Contract Details Vicinity Map
 


Description

LGM-001 - C North 3rd Lift
Accelerate to complete construction of 3rd levee enlargement.

This contract provides for raising about 1.25 miles (Sta 978+00 to Sta 1044+00) of the existing C North Section of the LGM project to the authorized elevation. The average increase in height will be about 1 foot. Embankment material will be obtained from an existing adjacent borrow pit on the protected side. There are no R/W or relocation issues at this time.


CONTRACT INFORMATION

LGM-001
Contract Award Q-2-2009
Contract Value $5-20M

Vicinity Map

Photos

Aerial of Site

  Close Window  
Revision Date: Wednesday, January 07, 2009