July 29, 2005
The Honorable A. J. Eggenberger
Chairman, Defense Nuclear
Facilities
Safety Board
625 Indiana Avenue, NW
Washington, D.C. 20004
Dear Mr. Chairman:
Enclosed is the Department of
Energy’s (DOE) Action Plan, “Lessons Learned from the Columbia Space Shuttle
Accident and Davis-Besse Reactor Pressure-Vessel Head Corrosion Event.” This Plan fulfills Commitment 17
in the Department’s Implementation Plan for Recommendation 2004-1. The Plan was developed with input from
applicable DOE Program Secretarial Offices and several field organizations. The Office of Corporate Performance Assurance
is responsible for coordinating the Department’s implementation of this Plan
and keeping me appraised of implementation progress.
If you have any questions,
please contact Mr. Frank Russo, Deputy Assistant Secretary, Office of Corporate
Performance Assessment, at (301) 903-8008.