Project
Status
Phase I—Auxiliary Gated Spillway
Contract for excavation of the auxiliary gated spillway was completed
in Sept. 2000.
Phase II--Auxiliary Gated Spillway
The spillway structure was completed in June of 2005.
The Moonshine Beach boat launch ramp and parking area were completed in
December of 2005.
Phase III-- New Moonshine Beach Recreation Area
Contract for construction of the relocated recreation area was completed
in October 2003.
December 2005--Work on the new Spillway was completed
in June. Work is finishing on the Moonshine Beach boat launch ramp
and parking area, and is expected to be completed soon.
Dam
Safety Project Nears Completion
LITTLE
ROCK, Ark., April 12, 2004 – The new auxiliary spillway
and the bridge over the spillway are complete and the last phase of construction,
upstream channel excavation, is nearing completion. The 500 ft long auxiliary
spillway has eight tainter gates is similar in appearance to the original
spillway that has ten tainter gates. Granite Construction Company of Watsonville,
Calif., constructed the new spillway, bridge and upstream channel under
a $44.2 million contract.
This work
followed an initial phase of excavation and earthen embankment construction
by Kiewit
Western Co. of Omaha, Neb., that was completed in September 2000. Mack
Inc. of Topeka, Kansas relocated the Moonshine Beach swimming area to
make room for the new spillway. Most of the new park has been completed,
with the exception of the boat launch ramp and parking area.
The auxiliary
spillway is the most cost-effective way to keep Table Rock Dam safe during
a catastrophic flood. The new spillway will only be used during extreme
flood emergencies.
Table Rock Dam was constructed between October 1954 and August 1958. It
consisted of 4,821 feet of earthen embankment with a 1,602 ft long concrete
section. The concrete section is designed to withstand the erosive forces
of water released from the spillway gates at the top of the dam. The designers
based the size of the spillway on the worst flood Mother Nature might
reasonably create based on weather data.
Under the
dam safety program, in the 1990’s, the spillway capacity was evaluated
using improved weather data, and more modern technology and safety requirements.
Engineers determined that the lake would rise ten feet higher during the
worst-case flood than previously calculated. An event of this magnitude
would overtop the earthen embankment and destroy Table Rock Dam with catastrophic
losses in downstream areas including Branson. To prevent the potential
loss of life and property damages, the Dam Safety Project was constructed.
After considering several options and gathering considerable public input,
the auxiliary spillway was determined to be the best solution.
Project
History
April
1999 – December 2000: initial phase of excavation and earthen
embankment construction.
July 2000 – July 2004: constructed auxiliary spillway,
bridge, and excavated upstream channel.
November 2001- October 2003: constructed new Moonshine
Beach recreation area.
Photos
Table
Rock Auxiliary Spillway Photo Album - A brief photographic history
of the project from May 2001 – April 2004.
PowerPoint
Slide Shows
Click on one
of these titles to learn more about the Table Rock Auxiliary Spillway.
Why is the spillway needed?
(project history)
Phases and explanation of construction
work (project phases)
Frequently
Asked Questions
Q1. Does
the construction effect the level of Table Rock Lake?
A1. No, construction of the auxiliary spillway does not effect the lake
level. In general, lake levels fall due to the withdrawal of water for
water supply, the generation of hydroelectric power and vaporation. Lake
levels rise due to runoff from rainfall. In the Table Rock Lake basin,
rainfall has been well below normal since July 1999 while water supply
usage and the generation of hydroelectric power has been normal. That
is the sole reason why the lake level is so low, lack of rainfall. Should
conditions worsen and the lake continues to recede, a Drought Contingency
Plan will guide us in water management decisions. If you have more questions
about lake levels, visit our River
and Lake Levels page. If you have specific questions about Table Rock's
Level, e-mail our reservoir
control office or our Table
Rock Lake office.
Q2. What
does the auxiliary spillway do?
A2. It provides additional capacity for the release
of floodwaters during extremely large and rare catastrophic flood events.
Q3. Has a
probable maximum flood event ever occurred at Table Rock Lake?
A3.
Not since records have been kept. This type of flood would be an extremely
rare event. The top of the flood control pool for the dam is 931, and
the maximum pool ever recorded at Table Rock Lake is 932.5 on May 10,
1961.
Q4. How much
does the spillway cost?
A4. The combined cost of the three construction
contracts for the auxiliary spillway is about $58.2 million.
Q5. Have
you assessed the environmental effects?
A5. The Corps district conducted an Environmental
Assessment in 1997 and determined that the project would cause no significant
adverse effects to the environment. As a result, a more detailed Environmental
Impact Statement was not prepared.
Q6. What
affect will there be on Table Rock Lake?
A6. There would be no change in the way Table Rock
Lake is operated from day to day. The new spillway would only be used
during extreme emergencies when lake levels exceed elevation 937 feet.
By that time, the existing spillway gates would be fully open and much
flooding would have already occurred. |