DEFENSE NUCLEAR FACILITIES SAFETY BOARD
July 8, 1996
MEMORANDUM FOR: | G. W. Cunningham, Technical Director | |
COPIES: | Board Members | |
FROM: | Cliff Moore | |
SUBJECT: | Trip Report - Initial Review of the Savannah River Site Consolidated Incineration Facility, June 10-12, 1996 |
The CIF has received an initial Resource Conservation and Recovery Act (RCRA) Part B permit for incineration. As a part of the permitting process, the CIF must demonstrate compliance with temperature, residence time, and emission requirements while operating at maximum loading conditions. This evolution, known as a "trial burn," is scheduled for the third week of November and will use non-radiological feed. Following successful completion of the trial burn, the CIF can begin radioactive operations.
The Board's staff noted that the change in categorization should be thoroughly reviewed in light of past and present experience. An incident at the Beta-Gamma Incinerator (BGI) resulted in sending 130 DWPF construction personnel to a medical facility because they were exposed to irritating gases after HALON was inadvertently incinerated. In addition, SRS sent improperly characterized material to a commercial incinerator in Tennessee causing the incinerator to violate its operating license conditions. Careful scrutiny of the justification for reducing the Hazard Categorization is warranted considering these past accidents and the close proximity of the CIF to other facilities.
The uncertainties involved in measuring the isotopic and curie content in each feedstream must be included in determining the total radioactive loading of the facility for comparison against specified limits. These uncertainties can be particularly large for solid waste as it is often heterogeneous and difficult to assay. Material accumulation also complicates inventory control. The radioactive constituents can collect in the ash, scrubber and quencher effluent, HEPA filters, and refractory brick. Considering the precision of the data needed for inventory control, measurement uncertainties and accumulation bring into question the ability to adhere to inventory limits imposed by the Technical Safety Requirements. For example, the fissile material inventory limit for the facility is only 624 grams of U-235 equivalent, an extremely small number requiring precise assay of both feed and discharged materials.
The reliability of the CIF inventory control program is further reduced following a full cleanout, where any material not accounted for is assumed fixed to the refractory or other equipment and the inventory is effectively reduced to zero. Not knowing the nuclide and corresponding curie contents in the CIF system makes adherence to specified material limits difficult at best.
The offgas duct work between the reheaters and stack has been sand blasted and coated with a protective polymer liner. The coating was selected for its chloride and abrasion resistance. The existing HEPA filter housings are being repaired for temporary use during the trial burn and drains have been added at the HEPA filter isolation valves to prevent water accumulation in the housings while they are off-line. However, the HEPA filters are still located at the lowest point in the offgas system and may be susceptible to collecting water if the drain system becomes plugged, which has occurred once already. Given the rapid failure of the offgas system and the fact that this system is the primary accident prevention and consequence mitigation system at the CIF, its performance should be closely monitored following facility startup.
One area of immediate concern with respect to radiological control is the ash drumming station. This station, designed for use at another facility and retrofitted for application at the CIF, exhibits poor radiological planning. At this station, an operator must place a lid on a 55- gallon drum of radioactive ash slurry, slide the drum to the concrete addition enclosure, and then attach the drum to an overhead crane to move it out of the area. Small piles of ash were observed around the station and the area will most likely be designated as a contamination area once radioactive operations commence. Given the repetitive, manual nature of the drumming operations, the high potential for direct contamination, and the attention to detail observed on other CIF systems, a more thorough ALARA review of this area is warranted.
As a result of the chronic lockout violations, all facility and construction personnel were reminded of the safety significance represented by a locked component and were informed that future lockout violations would result in termination. However, another significant lockout violation occurred at the CIF on June 28th. In this incident, a hand switch for the tertiary combustion fan was supposed to be in the "OFF" position but was found in the "AUTO" position. As with the previous incidents, this lockout had been independently verified. A potentially severe accident was prevented because the motor controller powering the fan was locked open.
During a walkthrough of the facility, the Board's staff made the following
observations: