Font Size

A+ | A- | Reset

Related Items

Contact Info

US Army Corps of Engineers
Los Angeles District
915 Wilshire Blvd., Suite 980
Los Angeles, CA 90017
By appointment only

District Commander:
COL Thomas H. Magness, IV

Public Affairs Office:
Jay Field, Chief

Telephone & Email:
For further questions, please
call or email us at...

Phone: (213) 452-3908/3333
Fax: (213) 452-4209

Content POC: Public Affairs
Technical POC: Webmaster

USACE RSS Feed


Home arrow News Room arrow Stories arrow Prado’s Extreme Makeover
Prado’s Extreme Makeover Print
Written by Greg Fuderer   
Thursday, 03 June 2004

Image
Ellie Encinas and Girish Desai inspect progress on modifications to Prado Dam’s downstream face. Construction on the new outlet works continues in the background.
Commuters on California State Highways 71 and 91 can see significant changes taking place at Prado Dam – at least during “rush hour” when freeway traffic slows to a crawl that allows a driver’s gaze to wander beyond the lane ahead.

Motorists have a new distraction at the intersection of the two Southern California freeways, where San Bernardino, Orange and Riverside counties meet. The 63-year-old dam is undergoing an extreme makeover that began about a year ago with a $67.4 million contract awarded to Yeager-Skanska, Inc. The modifications resulted from studies that reveal Prado Dam could not provide its intended level of flood protection. Numerous changes to the surrounding landscape (such as the increased construction of homes, businesses, malls and roads that reduce the area’s ability to absorb rain water and urban runoff, especially upstream) are the underlying factors for the update. Prado Dam is a major component of the Santa Ana River system upgrade, which runs from the Pacific Ocean near Huntington Beach to Seven Oaks Dam at the foothills of San Bernardino Mountains near Highland.

Image
Construction workers place concrete to form the new outlet works in Prado’s more-than-100-foot deep temporary notch. The upgrade will more than triple the dam’s ability to discharge water downstream safely.
The initial phase of the three-phase process will raise the dam 28 feet to a new height of 162 feet above the streambed. It will also build new intake tower and outlet works and modify the channel downstream from the dam. The Corps expects to award future contracts for two additional features: to construct several protective dikes in the basin and to raise the spillway adjacent to Prado Dam.

“As long as Congress keeps approving the funds and the Orange County Flood Control District acquires the necessary real estate,” said Girish Desai, who manages the project for the Corps, “we expect to finish everything by 2011.” Desai cautioned that those factors are contingent on many outside influences.

Ellie Encinas, the Corps’ Resident Engineer on the project, echoed that concern. “The current construction faces many challenges over the next 2 1/2 years,” she said, “primarily with funding shortages of about $13 million this fiscal year. The current construction funds will be exhausted in mid-June 2004. This will have a significant impact on construction progress, leaving a big hole in the ground and up to 2/3 of the embankment filled.”

Image
Amid a maze of rebar and plywood, workers begin the process of placing concrete that will form the heart of Prado’s internal workings.
The team of Corps, contractor and county representatives has made several changes to help with productivity. “We’ve applied a lot of lessons learned from the construction of Seven Oaks Dam,” Encinas said. “We’re very fortunate to have the knowledge and experience of folks like (the Corps’) Terry King and Yeager-Skanska's project engineer, Jim Vaughn.”

The Corps’ knowledge and experience continues to pay dividends with the contributions from LA District's Planning and Engineering divisions. “Doug Chitwood, Bill Halczak, Steve Vaughn and Hayley Lovan have helped Yeager-Skanska reduce potential cost and time impacts and deliver a quality product,” Encinas said.

At a recent visit to the site, Encinas and Desai surveyed the progress from high above the 108-foot notch cut into the dam’s eastern end. Amid a maze of sculpted rebar, workers placed concrete into molds. The structure will funnel water from six intake gates (roughly 10’ by 15’) into two discharge conduits (22’ by 23’ and 600’ long). Once the conduits are complete, earth workers will backfill the notch and contour it to match the upgraded dam’s embankments.

Image
A worker fastens rebar that will strengthen the dam’s inlet works. Prado’s control gates will be installed nearby.
When the six intake gates are operational, a Corps dam tender will adjust them to control the discharge rate from Prado’s basin, keeping it at a safe level and minimizing the potential for damage to people and property downstream. The new outlets will increase Prado’s discharge capacity from its present rate of 9,000 cubic feet per second (cfs) to 30,000 cfs. Modifications to the downstream channel will accommodate the increased water levels.

The contractor will place about 150 tons of new rock on Prado’s downstream face; the upstream face will remain essentially unchanged. Raising the dam and tying it into the previously built western end will increase the crest from 2,280 feet to 3,050 feet. By the time the project is complete, Prado’s downstream face will have received 1.5 million cubic yards of new earth material.

What could well be the last big dam project by the Corps involves the agency’s usual combination of people, machinery and vision. Scrapers, ‘dozers and compactors scurry across the top of the dam like so many gigantic insects, each trip adding nearly undetectable quantities that, when taken together, have forever altered Prado’s appearance.

In Prado’s case, beauty is more than skin deep.

 
< Prev   Next >
© 2009 US Army Corps of Engineers - Los Angeles District
This is an official US Government information system for authorized use only. It is intended for unclassified, non-sensitive, non-privacy act information.
About Us | Privacy and Security Notification | Section 508 Compliance | Site Map | Contact Us