February 11, 2005
Mr. Paul M. Golan
Acting Assistant Secretary for
Environmental Management
U.S. Department of Energy
1000 Independence Avenue, SW
Washington, DC 20585-0113
Dear Mr. Golan:
As
accelerated
deactivation and decommissioning (D&D) work is performed at the Department
of Energy’s (DOE) defense nuclear facilities, continued vigilance must be maintained
to ensure that an inadvertent criticality accident does not occur.
Enclosed is a report detailing
observations made by members of the staff of the Defense Nuclear Facilities
Safety Board (Board) concerning criticality safety issues at the Plutonium Finishing
Plant at the Hanford Site. Two recent
assay errors involving kilogram quantities of plutonium have occurred. The amount of plutonium involved is sufficient
to result in a criticality accident under abnormal conditions. The root causes of these errors appear to be a
lack of trained personnel and inadequate criticality safety procedures. These same deficiencies were identified by DOE
during reviews and assessments conducted in 2003, prior to the start of D&D
work in the Plutonium Finishing Plant. DOE also noted in its 2003 assessment that the
Fluor Hanford Senior Nuclear Criticality Safety Committee had been disbanded,
and that there was no evidence of a corporate strategy for criticality safety
as facilities transition from production work to D&D. Effective corrective actions are needed to
ensure that an inadvertent criticality accident is prevented.
On a broader scale, the fact
that appropriate DOE criticality experts identified these issues in 2003, but
were unable to ensure they were addressed, indicates that DOE’s Nuclear Criticality
Safety Program is not yet performing at an adequate level. DOE did not fully recognize the seriousness of
the problems or appreciate the potential for criticality accidents. As a
result DOE failed to ensure that the contractor had adequate trained personnel
and adequate criticality safety procedures for the D&D work.
Therefore, pursuant to 42 U.S.C.
§ 2286b(d), the Board requests a
briefing within 60 days of receipt of this letter that addresses the corrective
actions being taken in response to the recent assay errors and the related
issues discussed in the enclosed report.
Sincerely,
John T. Conway
Chairman
c: Mr. Keith A. Klein
Mr.
David H. Crandall
Mr.
Mark B. Whitaker, Jr.
Enclosure
DEFENSE
NUCLEAR FACILITIES SAFETY BOARD
Staff
Issue Report
December
28, 2004
MEMORANDUM FOR: J. K. Fortenberry, Technical Director
COPIES: Board Members
FROM: W. Yeniscavich
SUBJECT: Nuclear Criticality Safety
Issues at the Plutonium Finishing Plant
Purpose. This report documents criticality safety issues identified
by members of the staff of the Defense Nuclear Facilities Safety Board (Board)
during a visit to the Plutonium Finishing Plant (PFP) at the Hanford Site on
October 5 and 6, 2004. The report also
includes information obtained in subsequent discussions with personnel from the
Department of Energy’s Richland Operations Office (DOE-RL) and Fluor Hanford,
and during a review of documents received after the site visit. Members of the Board’s staff involved in this
review were W. Yeniscavich, J. Roarty, L. Zull, H. Massie, and D. Grover.
Background. The removal of the bulk plutonium inventory from the
processing equipment in PFP was completed in February 2004, and plant workers
have initiated deactivation and decommissioning (D&D) activities. There are 232 gloveboxes and hoods and other
areas that contain plutonium holdup.
DOE Review of Nondestructive Assay (NDA) Program―In August 2003, DOE-RL, assisted
by Facility Operations Support (EH-24), performed a review of the NDA program
at PFP. The main purpose of the review
was to determine the adequacy of the program to support the upcoming D&D
mission. The review revealed that the
NDA program and its associated infrastructure, including such aspects as
staffing, equipment availability, training programs, organization, and specific
measurement methods and techniques, were not adequate to support planned
D&D activities at PFP.
The report documenting the
August 2003 review noted that improvements were needed in training NDA
operators to understand the specific factors that affect measurements; that PFP
did not have a stand-alone, documented NDA program such as that implemented at
the Rocky Flats Environmental Technology Site during D&D activities; and
that there was no nationally recognized senior scientist on the NDA staff at
PFP. Specific areas requiring
improvement were not called deficiencies, but were treated as suggestions and
called “opportunities for improvement.”
DOE Review of Nuclear
Criticality Safety Program―In October 2003, personnel from DOE’s Office of Safety and
Engineering (EM-5) performed an assessment of the nuclear criticality safety
program at Fluor Hanford facilities. The
assessment focused on PFP because this facility had reported the majority of criticality
nonconformances. The assessment report noted
that the Nuclear Criticality Safety Program was well documented and
comprehensive, but the report also contained several observations and recommendations
for the contractor to review and identify appropriate corrective actions. The report reiterated the finding of the
August 2003 NDA review that NDA operators needed training on NDA techniques. In addition, the report noted that the Fluor
Hanford Senior Nuclear Criticality Safety Committee had been disbanded, and
that a corporate strategy was not evident for maintaining criticality safety
while transitioning from operations to D&D.
Plutonium Mass Errors in
Glovebox HA-9A. Plutonium holdup on the interior
walls and floors of a glovebox is determined by NDA. Plutonium holdup inside equipment within a glovebox
is also usually determined by NDA. PFP
analysts stated that in some cases, shielding by equipment prevents accurate
NDA measurements of holdup in the equipment. The alternative is to develop an engineering
estimate of holdup.
In May 2004, NDA measurements
were made and the fissile mass holdup in glovebox HA-9A was calculated. The glovebox was reassayed in September 2004,
and it was discovered that the May calculations for fissile mass were too low
by a factor of approximately three. When
these assays were performed, the detector was shielded with a 1/4-inch lead
disc to improve the detector’s performance. In the May calculations, however, the
correction factor for the lead disc was not included in the assay calculation,
resulting in the low assay results. The
May data and calculations were reviewed by a second and then by a third NDA
scientist without the error being detected.
A second error in the same
glovebox was discovered by PFP personnel on October 6,
2004. The engineering estimate of plutonium mass
within equipment in the glovebox was not provided to the group responsible for
tracking glovebox inventories. As a
result, the plutonium mass for glovebox HA-9A was under-recorded. The plutonium holdup in the equipment was not included
in the NDA measurements because attenuation caused by the density of the
equipment would have led to inaccurate results. Instead, an engineering estimate of plutonium
holdup in the equipment was developed. The estimate of plutonium holdup in equipment
is normally provided along with the letter providing the NDA results. In this case, the estimated plutonium holdup
in the equipment was not attached to the NDA results letter, and as a result,
the plutonium holdup in the equipment was not included in the glovebox
inventory.
Contractor’s Identification
of Apparent Causes. Contractor personnel reviewed
the deficiencies related to glovebox HA-9A and developed the following list of
apparent causes:
–
The
option for including lead shielding in the calculation was not selected.
–
The
two reviewers did not catch the error.
–
There
was time pressure to complete a large workload.
–
The
NDA results letter provided for inventory management did not include the holdup
in equipment, and no one recognized that the data were missing.
–
The
glovebox inventory tracking process did not have a formal method for including
data not acquired by the NDA.
Contractor’s Corrective
Actions. Contractor personnel developed a
list of 18 suggested
corrective actions. Many are short-term
immediate actions, such as suspending work and correcting immediate errors. The longer-term corrective actions include
hiring additional NDA personnel and implementing a formal checklist for
processing and reviewing NDA data. To
address the glovebox inventory error, contractor analysts proposed creating a
process to prevent a recurrence, the details of which remain to be developed.
DOE-RL personnel noted that the
NDA review process needs to be more rigorous, and that PFP has undergone a
significant loss of experienced personnel. DOE-RL managers believe it would have been
apparent to experienced operations personnel, based on process knowledge, that
the NDA calculation for glovebox HA-9A was in error. No individual with process experience was
involved in the review of the new NDA data; thus, the data were accepted without
question.
Issues To Be Addressed. Based on the information obtained during this review, the Board’s
staff has identified the following issues associated with the criticality
safety program at PFP: