This is the accessible text file for GAO report number GAO-08-1148T 
entitled 'Secure Border Initiative: DHS Needs to Address Significant 
Risks in Delivering Key Technology Investment' which was released on 
September 10, 2008.

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Testimony: 

Before the Committee on Homeland Security, House of Representatives: 

United States Government Accountability Office: 
GAO: 

For Release on Delivery: 
Expected at 10:00 a.m. EDT:
Wednesday, September 10, 2008: 

Secure Border Initiative: 

DHS Needs to Address Significant Risks in Delivering Key Technology 
Investment: 

Statement of Randolph C. Hite, Director: Information Technology 
Architecture and System Issues: 

GAO-08-1148T: 

GAO Highlights: 

Highlights of GAO-08-1148T, a testimony before the Committee on 
Homeland Security, House of Representatives. 

Why GAO Did This Study: 

The Department of Homeland Security’s (DHS) Secure Border Initiative 
(SBI) is a multiyear, multibillion-dollar program to secure the 
nation’s borders through, among other things, new technology, increased 
staffing, and new fencing and barriers. The technology component of 
SBI, which is known as SBInet, involves the acquisition, development, 
integration, and deployment of surveillance systems and command, 
control, communications, and intelligence technologies. 

GAO was asked to testify on its draft report, which assesses DHS’s 
efforts to (1) define the scope, timing, and life cycle management 
approach for planned SBInet capabilities and (2) manage SBInet 
requirements and testing activities. In preparing the draft report, GAO 
reviewed key program documentation, including guidance, plans, and 
requirements and testing documentation; interviewed program officials; 
analyzed a random probability sample of system requirements; and 
observed operations of the initial SBInet project. 

What GAO Found: 

Important aspects of SBInet remain ambiguous and in a continued state 
of flux, making it unclear and uncertain what technology capabilities 
will be delivered and when, where, and how they will be delivered. For 
example, the scope and timing of planned SBInet deployments and 
capabilities have continued to be delayed without becoming more 
specific. Further, the program office does not have an approved 
integrated master schedule to guide the execution of the program, and 
the nature and timing of planned activities has continued to change. 
This schedule-related risk is exacerbated by the continuous change in, 
and the absence of a clear definition of, the approach that is being 
used to define, develop, acquire, test, and deploy SBInet. 

SBInet requirements have not been effectively defined and managed. 
While the program office recently issued guidance that is consistent 
with recognized leading practices, this guidance was not finalized 
until February 2008, and thus was not used in performing a number of 
important requirements-related activities. In the absence of this 
guidance, the program’s efforts have been mixed. For example, while the 
program has taken steps to include users in developing high-level 
requirements, several requirements definition and management 
limitations exist. These include a lack of proper alignment (i.e., 
traceability) among the different levels of requirements, as evidenced 
by GAO’s analysis of a random probability sample of requirements, which 
revealed large percentages that were not traceable backward to higher 
level requirements, or forward to more detailed system design 
specifications and verification methods. 

SBInet testing has also not been effectively managed. While a test 
management strategy was drafted in May 2008, it has not been finalized 
and approved, and it does not contain, among other things, a high-level 
master schedule of SBInet test activities, metrics for measuring 
testing progress, and a clear definition of testing roles and 
responsibilities. Further, the program office has not tested the 
individual system components to be deployed to the initial deployment 
locations, even though the contractor initiated testing of these 
components with other system components and subsystems in June 2008. 

In light of these circumstances, our soon to be issued report contains 
eight recommendations to the department aimed at reassessing its 
approach to and plans for the program, including its associated 
exposure to cost, schedule and performance risks, and disclosing these 
risks and alternative courses of action to DHS and congressional 
decision makers. The recommendations also provide for correcting the 
weaknesses surrounding the program’s unclear and constantly changing 
commitments and its life cycle management approach and processes, as 
well as implementing key requirements development and management and 
testing practices. 

To view the full product, including the scope and methodology, click on 
[hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-08-1148T]. For more 
information, contact Randolph C. Hite at (202) 512-3439 or 
hiter@gao.gov. 

[End of section] 

Mr. Chairman and Members of the Committee: 

I appreciate the opportunity to participate in today's hearing on the 
Department of Homeland Security's (DHS) Secure Border Initiative (SBI). 
SBI is a multiyear, multibillion-dollar program to secure the nation's 
borders through enhanced use of surveillance technologies, increased 
staffing levels, improved infrastructure, and increased domestic 
enforcement of immigration laws. One component of SBI, known as SBInet, 
is focused on the acquisition and deployment of surveillance and 
command, control, communications, and intelligence technologies. This 
technology component is managed by the SBInet System Program Office 
within U.S. Customs and Border Protection (CBP). 

My statement summarizes our draft report on the department's efforts to 
define the scope, timing, and life cycle management approach for 
planned SBInet capabilities, as well as its efforts to manage SBInet 
requirements and testing activities. This report is based on a review 
of key program-related guidance, plans, and requirements and testing 
documentation, as well as our analysis of a random probability sample 
of system requirements, and our observations of operations of the 
initial SBInet project. In comments on a draft of this report, DHS 
stated that the report was factually sound, and it agreed with seven of 
eight recommendations and partially disagreed with the remaining 
recommendation. The department also stated that it is working to 
address our recommendations and resolve the management and operational 
challenges that the report identifies as expeditiously as possible. We 
plan to issue our final report on September 22, 2008. Both the report 
and this statement are based on work that we performed in accordance 
with generally accepted government auditing standards. Those standards 
require that we plan and perform the audit to obtain sufficient, 
appropriate evidence to provide a reasonable basis for our findings and 
conclusions based on our audit objectives. We believe that the evidence 
obtained provides a reasonable basis for our findings and conclusions 
based on our audit objectives. 

Summary: 

Important aspects of SBInet remain ambiguous and in a continued state 
of flux, making it unclear and uncertain what technology capabilities 
will be delivered and when, where, and how they will be delivered. For 
example, the scope and timing of planned SBInet deployments and 
capabilities have continued to change since the program began and 
remain unclear. Further, the program office does not have an approved 
integrated master schedule to guide the execution of the program and 
the nature and timing of planned activities have continued to change. 
This schedule-related risk is exacerbated by the continuous change in, 
and the absence of a clear definition of, the life cycle management 
approach that is being used to define, develop, acquire, test, and 
deploy SBInet. 

Further, SBInet requirements have not been effectively defined and 
managed. While the program office recently issued guidance that does a 
good job of defining key practices for effectively developing and 
managing requirements, the guidance was developed after several 
important activities had been completed. In the absence of this 
guidance, the program has not effectively performed key requirements 
definition and management practices, such as ensuring that different 
levels of requirements are properly aligned. 

Finally, SBInet testing has not been effectively managed. While a test 
management strategy was drafted in May 2008, it has not been finalized 
and approved, and it does not contain, among other things, a high-level 
master schedule of SBInet test activities and a clear definition of 
testing roles and responsibilities. Further, the program office has not 
tested the individual system components to be deployed to the initial 
deployment locations, even though the contractor initiated testing of 
these components with other system components and subsystems in June 
2008. 

Collectively, the above limitations in the scope and timing of SBInet's 
to-be-deployed capabilities, and the ambiguity surrounding the schedule 
and approach for accomplishing these deployments, as well as the 
weaknesses in requirements development and management and in test 
management, introduce considerable risks to the program. As such, it is 
imperative that the department immediately re-evaluate its plans and 
approach in relation to the status of the system and related 
development, acquisition, and testing activities. Our soon to be issued 
report contains recommendations to accomplish these things. Until DHS 
implements them, the chances that the system will require expensive and 
time-consuming rework, and that it will not meet user needs and perform 
as intended, will increase. 

Today we are also providing a statement for this committee that 
provides observations on SBInet tactical infrastructure (e.g., fencing) 
and the status of human capital and staffing efforts[Footnote 1].: 

Background: 

CBP's SBI program is to leverage technology, tactical 
infrastructure,[Footnote 2] and people to allow CBP agents to gain 
control of the nation's borders. Within SBI, SBInet is the program for 
acquiring, developing, integrating, and deploying an appropriate mix of 
surveillance technologies and command, control, communications, and 
intelligence (C3I) technologies. 

The surveillance technologies are to include a variety of sensor 
systems aimed at improving CBP's ability to detect, identify, classify, 
and track items of interest along the borders. Unattended ground 
sensors are to be used to detect heat and vibrations associated with 
foot traffic and metal associated with vehicles. Radars mounted on 
fixed and mobile towers are to detect movement, and cameras on fixed 
and mobile towers are to be used to identify, classify, and track items 
of interest detected by the ground sensors and the radars. Aerial 
assets are also to be used to provide video and infrared imaging to 
enhance tracking of targets. 

The C3I technologies are to include software and hardware to produce a 
Common Operating Picture (COP)--a uniform presentation of activities 
within specific areas along the border. The sensors, radars, and 
cameras are to gather information along the border, and the system is 
to transmit this information to the COP terminals located in command 
centers and agent vehicles, assembling this information to provide CBP 
agents with border situational awareness. 

SBInet Life Cycle Management Approach: 

A system life cycle management approach typically consists of a series 
of phases, milestone reviews, and related processes to guide the 
acquisition, development, deployment, and operation and maintenance of 
a system. The phases, reviews, and processes cover such important life 
cycle activities as requirements development and management, design, 
software development, and testing. 

In general, SBInet surveillance systems are to be acquired through the 
purchase of commercially available products, while the COP systems 
involve development of new, customized systems and software. Together, 
both categories are to form a deployable increment of SBInet 
capabilities, which the program office refers to as a "block." Each 
block is to include a release or version of the COP. The border area 
that receives a given block is referred to as a "project." 

Among the key processes provided for in the SBInet system life cycle 
management approach are processes for developing and managing 
requirements and for managing testing activities. SBInet requirements 
are to consist of a hierarchy of six types of requirements, with the 
high-level operational requirements at the top. These high-level 
requirements are to be decomposed into lower-level, more detailed 
system, component, design, software, and project requirements. SBInet 
testing consists of a sequence of tests that are intended first to 
verify that individual system parts meet specified requirements, and 
then verify that these combined parts perform as intended as an 
integrated and operational system. Having a decomposed hierarchy of 
requirements and an incremental approach to testing are both 
characteristics of complex information technology (IT) projects. 

Limited Definition of SBInet Deployments, Capabilities, Schedule, and 
Life Cycle Management Process Increases Program's Exposure to Risk: 

Important aspects of SBInet--the scope, schedule, and development and 
deployment approach--remain ambiguous and in a continued state of flux, 
making it unclear and uncertain what technology capabilities will be 
delivered and when, where, and how they will be delivered. For example, 
the scope and timing of planned SBInet deployments and capabilities 
have continued to change since the program began, and remain unclear. 
Further, the approach that is being used to define, develop, acquire, 
test, and deploy SBInet is similarly unclear and has continued to 
change. The absence of clarity and stability in these key aspects of 
SBInet introduces considerable program risks, hampers DHS's ability to 
measure program progress, and impairs the ability of Congress to 
oversee the program and hold DHS accountable for program results. 

Scope and Timing of Planned Deployments and Capabilities Are Not Clear 
and Stable: 

The scope and timing of planned SBInet deployments and capabilities 
have not been clearly established, but rather have continued to change 
since the program began. Specifically, as of December 2006, the SBInet 
System Program Office planned to deploy an "initial" set of 
capabilities along the entire southwest border by late 2008 and a 
"full" set of operational capabilities along the southern and northern 
borders (a total of about 6,000 miles) by late 2009. 

Since then, however, the program office has modified its plans multiple 
times. As of March 2008, it planned to deploy SBInet capabilities to 
just three out of nine sectors along the southwest border--Tucson 
Sector by 2009, Yuma Sector by 2010, and El Paso Sector by 2011. 
According to program officials, no deployment dates had been 
established for the remainder of the southwest or northern borders. 

At the same time, the SBInet System Program Office committed to 
deploying Block 1 technologies to two locations within the Tucson 
Sector by the end of 2008, known as Tucson 1 and Ajo 1. However, as of 
late July 2008, program officials reported that the deployment schedule 
for these two sites has been modified, and they will not be operational 
until "sometime" in 2009. The slippages in the dates for the first two 
Tucson deployments, according to a program official, will, in turn, 
delay subsequent Tucson deployments, although revised dates for these 
subsequent deployments have not been set. 

In addition, the current Block 1 design does not provide key 
capabilities that are in requirements documents and were anticipated to 
be part of the Block 1 deployments to Tucson 1 and Ajo 1. For example, 
the first deployments of Block 1 will not be capable of providing COP 
information to the agent vehicles. Without clearly establishing program 
commitments, such as capabilities to be deployed and when and where 
they are to be deployed, program progress cannot be measured and 
responsible parties cannot be held accountable. 

Program Schedule Is Unsettled: 

Another key aspect of successfully managing large programs like SBInet 
is having a schedule that defines the sequence and timing of key 
activities and events and is realistic, achievable, and minimizes 
program risks. However, the timing and sequencing of the work, 
activities, and events that need to occur to meet existing program 
commitments are also unclear. Specifically, the program office does not 
yet have an approved integrated master schedule to guide the execution 
of SBInet. Moreover, our assimilation of available information from 
multiple program sources indicates that the schedule has continued to 
change. Program officials attributed these schedule changes to the lack 
of a satisfactory system-level design, turnover in the contractor's 
workforce, including three different program managers and three 
different lead system engineers, and attrition in the SBInet Program 
Office, including turnover in the SBInet Program Manager position. 
Without stability and certainty in the program's schedule, program cost 
and schedule risks increase, and meaningful measurement and oversight 
of program status and progress cannot occur, in turn limiting 
accountability for results. 

SBInet Life Cycle Management Approach Has Not Been Clearly Defined and 
Has Continued to Change: 

System quality and performance are in large part governed by the 
approach and processes followed in developing and acquiring the system. 
The approach and processes should be fully documented so that they can 
be understood and properly implemented by those responsible for doing 
so, thus increasing the chances of delivering promised system 
capabilities and benefits on time and within budget. 

The life cycle management approach and processes being used by the 
SBInet System Program Office to manage the definition, design, 
development, testing, and deployment of system capabilities has not 
been fully and clearly documented. Rather, what is defined in various 
program documents is limited and not fully consistent across these 
documents. For example, officials have stated that they are using the 
draft Systems Engineering Plan, dated February 2008, to guide the 
design, development, and deployment of system capabilities, and the 
draft Test and Evaluation Master Plan, dated May 2008, to guide the 
testing process, but both of these documents appear to lack sufficient 
information to clearly guide system activities. For example, the 
Systems Engineering Plan includes a diagram of the engineering process, 
but the steps of the process and the gate reviews are not defined or 
described in the text of the document. Further, statements by program 
officials responsible for system development and testing activities, as 
well as briefing materials and diagrams that these officials provided, 
did not add sufficient clarity to describe a well-defined life cycle 
management approach. 

Program officials told us that both the government and contractor staff 
understand the SBInet life cycle management approach and related 
engineering processes through the combination of the draft Systems 
Engineering Plan and government-contractor interactions during design 
meetings. Nevertheless, they acknowledged that the approach and 
processes are not well documented, citing a lack of sufficient staff to 
both document the processes and oversee the system's design, 
development, testing, and deployment. They also told us that they are 
adding new people to the program office with different acquisition 
backgrounds, and they are still learning about, evolving, and improving 
the approach and processes. The lack of definition and stability in the 
approach and related processes being used to define, design, develop, 
acquire, test, and deploy SBInet introduces considerable risk that both 
the program officials and contractor staff will not understand what 
needs to be done when, and that the system will not meet operational 
needs and perform as intended. 

Limitations of SBInet Requirements Development and Management Efforts 
Increase Program Risk: 

DHS has not effectively defined and managed SBInet requirements. While 
the program office recently issued guidance that is consistent with 
recognized leading practices,[Footnote 3] this guidance was not 
finalized until February 2008, and thus was not used in performing a 
number of key requirements-related activities. In the absence of well- 
defined guidance, the program's efforts to effectively define and 
manage requirements have been mixed. For example, the program has taken 
credible steps to include users in the definition of requirements. 
However, several requirements definition and management limitations 
exist. 

Program Office Has Taken Steps to Involve Users in Developing High- 
Level Requirements: 

One of the leading practices associated with effective requirements 
development and management is engaging system users early and 
continuously. In developing the operational requirements, the System 
Program Office involved SBInet users in a manner consistent with 
leading practices. Specifically, it conducted requirements-gathering 
workshops from October 2006 through April 2007 to ascertain the needs 
of Border Patrol agents and established work groups in September 2007 
to solicit input from both the Office of Air and Marine Operations and 
the Office of Field Operations. Further, the program office is 
developing the COP technology in a way that allows end users to be 
directly involved in software development activities, which permits 
solutions to be tailored to their needs.[Footnote 4] Such efforts 
increase the chances of developing a system that will successfully meet 
those needs. 

Not All Levels of Requirements Have Been Adequately Baselined: 

The creation of a requirements baseline establishes a set of 
requirements that have been formally reviewed and agreed on, and thus 
serve as the basis for further development or delivery. According to 
SBInet program officials, the SBInet Requirements Development and 
Management Plan, and leading practices, requirements should be 
baselined before key system design activities begin in order to inform, 
guide, and constrain the system's design. 

While many SBInet requirements have been baselined, two types have not 
yet been baselined. According to the System Program Office, the 
operational requirements, system requirements, and various system 
component requirements have been baselined. However, as of July 2008, 
the program office had not baselined its COP software requirements and 
its project-level requirements for the Tucson Sector, which includes 
Tucson 1 and Ajo 1. According to program officials the COP requirements 
have not been baselined because certain interface requirements[Footnote 
5] had not yet been completely identified and defined. Despite the 
absence of baselined COP and project-level requirements, the program 
office has proceeded with development, integration, and testing 
activities for the Block 1 capabilities to be delivered to Tucson 1 and 
Ajo l. As a result, it faces an increased risk of deploying systems 
that do not align well with requirements, and thus may require 
subsequent rework. 

SBInet Requirements Have Not Been Sufficiently Aligned: 

Another leading practice associated with developing and managing 
requirements is maintaining bidirectional traceability from high-level 
operational requirements through detailed low-level requirements to 
test cases. The SBInet Requirements Development and Management Plan 
recognizes the importance of traceability, and the SBInet System 
Program Office established detailed guidance[Footnote 6] for populating 
and maintaining a requirements database for maintaining linkages among 
requirement levels and test verification methods. 

To provide for requirements traceability, the prime contractor 
established such a requirements management database. However, the 
reliability of the database is questionable. We attempted to trace 
requirements in the version of this database that the program office 
received in March 2008, and were unable to trace large percentages of 
component requirements to either higher-level or lower-level 
requirements. For example, an estimated 76 percent (with a 95 percent 
degree of confidence of being between 64 and 86 percent) of the 
component requirements that we randomly sampled could not be traced to 
the system requirements and then to the operational requirements. In 
addition, an estimated 20 percent (with a 95 percent degree of 
confidence of being between 11 and 33 percent) of the component 
requirements in our sample failed to trace to a verification method. 
Without ensuring that requirements are fully traceable, the program 
office does not have a sufficient basis for knowing that the scope of 
the contractor's design, development, and testing efforts will produce 
a system solution that meets operational needs and performs as 
intended. 

Limitations in Key SBInet Testing and Test Management Activities 
Increase Program Risk: 

To be effectively managed, testing should be planned and conducted in a 
structured and disciplined fashion. This includes having an overarching 
test plan or strategy and testing individual system components to 
ensure that they satisfy requirements prior to integrating them into 
the overall system. This test management plan should define the 
schedule of high-level test activities in sufficient detail to allow 
for more detailed test planning and execution to occur, define metrics 
to track test progress and report and address results, and define the 
roles and responsibilities of the various groups responsible for 
different levels of testing. 

However, the SBInet program office is not effectively managing its 
testing activities. Specifically, the SBInet Test and Evaluation Master 
Plan, which documents the program's test strategy and is being used to 
manage system testing, has yet to be approved by the SBInet Acting 
Program Manager, even though testing activities began in June 2008. 
Moreover, the plan is not complete. In particular, it does not (1) 
contain an accurate and up-to-date test schedule, (2) identify any 
metrics for measuring testing progress, and (3) clearly define and 
completely describe the roles and responsibilities of various entities 
that are involved in system testing. 

Further, the SBInet System Program Office has not performed individual 
component testing as part of integration testing. As of July 2008, 
agency officials reported that component-level tests had not been 
completed and were not scheduled to occur. Instead, officials stated 
that Block 1 components were evaluated based on what they described as 
"informal tests" (i.e., contractor observations of cameras and radar 
suites in operation at a National Guard facility in the Tucson Sector) 
and stated that the contractors' self-certification that the components 
meet functional and performance requirements was acceptable. Program 
officials acknowledged that this approach did not verify whether the 
individual components in fact met requirements. 

Without effectively managing testing activities, the chances of SBInet 
testing being effectively performed is reduced, which in turn increases 
the risk that the delivered and deployed system will not meet 
operational needs and not perform as intended. 

In closing, I would like to stress that a fundamental aspect of 
successfully implementing a large IT program like SBInet is 
establishing program commitments, including what capabilities will be 
delivered and when and where they will be delivered. Only through 
establishing such commitments, and adequately defining the approach and 
processes to be used in delivering them, can DHS effectively position 
itself for measuring progress, ensuring accountability for results, and 
delivering a system solution with its promised capabilities and 
benefits on time and within budget constraints. For SBInet, this has 
not occurred to the extent that it needs to for the program to have a 
meaningful chance of succeeding. In particular, commitments to the 
timing and scope of system capabilities remain unclear and continue to 
change, with the program committing to far fewer capabilities than 
originally envisioned. Further, how the SBInet system solution is to be 
delivered has been equally unclear and inadequately defined. Moreover, 
while the program office has defined key practices for developing and 
managing requirements, these practices were developed after several 
important requirements activities were performed. In addition, efforts 
performed to date to test whether the system meets requirements and 
functions as intended have been limited. 

Collectively, these limitations increase the risk that the delivered 
system solution will not meet user needs and operational requirements 
and will not perform as intended. In turn, the chances are increased 
that the system will require expensive and time-consuming rework. In 
light of these circumstances and risks surrounding SBInet, our soon to 
be issued report contains eight recommendations to the department aimed 
at reassessing its approach to and plans for the program--including its 
associated exposure to cost, schedule, and performance risks--and 
disclosing these risks and alternative courses of action for addressing 
them to DHS and congressional decision makers. The recommendations also 
provide for correcting the weaknesses surrounding the program's unclear 
and constantly changing commitments and its life cycle management 
approach and processes, as well as implementing key requirements 
development and management and testing practices. 

While implementing these recommendations will not guarantee a 
successful program, it will minimize the program's exposure to risk and 
thus the likelihood that it will fall short of expectations. For 
SBInet, living up to expectations is important because the program is a 
large, complex, and integral component of DHS's border security and 
immigration control strategy. 

Mr. Chairman, this concludes my statement. I would be pleased to answer 
any questions that you or other members of the committee may have at 
this time. 

Contacts and Acknowledgements: 

For further information, please contact Randolph C. Hite at (202) 512- 
3439 or at hiter@gao.gov. Other key contributors to this testimony were 
Carl Barden, Deborah Davis, Neil Doherty, Lee McCracken, Jamelyn Payan, 
Karl Seifert, Sushmita Srikanth, Karen Talley, and Merry Woo. 

[End of section] 

Footnotes: 

[1] GAO, Secure Border Initiative: Observations on Deployment 
Challenges, [hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-08-1141T] 
(Washington, D.C.: Sept. 2008). 

[2] Tactical infrastructure includes roads, vehicle barriers, 
pedestrian fences, etc. 

[3] The Capability Maturity Model Integration for Development® 
developed by the Software Institute of Carnegie Mellon University, 
defines key practices that are recognized hallmarks for successful 
organizations that, if effectively implemented, can greatly increase 
the chances of successfully developing and acquiring software and 
systems. See Carnegie Mellon Software Engineering Institute, Capability 
Maturity Model Integration for Development® version 1.2 (Pittsburgh, 
Penn., August 2006). 

[4] This method, Rapid Application Development and Joint Application 
Design (RAD/JAD), uses graphical user interfaces and direct end user 
involvement in a collaborative development approach. 

[5] Interface requirements describe the capabilities that must be in 
place in order to integrate components and products together. 

[6] SBInet Requirements Management Plan, January 15, 2007. 

[End of section] 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. Government Accountability Office: 
441 G Street NW, Room LM: 
Washington, D.C. 20548: 

To order by Phone: 
Voice: (202) 512-6000: 
TDD: (202) 512-2537: 
Fax: (202) 512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Ralph Dawn, Managing Director, dawnr@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: