[US LETTERHEAD]
March 4, 2002
The Honorable John T. Conway
Chairman
Defense Nuclear Facilities Safety Board
625 Indiana Avenue, N.W., Suite 700
Washington, DC 20004
Dear Mr. Chairman:
The following is provided in response to your October 15, 2001, letter, concerning integrated
safety management issues for the Department of Energy (DOE) Oak Ridge Operations Office
(OR) and its Environmental Management (EM) contractor, Bechtel Jacobs Company (BJC). The
Department regrets the lateness of our response.
The Department recognizes and takes full ownership for its safety management issues and as its
highest priority, has been focused on establishing a basis for continued operations required to
maintain limited activities in a safe condition and for implementation of compensatory measures
and controls. The Department recognizes that some of the improvements required are associated
with adopting a new, more rigorous culture related to nuclear safety and contractor management
and, as such, will take longer than has been anticipated. This response identifies recent actions
taken by DOE to improve the nuclear safety posture under the Oak Ridge Operations Office and
the Bechtel Jacobs Company. This response does not, however, include a comprehensive
corrective action plan. Because of recent management reassignments and anticipated program
restructuring, new expectations are being established that will impact the final corrective action
plan. Additionally, I believe the assessment of root causes has not been fully addressed to my
satisfaction. Rather than further delay a response to the Board, this letter should be viewed as an
interim status report with the commitment to provide the Board with periodic briefings and/or
status reports to assist your understanding and evaluation of our progress.
Following are some of the key actions taken since the receipt of your letter:
- On October 15, 2001, the DOE Assistant Secretary for Environmental
Management (EM) rescinded all delegations of authority, previously delegated to
the Oak Ridge Operations Office. EM issued new authorities on November 20,
2001, retaining the approval for the authorization basis for all Category 3 and
higher nuclear facilities within the EM program.
- The OR Manager formally revoked Integrated Safety Management (ISM) system
verifications for both OR and BJC on November 1, 2001. The Department is
identifying ISM deficiencies and flaws in the process used during the initial
certification and assessing root causes for this area. DOE believes strongly that
continued work is needed to support long-term and lasting gains. Consequently,
our integrated corrective action plan will identify near and longer term
improvement actions. But clearly, the OR/BJC feedback and continuous
improvement mechanisms were not operative and headquarters/field managers did
not effectively assess leading indicators. In addition, Oak Ridge's limited use of
external reviewers may have contributed to a lack of objectivity during the
previous ISM implementation
- An independent DOE headquarters review, led by Mr. Dae Chung of the
Department's National Nuclear Security Administration (NNSA), completed an
assessment of Safety Basis Authorization and Approval Basis for Oak Ridge
Operations Office and the Bechtel Jacobs Company in January 2002. This review
was comprehensive and identified many deficiencies in the area of nuclear safety
management processes. This report is included herein and we offer to brief the
Board on its results.
- Regarding the adequacy of the safety bases for nuclear facilities under the Oak
Ridge Operations Office, in early analysis DOE acknowledges that a fully
compliant Authorization Bases (AB) program for OR and its contractors against
l0CFR830 is at least 12 months away. Consequently, we must rely upon
compensatory measures to support continued safe nuclear operations. To support
such a position the Department recently completed a management review of safety
requirements, existing safety documentation, while also assessing a review of the
adequacy of those controls for individual facility operated under the BJC contract,
including those at Paducah and Portsmouth. As a result many activities were
suspended or curtailed and compensatory measures and controls were
implemented. Currently, a team of highly qualified nuclear safety experts is
conducting safety-basis walk-downs and presenting their results to a Senior OR
review panel for validation of conclusions. The panel has either accepted the
existing implementation and controls or recommended additional compensatory
measures where appropriate. The results from this effort will form the basis for
the OR Manager to accept a defined minimum safe posture for the BJC Category
2 and 3 nuclear facilities. A final report is being prepared and will be forwarded
to the Board by March 15, 2002.
- On February 14, 2002, the Assistant Manager for EM approved the Technical
Safety Requirements (TSR) for the East Tennessee Technology Park - Radiation
Criticality Accident Alarm System. This approval resolved the criticality alarm
system deficiencies and also provided a one-time extension to the Limiting
Conditions of Operations for Building K-29. Both of these approvals were
provided contingent upon completion of the contractor's implementation plans
and the DOE verification prior to resumption of operations.
- The Oak Ridge Operations Office and BJC are completing a comprehensive
review of the Work Smart Standards set for the BJC contract against the 109
orders of interest. The result of this review is the identification of 25 directives
that are applicable to the work scope currently performed by BJC, but were not
previously and directly included in the contract. Of these 25 directives, the
requirements for 14 directives are included through contract equivalencies, such
as prime contract clauses and/or ISMS descriptions in the BJC contract. Because
these requirements are being substantively met, OR plans to modify the BJC
contract using a Type 1 change control process or directed change. Of the
remaining directives, OR requested incorporation of four directives into the BJC
contract on January 28, 2002, [DOE 5480.19, 5480.20A, 420.1 Change 3 (Section
4.2 Fire Protection) and DOE STD 1120.98]. A letter from BJC with a revised
WSS set incorporating these four directives was submitted on February 28, 2002.
The review also identified one directive, 10 CFR 830 Part B, that is required by
regulation and for which BJC has submitted an implementation plan to OR.
Finally, six directives contain requirements that are not included in the current
BJC contract (DOE Orders 425.1, 433.1, 460.1, 460.2, 5400.1, 420.1, and
5480.4). A rough order magnitude cost assessment has been prepared for
implementation. The analysis and cost associated with implementation of these
six directives is expected to represent a Type II change revision or bilateral
agreement with the contractor and will be evaluated using ORO O 250, Chapter
V. If a Type II revision process is required DOE and BJC line managers, subject
matter experts and workers will evaluate the issues and recommend contract
modifications.
In addition to the above, the Office of Environmental Management performed an
independent evaluation of the adequacy of the BJC contract to properly manage
performance for the given statement of work. Mr. Michael Weis, EM, performed
this review during February 2002 and found the contract to be adequate, but
offered a number of recommendations related to contract management practice
improvements. His report is being completed and will be made available to the
Board by March 15, 2002. The Office of Environmental Management will
perform a verification of the OR/BJC WSS set review when the final report is
issued.
- The Department agrees with the Board that our technical competencies to support
management of nuclear operations for both our federal and contractor ranks need
strengthening. The Oak Ridge Operations Office is reviewing its responsibilities
in its Functions Responsibilities and Authorities Manual against required
technical competencies to identify gaps. The Oak Ridge Operations Office
expects to mitigate these deficiencies in technical competency through details of
Federal and contractor individuals as well as staff augmentation. As a
compensatory measure both OR and BJC are adding qualified, but temporary,
personnel from sites such as Savannah River and Rocky Flats to support ongoing
operations and corrective actions. The OR Manager appointed a Senior Facility
Representative for major facilities to provide additional technical support to the
OR Assistant Manager for Environmental Management. The Bechtel Jacobs
Company augmented its contract team with several qualified safety basis
professionals from BJC subcontractors, other Bechtel or Jacobs' sites, and from
their respective corporate offices. Additionally, progress is being made toward
obtaining additional full-time resources for both OR and BJC. For example, OR
hired a nuclear criticality safety engineer, who began work in February 2002 and
BJC hired a senior nuclear safety specialist with both DOE and Nuclear
Regulatory Commission experience who also reported in February 2002.
We continue to assess the effectiveness of our management and our technical competencies, both
within the Federal and contractor ranks. Recognizing that measurable and fundamental change is
necessary, the Department expects to announce modifications in the reporting relationships
between headquarters and the field as well as changes in our respective management teams. We
will continue to keep you informed of our progress in addressing the concerns at Oak Ridge
Operations Office and Bechtel Jacobs Company. The Oak Ridge Operations Office will forward
an integrated corrective action plan to the Board by April 19, 2002.
We are prepared to brief the Board at your convenience on our progress to date. If you have
further questions, please contact me on 202-586-7700.
Sincerely,
Robert G. Card
Enclosure