This is the accessible text file for GAO report number GAO-03-1141T 
entitled 'Kennedy Center: Improvements Needed to Strengthen the 
Construction Process' which was released on September 10, 2003.

This text file was formatted by the U.S. General Accounting Office 
(GAO) to be accessible to users with visual impairments, as part of a 
longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov.

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately.

On January 4, 2004, this document was revised to add various 
footnote references missing in the text of the body of the document.

Testimony: 

Before the Chairman, Subcommittee on Economic Development, Public 
Buildings, and Emergency Management, Committee on Transportation and 
Infrastructure, House of Representatives:

United States General Accounting Office:

GAO:

For Release on Delivery Expected at 10:00 a.m. EDT Wednesday, September 
10, 2003:

Kennedy Center:

Improvements Needed to Strengthen the Construction Process:

Statement of Mark L. Goldstein, Acting Director Physical Infrastructure 
Issues:

GAO-03-1141T:

GAO Highlights:

Highlights of GAO-03-1141T, a testimony before the Subcommittee on 
Economic Development, Public Buildings, and Emergency Management, 
Committee on Transportation and Infrastructure, House of 
Representatives 

Why GAO Did This Study:

In the mid-1990s, John F. Kennedy Center for the Performing Arts 
(Kennedy Center) officials recognized a need for additional parking 
and better site access. As a precursor to a planned project to 
construct an 8-acre plaza and two additional buildings at the site, 
the Kennedy Center is currently in the process of constructing a 
garage expansion and site improvement project. 

Because of congressional concerns over project delays and costs as 
well as challenges the Kennedy Center faces as it pursues this major 
construction effort, GAO was requested to examine (1) the garage 
expansion and site improvement project’s current costs, time frames, 
and scope compared to estimates provided to congressional stakeholders 
in 1997 and 1998 and (2) challenges the Kennedy Center faces in 
managing large construction projects. GAO issued its findings in a 
report entitled Kennedy Center: Improvements Needed to Strengthen the 
Management and Oversight of the Construction Process, GAO-03-823 
(Sept. 5, 2003). This testimony is based on that report.

What GAO Found:

As of July 2003, Kennedy Center officials estimated that the garage 
expansion and site improvement project would cost $88 million, the 
garage expansion would be completed in December 2003, the site 
improvements would be completed in summer 2004, and the project would 
include 525 parking spaces and various traffic flow improvements. 
These estimates vary substantially from estimates that Kennedy Center 
officials provided to congressional stakeholders in 1997 and 1998. At 
that time, Kennedy Center officials estimated that the project would 
cost $28 million, would be completed by August 2000, and would include 
between 900 and 1,000 parking spaces. According to Kennedy Center 
officials, the initial estimates were preliminary in nature and were 
based on some unrealistic assumptions. They acknowledged that they 
should have done a better job of informing Congress of the preliminary 
nature of the estimates and the subsequent events in the project’s 
planning and bidding phases that affected the costs, time frames, and 
scope. Kennedy Center officials said they now hold monthly meetings 
with Congress about the status of ongoing projects. 

The Kennedy Center faces certain challenges in managing large 
construction projects. Specifically, the Kennedy Center lacks (1) 
adequate policies and procedures to guide the planning and management 
of the construction process, (2) some timely construction data on 
schedules and costs for effectively overseeing construction projects 
and measuring results, and (3) key human capital resources and 
expertise that would be useful in managing the construction process. 
In its September 2003 report, GAO recommended that the Kennedy Center 
develop comprehensive project management policies and procedures, 
ensure development and use of timely data, and ensure that the needs 
for human capital expertise are met. Kennedy Center officials are now 
working to address these challenges. 

www.gao.gov/cgi-bin/getrpt?GAO-03-1141T.

To view the full product, including the scope and methodology, click 
on the link above. For more information, contact Mark L. Goldstein, 
(202) 512-2834, or goldsteinm@gao.gov.

[End of section]

Mr. Chairman, Ranking Minority Member, and Members of the Subcommittee:

We welcome the opportunity to testify before you today on our work 
related to selected aspects of the Kennedy Center's construction 
program. Specifically, my testimony will discuss the (1) differences 
between the current costs, time frames, and scope estimates of the 
garage expansion and site improvements project and the 1997 and 1998 
estimates provided to congressional stakeholders; and (2) challenges 
that the Kennedy Center faces in managing large construction projects. 
As you know, on September 5, 2003, we issued a report to you and the 
Ranking Minority Member on these issues.[Footnote 1] Therefore, my 
statement today will be short and primarily focus on the report's major 
findings and recommendations.

Let me begin by giving you a brief overview of the Kennedy Center's 
construction program and the garage expansion and site improvements 
project.

Overview:

The John F. Kennedy Center for the Performing Arts, which was 
established in 1964 as both a national cultural arts center and a 
memorial to the 35th President, opened in September 1971 as an 
independently administered bureau of the Smithsonian Institution. 
Shortly thereafter, in 1972, the Secretary of the Interior, through the 
National Park Service, assumed responsibility for maintenance and all 
other services related to the administration of the Kennedy Center 
facility. In 1994, legislation was enacted that transferred 
responsibility for operations and maintenance of the facility to the 
Kennedy Center Board of Trustees.[Footnote 2] The 1994 legislation also 
required the Kennedy Center to develop and update annually a 
comprehensive building needs plan that details the condition of the 
Kennedy Center facility and planned renovations.

The Kennedy Center receives annual appropriations to fund operations 
and maintenance as well as construction. The Kennedy Center also has 
other sources of funds to finance capital improvements in addition to 
annual appropriations, such as charitable donations and the ability to 
borrow funds. The John F. Kennedy Center Parking Improvement Act of 
1997 gave the Kennedy Center approval to design and construct the 
parking garage expansion and site improvements project.[Footnote 3] The 
garage expansion is being funded through a loan from the District of 
Columbia, which issued revenue bonds to provide the related 
funding,[Footnote 4] and the site improvements are being funded through 
annual appropriations. To assist in the construction of the garage 
expansion, the Kennedy Center has hired a construction management firm. 
For the site improvements, the Kennedy Center is using construction-
contracting services available to federal entities through a Corps of 
Engineers indefinite-delivery, indefinite-quantity contract. The Corps 
of Engineers is also providing limited management assistance to the 
project.

Garage Expansion and Site Improvements Project Estimates:

The July 2003 estimates of the garage expansion and site improvements 
project costs, time frames, and scope vary substantially from estimates 
that the Kennedy Center provided to Congress in 1997 and 1998. Current 
estimates show that the garage expansion is estimated to cost $45 
million, include 525 parking spaces, and be completed in December 2003. 
The site improvements are estimated to cost $43 million; include 
various improvements to the sidewalks, roads, and landscaping; and be 
completed in the summer of 2004. In contrast, in 1997 and 1998, Kennedy 
Center officials estimated that the garage expansion would cost $25 
million and include 900 to 1,000 parking spaces. The site improvements 
were estimated to cost $3 million and include construction of a new 
front entry driveway. At that time, Kennedy Center officials estimated 
that the garage expansion and site improvements project would be 
completed by August 2000.

According to Kennedy Center officials, the initial garage expansion 
estimates were preliminary in nature and were based on some unrealistic 
assumptions related to comparable construction projects, the failure to 
consider the need for year-round operations, and construction market 
conditions. In addition, Kennedy Center officials said that the final 
scope of the site improvements portion of the project increased 
significantly from the early estimates because they decided to 
accelerate the scheduling of some planned repairs in hopes of 
expediting the work and reducing the number of contractors, thus 
simplifying project coordination efforts. These officials acknowledged 
that they should have done a better job of informing Congress of the 
preliminary nature of the estimates and the subsequent events in the 
planning and bidding phases of the project that affected the costs, 
time frames, and scope. Kennedy Center officials said they are now 
holding monthly meetings with congressional stakeholders regarding the 
status of Kennedy Center projects.

Kennedy Center Faces Challenges in Managing its Construction Program:

In addition to problems associated with the planning phases of the 
projects, we also noted that the Kennedy Center faces a number of 
challenges in managing large construction projects. The Kennedy Center 
lacks (1) adequate policies and procedures to guide the planning and 
management of the construction process, (2) some timely construction 
data on schedules and costs for effectively overseeing construction 
projects and measuring results, and (3) key human capital resources and 
expertise that would be highly beneficial in managing the construction 
process. Let me elaborate on these three challenges.

* Policies and procedures--Although the Kennedy Center had some limited 
construction-related guidance, such as safety plans developed by the 
construction management contractor, it does not have formal, written 
project management policies and procedures to help guide and administer 
construction projects in various areas such as project organization, 
quality control and assurance, project execution, and day-to-day 
contract administration. Such policies and procedures would help ensure 
overall project oversight of all Kennedy Center construction projects, 
including the garage expansion and site improvements project.

* Timely construction data--The Kennedy Center does not always receive 
timely construction data on schedules and costs that are necessary for 
monitoring construction costs and measuring results, such as estimated 
total project costs. For example, regarding the garage expansion, the 
Kennedy Center decided to waive submission of key timely written 
project management reports from the construction manager and rely 
instead on weekly meetings. These weekly meetings are no substitute for 
timely written reports typically used in construction project 
management--reports that would have provided additional detailed 
information on schedules and costs that could have been helpful in 
project oversight.

* Human capital resources and expertise--Kennedy Center officials lack 
key human capital resources and expertise that would be highly 
beneficial in managing the construction process. For example, the 
Kennedy Center experienced significant turnover in both in-house staff 
and contractor personnel during the design stages of the garage 
expansion and site improvements project, which has contributed to 
reduced institutional knowledge of the project and has increased the 
time necessary to finalize design decisions. The President of the 
Kennedy Center told us he recognized that the Kennedy Center continues 
to lack adequate staff or expertise to manage its upcoming plaza and 
buildings project. However, Kennedy Center officials have since noted 
that they are in the process of filling key positions of director of 
capital projects and project manager, have engaged an architect and 
developer firm, and now feel that they do have sufficient staff and 
expertise.

These construction management challenges are not new to the Kennedy 
Center. In September 1995, a Kennedy Center consultant reported that 
there were no clear lines of responsibility within the existing 
facility management structure, and that job descriptions were not 
clearly defined.[Footnote 5] In addition, the consultant's report also 
noted that "An organized system should be developed for managing 
information concerning the facility operations to be used to monitor 
performance against established standards." Regarding human capital, we 
reported in 1993 that the Kennedy Center lacked a federal contracting 
officer, architects, engineers, or other professional occupations 
associated with capital projects.[Footnote 6] We concluded that the 
Kennedy Center did not have sufficient capability to effectively manage 
large-capital construction projects. Since 1993, the Kennedy Center 
added a contracting department with 5 full-time positions and an entire 
project management department consisting of 9 employees--6 full-time 
Kennedy Center employees, including 4 project managers and 2 support 
personnel, plus 3 contract employees.

Although it is difficult to determine the extent to which these 
challenges have hindered the Kennedy Center's efforts on the garage 
expansion and site improvements project to date, having adequate 
policies and procedures, timely construction data, and qualified human 
capital would help to strengthen the overall construction program and 
reduce risk. Addressing these challenges will become increasingly 
important as the Kennedy Center undertakes the larger, more costly, and 
more complex plaza and buildings project. The critical importance of 
having quality guidance, data, and human capital was highlighted by the 
National Research Council's 2000 report on federal organizations that 
contract out for construction management services to acquire and build 
facilities, such as the Kennedy Center.[Footnote 7] The council found 
that, among other things, these organizations should have (1) plans, 
policies, and procedures to define project goals and develop strategies 
and methods for achieving those goals; (2) detailed data to monitor 
progress and assess risks; and (3) in-house staff with sufficient 
management, financial, and technical skills necessary for effective 
oversight of all phases of the project. Effective policies and 
procedures would provide a road map for project managers on how best to 
estimate project costs, administer the contract, and define the roles 
and responsibilities of project staff. Timely data would allow project 
managers to effectively oversee project status and measure results to 
gauge effectiveness. Qualified human capital and expertise would 
improve efforts to control project costs, time frames, and scope.

We recognize that changes in costs, time frames, and scope are not 
unusual in construction projects. However, in the case of the Kennedy 
Center garage expansion and site improvements project, early estimates 
proved to be especially problematic and were based on unrealistic 
assumptions. Furthermore, if the Kennedy Center continues to operate 
without adequate construction polices and procedures, timely schedule 
and cost data, and qualified human capital, the success of its future 
plaza and buildings project will be at risk. Although making 
improvements in these areas is no guarantee of project success, such 
improvements would strengthen the overall construction program and 
reduce risk by providing greater effectiveness in managing and 
overseeing future projects and measuring results.

Given this, we recommended in our September 2003 report that the 
Kennedy Center:

* develop comprehensive project management policies and procedures to 
guide the construction process;

* ensure development and utilization of timely data to oversee 
construction projects;

* ensure that needs for human capital expertise are met.

Kennedy Center officials agreed with our findings and recommendations 
and acknowledged the importance of focusing on these areas. The 
officials said that they have initiated efforts to improve the overall 
construction program by (1) contacting the Federal Facilities Council 
for assistance with updating and improving construction management 
policies and procedures; (2) requesting monthly written project 
management reports; and (3) hiring additional in-house and contractor 
staff to assist in the upcoming plaza and buildings project.

Mr. Chairman, this concludes my prepared statement. I would be happy to 
respond to any questions you or the other members of the subcommittee 
may have at this time.

Contact and Acknowledgements:

For future contacts regarding this testimony, please contact Mark L. 
Goldstein at (202) 512-2834. Individuals making key contributions to 
this testimony included Terrell Dorn, Casey Brown, and David C. 
Merrill.

FOOTNOTES

[1] U.S. General Accounting Office, Kennedy Center: Improvements Needed 
to Strengthen Management and Oversight of the Construction Process, 
GAO-03-823 (Washington, D.C.: Sept. 5, 2003).

[2] The Kennedy Center Board of Trustees is composed of 36 general 
trustees who must be U.S. citizens and who are appointed by the 
President of the United States, 13 trustees designated ex-officio 
representatives of the executive branch and other government branches, 
and 10 congressional representative trustees. Each appointed trustee 
serves a term of 6 years.

[3] 20 U.S.C. 76i(b). 

[4] On December 15, 1999, the District of Columbia issued $34 million 
in District of Columbia revenue bonds and loaned the proceeds to the 
Kennedy Center for the purpose of constructing the garage expansion. 
The bonds are secured by parking revenues from the garage expansion. 
Payments of principal and interest on the bonds are insured by Ambac 
Assurance Corporation.

[5] Wiss, Janney, Elstner Associates, Inc., Trammell Crow Company, and 
Environmental Systems Design, Inc., Facility Management Assessment, 
Phase I (Washington, D.C.: September 1995).

[6] U.S. General Accounting Office, Kennedy Center: Information on the 
Capital Improvement Program, GAO/GGD-93-46 (Washington, D.C.: Feb. 9, 
1993). 

[7] National Research Council, Outsourcing Management Functions for the 
Acquisition of Federal Facilities (Washington, D.C.: National Academy 
Press, 2000). The council is the working arm of the National Academy of 
Sciences and the National Academy of Engineering, and it carries out 
studies to advise the federal government.