 252.234-7000 Notice of Earned Value Management System.
 252.234-7001 Earned Value Management System.


252.234-7000  Notice of Earned Value Management System.

As prescribed in 234.005-71(a), use the following provision:

 

NOTICE OF EARNED VALUE MANAGEMENT SYSTEM (MAR 1998)

 

      (a)  The offeror shall provide documentation that the cognizant Administrative Contracting Officer (ACO) has recognized that the proposed earned value management system (EVMS) complies with the EVMS criteria of DoD 5000.2-R, Mandatory Procedures for Major Defense Acquisition Programs (MDAPs) and Major Automated Information System (MAIS) Acquisition Programs, or that the proposed cost/schedule control system has been accepted by the Department of Defense.

 

      (b)  If the offeror proposes to use a system that does not meet the requirements of paragraph (a) of this provision, the offeror shall submit a comprehensive plan for compliance with the EVMS criteria.

 

              (1)  The plan shall—

 

                    (A)  Describe the EVMS the offeror intends to use in performance of the contract;

 

                    (B)  Distinguish between the offeror's existing management system and modifications proposed to meet the criteria;

 

                    (C)  Describe the management system and its application in terms of the 32 EVMS criteria;

 

                    (D)  Describe the proposed procedure for administration of the criteria as applied to subcontractors; and

 

                    (E)  Provide documentation describing the process and results of any third-party or self-evaluation of the system’s compliance with EVMS criteria.

 

              (2)  The offeror shall provide information and assistance as required by the Contracting Officer to support review of the plan.

 

              (3)  The Government will review the offeror’s plan for EVMS before contract award.

 

      (c)  Offerors shall identify the major subcontractors, or major subcontracted effort if major subcontractors have not been selected, planned for application of the criteria.  The prime contractor and the Government shall agree to subcontractors selected for application of the EVMS criteria.

 

(End of provision)

 

252.234-7001  Earned Value Management System.

As prescribed in 234.005-71(b), use the following clause:

 

EARNED VALUE MANAGEMENT SYSTEM (MAR 1998)

 

      (a)  In the performance of this contract, the Contractor shall use an earned value management system (EVMS) that has been recognized by the cognizant Administrative Contracting Officer (ACO) as complying with the criteria provided in DoD 5000.2-R, Mandatory Procedures for Major Defense Acquisition Programs (MDAPs) and Major Automated Information System (MAIS) Acquisition Programs.

 

      (b)  If, at the time of award, the Contractor’s EVMS has not been recognized by the cognizant ACO as complying with EVMS criteria (or the Contractor does not have an existing cost/schedule control system that has been accepted by the Department of Defense), the Contractor shall apply the system to the contract and shall be prepared to demonstrate to the ACO that the EVMS complies with the EVMS criteria referenced in paragraph (a) of this clause.

 

      (c)  The Government may require integrated baseline reviews.  Such reviews shall be scheduled as early as practicable and should be conducted within 180 calendar days after (1) contract award, (2) the exercise of significant contract options, or (3) the incorporation of major modifications.  The objective of the integrated baseline review is for the Government and the Contractor to jointly assess areas, such as the Contractor’s planning, to ensure complete coverage of the statement of work, logical scheduling of the work activities, adequate resourcing, and identification of inherent risks.

 

      (d)  Unless a waiver is granted by the ACO, Contractor-proposed EVMS changes require approval of the ACO prior to implementation.  The ACO shall advise the Contractor of the acceptability of such changes within 30 calendar days after receipt of the notice of proposed changes from the Contractor.  If the advance approval requirements are waived by the ACO, the Contractor shall disclose EVMS changes to the ACO at least 14 calendar days prior to the effective date of implementation.

 

      (e)  The Contractor agrees to provide access to all pertinent records and data requested by the ACO or duly authorized representative.  Access is to permit Government surveillance to ensure that the EVMS complies, and continues to comply, with the criteria referenced in paragraph (a) of this clause.

 

      (f)  The Contractor shall require the following subcontractors to comply with the requirements of this clause:

 

            (Contracting Officer to insert names of subcontractors selected for application of EVMS criteria in accordance with 252.234-7000(c).)

 

 

 

 

 

 

(End of clause)

 

 

 