[DNFSB
LETTERHEAD]
June 18, 2004
The Honorable Spencer Abraham
Secretary of Energy
1000 Independence Avenue, SW
Washington, DC 20585-1000
Dear Secretary Abraham:
Your letter of May 3, 2004,
transmitted a revision to the Implementation Plan for the Board’s
Recommendations 94-1,
Improved
Schedule for Remediation in the Defense Nuclear Facility Complex,
and 2000-1,
Prioritization for Stabilizing Nuclear Materials. The
revision provided new commitments and milestone dates for the treatment and
removal of sludge from the K-Basins at the Hanford Site, culminating in the
removal of all sludge from the basins by April 2007.
While the new completion date in
2007 reflects a significant delay relative to earlier commitments, the Board
notes that the sludge is to be packaged and ready for shipment off site instead
of remaining untreated on site as previously planned. The Board also recognizes that managers at the
spent fuel and sludge projects at Hanford must correct several programmatic deficiencies
to ensure safe handling and packaging of spent fuel and sludge at the K-Basins. These deficiencies have been well documented
and encompass the areas of design, testing, project management, and Integrated
Safety Management. Below are excerpts
from the Fluor Hanford, Inc. report, Broader Scope Issues Summary Report, Sludge Water
System, February
26, 2004.
The Board looks forward to effective
corrective action in these areas that have caused delays in the implementation
of Recommendations 94-1 and 2000-1.
The Board would like to commend
the Department of Energy (DOE) Richland Operations Office personnel who
conducted the oversight which led to the identification of nuclear safety and
engineering deficiencies in the SWS following the suspended Operational Readiness
Review (ORR) in April 2003. Furthermore,
the Board agreed with the DOE-Headquarters decision to require an ORR rather
than a Readiness Assessment for the retrieval of North Load Out Pit sludge. On June 9, 2004, members of your staff briefed
the Board on the results of this ORR. The rigor of the ORR appropriately provided
DOE the opportunity to validate that the contractor had implemented corrective
actions for operational deficiencies exhibited last year. The Board is encouraged that DOE is committed
to ensuring that this proper oversight continues to be applied to the sludge
removal project.
The Board and its staff will
continue to provide close oversight of the spent fuel and sludge projects to
verify that the new commitments are supported by resource-loaded schedules,
improved project management, and strong Integrated Safety Management Systems.
Sincerely,
John T. Conway
Chairman
c: Mr. Keith Klein
Mr.
Mark B. Whitaker, Jr.