![Image Image](https://webarchive.library.unt.edu/eot2008/20090109051937im_/http://www.spl.usace.army.mil/cms/images/stories/edwards/eafb_titlepic.jpg) (6/30/2005) The Corps solicits bids in a full and open competition for the Main Base Runway Replacement project at Edwards AFB, CA . View the solicitation.
Scope of Work
The project has incremental fundings from FY06 to FY08 for a total of PA $103,000,000. Phase I will construct a temporary asphalt runway with associated taxiway connectors 2,500 ft from the existing main runway to support the repair of the existing main runway. The new runway must be capable of supporting large aircraft, including the B-52. Phase II and III will repair the existing main runway.
![Image Image](https://webarchive.library.unt.edu/eot2008/20090109051937im_/http://www.spl.usace.army.mil/cms/images/stories/edwards/phasingplan_small.jpg) • Phase 1 (06) – Design all 3 Phases/Construct Construct new temporary asphalt runway with associated taxiways A, B, & C • Phase 2 (07) – Construct Construct first half of existing PCC runway • Phase 3 (08) – Construct Construct second half of existing PCC runway • Transition sections must be designed for NASA shuttle landing requirements and lack of federal funding between the three phases Project Milestones Kickoff Pre Design Meeting | Feb 8 2005 | Industry Day | March 10 2005 | Topo Survey | March – April 2005 | Geo Tech Survey | Mid March 2005 | Preliminary Step 1 Solicitation | April 27 2005 - Delayed* | 35 % RFP submittal | May 16 2005 | 90 % RFP submittal | July 8 2005 | Ready to Advertise (step 2 solicitation) | Aug 15 2005 | DB contract Award (FY06) | Nov 21 2005 | Project Photos
![Image Image](https://webarchive.library.unt.edu/eot2008/20090109051937im_/http://www.spl.usace.army.mil/cms/images/stories/edwards/existing_pcc_runway_small.jpg) Existing PCC Runway ![Image Image](https://webarchive.library.unt.edu/eot2008/20090109051937im_/http://www.spl.usace.army.mil/cms/images/stories/edwards/topographic_small.jpg) Topographic Survey ![Image Image](https://webarchive.library.unt.edu/eot2008/20090109051937im_/http://www.spl.usace.army.mil/cms/images/stories/edwards/staging_batching_small.jpg) Staging/Batch Plant Area ![Image Image](https://webarchive.library.unt.edu/eot2008/20090109051937im_/http://www.spl.usace.army.mil/cms/images/stories/edwards/boringloc_small.jpg) Boring Locations Documents:
Industrial Day Mar. 10, 2005 - Briefing Presentation (5.60MB PPT) - Attendees List (Contractor)
|