Pennsylvania Department of Public Welfare, DAB No. 996 (1988)

DEPARTMENTAL APPEALS BOARD

Department of Health and Human Services

SUBJECT:  Pennsylvania Department
of Public Welfare

Docket Nos. 88-99 88-207
Decision No. 996

DATE:  December 5, 1988

DECISION

The Pennsylvania Department of Public Welfare (State) appealed two
determinations by the Health Care Financing Administration (HCFA/Agency)
disallowing a total of $1,903,730 in federal financial participation
(FFP) claimed by the State.  The disallowance represented the difference
between the 75 percent enhanced funding rate, the allowable rate for
operational costs of Agency-approved mechanized information systems, and
the 50 percent rate for the costs of functioning components of the
State's Client Information System (CIS).  HCFA disallowed the claims
because expenditures are only eligible for the enhanced rate of FFP
after a state's entire mechanized claims processing and information
retrieval system has been approved by the Agency.  In the case at issue,
the Agency has not yet approved the State's system.

For the reasons discussed below, we uphold the Agency's disallowance.

Background

The State's CIS is an automated eligibility determination system
designed to be used by various federally assisted programs including the
Medicaid program.  In April 1982, the State submitted to HCFA an advance
planning document (APD) for the CIS, which was approved on June 21,
1983.  Agency's brief, p.1; State's appeal file, ex.3.  It is undisputed
that the APD contemplated that CIS would become operational in stages,
and that both parties agreed that operational costs of the CIS project
would be entitled to only 50 percent FFP until the CIS was fully
operational.  State's reply brief, p. 3.  The State, however, claimed 75
percent FFP for all operational costs of certain functioning components
of the CIS that were being used by the State's previously completed and
approved Medical Assistance Management Information System (MAMIS).

State's Position

The State argued that the Agency knew and understood that the CIS
project would yield components which could and would serve as
enhancements of MAMIS even before they served as components of the
completed CIS project.  State's brief, p.3.  The State argued that while
the parties agreed that the State would not seek 75 percent FFP for the
component parts of the CIS until it was fully operational, the parties
did not agree that the State would not seek 75 percent FFP for these
components that served as enhancements to the MAMIS when and if they
became operational as part of the MAMIS.  Id.  When the component parts
of the CIS became operational and were utilized by the MAMIS, the State
claimed 75 percent FFP for the components as part of the MAMIS, an
approved system.  (The State did not, however, claim the 75 percent
within the CIS, the system in which the parts were created.)

Analysis

The issue in this appeal is whether the State should receive 75 percent
FFP for phases of its incomplete CIS which have been utilized by the
State's MAMIS, and which the State now claims as expenditures entitled
to the enhanced rate of FFP as part of MAMIS.

The applicable authority is not in dispute in this case.   Section
1903(a)(3) of the Social Security Act (Act) provides for enhanced FFP
for mechanized claims processing and information retrieval systems
approved by the Secretary.  The regulation, basically, tracks the Act.

Section 433.116(a) of 42 C.F.R. provides that:

     FFP is available at 75 percent of expenditures for operation of a
     mechanized claims processing and information retrieval system
     approved by HCFA, from the first day of the calendar quarter after
     the date the system met the conditions of initial approval, as
     established by HCFA. . . .

The State reasoned that (1) operational costs of the MAMIS are entitled
to FFP at 75 percent, (2) components of the CIS are used in the MAMIS
and (3) therefore, the State is entitled to FFP at 75 percent for costs
of operation of the CIS components used in the MAMIS.

The primary flaw in the State's reasoning is in the third step, which
disregards the distinct requirements for receiving 75 percent (or other
enhanced) FFP.  By law, enhanced FFP requires something more.  Because
it is something special, the requirements are special, and include a
specific requirement for system approval before the funding is
available.  We said in Missouri Dept. of Social Services, DGAB No. 395
(1983):

     [W]henever a State is claiming funding under the various special
     authorizations in the Act of funding beyond the regular 50% rate,
     the State has the burden of showing how it meets the special
     qualifications. p. 6.

Enhanced funding is available only where it is specifically provided for
either in statute or regulation, and only after any approval required by
the appropriate federal agency has been granted.  Just because completed
and operational parts of the uncompleted CIS are being used in the
operation of an approved system (MAMIS) does not make these parts of the
CIS themselves approved for enhanced FFP.  As we said in Alabama
Medicaid Agency, DGAB No. 880 (1987):

     The Secretary has the authority to demand more than routine
     processing and payment of claims when the states are paid more than
     the ordinary 50% FFP for administrative costs. p. 15

The State has provided nothing to show how these components of the CIS,
in and of themselves, have been specifically approved by the Agency and
therefore qualify for the enhanced rate of FFP.  The fact that HCFA may
have been aware that, as CIS components became operational, they would
be used as parts of MAMIS, is simply not equivalent to the Agency's
express approval of enhanced funding for the whole system.
Additionally, the State argued that "the parties certainly did not
intend to simply leave the developed system lying fallow until the
entire CIS project was complete."  State's reply brief, p. 4.  This
statement is true, but it does not entitle the State to FFP at a rate
greater than 50 percent.  The critical factors which the State overlooks
are that in the APD the parties intended to have phases of the CIS
system that became operational used in the MAMIS system and that FFP for
the operational costs of any or all of the CIS system would not be
eligible for FFP at 75 percent until the entire system was completed and
approved.

This is shown in the APD, which is "a written plan of action to acquire
the proposed ADP services or equipment."  45 C.F.R. 95.605.  Even the
identification by the State of excerpts from the APD in its appeal file
shows that the State always knew that part of the CIS would be
integrated with the State's MAMIS system.  The Documents List identifies
Document 2 as being "[e]xcerpts from the Advance Planning Document for
the development and operation of CIS and its integration with MAMIS".
(Emphasis added)  It is not even necessary to examine the cited pages
from the APD to determine that the State always knew that CIS would be
used with MAMIS.

The APD also clearly provided that operating costs of the CIS would
receive FFP at only 50 percent until the entire system had been
completed and was approved.  The State admits on the first page of its
argument that "[t]here is no dispute in this matter that CIS has not
been approved and certified by HCFA."  Therefore parts of CIS which are
complete and were integrated with MAMIS would similarly be entitled to
only 50 percent FFP.

The State has never alleged that it requested approval of 75 percent FFP
for the operational components of CIS utilized by the State's MAMIS.
The State could have done so, conceivably, since the record shows that
the original APD, which called for 50 percent FFP for operational costs
of all CIS components until completion of the entire system, was revised
and updated several times since 1983.  In fact, certain development
costs were later approved in an updated APD for FFP at 75 percent and 90
percent.  Agency Exhibit 2.

The Agency has undertaken an obligation to pay 75 percent for
operational costs of the CIS (or any other such system) only after it is
completed.  Nor is the fact that the APDs for the CIS project, which
provided that components of the CIS would be utilized by the MAMIS, were
approved by the Agency a determinative factor in this case.  The State
is receiving the rate of FFP that HCFA agreed to pay it until the system
is completed.  The system is not completed, and so the State is
receiving the 50 percent FFP it was supposed to receive until
completion.  Indeed, common sense would dictate that since the entire
CIS is not operational, if the operational components of the CIS were to
be used at all, they would be used with some other system.

In reviewing the applicable regulation itself, we find that the
regulation envisioned enhanced funding for expenditures relating to the
same system that the parts were created for, not just any system that is
able to utilize the parts, and then only after the entire system has
been approved.  The regulation at 42 C.F.R. 433.116(a) states that "FFP
is available at 75 percent of expenditures for operation . . . from the
first day of the calendar quarter after the date the system met the
conditions of initial approval."  (Emphasis added)  To interpret the
regulation otherwise would render it meaningless, allowing costs of
unapproved systems to circumvent the HCFA approval process simply by
having a previously approved system utilize components of the unapproved
system.

Conclusion

Based on the foregoing, we find that the State improperly claimed 75
percent FFP for the operational components of the incomplete and
unapproved CIS.  Therefore, we uphold the disallowance.


              ____________________________
     Donald F. Garrett


     ____________________________
     Norval D. (John) Settle


     ___________________________
     Alexander G. Teitz Presiding
     Board