Upper Des Plaines River, Phase I
Project Manager: Kirksey, Felicia


Introduction:
 
Des Plaines River, IL Des Plaines River, IL Phase I) Authority: Section 101(b)(10), WRDA 1999 (PL 106-53)

Project Description:

The project has six structural features: Levee 37, Buffalo Creek Reservoir Expansion, Big Bend Lake Reservoir Expansion, Van Patten Woods Lateral storage area, North Mill Creek Dam Modification, and Levee 50. The Des Plaines River has a long history of flooding that has caused significant economic losses. The maximum flood of record, September 1986, caused an estimated $35 million in damage to 10,000 dwellings and 263 business and industrial sites, and required evacuation of 15,000 residents. In this area of 33 municipalities along 67 miles of river in two counties, severe impacts to the area transportation networks were also identified.

Costs:

  • Estimated Federal Cost:            $41,470,000
  • Estimated Non-Federal Cost:    $22,300,000
    1. Cash (3,188,000)
    2. Other (19,112,000)
  • Total Estimated Project Cost:    $63,770,000
  • Allocation thru FY 2005:           $2,961,000
  • Allocation for FY 2006:            $3,712,5001

Current Status:

Continuing plans and specifications on two construction contracts for Levee 37 (floodwall). - IDNR completed construction on second phase of Levee 50 and is preparing to award a construction contract on third phase of Levee 50. - Negotiating draft PCA (includes coordination of schedule of work on 4 remaining features). - Coordinating concept design with stakeholders for Big Bend Reservoir Expansion.


Page Last Updated: 22 June 2006
Privacy and Security Notice
Information Quality Act (IQA)