[DOE LETTERHEAD]
November 26, 2002
The Honorable John T. Conway
Chairman
Defense Nuclear Facilities Safety Board
625 Indiana Avenue, NW, Suite 700
Washington, D.C. 20004-2901
Dear Mr. Chairman:
The purpose of this letter is to provide
status information on two Board Recommendations as they apply to Rocky Flats.
Recommendation 94-3:
The decision has been made not to upgrade
Building 371. The upgrades under
consideration were for an interim nuclear material storage option based on
“Go/No Go” criteria in Milestone 6-5 of the Recommendation 94-3 Integrated
Program Plan. The basis for this
decision is the considerable progress the site has made in packaging nuclear
material and -shipping to Savannah River.
This closes the deferred decision delineated in our March 6, 2002,
letter.
Recommendation 00-01:
The Department committed to complete
stabilization and packaging Plutonium Metals and Oxides at the Rocky Flats
Environmental Technology Site by May 2002.
Based on expected through-put, DOE now projects that the milestone will
be completed by October 2003.
If you have any questions, please call me at
(202) 586-7709 or Mr. Paul Golan, Chief Operating Officer, at (202) 586-0738.
Sincerely,
Jessie Hill Roberson
Assistant Secretary for
Environmental Management
Enclosure
cc:
M. Whitaker, S-3.1
Justification
The January 2003 completion date for
repackaging all plutonium material will not be met due to current Plutonium
Stabilization and Packaging System (PuSPS) production rates, feed material
uncertainties, and diminishing system reliability. Improvements to increase overall production rates continue to be
implemented. To further reduce
uncertainties in the completion date, a portion of the lower purity oxides will
be blended, as required, and repackaged to be shipped to the Waste Isolation
Pilot Plant (WIPP). Repackaging of
these lower purity oxides is expected to be complete by July 2003. The remainder of the plutonium metals and
oxides will be repackaged to the 3013 standard by October 2003.
Uncertainties regarding future PuSPS
production indicate that the prior 100 containers-per-month output will be
difficult to maintain during the remainder of the packaging campaign. The following uncertainties may have an
adverse impact on future production rates.
·
Pu metal
packaging should be complete by the end of 2002. From that point, PuSPS packaging will be limited to oxide. Oxide-only packaging will be less efficient
since packaging of metal can be performed concurrently with oxide; a reduction
in packaging throughput of approximately 15 percent is expected to result.
·
Starting in
November 2002 packaging of oxide material will be limited to impure oxides
(i.e., materials containing <80%
Pu). Potential problems processing low
purity oxides include: an increase in
anomalous materials, the presence of impurities that could cause problems with
the processing equipment (e.g., stabilization furnaces, moisture measurement
equipment), and moisture measurement uncertainties caused by impurities. These problems could reduce the throughput
rate of 3013-compliant containers.
·
Thermal
Gravimetric Analysis, with Fourier Transform Infrared detector (TGA/FTIR) will
be used to measure moisture in oxide containing <80% Pu.
The ability of TGA/FTIR to function satisfactorily, on a production
basis with Rocky Flats’ materials, has not been established. Additionally, there is no alternative method
available in the event that this method does not perform in an acceptable
manner.
·
As the
processing equipment in the PuSPS ages, the downtime for maintenance and
repairs may increase.
All of these uncertainties combined indicate
that PuSPS production rate may drop below the 100 cans per month experienced
throughout most of 2002. However,
current projections indicate that 85 cans per month should be sustainable. At this rate the PuSPS should complete
packaging operations in the summer of 2003.
The October 2003 completion date is recommended to provide contingency for
delays affecting PuSPS such as density issues, the possibility that the Pu
Composites may be packaged into 3013 containers, and unanticipated downtime.
Approximately 970 kgs of low purity oxides containing
approximately 180 kgs of plutonium are to be repackaged and shipped to
WIPP. Based on crew availability and
past residue production rates, it is estimated that repackaging will be
complete by July 2003. Besides reducing
uncertainties in 3013 repackaging, repackaging the lower purity oxides to WIPP
is less costly and slightly reduces worker radiation exposure.