Frequently Asked Questions: Service Pack 14 – Managers Course

Question


When does the Manage Data Development (MDD) trigger? Also, does Manage Prelim initiate once Manage Data Development ends? Does Manage Post Prelim begin when Manage Prelim ends?

Answer


When Obligate Funds is complete, Manage Data Development starts. Manage Preliminary Map Production starts when the last data development task passes QA, and the Manager checks off 'Area Complete' under the DFIRM section within the Manage Data Development activity.. Manage Post-Preliminary Processing begins when the Distribute Preliminary Map Products task is completed, independent of Manage Prelim.