[DNFSB
LETTERHEAD]
September 10, 2004
The Honorable Linton Brooks
Administrator
National Nuclear Security
Administration
U.S. Department of Energy
1000 Independence Avenue, SW
Washington, DC 20585-0701
Dear Ambassador Brooks:
The Defense Nuclear Facilities
Safety Board (Board) received a letter dated August 9, 2004, from the National
Nuclear Security Administration (NNSA) requesting a second 90-day extension for
a report requested by the Board on conduct of engineering at Los Alamos
National Laboratory (LANL). �On January
27, 2004, the Board requested a report that would:
The Board also stated that the
latter two items should identify actions to implement the needed changes in a
timely manner.
In its first request for an
extension, NNSA reported some progress toward enhancing conduct of engineering
work for facility work, but stated that a significant effort was still required
to develop a program and an implementation plan for nonfacility work, such as research,
development, demonstration, testing, and production. �The August 9, 2004, letter from NNSA
requesting a second 90-day extension noted that the laboratory director had
ordered a suspension of most activities at LANL, and stated that the
development of a resource-loaded implementation plan is tied to the resumption
process.
It is clear from briefings to
the Board on July 14 and August 19, 2004, that significant effort remains to
finalize the implementation plans, particularly for the application of engineering
practices to nonfacility work. �While the
Board agrees to the requested extension, NNSA should
ensure that the report is timely and includes detailed, resource-loaded implementation
plans and schedules fully addressing all three items listed above.
Sincerely,
John T. Conway
Chairman
c: ��Mr. Mark B. Whitaker, Jr.
Mr.
Edwin L. Wilmot