Project Status
Comprising
3,463 linear feet of bridge elevated 65 feet above the navigation channel,
and 653 feet of walled embankments, the bridge over Murray Lock and
Dam will be the second longest Pedestrian / Bicycle bridge in the United
States. It will be the longest bridge specifically constructed as a
Pedestrian / Bicycle bridge. Special marine-based construction techniques
will be required for the construction of the bridge.
The bridge
will have a 14-foot wide deck, capable of handling pedestrian and bicycle
traffic. It will be constructed with weathering steel girders to minimize
the requirements for future maintenance. The bridge will be built with
gentle slopes to assure compliance with Uniform Federal Accessibility
Standards. The bridge is capable of holding two 36” future utility pipelines.
The contractor is Jensen Construction of Sand Springs, Oklahoma.
The
bridge will unite about 17 miles of scenic riverside trails in the cities
of Little Rock and North Little Rock, and may in the future connect
with 7,000 acres of various city, county, state and federal park land.
The aerial
photograph shows the approximate path of the bridge over Murray Lock
and Dam. The bridge would cross the river near the Murray Hydroelectric
power plant.
Project
Schedule
10/07/04
- Notice
to proceed on construction issues. Construction will be complete
late summer of 2006.
4/15/04
- Corps issues notice in FedBizOps to inform prospective contractors
of the upcoming advertisement for bids.
5/25/04 - Corps issues solicitation for competitive proposals from prospective
contractors.
6/08/04 - Presolicitation Conference.
6/29/04 - Competitive proposals due.
8/09/04 - Contract award date.
9/09/04
- Contractor notice to proceed.
Late
fall 2006 - Bridge completion. The construction contract is
on schedule, however the completion date could be impacted by water
fluctuations. Once past the season such events occur, by late Spring
06, a more accurate projection can be made.
The bridge
opening date is currently scheduled for September 30, 2006.
Project
History
2005 Winter -
Award of construction contract made and construction is underway.
2004 Winter
– Preparation of construction plans and specifications are nearing completion.
2003 Summer
– The Corps issued a contract to Cromwell-Garver joint venture for preparation
of construction plans and specifications.
2002 December
– Garver Engineers completed a Design Report, which determined: that
the existing dam structure could support a bridge; the required length
of bridge; evaluated design alternatives; and, developed cost estimates
for construction of the bridge and embankment structures.
2001 November
7 - Awarded delivery order for Design Report.
2000 November
16 – Judge Villines and General Melcher of the Corps Southwestern Division
signed a Memorandum of Agreement for the Corps to design and construct
a pedestrian/bicycle bridge over Murray Lock and Dam.