Levee System Information for Stakeholders

Flood Protection Restoration (Zone AR) Requirements

Read general information about levee systems on the Levee System Introduction page.

The flood protection restoration (Zone AR) determination process can be used when a Federal flood protection system, such as a levee system, no longer provides a 1-percent-annual-chance level of flood protection. This designation indicates that the increased flood hazard and associated risk is considered temporary and recognizes that a levee system is being restored to provide the 1-percent-annual-chance level of flood protection, thereby reducing the flood risk to people and structures in the levee-impacted areas.

The Zone AR determination process may result in reductions in the flood insurance premium costs and in the elevation requirements for new construction and substantial improvements to existing structures. The process also helps eligible communities establish a plan for restoring flood protection with the assurance that the restoration project, if constructed as proposed, will result in the eventual removal of the Special Flood Hazard Area (SFHA) designation from the levee-impacted areas.

Eligibility Requirements

A community may be eligible to apply for the Zone AR designation if the Federal Emergency Management Agency (FEMA) determines that the community is engaged in the process of restoring a flood protection system that was:

Back To Top

Application and Submittal Requirements

To apply for the Zone AR designation, the Chief Executive Officer (CEO) of the community or another community official designated by the CEO must submit a formal written request to the Administrator of the FEMA Regional Office that serves the community along with the supporting data and documentation outlined in Section 65.14 of the National Flood Insurance Program (NFIP) regulations, and any additional information requested by FEMA, if necessary. FEMA will not initiate any action to designate flood protection restoration zones without receiving a formal written request from the community that complies with all requirements of Section 65.14.

Back To Top

Limitations and Completion Requirements

A community may have a Zone AR designation only once during the restoration of a particular levee system. This limitation does not preclude future Zone AR designations should a fully restored, certified, and accredited levee system become decertified for a second or subsequent time.

A community that receives Federal funds for the purpose of designing, or constructing, or designing and constructing the restoration project must complete the restoration or meet the adequate progress requirements of Section 61.12 of the NFIP regulations within a specified period. The completion date for federally funded projects is not to exceed a maximum of 10 years from the date of submittal of the community's application for the Zone AR designation.

A community that does not receive Federal funds for the purpose of designing or constructing the project must also complete the restoration within a specified period, not to exceed a maximum of 5 years from the date of submittal of the community's application for the Zone AR designation. Because no Federal funds are involved, the project would not be eligible for a Zone A99 designation under the provisions of Section 61.12 of the NFIP regulations. The designated restoration period may not be extended beyond the maximum allowable under this limitation.

Back To Top

Exclusions

The provisions of Section 65.14 of the NFIP regulations do not apply to a levee system in a coastal high hazard area as defined in Section 59.1 of the NFIP regulations. This exclusion includes areas that would be subject to coastal high hazards as a result of the decertification of a previously certified levee system that had been accredited and shown on the effective FIRM or DFIRM for a community as providing 1-percent-annual-chance flood protection.

Back To Top

FEMA Review and Response

FEMA will review all data and documentation submitted in support of the community's application for the Zone AR designation. Upon completing this review, FEMA will respond, in writing, to the CEO of the community, in accordance with the procedures specified in Section 65.9 of the NFIP regulations.

If FEMA issues a flood protection restoration determination, they will prepare new or revised FIRM or DFIRM panels that designate the temporary flood hazard areas that are impacted by the levee system as Zone AR. Existing SFHAs shown on the effective FIRM or DFIRM panel(s) for the areas that are further inundated by Zone AR flooding will be designated as one of the following flood insurance risk zones:

Zones AR/AE, AR/AH, AR/AO, and AR/A are referred to collectively as dual flood zones.

Back To Top

Requirements for Maintaining Zone AR Designation

To maintain the Zone AR designation, the following requirements must be met:

The FEMA Regional Office that serves the affected community/communities will make an annual assessment and recommendation to the FEMA Administrator as to the viability of the restoration plan and will conduct periodic onsite inspections of the restoration project.

Back To Top

Flood Insurance Requirements

The following flood insurance requirements apply in areas designated Zone AR on an effective FIRM or DFIRM:

The effective date for any flood insurance risk premium rates established for Zone AR is the effective date of the new or revised FIRM or DFIRM showing the Zone AR designations.

Back To Top

Floodplain Management and Building Requirements

The floodplain management and building requirements below apply when FEMA has issued a Letter of Final Determination for a new or revised FIRM or DFIRM and has identified flood protection restoration areas by designating the areas as Zones AR or as dual flood zones (i.e., AR/A1-30, AR/AE, AR/AH, AR/AO, or AR/A) on the FIRM or DFIRM. These requirements also apply in areas designated Zone AR on an effective FIRM or DFIRM. These floodplain management and building requirements are in accordance with Paragraph 60.3(f) of the NFIP regulations.

Back To Top

Requirements for Removing Zone AR Designation

Once a levee system restoration or construction project has made adequate progress, as defined in Section 61.12 of the NFIP regulations, the CEO of the community or another community official designated by the CEO may submit written evidence that the criteria of Section 61.12 have been met and request that FEMA make an adequate progress determination and revise the FIRM or DFIRM to show a Zone A99 designation for the levee-impacted area. Additional information on the data, documentation, and mapping requirements for Zone A99 designations is provided on the Adequate Progress (Zone A99) Requirements page.

The Zone AR designation also may be removed when the levee system restoration project has been completed. The requirements are as follows:

Upon receipt of the required data and documentation, FEMA will revise the affected FIRM or DFIRM panel(s) and related products to reflect the impact of the completed project on flood risks in the levee-impacted area.

FEMA also has procedures for removing the Zone AR designation due to non-compliance with the restoration schedule or as a result of a finding that satisfactory progress is not being made to complete the restoration. These procedures and the resulting action that will be taken by FEMA are documented in Paragraph 65.14(i) of the NFIP regulations.

Back To Top

Useful Resources

The levee system resources listed below provide more information on regulatory requirements, procedural requirements, and benefits of flood protection restoration zone and adequate progress determinations. These and other useful FEMA, NFIP, and Flood Map Modernization (Map Mod) resources are located in the FEMA Library.

Back To Top

For More Information

For more information or additional assistance:

Back To Top

Return to the Levee System Construction and Restoration Projects page.

Last Modified: Tuesday, 07-Oct-2008 09:56:32 EDT

References


Online Tools


Related Topics


Government Links