Initiative to Improve Recreational Boating on
Lake Barkley
| |
The purpose of the Project Management Plan (PMP)
is to clearly define primary focus areas (or goals) and high
priority issues.
PMP Management: The
Project Delivery Team (PDT) will develop the PMP for
approval. This is a living document and as new information
is obtained or conditions change, edits may be made.
Approval must be obtained for any significant amendments to the
PMP. Significant changes are defined as follows:
|
Any modification to the PMP that increases costs
|
|
Any Extension of the completion schedule for an item of work
|
|
Any assignment of work to Federal or state agencies not in
current budget
|
DRAFT PMP in
pdf format
Requests for Revision to Guide Curve:
On February 25, 2005, U.S. Congressman Ed Whitfield requested
the Corps evaluate possible adjustments to keep summer water
levels higher by extending "summer pool" through July 15.
The request could not be immediately implemented through a
Categorical Exclusion due to significant comments from wildlife
agencies regarding impacts to vegetation, aquatic resources and
waterfowl.
|
|
|