Home  » MIP User Care » FAQs

Frequently Asked Questions: General

Question


Can the 90-day "clock" for EV information - triggered when a Manager enters actual end date for Distribute Preliminary & updates percent complete to 100% - be reset? (e.g. if the Manager goes back and changes the 100% to something less)

Answer


No. The Producer is the person driving the workflow, and that clock is tied to when the Producer completes that step. But if the Manager is unable to complete the EV update within the 90-day timeframe, contact your RMC who may be able to make those updates for you.

Return to FAQ Page