NEPA 2003

The following is a list of ongoing and completed projects for the Alturas Field Office. The level of analysis are: 

  • CX=Categorical Exclusion-The project falls into one of several categories of minor, routine projects excluded from needing more analysis.  Each time a specific categorical exclusion is used, the required review must be prepared.  
  • EA=Environmental Assessment-An EA must be prepared for proposed actions that (1) are not exempt from NEPA, (2) have not been categorically excluded, (3) have not been covered in an existing Resource Management Plan EIS or other environmental analysis, or (4) do not normally or obviously required an EIS.  An EA may be prepared for any action at any time to assist in planning and decision making.  A Finding of No Significant Impact (FONSI) is prepared if the criteria are met.
  • EIS=Environmental Impact Statement-When a proposed action, including a proposed policy or legislative recommendation, is projected to have a significant impact on the quality of the human environment, an EIS must be prepared.  An EIS is intended to provide decision makers and the public with a complete and objective evaluation of significant environmental impacts, both beneficial and adverse, resulting from a proposed action and all reasonable alternatives.  An EIS is a major vehicle for fulfilling the substantive environmental goals set forth in NEPA.  

Comment/Appeal Period

The Field Office Manager has the discretion to determine whether or not the EA and FONSI should be made available for public review prior to making a final decision, as defined in the CEQ regulations (40 CFR 1501.4(e)(2)).  Program-specific guidance should also be consulted to determine if the EA and FONSI must be reviewed by the public prior to a decision.  The manager must notify the public, including affected State and local governments and Indian tribes, of the review period (40 CFR 1506.6).  The comment period for an EA is generally 30 days.  If a public review is determined unnecessary, the affected and interested public must be notified of the availability of the EA and the FONSI (40 CFR 1501.4(e)(1) and 1506.6).  The manager responsible for authorizing the action determines the appropriate means for notifying the public and ensuring availability based on the extent of concern and interest in the action.  Any person who is adversely affected by the decision has the right to appeal within 30 days of the signing of  the Decision Record (DR) (43CFR 4.410(a) and 43 CRF 4.411(a)).  


NEPA Number 
Type 
Project Name 
Project Description 
Project Leader 
Start Date 
Comments Due 
FONSI/ DR signed 
Appeal period over 
Comments/ Status 
CA320-
NEPA03-01 
CX 
J&D Guide Permit 
Issue guide permit for public lands for Alturas and Surprise F.O.´s 
Singleton 
9/30/02 
10/1/02 
 
N/A
Permit issued
Continuing 2002 Permit
 
CA320-
NEPA03-02 
EA 
Medussahead Research 
Application of herbicides and burning on Medussahead plots 
Dolan 
10/2/02 
10/16/02 
 
 
EA Not Completed
CA320-
NEPA03-03 
CX 
Yankee Jim Reservoir Repair Modofication 
Reservoir and modification 
Lowrey 
10/2/02 
N/A
09/09/02
N/A
Project Completed 
CA320-
NEPA03-04 
EA 
Villalobos Flat Rock Permit - 2002 
Flat Rock Sale 
Singleton 
9/1/02 
10/11/02 
11/04/02
 
Permit Issued
CA320-
NEPA03-05 
CX 
Dobe Swale Exclosure 
Exclosure Fencing 
Lowrey 
10/28/02 
N/A
10/28/02
N/A
Project Completed 
CA320-
NEPA03-06 
      EA 
Midnight Harvesting Access Road 
Road Right-of-Way 
Humm 
10/5/02 
10/30/02 
10/30/02 
12/31/02
Project Completed 
CA320-NEPA03-07 
      EA Addendum 
Yankee Jim Underburn 
Prescribed Burn 
Wheeler 
 
10/31/02 
11/06/02 
 
Project Partially Completed 
CA320-NEPA03-08 
      EA 
Rock/Meja Spring 
Exclosure Construction 
Lowrey 
11/02 
11/20/02 
11/26/03
 
Fall 2004 Construction
CA320-NEPA-09 
      EA 
East/West Spring 
Spring Development and Exclosures 
Lowrey 
11/02 
11/22/02 
11/26/02
01/10/03
Fall 2004 Construction
CA320-NEPA03-10 
      EA 
Millward Fence Extension  
Fence Construction 
Lowrey  
12/12 
01/03/03
01/05/03
2/19/03
Summer 2004 Construction
CA320-NEPA03-11 
EA 
South Graves Permit Renewal 
Permit Renewal 
Lowrey 
12/13 
02/04/03
02/06/03
03/23/03
10 Year Permit Issued
CA320-NEPA03-12
 
 
EA
 
Modoc Gulch Permit Renewal
Permit Renewal
Lowrey
01/23/03
02/06/03
02/22/03
4/08/03
10 Year Permit Issued
CA320-NEPA03-13
EA
 
Big Tablelands Permit Renewal
Permit Renewal
Lowrey
01/30/03
01/10/03
02/22/03
04/08/03
10 Year Permit Issued
CA320-NEPA03-14
EA
 
North Red Rock Lake
Permit Renewal
Lowrey
02/06/03
02/18/03
02/20/03
04/06/03
10 Year Permit Issued
CA320-NEPA03-15
EA
 
Cold Springs South McDonald
Permit Renewal
Butow
01/09/03
03/24/03
04/17/03
06/01/03
Signed and Completed
CA320-NEPA03-16
EA
 
Bloody Point
Permit Renewal
Lowrey
03/03/03
03/24/03
04/01/03
05/16/03
10 Year Permit Issued
CA320-NEPA03-17
CX
 
Dorris Dump
 
Dump Cleanup
Prisco
03/07/03
03/10/03
03/12/03
N/A
Project Completed
CA320-NEPA03-18
EA
 
North Ash AMP and Permit Renewal
Permit Renewal and AMP
Butow
3/03/03
4/11/03
 
 
EA Not Completed
CA320-NEPA03-19
EA
 
South Graves JUOC Removal
Juniper Removal Projects
Lowrey
3/03/03
6/09/03
06/16/03
08/07/03
Project Not Completed
CA320-NEPA03-20
EA
 
Ash Creek Fence Phase 1
Fence Construction
Butow
3/03/03
4/12/03
4/16/03
8/23/03
Project Completed, Permittee Construction
CA320-NEPA03-21
EA
 
Nelson Corral Permit
Permit Renewal
Butow
3/03/03
4/18/03
 
 
EA Protested, Awaiting Final Decision
CA320-NEPA03-22
EA
 
Widow Peak ROW
Road Improvement
Humm
04/21/03
5/23/03
06/03
07/25/03
ROW Granted
CA320-NEPA03-23
CX
 
Bear Spring Fence Reconstruct
Exclosure
Singleton
4/21/03
5/27/03
05/28/03
N/A
Project Completed
CA320-NEPA03-24
EA
 
Dixie Valley, Bald Mountain
Permit Renewal
Lowrey
5/9/03
06/23/03
07/17/03
09/07/03
10 Year Permit Issued
CA320-NEPA03-25
EA
 
Tule Mountain
Permit Renewal
Lowrey
 
 
 
 
Pending Authorization Adjustment
CA320-NEPA03-26
EA
 
Roberts Reservoir
Permit Renewal
Lowrey
5/30/03
07/14/03
07/17/03
09/07/03
10 Year Permit Issued
CA320-NEPA03-27
EA
 
Tule Mountain Juniper Removal
Juniper Removal
Lowrey
4/03
6/30/03
07/13/03
08/27/03
Project Not Completed
CA320-NEPA03-28
CX
 
North Spring Exclosure
Exclosure
Schmidt
6/03
6/3/03
6/3/03
N/A
Project Completed
CA320-NEPA03-29
EA
 
Curley Spring Exclosure
Exclosure
Foster-Curley
6/5/03
07/07/03
07/08/03
08/22/03
2004 Construction
CA320-NEPA03-30 
Addendum to EA Ca-320-NEPA-02-01
 
JOB Spring Road Construction 
Juniper Cut & Access Road 
Butow 
6/23/03 
 
 
 
2004 Construction 
CA320-NEPA03-31 
EA
 
N. Ash Valley Pasture 1 Fence 
Fence Construction 
Butow 
6/26/03 
7/1/03 
7/2/03 
8/23/03 
 
CA320-NEPA03-32 
CX
 
King-Francis Road ROW 
Right-of-Way 
Humm 
8/27/03 
N/A 
8/28/03 
N/A 
ROW Granted  
CA320-NEPA03-33 
EA
 
Beaver Creek Riparian Fence 
Riparian Protection Fence 
Dolan 
8/13/03 
9/2/03 
 
 
EA Not Completed 
CA320-NEPA03-34 
CX
 
Yankee Jim Fence Removal & Juniper Cut 
Fence Removal and Juniper Cut 
Lowrey 
9/15/03 
N/A 
10/20/03 
N/A 
Project Implemented 10/20/03 
CA320-NEPA03-35 
EA
 
Red Rock Wild Horse Gather 
Wild Horse Gather 
Butow 
9/1/03 
9/19/03 
9/19/03 
11/3/03 
Gather Completed