
The description in the table reflects the scope of work for the two 
contracts sampled and not for the broader scope of services that AERC 
delivers under the interagency agreement. GSA provides facilities 
program and project management services at ports of entry, 
infrastructure design and construction services, and coordination of 
services between GSA personnel and US-VISIT. The table should reflect 
this. 

* On page 43, GAO states: "For CBP, a list of contracting actions 
provided by program officials included discrepancies that raised 
questions about the accuracy both of the list and of the invoiced 
amounts. First, the task order number of a 2002 contracting action 
changed during our period of review, and CBP initially reported the 
task order as two different contracting actions, one issued in 2002 and 
another issued in 2004. " 

A task order could be reported as two different contracting actions 
simply because of its two different numbering patterns. The different 
numbering patterns are due to the merging of U.S. Customs under DHS and 
not as an inconsistent error. Contract actions awarded prior to FY 2004 
were based on the U.S. Customs contract numbering system; however, by 
October 1, 2003 (FY 2004), DHS required components to utilize its 
unique procurement instrument identifiers for all contract actions. 
That is the date on which SAP Release 2, CBP's new financial system, 
implemented its procurement module. All contract actions awarded in FY 
2004 against a contract awarded prior to FY 2004 have different 
contract numbers than the originating contracts. The old contract 
numbers are referenced on the face page of applicable award documents 
signed after October 1, 2003. 

On page 45, in the section entitled "Several Payments to Contractors 
for US-VISIT Work Were Improperly Paid and Accounted for, " GAO states: 
"A duplicate payment was made on an invoice for over $3 million. APMO 
had sent an authorization for payment in full on the invoice to its 
finance center. Then, 1 month later, APMO sent another authorization 
for payment in full on the same invoice. The second payment was later 
noticed, and the contractor refunded the amount. " 

US-VISIT agrees that this invoice was submitted by the prime contractor 
once, transmitted by US-VISIT twice, paid twice, and collected once 
when the second payment was discovered. The duplicate payment was at 
least partially caused by a communications problem. APMO validated the 
invoice and sent an authorization for payment in full to its finance 
center. One month later, APMO checked on the status of the payment, and 
was told that the invoice number in question was not held in the 
finance center. It had apparently been logged into the Finance Center's 
financial management system under a slightly different control number, 
and was actually being processed. Assuming it to be lost, APMO sent 
another authorization for payment in full on the same invoice. Both 
invoices were paid. The second payment was later noticed and the 
contractor refunded the second payment. 

GAO also states: "Also at APMO, two questionable payments were made 
that arose from the overriding of controls created for the prime US- 
VISIT contract. The prime contract has been implemented through 12 task 
orders with multiple modifications that either increased funding or 
made other changes to the contract terms. To account for the 
obligations made on each task order, the program's Office of Budget and 
Finance created separate tracking codes in the financial system for 
each task order and sometimes for each modification of a task order. 
The separate tracking of each obligation is a good control for tracking 
and controlling spending against task order funds. However, APMO 
overrode this control when it instructed the finance center to pay two 
invoices-one for about $742, 000 and one for about $101, 000-out of the 
wrong account: that is, with funds for task orders other than those for 
which the invoices were billed." 

While the cause of the questionable payments is not completely clear 
from the available evidence, both transactions are almost certainly 
errors arising from processes with significant manual components, as 
opposed to deliberate control overrides, since adequate funds were 
available in the correct accounts for each case. In the case of the 
second incorrect transaction, communication could have been an issue as 
well. While APMO incorrectly directed that payment of the first invoice 
($742,000) was to be made from the account of another task order, file 
documentation indicates that the second invoice was correctly processed 
by APMO, and subsequently paid by the Finance Center from an incorrect 
account, i.e., with funds for a task order other than those billed by 
the invoice. 

* On page 46, GAO states: "The other set of overpayments, although 
small in dollar value, exemplify a significant breakdown in internal 
control. As a result, AERC overpaid the vendor by about $26,600. 
Moreover, it was the contractor, not AERC, that noticed the overpayment 
and refunded it. " 

To clarify: The vendor notified the AERC Finance Center of the 
overpayment on September 13, 2005. The US-VISIT Office of Facilities 
and Engineering independently identified a billing discrepancy on 
November 1, 2005, and requested clarification from AERC the following 
day. The billing error was detected by OFE after reviewing the AERC 
monthly report issued on October 19, 2005. Although the vendor reported 
the overpayment first, OFE did request clarification independently. 

In addition, although GAO discloses that the overpayments were small in 
value, it should perform a materiality test in accordance with 
accounting principles and make a determination whether the overpayment 
should be disclosed in a public report. 

Thank you for the opportunity to review the GAO report. We would be 
happy to answer any questions or address any information needs you or 
your staff may have. 

Sincerely, 

Signed by: 

Steven J. Pecinovsky: 
Director, Departmental GAO/IG Liaison Office: 

[End of section] 

Appendix III: Detailed Agency Evaluations: 

We evaluated the extent to which the agencies covered by our review (US-
VISIT APMO, GSA, AERC, CBP, TSA, and ICE[Footnote 54]) had established 
and implemented effective contract management and oversight practices 
for the contracting actions that we reviewed. 

Details are presented, by agency, in this appendix. Some practices are 
further divided into subpractices. The extent to which practices/ 
subpractices were judged to be established/implemented was categorized 
as one of the following: 

Filled in = established/implemented: 

Half filled in = partially established/implemented: 

Empty = not established/implemented: 

We judged whether the practice was established, partially established, 
or not established depending on whether the agency had documented 
policies and procedures addressing the practice and all, some, or none 
of the subpractices (where applicable). We judged whether a practice 
was implemented, partially implemented, or not implemented on the basis 
of documentation demonstrating that the practice and all, some, or none 
of the subpractices (where applicable) had been implemented for the 
contracting actions that we reviewed. 

We judged that an agency had "partially established" the requirement 
for a practice or subpractice if the agency relied only on the FAR 
requirement to perform this activity, but did not establish a process 
(i.e., documented procedures) for how the FAR requirement was to be 
met. 

We judged that an agency had "partially implemented" a practice or 
subpractice if it had implemented some, but not all, facets of the 
practice (including its own related requirements for that practice). 

Table 6: Evaluation of US-VISIT Acquisition and Program Management 
Office: 

Practice: Establish and maintain a plan for performing the contract 
oversight process; 
Practice components: Include a contract oversight process description; 
Requirement established: No; 
Practice Implemented: FY 2004: No; 
Practice Implemented: FY 2005: No.  

Practice: Establish and maintain a plan for performing the contract 
oversight process; 
Practice components: Include standards for work products; 
Requirement established: No; 
Practice Implemented: FY 2004: No; 
Practice Implemented: FY 2005: No.  

Practice: Establish and maintain a plan for performing the contract 
oversight process; 
Practice components: Include requirements for work products; 
Requirement established: No; 
Practice Implemented: FY 2004: No; 
Practice Implemented: FY 2005: No.  

Practice: Establish and maintain a plan for performing the contract 
oversight process; 
Practice components: : Include resources required to perform the 
process; 
Requirement established: No; 
Practice Implemented: FY 2004: No; 
Practice Implemented: FY 2005: No.   

Practice: Establish and maintain a plan for performing the contract 
oversight process; 
Practice Components: Include evaluations and reviews to be conducted 
with the contractor; 
Requirement established: No; 
Practice Implemented: FY 2004: No; 
Practice Implemented: FY 2005: No.  

Practice: Assign responsibility and authority for performing the 
contractor oversight process; 
Practice Components: Assign responsibility and authority for performing 
the specific tasks of the process. 
Requirement established: Yes; 
Practice Implemented: FY 2004: Yes; 
Practice Implemented: FY 2005: Yes.  

Practice: Train the people performing or supporting the contract 
oversight process as needed; 
Practice components: Include training requirements; 
Requirement established: Yes; 
Practice Implemented: FY 2004: Yes; 
Practice Implemented: FY 2005: Yes.   

Practice: Document the contract; 
Practice components: Include a statement of work; 
Requirement established: Yes; 
Practice Implemented: FY 2004: Yes; 
Practice Implemented: FY 2005: Yes.   

Practice: Document the contract; 
Practice components: Include a list of agreed upon deliverables; 
Requirement established: Yes; 
Practice Implemented: FY 2004: Yes; 
Practice Implemented: FY 2005: Yes. 

Practice: Document the contract; 
Practice components: Include a schedule; 
Requirement established: Yes; 
Practice Implemented: FY 2004: Yes; 
Practice Implemented: FY 2005: Yes.  

Practice: Document the contract; 
Practice components: Include a budget; 
Requirement established: Yes; 
Practice Implemented: FY 2004: Yes; 
Practice Implemented: FY 2005: Yes. 

Practice: Document the contract; 
Practice components: Include who from the project is responsible and 
authorized to make changes to the contract; 
Requirement established: N/A; 
Practice Implemented: FY 2004: Yes; 
Practice Implemented: FY 2005: Yes.  

Practice: Document the contract; 
Practice components: Include deliverable acceptance criteria; 
Requirement established: Yes; 
Practice Implemented: FY 2004: Yes; 
Practice Implemented: FY 2005: Yes.  

Practice: Document the contract; 
Practice components: Include the type and depth of oversight of the 
contractor, procedures, and evaluation criteria to be used in 
monitoring the contractor's performance; 
Requirement established: Yes; 
Practice Implemented: FY 2004: Yes; 
Practice Implemented: FY 2005: Yes. 

Practice: Document the contract; 
Practice components: Include the types of reviews that will be 
conducted with the contractor; 
Requirement established: Yes; 
Practice Implemented: FY 2004: Yes; 
Practice Implemented: FY 2005: Yes. 

Practice: Verify and accept the deliverables; 
Practice components: Define acceptance procedures; 
Requirement established: Yes; 
Practice Implemented: FY 2004: Yes; 
Practice Implemented: FY 2005: Yes.  

Practice: Verify and accept the deliverables; 
Practice components: Verify that acquired products satisfy their 
requirements; 
Requirement established: Yes; 
Practice Implemented: FY 2004: Yes; 
Practice Implemented: FY 2005: Yes. 

Practice: Verify and accept the deliverables; 
Practice components: Document the results of the acceptance review or 
test; 
Requirement established: Yes; 
Practice Implemented: FY 2004: Yes; 
Practice Implemented: FY 2005: Yes.  

Practice: Verify and accept the deliverables; 
Practice components: Agree to an action plan for work products that do 
not pass their review or test; 
Requirement established: Yes; 
Practice Implemented: FY 2004: Yes; 
Practice Implemented: FY 2005: Yes. 

Practice: Verify and accept the deliverables; 
Practice components: Identify, document, and track action items to 
closure; 
Requirement established: Yes; 
Practice Implemented: FY 2004: Yes; 
Practice Implemented: FY 2005: Yes. 

Practice: Monitor risks involving the contractor and take corrective 
actions as necessary; 
Practice components: Identify and categorize risk (for example, risk 
likelihood, risk consequence, and thresholds to trigger management 
activities); 
Requirement established: Yes; 
Practice Implemented: FY 2004: Yes; 
Practice Implemented: FY 2005: Yes. 

Practice: Monitor risks involving the contractor and take corrective 
actions as necessary; 
Practice components: Analyze risk using the assigned categories; 
Requirement established: Yes; 
Practice Implemented: FY 2004: Yes; 
Practice Implemented: FY 2005: Yes. 

Practice: Conduct technical reviews with the contractor; 
Practice components: Ensure the technical commitments are being met, 
communicated, and resolved in a timely manner; 
Requirement established: Yes; 
Practice Implemented: FY 2004: Yes; 
Practice Implemented: FY 2005: Yes.  

Practice: Conduct technical reviews with the contractor; 
Practice components: Review the contractor's technical activities and 
verify that the contractor's interpretation and implementation of the 
requirements are consistent with the project's interpretation; 
Requirement established: Yes; 
Practice Implemented: FY 2004: Yes; 
Practice Implemented: FY 2005: Yes.  

Practice: Conduct management reviews with the contractor;   
Practice components: Review critical dependencies;  
Requirement established: Yes; 
Practice Implemented: FY 2004: Yes; 
Practice Implemented: FY 2005: Yes.  

Practice: Conduct management reviews with the contractor; 
Practice components: Review project risks involving the contractor; 
Requirement established: Yes; 
Practice Implemented: FY 2004: Yes; 
Practice Implemented: FY 2005: Yes.  

Practice: Conduct management reviews with the contractor; 
Practice components: Practice components: Review schedule and budget; 
Requirement established: Yes; 
Practice Implemented: FY 2004: Yes; 
Practice Implemented: FY 2005: Yes.   

Legend: 

Filled in = Established/implemented: 

Half filled in = Partially established/implemented: 

Empty = Not established/implemented: 

Sources: Software Engineering Institute (SEI), GAO analysis of agency 
data. 

Note: The following are the services provided in the contracts 
described, by fiscal year. 

FY 2004: Program-level management: 

FY 2005: US-VISIT strategic plan development: 

[End of table] 

Table 7: Evaluation of General Services Administration: 

Practice: Establish and maintain a plan for performing the contract 
oversight process; 
Practice components: Include a contract oversight process description; 
Requirement established: No; 
Practice Implemented: FY 2002: No; 
Practice Implemented: FY 2003: No; 
Practice Implemented: FY 2004: No; 
Practice Implemented: FY 2005: No.  

Practice: Establish and maintain a plan for performing the contract 
oversight process; 
Practice components: Include standards for work products; 
Requirement established: No; 
Practice Implemented: FY 2002: No; 
Practice Implemented: FY 2003: No; 
Practice Implemented: FY 2004: No; 
Practice Implemented: FY 2005: No.  

Practice: Establish and maintain a plan for performing the contract 
oversight process; 
Practice components: Include requirements for work products; 
Requirement established: No; 
Practice Implemented: FY 2002: No; 
Practice Implemented: FY 2003: No; 
Practice Implemented: FY 2004: No; 
Practice Implemented: FY 2005: No.  

Practice: Establish and maintain a plan for performing the contract 
oversight process; 
Practice components: : Include resources required to perform the 
process; 
Requirement established: No; 
Practice Implemented: FY 2002: No; 
Practice Implemented: FY 2003: No; 
Practice Implemented: FY 2004: No; 
Practice Implemented: FY 2005: No.   

Practice: Establish and maintain a plan for performing the contract 
oversight process; 
Practice Components: Include evaluations and reviews to be conducted 
with the contractor; 
Requirement established: No; 
Practice Implemented: FY 2002: No; 
Practice Implemented: FY 2003: No; 
Practice Implemented: FY 2004: No; 
Practice Implemented: FY 2005: No.  

Practice: Assign responsibility and authority for performing the 
contractor oversight process; 
Practice Components: Assign responsibility and authority for performing 
the specific tasks of the process. 
Requirement established: Yes; 
Practice Implemented: FY 2002: Yes; 
Practice Implemented: FY 2003: Yes; 
Practice Implemented: FY 2004: Yes; 
Practice Implemented: FY 2005: Yes.  

Practice: Train the people performing or supporting the contract 
oversight process as needed; 
Practice components: Include training requirements; 
Requirement established: Yes; 
Practice Implemented: FY 2002: Yes; 
Practice Implemented: FY 2003: Yes; 
Practice Implemented: FY 2004: Yes; 
Practice Implemented: FY 2005: Yes.   

Practice: Document the contract; 
Practice components: Include a statement of work; 
Requirement established: Partially; 
Practice Implemented: FY 2002: Yes; 
Practice Implemented: FY 2003: Yes; 
Practice Implemented: FY 2004: Yes; 
Practice Implemented: FY 2005: Yes.   

Practice: Document the contract; 
Practice components: Include a list of agreed upon deliverables; 
Requirement established: Partially; 
Practice Implemented: FY 2002: No; 
Practice Implemented: FY 2003: Yes; 
Practice Implemented: FY 2004: Yes; 
Practice Implemented: FY 2005: Yes. 

Practice: Document the contract; 
Practice components: Include a schedule; 
Requirement established: Partially; 
Practice Implemented: FY 2002: Yes; 
Practice Implemented: FY 2003: Yes; 
Practice Implemented: FY 2004: Yes; 
Practice Implemented: FY 2005: Yes.  

Practice: Document the contract; 
Practice components: Include a budget; 
Requirement established: No; 
Practice Implemented: FY 2002: Yes; 
Practice Implemented: FY 2003: Yes; 
Practice Implemented: FY 2004: Yes; 
Practice Implemented: FY 2005: Yes. 

Practice: Document the contract; 
Practice components: Include who from the project is responsible and 
authorized to make changes to the contract; 
Requirement established: N/A; 
Practice Implemented: FY 2002: Yes; 
Practice Implemented: FY 2003: Yes; 
Practice Implemented: FY 2004: Yes; 
Practice Implemented: FY 2005: Yes.  

Practice: Document the contract; 
Practice components: Include deliverable acceptance criteria; 
Requirement established: Partially; 
Practice Implemented: FY 2002: Yes; 
Practice Implemented: FY 2003: Yes; 
Practice Implemented: FY 2004: Yes; 
Practice Implemented: FY 2005: Yes.  

Practice: Document the contract; 
Practice components: Include the type and depth of oversight of the 
contractor, procedures, and evaluation criteria to be used in 
monitoring the contractor's performance; 
Requirement established: Partially; 
Practice Implemented: FY 2002: Partially; 
Practice Implemented: FY 2003: Partially; 
Practice Implemented: FY 2004: Partially; 
Practice Implemented: FY 2005: Yes. 

Practice: Document the contract; 
Practice components: Include the types of reviews that will be 
conducted with the contractor; 
Requirement established: No;
Practice Implemented: FY 2002: No; 
Practice Implemented: FY 2003: Yes;  
Practice Implemented: FY 2004: Yes; 
Practice Implemented: FY 2005: No. 

Practice: Verify and accept the deliverables; 
Practice components: Define acceptance procedures; 
Requirement established: Partially; 
Practice Implemented: FY 2002: No; 
Practice Implemented: FY 2003: Partially; 
Practice Implemented: FY 2004: Partially; 
Practice Implemented: FY 2005: Partially.  

Practice: Verify and accept the deliverables; 
Practice components: Verify that acquired products satisfy their 
requirements; 
Requirement established: Partially; 
Practice Implemented: FY 2002: No; 
Practice Implemented: FY 2003: Partially; 
Practice Implemented: FY 2004: Partially; 
Practice Implemented: FY 2005: Partially. 

Practice: Verify and accept the deliverables; 
Practice components: Document the results of the acceptance review or 
test; 
Requirement established: Partially; 
Practice Implemented: FY 2002: No; 
Practice Implemented: FY 2003: Partially; 
Practice Implemented: FY 2004: Partially; 
Practice Implemented: FY 2005: Partially. 

Practice: Verify and accept the deliverables; 
Practice components: Agree to an action plan for work products that do 
not pass their review or test; 
Requirement established: No; 
Practice Implemented: FY 2002: N/A; 
Practice Implemented: FY 2003: N/A; 
Practice Implemented: FY 2004: N/A; 
Practice Implemented: FY 2005: N/A. 

Practice: Verify and accept the deliverables; 
Practice components: Identify, document, and track action items to 
closure; 
Requirement established: No; 
Practice Implemented: FY 2002: N/A; 
Practice Implemented: FY 2003: N/A; 
Practice Implemented: FY 2004: N/A; 
Practice Implemented: FY 2005: N/A. 

Practice: Monitor risks involving the contractor and take corrective 
actions as necessary; 
Practice components: Identify and categorize risk (for example, risk 
likelihood, risk consequence, and thresholds to trigger management 
activities); 
Requirement established: Partially;
Practice Implemented: FY 2002: No; 
Practice Implemented: FY 2003: No;  
Practice Implemented: FY 2004: No; 
Practice Implemented: FY 2005: No. 

Practice: Monitor risks involving the contractor and take corrective 
actions as necessary; 
Practice components: Analyze risk using the assigned categories; 
Requirement established: Partially;
Practice Implemented: FY 2002: No; 
Practice Implemented: FY 2003: No;  
Practice Implemented: FY 2004: No; 
Practice Implemented: FY 2005: No. 

Practice: Conduct technical reviews with the contractor; 
Practice components: Ensure the technical commitments are being met, 
communicated, and resolved in a timely manner; 
Requirement established: No;
Practice Implemented: FY 2002: No; 
Practice Implemented: FY 2003: Partially;  
Practice Implemented: FY 2004: Yes; 
Practice Implemented: FY 2005: No.  

Practice: Conduct technical reviews with the contractor; 
Practice components: Review the contractor's technical activities and 
verify that the contractor's interpretation and implementation of the 
requirements are consistent with the project's interpretation; 
Requirement established: No;
Practice Implemented: FY 2002: No; 
Practice Implemented: FY 2003: Partially;  
Practice Implemented: FY 2004: Yes; 
Practice Implemented: FY 2005: No.  

Practice: Conduct management reviews with the contractor;   
Practice components: Review critical dependencies;  
Requirement established: No; 
Practice Implemented: FY 2002: No; 
Practice Implemented: FY 2003: Yes; 
Practice Implemented: FY 2004: Yes; 
Practice Implemented: FY 2005: No.  

Practice: Conduct management reviews with the contractor; 
Practice components: Review project risks involving the contractor; 
Requirement established: No; 
Practice Implemented: FY 2002: No; 
Practice Implemented: FY 2003: No; 
Practice Implemented: FY 2004: No; 
Practice Implemented: FY 2005: No.  

Practice: Conduct management reviews with the contractor; 
Practice components: Practice components: Review schedule and budget; 
Requirement established: No;
Practice Implemented: FY 2002: No; 
Practice Implemented: FY 2003: Partially;  
Practice Implemented: FY 2004: Partially; 
Practice Implemented: FY 2005: No.   

Legend: 

Filled in = Established/implemented: 

Half filled in = Partially established/implemented: 

Empty = Not established/implemented: 

Sources: SEI, GAO analysis of agency data. 

Note: The following are the services provided in the contracts 
described, by fiscal year. 

FY 2002: Pre-award and post-award acquisition services: 

FY 2003: Planning and mobilization for feasibility studies: 

FY 2004: Program management of US-VISIT at ports of entry: 

FY 2005: Program management of US-VISIT at ports of entry: 

[End of Table] 

Table 8: Evaluation of Army Corps of Engineers Architect-Engineer 
Resource Center: 

Practice: Establish and maintain a plan for performing the contract 
oversight process; 
Practice components: Include a contract oversight process description; 
Requirement established: No; 
Practice Implemented: FY 2003: No; 
Practice Implemented: FY 2005: No.  

Practice: Establish and maintain a plan for performing the contract 
oversight process; 
Practice components: Include standards for work products; 
Requirement established: No; 
Practice Implemented: FY 2003: No; 
Practice Implemented: FY 2005: No.  

Practice: Establish and maintain a plan for performing the contract 
oversight process; 
Practice components: Include requirements for work products; 
Requirement established: No; 
Practice Implemented: FY 2003: No; 
Practice Implemented: FY 2005: No.  

Practice: Establish and maintain a plan for performing the contract 
oversight process; 
Practice components: : Include resources required to perform the 
process; 
Requirement established: No; 
Practice Implemented: FY 2003: No; 
Practice Implemented: FY 2005: No.   

Practice: Establish and maintain a plan for performing the contract 
oversight process; 
Practice Components: Include evaluations and reviews to be conducted 
with the contractor; 
Requirement established: No; 
Practice Implemented: FY 2003: No; 
Practice Implemented: FY 2005: No.  

Practice: Assign responsibility and authority for performing the 
contractor oversight process; 
Practice Components: Assign responsibility and authority for performing 
the specific tasks of the process. 
Requirement established: Yes; 
Practice Implemented: FY 2003: Yes; 
Practice Implemented: FY 2005: Yes.  

Practice: Train the people performing or supporting the contract 
oversight process as needed; 
Practice components: Include training requirements; 
Requirement established: Yes; 
Practice Implemented: FY 2003: Yes; 
Practice Implemented: FY 2005: Yes.   

Practice: Document the contract; 
Practice components: Include a statement of work; 
Requirement established: Partially; 
Practice Implemented: FY 2003: Yes; 
Practice Implemented: FY 2005: Yes.   

Practice: Document the contract; 
Practice components: Include a list of agreed upon deliverables; 
Requirement established: Partially; 
Practice Implemented: FY 2003: Yes; 
Practice Implemented: FY 2005: Yes. 

Practice: Document the contract; 
Practice components: Include a schedule; 
Requirement established: Partially; 
Practice Implemented: FY 2003: Yes; 
Practice Implemented: FY 2005: Yes.  

Practice: Document the contract; 
Practice components: Include a budget; 
Requirement established: No; 
Practice Implemented: FY 2003: Yes; 
Practice Implemented: FY 2005: Yes. 

Practice: Document the contract; 
Practice components: Include who from the project is responsible and 
authorized to make changes to the contract; 
Requirement established: N/A; 
Practice Implemented: FY 2003: No; 
Practice Implemented: FY 2005: Yes.  

Practice: Document the contract; 
Practice components: Include deliverable acceptance criteria; 
Requirement established: Partially; 
Practice Implemented: FY 2003: No; 
Practice Implemented: FY 2005: Yes.  

Practice: Document the contract; 
Practice components: Include the type and depth of oversight of the 
contractor, procedures, and evaluation criteria to be used in 
monitoring the contractor's performance; 
Requirement established: Partially; 
Practice Implemented: FY 2003: No; 
Practice Implemented: FY 2005: Partially. 

Practice: Document the contract; 
Practice components: Include the types of reviews that will be 
conducted with the contractor; 
Requirement established: No; 
Practice Implemented: FY 2003: No; 
Practice Implemented: FY 2005: Yes. 

Practice: Verify and accept the deliverables; 
Practice components: Define acceptance procedures; 
Requirement established: No; 
Practice Implemented: FY 2003: No; 
Practice Implemented: FY 2005: No.  

Practice: Verify and accept the deliverables; 
Practice components: Verify that acquired products satisfy their 
requirements; 
Requirement established: Partially; 
Practice Implemented: FY 2003: Partially; 
Practice Implemented: FY 2005: Partially. 

Practice: Verify and accept the deliverables; 
Practice components: Document the results of the acceptance review or 
test; 
Requirement established: Partially; 
Practice Implemented: FY 2003: Partially; 
Practice Implemented: FY 2005: Partially.  

Practice: Verify and accept the deliverables; 
Practice components: Agree to an action plan for work products that do 
not pass their review or test; 
Requirement established: No; 
Practice Implemented: FY 2003: N/A; 
Practice Implemented: FY 2005: N/A. 

Practice: Verify and accept the deliverables; 
Practice components: Identify, document, and track action items to 
closure; 
Requirement established: No; 
Practice Implemented: FY 2003: N/A; 
Practice Implemented: FY 2005: N/A. 

Practice: Monitor risks involving the contractor and take corrective 
actions as necessary; 
Practice components: Identify and categorize risk (for example, risk 
likelihood, risk consequence, and thresholds to trigger management 
activities); 
Requirement established: No; 
Practice Implemented: FY 2003: No; 
Practice Implemented: FY 2005: No. 

Practice: Monitor risks involving the contractor and take corrective 
actions as necessary; 
Practice components: Analyze risk using the assigned categories; 
Requirement established: No; 
Practice Implemented: FY 2003: No; 
Practice Implemented: FY 2005: No. 

Practice: Conduct technical reviews with the contractor; 
Practice components: Ensure the technical commitments are being met, 
communicated, and resolved in a timely manner; 
Requirement established: No; 
Practice Implemented: FY 2003: No; 
Practice Implemented: FY 2005: No.  

Practice: Conduct technical reviews with the contractor; 
Practice components: Review the contractor's technical activities and 
verify that the contractor's interpretation and implementation of the 
requirements are consistent with the project's interpretation; 
Requirement established: No; 
Practice Implemented: FY 2003: No; 
Practice Implemented: FY 2005: No. 

Practice: Conduct management reviews with the contractor;   
Practice components: Review critical dependencies;  
Requirement established: No; 
Practice Implemented: FY 2003: No; 
Practice Implemented: FY 2005: No.  

Practice: Conduct management reviews with the contractor; 
Practice components: Review project risks involving the contractor; 
Requirement established: No; 
Practice Implemented: FY 2003: No; 
Practice Implemented: FY 2005: No.  

Practice: Conduct management reviews with the contractor; 
Practice components: Review schedule and budget; 
Requirement established: No; 
Practice Implemented: FY 2003: No; 
Practice Implemented: FY 2005: No.   

Legend: 

Filled in = Established/implemented: 

Half filled in = Partially established/implemented: 

Empty = Not established/implemented: 

Sources: SEI, GAO analysis of agency data. 

Note: The following are the services provided in the contracts 
described, by fiscal year. 

FY 2003: On-site program management at ports of entry: 

FY 2005: Economic impact assessment of US-VISIT along northern and 
southern borders: 

[End of Table] 

Table 9: Evaluation of Customs and Border Protection: 

Practice: Establish and maintain a plan for performing the contract 
oversight process; 
Practice components: Include a contract oversight process description; 
Requirement established: Yes; 
Practice implemented: FY 2002: No; 
Practice Implemented: FY 2003: No; 
Practice Implemented: FY 2004: Partially.  

Practice: Establish and maintain a plan for performing the contract 
oversight process; 
Practice components: Include standards for work products; 
Requirement established: No; 
Practice implemented: FY 2002: No; 
Practice Implemented: FY 2003: No; 
Practice Implemented: FY 2004: Partially.  

Practice: Establish and maintain a plan for performing the contract 
oversight process; 
Practice components: Include requirements for work products; 
Requirement established: No; 
Practice implemented: FY 2002: No; 
Practice Implemented: FY 2003: No; 
Practice Implemented: FY 2004: Partially.  

Practice: Establish and maintain a plan for performing the contract 
oversight process; 
Practice components: : Include resources required to perform the 
process; 
Requirement established: No; 
Practice implemented: FY 2002: No; 
Practice Implemented: FY 2003: No; 
Practice Implemented: FY 2004: No.  

Practice: Establish and maintain a plan for performing the contract 
oversight process; 
Practice Components: Include evaluations and reviews to be conducted 
with the contractor; 
Requirement established: Yes; 
Practice implemented: FY 2002: No; 
Practice Implemented: FY 2003: No; 
Practice Implemented: FY 2004: Partially.  

Practice: Assign responsibility and authority for performing the 
contractor oversight process; 
Practice Components: Assign responsibility and authority for performing 
the specific tasks of the process. 
Requirement established: Yes; 
Practice implemented: FY 2002: Yes; 
Practice Implemented: FY 2003: Yes; 
Practice Implemented: FY 2004: Yes.  

Practice: Train the people performing or supporting the contract 
oversight process as needed; 
Practice components: Include training requirements; 
Requirement established: Yes; 
Practice implemented: FY 2002: No; 
Practice Implemented: FY 2003: No; 
Practice Implemented: FY 2004: Partially.   

Practice: Document the contract; 
Practice components: Include a statement of work; 
Requirement established: Yes; 
Practice implemented: FY 2002: Partially; 
Practice Implemented: FY 2003: Partially; 
Practice Implemented: FY 2004: Yes.   

Practice: Document the contract; 
Practice components: Include a list of agreed upon deliverables; 
Requirement established: No; 
Practice implemented: FY 2002: Yes; 
Practice Implemented: FY 2003: Yes; 
Practice Implemented: FY 2004: Yes. 

Practice: Document the contract; 
Practice components: Include a schedule; 
Requirement established: Yes; 
Practice implemented: FY 2002: Yes; 
Practice Implemented: FY 2003: Yes; 
Practice Implemented: FY 2004: Yes. 

Practice: Document the contract; 
Practice components: Include a budget; 
Requirement established: No; 
Practice implemented: FY 2002: Yes; 
Practice Implemented: FY 2003: Yes; 
Practice Implemented: FY 2004: Yes. 

Practice: Document the contract; 
Practice components: Include who from the project is responsible and 
authorized to make changes to the contract; 
Requirement established: N/A; 
Practice implemented: FY 2002: Yes; 
Practice Implemented: FY 2003: Yes; 
Practice Implemented: FY 2004: Yes. 

Practice: Document the contract; 
Practice components: Include deliverable acceptance criteria; 
Requirement established: Yes; 
Practice implemented: FY 2002: No; 
Practice Implemented: FY 2003: No; 
Practice Implemented: FY 2004: Yes.  

Practice: Document the contract; 
Practice components: Include the type and depth of oversight of the 
contractor, procedures, and evaluation criteria to be used in 
monitoring the contractor's performance; 
Requirement established: Partially; 
Practice implemented: FY 2002: Partially; 
Practice Implemented: FY 2003: Partially; 
Practice Implemented: FY 2004: Partially. 

Practice: Document the contract; 
Practice components: Include the types of reviews that will be 
conducted with the contractor; 
Requirement established: Yes; 
Practice implemented: FY 2002: No; 
Practice Implemented: FY 2003: No; 
Practice Implemented: FY 2004: No. 

Practice: Verify and accept the deliverables; 
Practice components: Define acceptance procedures; 
Requirement established: Yes; 
Practice implemented: FY 2002: Yes; 
Practice Implemented: FY 2003: Yes; 
Practice Implemented: FY 2004: Yes.  

Practice: Verify and accept the deliverables; 
Practice components: Verify that acquired products satisfy their 
requirements; 
Requirement established: Yes; 
Practice implemented: FY 2002: Yes; 
Practice Implemented: FY 2003: Partially; 
Practice Implemented: FY 2004: Yes. 

Practice: Verify and accept the deliverables; 
Practice components: Document the results of the acceptance review or 
test; 
Requirement established: Yes; 
Practice implemented: FY 2002: Yes; 
Practice Implemented: FY 2003: Partially; 
Practice Implemented: FY 2004: Yes.  

Practice: Verify and accept the deliverables; 
Practice components: Agree to an action plan for work products that do 
not pass their review or test; 
Requirement established: Partially; 
Practice implemented: FY 2002: No; 
Practice Implemented: FY 2003: No; 
Practice Implemented: FY 2004: No. 

Practice: Verify and accept the deliverables; 
Practice components: Identify, document, and track action items to 
closure; 
Requirement established: Partially; 
Practice implemented: FY 2002: Yes; 
Practice Implemented: FY 2003: No; 
Practice Implemented: FY 2004: No. 

Practice: Monitor risks involving the contractor and take corrective 
actions as necessary; 
Practice components: Identify and categorize risk (for example, risk 
likelihood, risk consequence, and thresholds to trigger management 
activities); 
Requirement established: Yes; 
Practice implemented: FY 2002: No; 
Practice Implemented: FY 2003: Yes; 
Practice Implemented: FY 2004: Yes. 

Practice: Monitor risks involving the contractor and take corrective 
actions as necessary; 
Practice components: Analyze risk using the assigned categories; 
Requirement established: Yes; 
Practice implemented: FY 2002: No; 
Practice Implemented: FY 2003: Yes; 
Practice Implemented: FY 2004: Yes.  

Practice: Conduct technical reviews with the contractor; 
Practice components: Ensure the technical commitments are being met, 
communicated, and resolved in a timely manner; 
Requirement established: Yes; 
Practice implemented: FY 2002: No; 
Practice Implemented: FY 2003: No; 
Practice Implemented: FY 2004: Yes.  

Practice: Conduct technical reviews with the contractor; 
Practice components: Review the contractor's technical activities and 
verify that the contractor's interpretation and implementation of the 
requirements are consistent with the project's interpretation; 
Requirement established: Yes; 
Practice implemented: FY 2002: No; 
Practice Implemented: FY 2003: No; 
Practice Implemented: FY 2004: Yes. 

Practice: Conduct management reviews with the contractor;   
Practice components: Review critical dependencies;  
Requirement established: Partially; 
Practice implemented: FY 2002: No; 
Practice Implemented: FY 2003: Yes; 
Practice Implemented: FY 2004: Yes. 

Practice: Conduct management reviews with the contractor; 
Practice components: Review project risks involving the contractor; 
Requirement established: Partially; 
Practice implemented: FY 2002: No; 
Practice Implemented: FY 2003: Yes; 
Practice Implemented: FY 2004: Yes.  

Practice: Conduct management reviews with the contractor; 
Practice components: Review schedule and budget; 
Requirement established: Partially; 
Practice implemented: FY 2002: Partially; 
Practice Implemented: FY 2003: Yes; 
Practice Implemented: FY 2004: No.   

Legend: 

Filled in = Established/implemented: 

Half filled in = Partially established/implemented: 

Empty = Not established/implemented: 

Sources: SEI, GAO analysis of agency data. 

Note: The following are the services provided in the contracts 
described, by fiscal year. 

FY 2002: Commercial recovery services: 

FY 2003: Infrastructure upgrades at ports of entry: 

FY 2004: Software maintenance and development for Increment 2B: 

[End of Table] 

Table 10: Evaluation of Transportation Security Administration: 

Practice: Establish and maintain a plan for performing the contract 
oversight process; 
Practice components: Include a contract oversight process description; 
Requirement established: Yes; 
Practice Implemented: FY 2003: No; 

Practice: Establish and maintain a plan for performing the contract 
oversight process; 
Practice components: Include standards for work products; 
Requirement established: No; 
Practice Implemented: FY 2003: No; 

Practice: Establish and maintain a plan for performing the contract 
oversight process; 
Practice components: Include requirements for work products; 
Requirement established: No; 
Practice Implemented: FY 2003: No; 

Practice: Establish and maintain a plan for performing the contract 
oversight process; 
Practice components: : Include resources required to perform the 
process; 
Requirement established: No; 
Practice Implemented: FY 2003: Partially; 

Practice: Establish and maintain a plan for performing the contract 
oversight process; 
Practice Components: Include evaluations and reviews to be conducted 
with the contractor; 
Requirement established: No; 
Practice Implemented: FY 2003: No; 

Practice: Assign responsibility and authority for performing the 
contractor oversight process; 
Practice Components: Assign responsibility and authority for performing 
the specific tasks of the process. 
Requirement established: Partially; 
Practice Implemented: FY 2003: Yes; 

Practice: Train the people performing or supporting the contract 
oversight process as needed; 
Practice components: Include training requirements; 
Requirement established: Partially; 
Practice Implemented: FY 2003: No; 

Practice: Document the contract; 
Practice components: Include a statement of work; 
Requirement established: No; 
Practice Implemented: FY 2003: No; 

Practice: Document the contract; 
Practice components: Include a list of agreed upon deliverables; 
Requirement established: No; 
Practice Implemented: FY 2003: No; 

Practice: Document the contract; 
Practice components: Include a schedule; 
Requirement established: Yes; 
Practice Implemented: FY 2003: No; 

Practice: Document the contract; 
Practice components: Include a budget; 
Requirement established: No; 
Practice Implemented: FY 2003: Yes; 

Practice: Document the contract; 
Practice components: Include who from the project is responsible and 
authorized to make changes to the contract; 
Requirement established: N/A; 
Practice Implemented: FY 2003: Yes; 

Practice: Document the contract; 
Practice components: Include deliverable acceptance criteria; 
Requirement established: No; 
Practice Implemented: FY 2003: Yes; 

Practice: Document the contract; 
Practice components: Include the type and depth of oversight of the 
contractor, procedures, and evaluation criteria to be used in 
monitoring the contractor's performance; 
Requirement established: No; 
Practice Implemented: FY 2003: No; 

Practice: Document the contract; 
Practice components: Include the types of reviews that will be 
conducted with the contractor; 
Requirement established: No; 
Practice Implemented: FY 2003: No; 

Practice: Verify and accept the deliverables; 
Practice components: Define acceptance procedures; 
Requirement established: Yes; 
Practice Implemented: FY 2003: Yes; 

Practice: Verify and accept the deliverables; 
Practice components: Verify that acquired products satisfy their 
requirements; 
Requirement established: Yes; 
Practice Implemented: FY 2003: Yes; 

Practice: Verify and accept the deliverables; 
Practice components: Document the results of the acceptance review or 
test; 
Requirement established: Yes; 
Practice Implemented: FY 2003: Yes; 

Practice: Verify and accept the deliverables; 
Practice components: Agree to an action plan for work products that do 
not pass their review or test; 
Requirement established: No; 
Practice Implemented: FY 2003: No; 

Practice: Verify and accept the deliverables; 
Practice components: Identify, document, and track action items to 
closure; 
Requirement established: No; 
Practice Implemented: FY 2003: No; 

Practice: Monitor risks involving the contractor and take corrective 
actions as necessary; 
Practice components: Identify and categorize risk (for example, risk 
likelihood, risk consequence, and thresholds to trigger management 
activities); 
Requirement established: Yes; 
Practice Implemented: FY 2003: Yes; 

Practice: Monitor risks involving the contractor and take corrective 
actions as necessary; 
Practice components: Analyze risk using the assigned categories; 
Requirement established: Yes; 
Practice Implemented: FY 2003: Partially; 

Practice: Conduct technical reviews with the contractor; 
Practice components: Ensure the technical commitments are being met, 
communicated, and resolved in a timely manner; 
Requirement established: No; 
Practice Implemented: FY 2003: No; 

Practice: Conduct technical reviews with the contractor; 
Practice components: Review the contractor's technical activities and 
verify that the contractor's interpretation and implementation of the 
requirements are consistent with the project's interpretation; 
Requirement established: No; 
Practice Implemented: FY 2003: No; 

Practice: Conduct management reviews with the contractor;   
Practice components: Review critical dependencies;  
Requirement established: No; 
Practice Implemented: FY 2003: No; 

Practice: Conduct management reviews with the contractor; 
Practice components: Review project risks involving the contractor; 
Requirement established: No; 
Practice Implemented: FY 2003: Partially; 

Practice: Conduct management reviews with the contractor; 
Practice components: Review schedule and budget; 
Requirement established: No; 
Practice Implemented: FY 2003: Yes; 

Legend: 

Filled in = Established/implemented: 

Half filled in = Partially established/implemented: 

Empty = Not established/implemented: 

Sources: SEI, GAO analysis of agency data. 

Note: The following are the services provided in the contract 
described: 

FY 2003: Air/sea exit: 

[End of table] 

Table 11: Evaluation of Immigration and Customs Enforcement: 

Practice: Establish and maintain a plan for performing the contract 
oversight process; 
Practice components: Include a contract oversight process description; 
Requirement established: Yes; 

Practice: Establish and maintain a plan for performing the contract 
oversight process; 
Practice components: Include standards for work products; 
Requirement established: No; 

Practice: Establish and maintain a plan for performing the contract 
oversight process; 
Practice components: Include requirements for work products; 
Requirement established: No; 

Practice: Establish and maintain a plan for performing the contract 
oversight process; 
Practice components: : Include resources required to perform the 
process; 
Requirement established: No; 

Practice: Establish and maintain a plan for performing the contract 
oversight process; 
Practice Components: Include evaluations and reviews to be conducted 
with the contractor; 
Requirement established: Partially; 

Practice: Assign responsibility and authority for performing the 
contractor oversight process; 
Practice Components: Assign responsibility and authority for performing 
the specific tasks of the process. 
Requirement established: Yes; 

Practice: Train the people performing or supporting the contract 
oversight process as needed; 
Practice components: Include training requirements; 
Requirement established: Yes; 

Practice: Document the contract; 
Practice components: Include a statement of work; 
Requirement established: Yes;  

Practice: Document the contract; 
Practice components: Include a list of agreed upon deliverables; 
Requirement established: No; 

Practice: Document the contract; 
Practice components: Include a schedule; 
Requirement established: No; 

Practice: Document the contract; 
Practice components: Include a budget; 
Requirement established: No; 

Practice: Document the contract; 
Practice components: Include who from the project is responsible and 
authorized to make changes to the contract; 
Requirement established: N/A; 

Practice: Document the contract; 
Practice components: Include deliverable acceptance criteria; 
Requirement established: Yes; 

Practice: Document the contract; 
Practice components: Include the type and depth of oversight of the 
contractor, procedures, and evaluation criteria to be used in 
monitoring the contractor's performance; 
Requirement established: Yes; 

Practice: Document the contract; 
Practice components: Include the types of reviews that will be 
conducted with the contractor; 
Requirement established: No; 

Practice: Verify and accept the deliverables; 
Practice components: Define acceptance procedures; 
Requirement established: Yes; 

Practice: Verify and accept the deliverables; 
Practice components: Verify that acquired products satisfy their 
requirements; 
Requirement established: Yes; 

Practice: Verify and accept the deliverables; 
Practice components: Document the results of the acceptance review or 
test; 
Requirement established: No; 

Practice: Verify and accept the deliverables; 
Practice components: Agree to an action plan for work products that do 
not pass their review or test; 
Requirement established: No; 

Practice: Verify and accept the deliverables; 
Practice components: Identify, document, and track action items to 
closure; 
Requirement established: No; 

Practice: Monitor risks involving the contractor and take corrective 
actions as necessary; 
Practice components: Identify and categorize risk (for example, risk 
likelihood, risk consequence, and thresholds to trigger management 
activities); 
Requirement established: Yes; 

Practice: Monitor risks involving the contractor and take corrective 
actions as necessary; 
Practice components: Analyze risk using the assigned categories; 
Requirement established: No; 

Practice: Conduct technical reviews with the contractor; 
Practice components: Ensure the technical commitments are being met, 
communicated, and resolved in a timely manner; 
Requirement established: Partially; 

Practice: Conduct technical reviews with the contractor; 
Practice components: Review the contractor's technical activities and 
verify that the contractor's interpretation and implementation of the 
requirements are consistent with the project's interpretation; 
Requirement established: No; 

Practice: Conduct management reviews with the contractor;   
Practice components: Review critical dependencies;  
Requirement established: No; 

Practice: Conduct management reviews with the contractor; 
Practice components: Review project risks involving the contractor; 
Requirement established: No.  

Practice: Conduct management reviews with the contractor; 
Practice components: Review schedule and budget; 
Requirement established: No.  

Legend: 

Filled in = Established/implemented: 

Half filled in = Partially established/implemented: 

Empty = Not established/implemented: 

Sources: SEI, GAO analysis of agency data. 

[End of Table] 

[End of section] 

Appendix IV: GAO Contacts and Staff Acknowledgments: 

GAO Contacts: 

Randolph C. Hite, (202) 512-3439 or hiter@gao.gov: 

McCoy Williams, (202) 512-9095 or williamsm1@gao.gov: 

Staff Acknowledgments: 

In addition to the contacts named above, the following people made key 
contributions to this report: Deborah Davis, Assistant Director; Casey 
Keplinger, Assistant Director; Sharon Byrd; Shaun Byrnes; Barbara 
Collier; Marisol Cruz; Francine Delvecchio; Neil Doherty; Heather 
Dunahoo; Dave Hinchman; James Houtz; Stephanie Lee; David Noone; Lori 
Ryza; Zakia Simpson; and Charles Youman. 

FOOTNOTES 

[1] The DHS agencies are the US-VISIT Acquisition and Program 
Management Office, US-VISIT Facilities & Engineering Management, U.S. 
Customs and Border Protection, Immigration and Customs Enforcement, and 
the Transportation Security Administration. The non-DHS agencies are 
the General Services Administration and the U.S. Army Corps of 
Engineers Architect-Engineering Resource Center. 

[2] To judgmentally select our set of contracting actions, we 
identified the DHS and non-DHS agencies that managed US-VISIT-related 
contracts and, for each agency, we selected one contracting action for 
US-VISIT-related work awarded in each fiscal year from March 1, 2002, 
through March 31, 2005. Not all organizations awarded contracting 
actions in every fiscal year covered under our review, in which case an 
action was not selected for that fiscal year for that organization. Our 
judgmental selection did not include contracting actions from one of 
the responsible organizations (DHS's Immigration and Customs 
Enforcement) because this agency did not provide requested 
documentation in time for us to include it in our analysis of 
contracting actions. 

[3] AERC is a component of the Department of Defense. 

[4] 8 U.S.C. 1365a; 6 U.S.C. 251 (transferred relevant Immigration and 
Naturalization Service functions to DHS); 8 U.S.C. 1732(b). 

[5] Over the last 3 years, we have issued five reports on the US-VISIT 
program that, among other things, identified fundamental challenges 
that the department faced in delivering promised program capabilities 
and benefits on time and within budget. For our most recent report, see 
GAO, Homeland Security: Recommendations to Improve Management of Key 
Border Security Program Need to Be Implemented, GAO-06-296 (Washington, 
D.C.: Feb. 14, 2006). 

[6] The Visa Waiver Program permits foreign nationals from designated 
countries to apply for admission to the United States for a maximum of 
90 days as nonimmigrant visitors for business or pleasure. 

[7] Radio frequency technology relies on proximity cards and card 
readers. Radio frequency devices read the information contained on the 
card when the card is passed near the device and can also be used to 
verify the identity of the cardholder. 

[8] At one port of entry, these capabilities were not fully operational 
until January 7, 2006, because of a telephone company strike that 
prevented the installation of a T-1 line. 

[9] An indefinite-delivery/indefinite-quantity contract provides for an 
indefinite quantity, within stated limits, of supplies or services 
during a fixed period of time. The government schedules deliveries or 
performance by placing orders with the contractor. 

[10] Accenture's partners include, among others, Raytheon Company, the 
Titan Corporation, and SRA International, Inc. 

[11] DHS uses inter-and intra-agency agreements (IAAs) to document 
agreements entered into between federal agencies, or major 
organizational units within an agency, which specify the goods to be 
furnished or tasks to be accomplished by one agency (the servicing 
agency) in support of the other (the requesting agency). 

[12] Ownership and management of IDENT was transferred to US-VISIT in 
2004; ownership of ADIS was transferred to US-VISIT in 2005, but 
management was transferred to CBP. 

[13] Reimbursable work authorizations are used by GSA to capture and 
bill GSA's customers for, among other things, the cost of providing 
services in space managed by GSA over and above the basic operations 
financed through rent for that space. In the case of US-VISIT, 
reimbursable work authorizations were used to reimburse services 
required in support of US-VISIT deployment efforts at the GSA-owned 
ports of entry. 

[14] IPAC is the primary method used by most federal entities to 
electronically bill and/or pay for services and supplies within the 
government. 

[15] This number was derived from information provided to us by the 
agencies, as well as analysis of provided documentation. Additionally, 
and as noted in appendix I, weaknesses in DHS's financial systems call 
into question the accuracy of these numbers. Further, this number does 
not include any obligations from ICE, as it did not report US-VISIT- 
related obligations to us in time for us to include in our analysis of 
contracting actions. 

[16] On the basis of previous audit findings, we do not consider this 
amount reliable. DHS's independent auditors determined that its IPAC 
system presented a weakness in DHS's financial management environment. 

[17] GAO, High-Risk Series: An Update, GAO-05-207 (Washington, D.C.: 
January 2005). 

[18] GAO, Homeland Security: Successes and Challenges in DHS's Efforts 
to Create an Effective Acquisition Organization, GAO-05-179 
(Washington, D.C.: Mar. 29, 2005). 

[19] GAO, Standards for Internal Control in the Federal Government, 
GAO/AIMD-00-21.3.1 (Washington, D.C.: November 1999). 

[20] OMB Circular A-123, Management's Responsibility for Internal 
Control (effective beginning with fiscal year 2006) (revised Dec. 21, 
2004). 

[21] GAO, Internal Control Management and Evaluation Tool, GAO-01-1008G 
(Washington, D.C.: August 2001). 

[22] The FAR system establishes the uniform set of policies and 
procedures for acquisition by all executive branch agencies. This 
system consists of the FAR, which is the primary document, and agency 
acquisition regulations that implement or supplement the FAR. 

[23] Carnegie Mellon University Software Engineering Institute, 
Capability Maturity Model Integration, Systems Engineering Integrated 
Product and Process Development, Continuous Representation, version 1.1 
(March 2002). 

[24] Capability Maturity Model Integration, Systems Engineering 
Integrated Product and Process Development, Continuous Representation, 
version 1.1. 

[25] An apparent exception was the schedule, which was reported as 
having a potential problem: deliverables were identified in the 
integrated master schedule as not being complete. However, US-VISIT 
reported that the deliverables were delivered on time. 

[26] DHS IAAs were previously referred to as "reimbursable agreements." 
Five of the agreements were actually reimbursable work authorizations 
for which there was no IAA. 

[27] GAO-05-207. 

[28] DHS, Reimbursable Agreements, Management Directive System, MD 
0710.1. 

[29] Air/sea exit, which was developed by TSA, collects biometric exit 
data for select foreign nationals; it is currently deployed to 14 
airports and seaports. 

[30] Capability Maturity Model Integration, Systems Engineering 
Integrated Product and Process Development, Continuous Representation, 
version 1.1. 

[31] No results are provided for ICE regarding implementation of these 
practices because we were unable to obtain contract documentation in 
time for our analysis. 

[32] The contracting officer is the person with authority to procure, 
enter into, administer, and terminate contracts and make related 
determinations and findings. The project manager is responsible for 
planning, directing, controlling, structuring, and motivating the 
project. The COTR reviews contractor performance regularly, ensures 
that contractual milestones are met and standards are being maintained, 
conducts regular inspections of contractor deliverables throughout the 
contract period, and ensures that all contract conditions and clauses 
are acted upon. 

[33] No results are provided for ICE regarding implementation of these 
practices because we were unable to obtain contract documentation in 
time for our analysis. 

[34] All of the deficiencies were level 3, which TSA defines as a 
defect that negatively impacts the environment and/or the application 
but that can be overcome by a manual workaround, by additional 
training, or by addressing the fix as part of a subsequent enhancement. 

[35] GAO, Financial Management: Department of Homeland Security Faces 
Significant Financial Management Challenges, GAO-04-774 (Washington, 
D.C.: July 19, 2004). 

[36] For the 7-month period from March 1, 2003, to September 30, 2003, 
DHS received a qualified opinion from its independent auditors on its 
consolidated balance sheet as of September 30, 2003, and the related 
statement of custodial activity for the 7 months ending September 30, 
2003. Auditors were unable to opine on the consolidated statements of 
net costs and changes in net position, combined statement of budgetary 
resources, and consolidated statement of financing. For fiscal years 
2004 and 2005, DHS's independent auditors were unable to opine on any 
of its financial statements. 

[37] DHS, Performance and Accountability Report: Fiscal Year 2005 (Nov. 
15, 2005). 

[38] Under standards issued by the American Institute of Certified 
Public Accountants, "reportable conditions" are matters coming to the 
auditors' attention relating to significant deficiencies in the design 
or operation of internal controls that, in the auditors' judgment, 
could adversely affect the department's ability to record, process, 
summarize, and report financial data consistent with the assertions of 
management in the financial statements. Material weaknesses are 
reportable conditions in which the design or operation of one or more 
of the internal control components does not reduce (to a relatively low 
level) the risk that misstatements, in amounts that would be material 
in relation to the financial statements being audited, may occur and 
not be detected in a timely period by employees in the normal course of 
performing their assigned functions. 

[39] DHS, Performance and Accountability Report: Fiscal Year 2004 (Nov. 
18, 2004), and Performance and Accountability Report: Fiscal Year 2005 
(Nov. 15, 2005). 

[40] GAO/AIMD-00-21.3.1. 

[41] GAO-01-1008G. 

[42] The $7.5 million reported as the invoiced amount is the addition 
of the invoiced amounts reported separately for the 2002 and 2004 task 
order numbers. 

[43] GAO-01-1008G. 

[44] Refund documentation did not provide evidence showing whether DHS 
officials or contractor staff noticed the overpayment. 

[45] GAO-01-1008G. 

[46] DHS, Reimbursable Agreements, Management Directive System, MD 
0710.1. 

[47] Codified at 31 U.S.C. §§ 3901-3904 and implemented at 5 C.F.R. pt 
1315. 

[48] DHS, Performance and Accountability Report: Fiscal Year 2005 (Nov. 
15, 2005). 

[49] That is, the agency had not documented these processes and 
activities and established their performance, as would be consistent 
with the best practice. 

[50] The FAR system establishes the uniform set of policies and 
procedures for acquisition by all executive branch agencies. This 
system consists of the primary FAR document and agency acquisition 
regulations that implement or supplement the FAR. 

[51] Capability Maturity Model Integration, Systems Engineering 
Integrated Product and Process Development, Continuous Representation, 
version 1.1. 

[52] DHS, Reimbursable Agreements, Management Directive System, MD 
0710.1. 

[53] GAO/AIMD-00-21.3.1; GAO-01-1008G. 

[54] No results are provided for ICE regarding implementation of best 
practices, because we were unable to obtain contract documentation in 
time for analysis. 

GAO's Mission: 

The Government Accountability Office, the investigative arm of 
Congress, exists to support Congress in meeting its constitutional 
responsibilities and to help improve the performance and accountability 
of the federal government for the American people. GAO examines the use 
of public funds; evaluates federal programs and policies; and provides 
analyses, recommendations, and other assistance to help Congress make 
informed oversight, policy, and funding decisions. GAO's commitment to 
good government is reflected in its core values of accountability, 
integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through the Internet. GAO's Web site ( www.gao.gov ) contains 
abstracts and full-text files of current reports and testimony and an 
expanding archive of older products. The Web site features a search 
engine to help you locate documents using key words and phrases. You 
can print these documents in their entirety, including charts and other 
graphics. 

Each day, GAO issues a list of newly released reports, testimony, and 
correspondence. GAO posts this list, known as "Today's Reports," on its 
Web site daily. The list contains links to the full-text document 
files. To have GAO e-mail this list to you every afternoon, go to 
www.gao.gov and select "Subscribe to e-mail alerts" under the "Order 
GAO Products" heading. 

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. Government Accountability Office 

441 G Street NW, Room LM 

Washington, D.C. 20548: 

To order by Phone: 

Voice: (202) 512-6000: 

TDD: (202) 512-2537: 

Fax: (202) 512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: www.gao.gov/fraudnet/fraudnet.htm 

E-mail: fraudnet@gao.gov 

Automated answering system: (800) 424-5454 or (202) 512-7470: 

Public Affairs: 

Jeff Nelligan, managing director, 

NelliganJ@gao.gov 

(202) 512-4800 

U.S. Government Accountability Office, 

441 G Street NW, Room 7149 

Washington, D.C. 20548: