Description
LGM-001 - C North 3rd Lift
Accelerate to complete construction of 3rd levee enlargement.
This contract provides for raising about 1.25 miles (Sta 978+00 to Sta 1044+00) of the existing C North Section of the LGM project to the authorized elevation. The average increase in height will be about 1 foot. Embankment material will be obtained from an existing adjacent borrow pit on the protected side. There are no R/W or relocation issues at this time.
|