[DNFSB LETTERHEAD]

January 13, 2000

Brigadier General Thomas F. Gioconda
Acting Assistant Secretary for Defense programs
Department of Energy
1000 Independence Avenue, SW
Washington, DC 20585-0104

Dear General Gioconda:

The Defense Nuclear Facilities Safety Board (Board) staff issue report, subject: W79 Dismantlement Program In-Progress Review, dated June 30, 1999, has been revised to correct information that was not available to the Board's staff at the time the report was issued. This staff issue report originally stated that two of the three workstations for high explosive dissolution had not been accepted. However, the Board has been informed that two workstations have been accepted, and the third workstation is no longer planned for use. Reference to the nonacceptance of the workstations has been removed in the enclosed revised issue report.

Sincerely,

John T. Conway
Chairman

c: Mr. Rick Glass
Mr. Mark B. Whitaker, Jr.

Enclosure

 


DEFENSE NUCLEAR FACILITIES SAFETY BOARD

Staff Issue Report - Revised (December 16, 1999)

June 30, 1999

MEMORANDUM FOR: G. W. Cunningham, Technical Director
J. K. Fortenberry, Deputy Technical Director
COPIES: Board Members
FROM: J. Deplitch
SUBJECT: W79 Dismantlement Program In-Progress Review, Revision 1

This report documents an in-progress review of the W79 Dismantlement Program conducted at the Pantex Plant, June 22-24, 1999, by members of the staff of the Defense Nuclear Facilities Safety Board (Board) J. Deplitch and M. Forsbacka and outside expert L. McGrew. The review included observation of W79 bay and cell operations; review of the authorization basis, implementation of controls, and change control; and review of potential safety issues, incidents, occurrences, and corrective actions. The staff identified no adverse safety issues.

W79 Dismantlement Program. W79 dismantlement operations began in June 1998 after more than a year of readiness reviews. The tooling developed for the W79 Dismantlement Program was originally intended to dismantle all of the W79 units in a year. The W79 dismantlement is currently scheduled to be completed in about 5 years. The disassembly and high explosive (HE) dimethylsulfoxide (DMSO) dissolution process take longer than was planned, and the resources applied to the program do not support earlier completion.


W79 Dismantlement Operations. There have been no major changes to the W79 dismantlement operations since startup. Minor procedural and tooling changes have addressed improvements to the dismantlement process and unexpected difficulties with the W79 units. The change control process in place for the W79 program appeared sufficient to preserve all controls during change implementation: