This is the accessible text file for GAO report number GAO-06-444T 
entitled 'Census Bureau: Important Activities for Improving Management 
of Key 2010 Decennial Acquisitions Remain to be Done' which was 
released on March 1, 2006. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Testimony Before the Subcommittee on Federalism and the Census, 
Committee on Government Reform, House of Representatives: 

For Release on Delivery Expected at 10:00 a.m. EST Wednesday, March 1, 
2006: 

Census Bureau: 

Important Activities for Improving Management of Key 2010 Decennial 
Acquisitions Remain to be Done: 

Statement of David A. Powner, Director, Information Technology 
Management Issues: 

GAO-06-444T: 

GAO Highlights: 

Highlights of GAO-06-444T, testimony before the Committee on Government 
Reform, Subcommittee on Federalism and the Census: 

Why GAO Did This Study: 

The Census Bureau plans to increase its use of automation to conduct 
the 2010 Decennial Census. Two key acquisitions are the Decennial 
Response Integration System (DRIS) and the Field Data Collection 
Automation program (FDCA). DRIS is expected to standardize and 
integrate data from census forms and other response modes. FDCA is 
expected to provide automation support for field data collection 
activities. Last year, you asked GAO to assess the status, plans, and 
management capabilities of both of these projects. In January 2006, GAO 
briefed the subcommittee staff on the results of that work. At your 
request, this testimony summarizes key findings from that briefing, 
including the status and management capabilities of each project. 

What GAO Found: 

The Census Bureau has initiated efforts to acquire DRIS and FDCA, key 
systems it needs to perform the 2010 Decennial Census. It awarded a 
contract for DRIS in October 2005; the system is currently in a design 
and development phase. The bureau expects to award a contract for FDCA 
development in March 2006. While both projects’ life cycle cost 
estimates are currently considered procurement sensitive, together they 
are expected to make up a large portion of the $1.8 billion program to 
develop, test, and implement decennial census systems. Both 
acquisitions involve ambitious schedules in order to be able to deliver 
the needed functionality to support a planned 2008 census dress 
rehearsal and the eventual 2010 census activities. 

While both project offices have implemented initial acquisition 
management activities, neither has the full set of capabilities they 
need to effectively manage the acquisitions (see table below). 
Specifically, the DRIS project completed its solicitation activities 
and the FDCA project has completed most of its solicitation activities. 
However, activities in other management areas have been initiated but 
not completed. For example, the DRIS project office has established 
baseline requirements for the acquisition, but the bureau has not yet 
validated them or implemented a process for managing the requirements. 
Also, while the FDCA project office has initiated efforts to oversee 
the contractor’s performance, such as requiring earned value management 
reporting (a project management tool that integrates cost, schedule, 
and scope of work to aid project planning and control) and hiring staff 
with contracting experience, it has not yet determined which 
performance measures it will use to track the contractor and its own 
internal project office performance. Until these and other basic 
contract management activities are fully implemented, both projects 
face increased risks that the systems will experience cost overruns, 
schedule delays, and performance shortfalls. 

Status of Acquisition Management Activities for Key Decennial Systems: 

[See PDF for image] 

[End of figure] 

What GAO Recommends: 

GAO recommends that the Census Director ensure that the bureau 
completes key activities needed to effectively manage its acquisitions. 
In commenting on a draft of GAO’s briefing, bureau officials generally 
agreed with the recommendations and noted that time and budget 
constraints had driven the bureau to proceed with its acquisitions 
before all of the recommended activities had been completed. Officials 
stated that they plan to complete these activities as soon as possible. 

www.gao.gov/cgi-bin/getrpt?GAO-06-444T. 

To view the full product, including the scope and methodology, click on 
the link above. For more information, contact David A. Powner at (202) 
512-9286 or pownerd@gao.gov. 

[End of section] 

Mr. Chairman and Members of the Subcommittee: 

We appreciate the opportunity to participate in today's hearing to 
discuss our work on key acquisitions supporting the 2010 Decennial 
Census. As you know, the Census Bureau is currently planning the 
decennial census--the nation's oldest and most comprehensive source of 
population and housing data. While apportionment--the proportional 
distribution of the number of members of the U.S. House of 
Representatives in each state on the basis of the population of each 
state--is the most widely known use of census data, the data are also 
used for congressional redistricting, managing federal agencies, and 
allocating federal funds. These data are disseminated to state and 
local governments, academia, and the private sector for use in 
understanding this country's people and their social, demographic, and 
economic characteristics. The next decennial census is required to 
begin on April 1, 2010, and the Secretary of Commerce is required to 
report to the President the tabulation of total population by states 
within 9 months of that date.[Footnote 1] 

In June 2005, we reported on the Census Bureau's progress in five 
information technology (IT) management areas--investment management, 
systems development/management, enterprise architecture management, 
information security, and human capital.[Footnote 2] These IT 
management areas are important because they have substantial influence 
on the effectiveness of organizational operations and--if applied 
effectively--can reduce the risk of cost and schedule overruns, and 
performance shortfalls. We reported that, while the bureau had many 
practices in place, much remained to be done to fully implement 
effective IT management capabilities. We also made several 
recommendations to improve the bureau's management. Given the 
weaknesses we noted in the five management areas and the importance of 
IT investments to the upcoming 2010 Decennial Census, you asked us to 
review two planned Census Bureau acquisitions: the Decennial Response 
Integration System (DRIS)--a system for integrating paper, Internet, 
and telephone responses; and the Field Data Collection Automation 
(FDCA) program--the systems, equipment, and infrastructure field staff 
will use to collect census data. 

In January, we presented a detailed briefing to the committee and 
subcommittee staffs, which is provided in appendix I. At your request, 
I will discuss key findings from that briefing, specifically covering 
each project's status and management capabilities. An overview of the 
approach we used to perform this work--our objectives, scope, and 
methodology--is provided in appendix II. 

Results in Brief: 

The Census Bureau has initiated efforts to acquire DRIS and FDCA, key 
systems it needs to perform the 2010 Decennial Census. It awarded a 
contract for DRIS in October 2005; the system is currently in a design 
and development phase. The bureau expects to award a contract for FDCA 
development in March 2006. While both projects' life cycle cost 
estimates are currently considered procurement sensitive, together they 
are expected to make up a large portion of the $1.8 billion program to 
develop, test, and implement decennial census systems. Both 
acquisitions involve ambitious schedules in order to be able to deliver 
the needed functionality to support a planned 2008 census dress 
rehearsal and the eventual 2010 census activities. 

While both project offices have implemented initial acquisition 
management activities, neither has the full set of capabilities they 
need to effectively manage the acquisitions. Specifically, the DRIS 
project completed its solicitation activities and the FDCA project has 
completed most of its solicitation activities. However, activities in 
other management areas have been initiated but not completed. For 
example, the DRIS project office has established baseline requirements 
for the acquisition, but the bureau has not yet validated them or 
implemented a process for managing the requirements. Also, the project 
office identified project risks, but has not yet developed written 
mitigation plans or established milestones for completing key risk 
mitigation activities. Regarding FDCA, the project office has developed 
baseline functional requirements for the acquisition, but the bureau 
has not yet validated them. Also, while the FDCA project office has 
initiated efforts to oversee the prospective contractor's performance, 
such as requiring earned value management[Footnote 3] reporting and 
hiring staff with contracting experience, it has not yet determined 
which performance measures it will use to track the contractor and its 
own internal project office performance. Additionally, the project 
office identified risks, but it has not yet implemented a risk 
management process. Specifically, it has not yet assigned 
responsibilities, developed detailed mitigation plans for managing the 
risks, or established milestones for completing key mitigation 
activities. 

Until these and other basic management activities are fully 
implemented, both projects face increased risks that the systems will 
experience cost overruns, schedule delays, and performance shortfalls. 
We are making recommendations to the Director of the Census Bureau to 
ensure that both project offices complete key activities needed to 
effectively manage acquisitions, including activities associated with 
effective project planning, requirements management, risk management, 
and performance measurement. 

Background: 

The Census Bureau's mission is to serve as the leading source of 
quality data about the nation's people and economy. While apportionment 
is the most widely known use of census data, the data are also used for 
congressional redistricting, managing federal agencies, allocating 
federal funds, and they are disseminated to state and local 
governments, academia, and the private sector. Data from a decennial 
census provide official, uniform information gathered over the decades 
on the country's people and their social, demographic, and economic 
characteristics. They provide the baselines for countless other surveys 
and are used to develop sampling frames for a number of other federal 
data collections, such as the Current Population Survey, which is used 
to measure participation in the labor market and unemployment 
rates.[Footnote 4] 

The bureau's decennial census organization, which is responsible for 
the decennial census program, is comprised of several divisions and 
offices. The Decennial Management Division is responsible for 
implementing the decennial census. The Decennial Systems and Contracts 
Management Office manages selected system contracts supporting the 
decennial census. 

To support the 2010 Decennial Census, the bureau manages a $1.8 billion 
program called "2010 Testing, Evaluation, and Systems Design," which 
calls for the acquisition and testing of systems and technologies. Two 
of the key acquisitions associated with this program are DRIS and FDCA. 
In addition, other key systems support the planned 2010 decennial 
census. Together, these and other systems are to support the 
collection, processing, and dissemination of census data. Figure 1 
shows an overview of the key systems planned to support the 2010 
Decennial Census. 

Figure 1: Overview of Systems Supporting the 2010 Decennial Census: 

[See PDF for image] 

[End of figure] 

To effectively manage major IT programs, organizations should use sound 
acquisition and management processes to minimize risks and thereby 
maximize chances for success. Such processes include project and 
acquisition planning, solicitation, requirements development and 
management, risk management, contract tracking and oversight/project 
monitoring and control, quality assurance, and executive oversight (see 
table 1 for a description of each process). Such processes have been 
identified and endorsed by leading organizations such as the Software 
Engineering Institute and the Chief Information Officer's Council, and 
in our prior work analyzing best practices in industry and government. 
Our work has shown that such processes are significant factors in 
successful systems acquisitions and development programs, and they 
improve the likelihood of meeting cost and schedule estimates as well 
as performance. 

Table 1: Selected Processes for Effectively Managing IT Programs: 

Process area: Project and acquisition planning; 
Description: Effective project planning involves establishing and 
maintaining plans defining project scope and activities, including 
overall budget and schedule, key deliverables, and milestones for key 
deliverables. It also involves ensuring that the project team has the 
skills and knowledge needed to manage the project and obtaining 
stakeholder commitment to the project plan. Effective acquisition 
planning involves developing an acquisition strategy that includes 
objectives, projected costs and schedules, and risks. 

Process area: Solicitation; 
Description: This activity includes identifying the needs within a 
particular acquisition, developing and implementing a solicitation 
plan, preparing for the evaluation of responses, issuing a solicitation 
package, evaluating responses, conducting supporting negotiations, and 
making recommendations for award of the contract. 

Process area: Requirements development and management; 
Description: Requirements development involves eliciting, analyzing, 
and validating customer and stakeholder needs and expectations. 
Requirements management involves establishing an agreed-upon set of 
requirements, ensuring traceability between operational and product 
requirements, and managing any changes to the requirements in 
collaboration with stakeholders. 

Process area: Risk management; 
Description: An effective risk management process identifies potential 
problems before they occur, so that risk-handling activities may be 
planned and invoked as needed across the life of the product and 
project in order to mitigate adverse impacts on achieving objectives. 
Key activities include identifying and analyzing risks, assigning 
resources, developing risk mitigation plans and milestones for key 
mitigation deliverables, briefing senior-level managers on high-
priority risks, and tracking risks to closure. 

Process area: Contract tracking and oversight/project monitoring and 
control; 
Description: These processes provide oversight of the contractor's and 
the project office's performance, in order to allow appropriate 
corrective actions if actual performance deviates significantly from 
the plan. Key activities in tracking both the contractor's and the 
project office's performance include the selection of performance 
measures, communicating status, taking corrective actions, and 
determining progress. 

Process area: Process and product quality assurance; 
Description: This process area provides staff and management with 
objective insight into processes and associated work products. This 
includes the objective evaluation of project processes and products 
against approved descriptions and standards. Key activities include 
developing a quality assurance plan, assigning resources to quality 
assurance activities, and implementing quality assurance activities. 
Through quality assurance, the project team is able to identify and 
document noncompliance issues and provide appropriate feedback to 
project staff. 

Process area: Executive oversight and governance; 
Description: Office of Management and Budget and GAO guidance call for 
agencies to establish IT investment management boards comprised of key 
executives to regularly track the progress of major systems 
acquisitions. These boards should have documented policies and 
procedures for management oversight of IT projects and systems, and 
should be able to adequately oversee the project's progress toward cost 
and schedule milestones and their risks. The board should also employ 
early warning systems that enable it to take corrective actions at the 
first sign of cost, schedule, and performance slippages. 

Source: GAO summary of leading practices, including practices 
identified by the Software Engineering Institute, the Chief Information 
Officer's Council, and the Office and Management and Budget. 

[End of table] 

DRIS Project Under Way but Key Management Activities Remain To Be 
Implemented: 

DRIS is intended to receive, capture, and standardize census data 
provided by respondents via census forms, telephone agents, and the 
Internet. DRIS is also intended to standardize data collected via 
mobile computing devices and perform other functions, such as provide 
assistance to the public via telephone and the Internet. 

On October 5, 2005, the bureau awarded a cost-plus-award-fee contract 
for DRIS to Lockheed Martin Corporation and its seven subcontractors to 
design, develop, and implement a system for standardizing and 
integrating the data from all of the response modes. The contract has a 
6-year performance period, which includes designing and developing the 
system, conducting the census dress rehearsal in 2008, conducting 2010 
census operations, and archiving data and disposing of equipment after 
the census is completed. After the contract was awarded, the project 
got off to a slow start because of a bid protest that has since been 
withdrawn. The DRIS project office is currently reassessing the project 
schedule due to delays associated with the bid protest. The project 
office plans to complete this assessment and perform an integrated 
baseline review by March 2006.[Footnote 5] 

The DRIS project office has initiated activities supporting key project 
management processes, but does not yet have the full set of acquisition 
management capabilities it needs to effectively manage the acquisition. 
Table 2 provides a summary of the status of the DRIS project in each of 
the process areas we evaluated. 

Table 2: Summary of the Status of DRIS Acquisition Management 
Capabilities: 

Capability: Project and acquisition planning; 
Status: Initiated, but key activities remain to be completed, such as 
finalizing the project management plan and identifying key deliverables 
beyond 2008. 

Capability: Solicitation; 
Status: Key activities completed and contract awarded ahead of 
schedule. 

Capability: Requirements development and management; 
Status: Initiated, but key activities remain to be completed, such as 
validating requirements and implementing a requirements management 
process. 

Capability: Risk management; 
Status: Initiated, but key activities remain to be performed such as 
preparing mitigation plans and holding senior-level briefings. 

Capability: Contract tracking and oversight/project monitoring and 
control; 
Status: Initiated, but project office performance measures have not yet 
been established. 

Capability: Process and product quality assurance; 
Status: Initiated, but a quality assurance process is not yet in place. 

Capability: Executive oversight/governance; 
Status: Initiated, but key governance activities remain to be 
completed. 

Source: GAO analysis of Census Bureau data. 

[End of table] 

The DRIS project office has made progress in building management 
capabilities, but more remains to be done in key areas. For example, 
the project office completed its solicitation activities and awarded 
the contract ahead of schedule. In the area of requirements development 
and management, the project office established basic functional 
requirements for the acquisition and the Decennial Management Division 
has developed a detailed change control process for managing 
requirements for all 2010 Decennial Census systems, including DRIS. 
However, the division has not yet conducted a thorough validation of 
DRIS requirements, ensured traceability between DRIS and operational 
requirements, or approved the DRIS baseline requirements. Further, the 
division has not yet staffed the teams responsible for managing 
requirements or initiated any requirements management activities. 

Until the bureau obtains validation and approval of DRIS requirements, 
it faces increased risk that new and changing requirements could be 
identified throughout the system's development. Changes identified late 
in the development cycle could be costly to implement and could 
increase the risk that the system will not be ready in time to support 
census activities. Further, until the bureau staffs and implements its 
planned requirements management process, it may not be able to 
effectively ensure that resulting products meet requirements. 

In the area of risk management, the DRIS project office has developed a 
pre-award risk management plan that defines staff roles and 
responsibilities and includes procedures for identifying and tracking 
risks and risk mitigation actions. Since awarding the contract, the 
team has updated the pre-award risks. However, the project team has not 
written mitigation steps or dates associated with the team's plans for 
addressing high-impact risks, and the project team has not conducted 
senior-level briefings. Until the project team develops risk mitigation 
plans with milestones for key activities and regularly briefs senior- 
level managers on risks and risk mitigation plans, it faces increased 
probability that DRIS will not be delivered on schedule, within budget, 
or perform as expected. 

In the area of contract and project monitoring, the DRIS project team 
plans to provide contract tracking and oversight through reports 
including earned value management and monthly status reports. However, 
the project office has not yet selected detailed performance measures 
for tracking the contractor or its own internal progress (such as 
progress against planned milestones, number of risks opened and closed, 
number and frequency of changes to requirements, and frequency of 
quality assurance reviews). As a result, the project team is not able 
to ensure that it will be able to identify and document any 
noncompliance issues and take appropriate corrective actions. 

One of the root causes of the project's delay in completing key 
management activities is that the Census Bureau lacks the 
organizational policies for managing major acquisitions. As a result, 
the success of major acquisitions such as DRIS is highly dependent on 
the knowledge, skills, and qualifications of the project offices. 
Without a minimum set of required steps and processes, Census 
acquisitions are at increased risk of being run in an ad hoc and 
chaotic manner--potentially resulting in increased project costs, 
delayed schedules, and performance shortfalls. In commenting on a draft 
of our briefing, agency officials acknowledged that the bureau does not 
have an organizational acquisition management policy, but noted that, 
even if there were a policy, time and budget constraints have driven 
the bureau to proceed with its acquisitions before all of the 
recommended activities have been completed. Officials stated that they 
plan to complete these activities as soon as possible. 

FDCA Program Has Been Initiated but Key Management Activities Remain To 
Be Performed: 

The FDCA program is expected to provide automation support for field 
data collection operations for the 2010 Census. The program is expected 
to provide office automation for regional and local census offices; the 
telecommunications infrastructure for headquarters, regional, and local 
offices; and mobile computing devices for field workers. The bureau 
plans to have field-based enumerators use nearly 500,000 mobile 
computing devices to support decennial census field operations. Our 
companion testimony provides details on mobile computing devices and 
concerns about the reliability observed during testing.[Footnote 6] 
Enumerators from local census offices will use these mobile computing 
devices to complete activities including address canvassing (visiting 
households to update address lists and collect global positioning 
coordinates to update maps) and conducting non-response follow-up 
(visiting households to obtain information from households that do not 
provide responses via mail, Internet, or phone). The bureau plans to 
award the FDCA contract, which is expected to be a cost-reimbursement 
contract with multiple incentives, on March 31, 2006. The contract is 
expected to have four phases--one planning and three execution phases. 

The FDCA project office has initiated many key processes to oversee and 
manage the contract, but has not yet implemented the full set of 
acquisition management capabilities it needs to fully manage the 
acquisition. Table 3 provides a summary of the status of the FDCA 
project in each of the process areas we evaluated. 

Table 3: Summary of the Status of FDCA Acquisition Management 
Capabilities: 

Capability: Project and acquisition planning; 
Status: Initiated, but key activities remain to be completed, such as 
identifying deliverables and milestones, and obtaining stakeholder buy-
in on a project plan that includes the project's estimated costs, 
budget, and schedules. 

Capability: Solicitation; 
Status: Key activities completed; bureau officials said that they are 
on schedule to award the contract in March 2006. 

Capability: Requirements development and management; 
Status: Initiated, but key activities remain to be completed such as 
validating requirements. 

Capability: Risk management; 
Status: Initiated, but key activities remain to be performed such as 
assigning responsibilities for risks and preparing mitigation plans. 

Capability: Contract tracking and oversight/project monitoring and 
control; 
Status: Initiated, but key performance measures have not yet been 
established; bureau officials said that they expect to define these 
metrics after contract award. 

Capability: Process and product quality assurance; 
Status: Initiated; the quality assurance process is expected to be 
implemented after contract award. 

Capability: Executive oversight/governance; 
Status: Initiated, but key governance activities remain to be 
completed. 

Source: GAO analysis of Census Bureau data. 

[End of table] 

The FDCA project office has made progress in building management 
capabilities, but more remains to be done in key areas. For example, 
the project office completed many key solicitation activities and plans 
to award a contract in March 2006. In the requirements development and 
management area, the project office and the Decennial Management 
Division developed FDCA-specific functional requirements with 
participation from stakeholders. The office has also drafted a 
requirements management plan. However, the division has not yet 
validated and approved a baseline set of operational requirements or 
ensured traceability between its operational requirements and the FDCA 
request for proposal. Until the bureau finalizes its operational 
requirements for the census and ensures that the FDCA request for 
proposal is consistent with the baseline requirements, the project will 
be at risk of having changes to the requirements, potentially affecting 
its ambitious development and implementation schedule. 

In the risk management area, the project office has developed a draft 
risk management process and identified a number of high-level risks for 
the FDCA project. Also, to manage its schedule and technical risks, the 
project office has adopted an approach calling for pre-award prototype 
development. However, the FDCA project office has not yet revisited or 
analyzed the identified risks, begun prioritizing and tracking project 
risks, or documented risk mitigation plans. Until the team implements 
an effective risk management process, it will lack a mechanism to 
address known and unknown problems. 

Additionally, in the contract and project monitoring area, the project 
office has initiated efforts to oversee the contractor's performance, 
such as requiring earned value management reporting and hiring staff 
with contract tracking and oversight experience. However, the project 
office has not yet selected detailed performance measures for tracking 
the contractor or its own internal progress (such as progress against 
planned milestones, number of risks opened and closed, number and 
frequency of changes to requirements, and frequency of quality 
assurance reviews). Without such practices in place, the project team 
is not able to ensure that it will be able to identify problems and 
take appropriate corrective actions in a timely manner. 

Conclusions: 

While the DRIS and FDCA project offices have initiated important steps 
in establishing sound and capable project management, neither has 
completed all of the important activities needed to adequately manage 
the acquisitions. Incomplete management activities, including those for 
requirements management, risk management, and contract and project 
monitoring, increase the risk that these projects will encounter 
problems in meeting cost and schedule expectations. Given the immovable 
deadline for performing the 2010 Decennial Census, if unexpected 
problems or changes occur, it is more likely that the bureau will face 
cost overruns or be forced to accept a system with limited 
functionality. Since the DRIS contract was awarded in October 2005, and 
the FDCA contract is expected to be awarded in March, it is critical 
that the DRIS project office expeditiously put in place key elements of 
sound acquisition management capability. Bureau officials acknowledge 
the importance of implementing these acquisition management processes 
and state that they plan do to so as soon as possible. 

Recommendations for Executive Action: 

To ensure that the bureau adequately manages the DRIS project, we 
recommend that the Director of the Census Bureau direct the project 
office to take the following six actions: 

* Complete the DRIS project plan and obtain stakeholders' commitment to 
the plan before initiating further development work. 

* Obtain validation, management, and customer approval of DRIS 
requirements. 

* Staff teams and perform planned requirements management activities. 

* Develop mitigation plans with milestones for key activities, and 
regularly brief senior managers on important risks. 

* Establish performance measures and monitor results for contractor and 
project office activities. 

* Implement a quality assurance process by establishing 
responsibilities for assuring product quality and defining how 
inspections, reviews, and walkthroughs will be used to measure quality. 

Further, to ensure that the bureau improves its ability to manage this 
and other acquisitions, we recommend that the Director of the Census 
Bureau immediately establish and enforce a system acquisition 
management policy that incorporates best practices in system and 
software acquisition management (including those highlighted in our 
briefing). 

To ensure that the bureau adequately manages the FDCA project, we 
recommend that the Director of the Census Bureau direct the project 
office to take the following four actions: 

* Obtain stakeholder commitment to a project plan that includes 
estimated project costs and schedules, including deliverables and 
milestones. 

* Obtain validation and approval of baseline requirements. 

* Identify, prioritize, and assign responsibilities for risks, and 
develop and implement risk mitigation plans and actions. 

* Develop internal and contractor performance measures and prepare to 
track project cost, schedule, and performance. 

Agency Comments and Our Evaluation: 

In providing oral and e-mail comments on a draft of our briefing, 
Census Bureau officials--including the Associate Director for the 
Decennial Census and the Assistant Director for Decennial Information 
Technology and Geographic Systems--generally agreed with our 
recommendations and stated that time constraints and budgets have 
driven the bureau to proceed with its acquisitions before all of the 
recommended activities have been completed. Officials stated that they 
plan to complete these activities as soon as possible. 

Bureau officials also stated that they intend to rely on the DRIS and 
FDCA contractors to help refine requirements, project plans, and 
performance measures. However, our experience in reviewing major system 
acquisitions in recent years has shown that there are risks associated 
with relying too heavily on contractors to perform key management and 
oversight activities. For example, after a long history of significant 
cost increases and schedule delays on its Business System Modernization 
program, the Internal Revenue Service recently began transferring 
responsibility for key program management operations (including cost 
and schedule estimation and measurement, integration testing, and risk 
management) away from its contractor and back to the agency because of 
the contractor's poor performance in these areas.[Footnote 7] Clearly, 
it is important for the government to exercise strong leadership in 
managing requirements, plans, risks, and performance measures. Bureau 
officials also offered technical corrections, which we incorporated in 
the briefing and in this statement as appropriate. 

This concludes my statement. I would be pleased to respond to any 
questions that you or other members of the Subcommittee may have at 
this time. 

Contacts and Acknowledgements: 

If you have any questions regarding this testimony, please contact 
David Powner at (202) 512-9286 or by e-mail at [Hyperlink, 
pownerd@gao.gov]. Individuals making contributions to this testimony 
include Neil Doherty, Amanda Gill, Nancy Glover, Colleen Phillips, and 
Cynthia Scott. 

[End of section] 

Appendix I: GAO Briefing to Committee and Subcommittee Staffs on 
January 30, 2006: 

Census Bureau: 

Key Acquisitions Supporting the 2010 Decennial Census Face Challenges: 

Briefing for the Committee on Government Reform and its Subcommittee on 
Federalism and the Census: 
House of Representatives: 

January 30, 2006: 

Briefing Outline: 

Introduction: 

Objectives: 

Scope and Methodology: 

Results in Brief: 

Background: 

Decennial Response Integration System: 
* Overview, Status, and Plans: 
* Acquisition Management Capabilities: 
* Conclusions: 
* Recommendations: 

Field Data Collection Automation program: 
* Overview, Status, and Plans: 
* Acquisition Management Capabilities: 
* Conclusions and Recommendations: 

Agency Comments and Our Evaluation: 

Introduction: 

In June 2005, we reported on the Census Bureau's progress in five 
information technology (IT) management areas-investment management, 
systems development/management, enterprise architecture management, 
information security, and human capital. [NOTE 1] We reported that, 
while the bureau had many practices in place, much remained to be done 
to fully implement effective IT management capabilities. We made 
several recommendations intended to improve these capabilities across 
the bureau. 

Given the weaknesses we noted in the five IT management areas and the 
importance of IT investments to the upcoming 2010 Decennial Census, the 
Chairman of the House Committee on Government Reform and the Chairman 
and Ranking Member of the Subcommittee on Federalism and the Census 
requested that we assess the bureau's ability to manage important new 
acquisitions intended to support the decennial census. 

NOTE: 

[1] GAO, Information Technology Management. Census Bureau Has 
Implemented Many Key Practices, but Additional Actions Are Needed, GAO-
05-661 (Washington, D.C.: June 16, 2005). 

Objectives: 

As part of the Census Bureau's plans to increase the use of automation 
and technology for the 2010 Decennial Census, the bureau will be 
undertaking several major acquisitions including the Decennial Response 
Integration System (DRIS)-a system for integrating paper, Internet, and 
telephone responses, and the Field Data Collection Automation (FDCA) 
program-the systems and support equipment for field office data 
collection activities. 

Our objectives for each of these acquisitions are to: 

* provide an overview, status, and plans (including costs, schedule, 
and deliverables) and: 

* determine if the bureau has capabilities in place to successfully 
manage and oversee the acquisitions. 

Scope and Methodology: 

To provide the project's overview, status, and plans, we analyzed 
current project documents including plans, acquisition documents, and 
deliverables, and we interviewed project officials. 

To determine if the bureau has capabilities in place to successfully 
manage and oversee the acquisitions, we identified sound IT systems 
acquisition and management processes from industry standards, including 
those developed by the Software Engineering Institute, and compared 
them to the Census Bureau's practices for the selected acquisitions. We 
evaluated the following processes: 

* project and acquisition planning; 
* solicitation; 
* requirements development and management; 
* risk management; 
* contract tracking and oversight/project monitoring and control; 
* process and product quality assurance; 
* executive oversight and governance. 

In each process area, we evaluated project documentation and 
interviewed project officials to determine the status of the bureau's 
efforts. 

We conducted our review between July 2005 and January 2006 at Census 
Bureau headquarters in Suitland, Maryland, in accordance with generally 
accepted government auditing standards. 

Results in Brief: 

The Census Bureau has initiated efforts to acquire the major systems it 
needs to perform the 2010 Decennial Census, including the Decennial 
Response Integration System (DRIS), and the Field Data Collection 
Automation (FDCA) program. It awarded a contract for DRIS in October 
2005 and the system is currently in a design and development phase. The 
bureau expects to award a contract for FDCA development in March 2006. 
While both projects' life cycle cost estimates are currently considered 
procurement sensitive, together they are expected to make up a large 
portion of the $1.8 billion program to develop, test, and implement 
decennial census systems. Both acquisitions involve ambitious schedules 
in order to be able to deliver the needed functionality to support a 
planned 2008 census dress rehearsal and the eventual 2010 census 
activities. 

While both projects have implemented initial project management 
activities, neither has the full set of acquisition management 
capabilities they need to fully manage the acquisitions. For example, 
the DRIS project office has a draft project plan that contains many of 
the needed elements, but it has not yet completed the plan or obtained 
written stakeholder buy-in on it. It established baseline requirements 
for the acquisition, but the bureau has not yet validated them or 
implemented a process for managing the requirements. Also, the project 
office identified risks, but has not yet implemented a risk management 
process. Specifically, the project office has not yet developed written 
mitigation plans or established milestones for completing key risk 
mitigation activities. 

Regarding FDCA, its project office has initiated a project plan, but 
has not yet obtained written stakeholder buy-in on an overall plan that 
includes the project's estimated costs, budget, and schedules. It has 
identified requirements for the acquisition, but the bureau has not yet 
approved a validated set of requirements or ensured that the 
acquisition requirements are traceable to the broader set of 
operational requirements for the decennial census. Further, while the 
project office identified risks, it has not yet assigned 
responsibilities or developed detailed mitigation plans for managing 
the risks, or established milestones for completing key mitigation 
activities. 

Until these and other basic management capabilities are fully 
implemented, both projects face increased risks that the systems will 
experience cost overruns, schedule delays, and performance shortfalls. 
We are making recommendations to both project offices and to the bureau 
to help improve acquisition management capabilities. 

In commenting on a draft of this briefing, Census Bureau officials, 
including the Associate Director for the Decennial Census and the 
Assistant Director for Decennial Information Technology and Geographic 
Systems, generally agreed with our recommendations and stated that time 
constraints and budgets have driven the bureau to proceed with its 
acquisitions before all of the recommended activities have been 
completed. Officials noted that they plan to complete these activities 
as soon as possible. They also offered technical corrections, which we 
have incorporated as appropriate. 

Background: 

Census Bureau Mission and Core Activities: 

The Census bureau's mission is to serve as the leading source of 
quality data about the nation's people and economy. The bureau's core 
activities include: 

* conducting decennial, economic, and government censuses, 
* conducting demographic and economic surveys, 
* managing international demographic and socioeconomic databases and 
providing technical advisory services to foreign governments, and 
* performing other activities such as producing official population 
estimates and projections. 

Public and private decision makers use census population and 
socioeconomic data for various purposes. For example: 

* decennial census data are used to determine congressional and state 
legislative districts and to distribute hundreds of billions of dollars 
in federal funds each year, 
* federal agencies use census data to evaluate the effectiveness of 
established programs, and, 
* businesses use census data to target new services and products and to 
tailor existing ones to demographic changes. 

Census Bureau Organization: 

The bureau is a large and complex organization. A conceptual view of 
the agency includes three core organizations, two auxiliary 
organizations that provide guidance and operational support for the 
core organizations, and three support organizations that provide 
administrative and technical support for the entire bureau. Each of 
these organizations is headed by an associate director, who reports to 
the deputy director of the Census Bureau. 

Census Bureau: 

[See PDF for image] 

Source: U.S. Census Bureau, GAO. 

[End of figure] 

The Bureau's Decennial Census: 

The bureau's Decennial Census organization is responsible for the 
decennial census program, the nation's oldest and most comprehensive 
source of population and housing information. 

Conducting a decennial census involves: 

* identifying and correcting addresses for all known living quarters in 
the United States, 
* sending questionnaires to housing units, 
* following up with non-respondents through personal interviews, 
* trying to identify people with non-traditional living arrangements, 
* managing a voluminous workforce responsible for follow-up activities, 
* collecting census data from questionnaires, calls, and personal 
interviews, 
* summarizing and tabulating census data, and: 
* disseminating census analytical results to the public. 

The Decennial Census organization is comprised of divisions and 
offices, including the Decennial Management Division (DMD), which is 
responsible for implementing the decennial census, and the Decennial 
Systems and Contracts Management Office, which manages selected system 
contracts supporting the decennial census. 

Plans for the 2010 Decennial Systems: 

To support the 2010 Decennial Census, the bureau manages a $1.8 billion 
program called "2010 Testing, Evaluation, and Systems Design," which 
calls for the acquisition and testing of systems and technologies. Two 
of the key acquisitions are the Decennial Response Integration System 
(DRIS) and the Field Data Collection Automation (FDCA) program. 

DRIS is expected to be a system for collecting data and integrating 
census responses that come in through multiple routes, including census 
forms, telephone agents, the Internet, and from mobile computing 
devices used by field staff. DRIS is expected to standardize the 
response data and to provide it to other bureau systems for analysis 
and processing. 

The FDCA program is expected to provide mobile computing devices, 
office automation, and an IT infrastructure to support collection of 
census data in local and regional offices. Mobile computing devices 
will be used to update the bureau's address list, to perform follow up 
at addresses for which no questionnaire was returned, and to perform 
activities to measure census coverage. 

Plans for the 2010 Decennial Systems: 

In addition to DRIS and FDCA, other key systems support the planned 
2010 decennial census. These include: 

* master address file/topologically integrated geographic encoding and 
referencing-this is an existing system that contains the master list of 
addresses for the census, 

* headquarters data processing systems-these are existing systems used 
to process census data as well as a management information system, 

* data access and dissemination system II-this is a planned upgrade to 
an existing system to disseminate 2010 census data to the public. 

Together, these systems are to support the collection, processing, and 
dissemination of census data, as illustrated on the next page. 

Overview of systems supporting the 2010 Decennial Census: 

[See PDF for image] 

Source: GAO analysis of Census data. 

[End of figure] 

The bureau plans a series of tests in the years leading up to the 
decennial census. 

2004: The bureau tested critical field operations using systems under 
conditions similar to those to be used during the decennial census. In 
particular, the agency studied the feasibility of using hand-held 
mobile computing devices equipped with Global Positioning System 
capability to conduct non-response follow-up operations. We recently 
reported on lessons learned during this test. [NOTE 2] 

2006: The bureau plans to test the methodology and functions of the 
integration of systems needed to carry out the census, focusing on 
efforts to automate non-response follow-up activities and the 
initiatives to update the address list. 

2008: The bureau plans to conduct a final operational test of the 
entire complement of methodological, procedural, and systems 
innovations for the 2010 Decennial Census. This test is known as the 
Dress Rehearsal. 

NOTE: 

[2] GAO, 2010 CENSUS: Basic Design Has Potential, but Remaining 
Challenges Need Prompt Resolution, GAO-05-9 (Washington, D.C.: Jan. 12, 
2005). 

DRIS: 

Overview, Status, and Plans: 

During the prior decennial census, called Census 2000, responsibilities 
for designing and developing a system for capturing census data and 
related functions were shared by the bureau and several contractors. 
The bureau designed and developed a system for collecting data from the 
Internet, while one contractor developed a system for providing 
telephone assistance to the public, and another contractor developed a 
system for capturing data from responses returned by mail and from the 
field operations targeting non-responders. Another contractor provided 
the staffing and facilities for operating the data capture system while 
the census was underway. The bureau then integrated all of the data. 
Subsequently, the bureau found that this diversified approach resulted 
in data that was not standardized and added to the cost of processing 
census data. 

For the 2010 Decennial Census, the bureau plans to have a single 
contractor design, develop, and implement a system (DRIS) for 
standardizing and integrating the data from all of the response modes 
(paper, telephone, Internet, and from field operations). [NOTE 3] DRIS 
is intended to: 

* receive, capture, and standardize census data provided by respondents 
via census forms, telephone agents, and the Internet, 
* standardize data collected via mobile computing devices, 
* provide the data to the headquarters data processing system, 
* provide assistance to the public via telephone and the Internet, and 
* monitor the quality and status of data capture operations. 

DRIS is expected to process an estimated 90 million mailed paper 
responses, 40 million field responses, 9 million telephone calls, and 9 
million Internet visits. 

According to the bureau, qualitative improvements expected from DRIS 
include: 

* integrating paper, Internet, and telephone responses within a 
workflow control system that will provide more timely information than 
existed in previous censuses and reduce the number of cases of non-
response follow-up, 

* providing near real-time data that will support the planned second 
mailing to non-responding addresses, and: 

* reducing redundant efforts for the Census Bureau and contractors that 
existed for different contracts during Census 2000 by integrating key 
functions under one contract. In particular, efforts in the areas of 
security, data integration, change control, and contractor 
administration are expected to be reduced. 

The bureau began acquisition planning for DRIS in 2003. Between 2003 
and September 2005, the bureau spent about $7.5 million on researching 
data capture technologies, conducting web-based vendor briefings, 
obtaining comments from prospective vendors, and developing DRIS 
planning documents, strategies, and analyses. During this time, the 
bureau also established the DRIS project office within the Decennial 
Systems and Contracts Management Office (DSCMO). 

Further, between February and August 2005, the bureau completed 
solicitation activities as follows: 

* In February 2005, the bureau issued a request for proposal (RFP) for 
DRIS. 

* From March 2005 through August 2005, the bureau solicitation team 
reviewed and evaluated proposals and obtained oral presentations from 
vendors. 

* In August 2005, the solicitation team made a presentation to the 
Source Selection Evaluation Board and recommended a vendor for contract 
award. 

On October 5, 2005 the bureau awarded the contract for DRIS to Lockheed 
Martin Corporation and its 7 subcontractors. The DRIS performance 
contract is a cost-plus-award-fee contract. The contract has a 6-year 
performance period divided into 3 primary phases as follows: 

Phase I: October 2005 through December 2008: 

Includes delivering detailed design documentation, developing and 
testing DRIS, conducting the 2008 dress rehearsal, and identifying data 
centers for the 2010 Census. 

Phase II: August 2008 through the end of January 2011: 

Includes opening data center sites, completing operational testing, 
conducting 2010 Census operations, and closing down the DRIS 2010 
operations facilities once the census is complete. 

Phase III: July 2010 through end of contract: 

Includes archiving DRIS data and images in accordance with National 
Archives and Records Administration guidelines and disposing of DRIS 
equipment once it is no longer needed. 

Phases I and II of this contract are valued up to $553 million. The 
total life cycle cost of the project is considered procurement 
sensitive pending the pricing of phase III. 

Phase I of the contract involves the following key activities: 

Activity: Perform integrated baseline review[NOTE 4]; 
Due Date: March 2006. 

Activity: Deliver DRIS acquisition planning documents; 
Due Date: February-October 2006. 

Activity: Certify DRIS as ready for use at all 2008 dress rehearsal 
facilities; 
Due Date: December 2007. 

Activity: Deliver proposal for phase II-system operations and 
facilities; 
Due Date: September 2008. 

Activity: Complete dress rehearsal and production activities; 
Due Date: December 2008. 

[End of table] 

The DRIS project team is currently reassessing these phase I dates due 
to delays associated with a bid protest that has since been withdrawn. 
It expects to identify new dates by March 2006. These new dates will 
likely result in the first modification to the contract. 

Also, the team expects to work with the contractor during phase I to 
develop the milestones and deliverables for phases II and III. 

NOTES: 

[3] While the DRIS contractor is expected to standardize and organize 
response data from the hand-held computers, the scope of the DRIS 
contract does not include providing the systems or staff used for field 
enumeration operations. 

[4] An integrated baseline review is a joint assessment by the 
contractor and the project team of the technical plans for a work 
segment as well as the adequacy of the budgets, resources, and 
schedules estimated to complete that work. This review results in a 
detailed plan for work activities, costs, and schedules that is used as 
the basis for tracking the earned value of the contractor's 
deliverables. 

DRIS: 

Acquisition Management Capabilities: 

To effectively manage major IT programs, organizations use sound 
acquisition and management processes to minimize risks and thereby 
maximize chances for success. Such processes have been identified by 
leading organizations such as the Software Engineering Institute, the 
Chief Information Officer's Council, and in our prior work analyzing 
best practices in industry and government. Key areas include: 

* project and acquisition planning, 
* contract tracking and oversight/project monitoring and control, 
* solicitation, 
* requirements development and management, 
* process and product quality assurance, 
* risk management,  
* executive oversight and governance. 

Our work has shown that such processes are significant factors in 
successful systems acquisitions and development programs and that they 
improve the likelihood of meeting cost and schedule estimates as well 
as performance requirements. 

DRIS: 

Summary-Acquisition Management Capabilities: 

Summary of the status of DRIS acquisition management capabilities. 

[See PDF for image] 

[End of table] 

Project and acquisition planning: 

Effective project planning involves establishing and maintaining plans 
defining project scope and activities, including overall budget and 
schedule, key deliverables, and milestones for key deliverables. It 
also involves ensuring that the project team has the skills and 
knowledge needed to manage the project and obtaining stakeholder 
commitment to the project plan. Effective acquisition planning involves 
developing an acquisition strategy that includes objectives, projected 
costs and schedules, and risks. 

The DRIS project team has: 

* defined the overall project scope, budget, and schedule, 

* developed a draft project management plan that identifies key 
deliverables and milestones for these deliverables through the 2008 
dress rehearsal, 

* assigned an experienced and certified project manager and project 
team, and: 

* developed an acquisition strategy that outlines the acquisition 
objectives, scope, costs, schedules, and risks. 

However, the project team has not yet finalized its project plan, 
identified key deliverables beyond 2008, or obtained stakeholder 
commitment to the plan. The project team has not yet completed these 
activities in part because there is no Census Bureau policy requiring 
them to do so prior to contract award. 

Until a project plan is completed and approved, the project lacks 
assurance that it is moving in the right direction. Without this 
assurance, it is more likely to encounter unanticipated changes in 
direction-which could affect system cost, schedule, and deliverables. 

Solicitation: 

This activity includes identifying the needs within a particular 
acquisition, developing and implementing a solicitation plan, preparing 
for the evaluation of responses, issuing a solicitation package, 
evaluating responses, conducting supporting negotiations, and making 
recommendations for award of the contract. 

The DRIS project team has: 

* identified the needs for the DRIS acquisition including telephone, 
Internet, and paper data capture modes, 

* developed source selection procedures, 

* developed the evaluation criteria for evaluating vendors' proposals 
(including criteria for the technical and program management 
approaches), 

* conducted training on the evaluation process and on using an 
automated tool, and submitted a recommendation for contract award to 
the source selection officer in August 2005. 

The contract was awarded in October 2005. 

Requirements development and management: 

Requirements development involves eliciting, analyzing, and validating 
customer and stakeholder needs and expectations. Requirements 
management involves establishing an agreed-upon set of requirements, 
ensuring traceability between operational and product requirements, and 
managing any changes to the requirements in collaboration with 
stakeholders. 

To develop and manage DRIS requirements: 

* DMD, the organization that oversees the project as well as the 
overall decennial census, developed draft operational requirements for 
the overall decennial census, 

* the project team established basic functional requirements for the 
DRIS acquisition based on the data capture activities used during 
Census 2000 and assumptions for the 2010 Census data capture needs, 

* stakeholders reviewed the DRIS requirements and made suggestions for 
clarifying them, and: 

* DMD developed a detailed process for managing requirements for all 
2010 decennial systems, including DRIS; these are to be executed by DMD 
implementation teams. 

However, DMD has not yet conducted a thorough validation of DRIS 
requirements, ensured traceability between DRIS and operational 
requirements, or approved the DRIS baseline requirements. Part of the 
reason that these activities have not been completed is that there is 
no Census Bureau policy requiring them to do so prior to contract 
award. Further, DMD has not yet staffed the teams responsible for 
managing requirements or initiated any requirements management 
activities. 

Until the project team obtains validation and approval of DRIS 
requirements and ensures these requirements are traceable to the 
operational requirements, it faces increased risk that new and changing 
requirements could be identified throughout the system's development. 
[NOTE 5] Changes identified late in the development cycle could be 
costly to implement and could increase the risk that the system will 
not be ready in time to support census activities. 

Further, until the bureau staffs and implements its planned 
requirements change management process, it may not be able to 
effectively ensure that resulting products meet requirements. As a 
result, DRIS may not provide the functionality needed or the bureau may 
experience cost increases and schedule delays. 

Risk Management: 

An effective risk management process identifies potential problems 
before they occur, so that risk-handling activities may be planned and 
invoked as needed across the life of the product and project in order 
to mitigate adverse impacts on achieving objectives. Key activities 
include identifying and analyzing risks, assigning resources, 
developing risk mitigation plans and milestones for key mitigation 
deliverables, briefing senior-level managers on high priority risks, 
and tracking risks to closure. 

The DRIS project team has: 

* developed a pre-award risk management plan that defines staff roles 
and responsibilities and includes procedures for identifying and 
tracking risks and risk mitigation actions, 

* identified pre-award risks including: 

- insufficient project office or contracting office resources; 
- a bid protest; 
- inadequate funding; 
- failure to obtain agreement on quality control operations; 
- failure to mitigate privacy risks; 
- inadequate system sizing and related testing; 
- design not flexible enough to accommodate changes in technology 
related to security; 
- failure to document and test external interfaces. 

* assigned responsibilities for managing the risks and discussed 
mitigating actions, and 

* participated in monthly meetings to analyze and discuss the status of 
certain pre-award risks. 

Since contract award in October 2005, the project team has: 

* assigned a risk manager to provide oversight for the risk program, 

* implemented a tool for tracking risks and actions taken, and: 

* reviewed risks and updated the risk database. 

Also, the project team plans to: 

* conduct monthly internal reviews of DRIS risks and refer high risks 
to higher-level officials for input and approval of actions, 

* participate in the contractor's risk reviews and monitor the 
contractor's risk management plans as part of the contract's 
surveillance process, and: 

* implement a process to assess risks based on the probability of 
occurrence and the impact on business drivers. 

However, in the months since the contract was awarded, the project team 
has not developed written risk mitigation plans, identified milestones 
for key mitigation activities, or briefed senior management on its 
risks and risk mitigation plans. Specifically, there are no written 
mitigation steps or dates associated with the agencies' plans for 
addressing high-impact risks, and senior-level briefings on these risks 
have not been held. Part of the reason that these activities have not 
been completed is that there is no organizational policy requiring 
completion of these activities. 

Until the project team develops risk mitigation plans with milestones 
for key activities, and regularly briefs senior-level managers on risks 
and risk mitigation plans, it faces increased probability that DRIS 
will not be delivered on schedule, within budget, or perform as 
expected. 

Contract tracking and oversight/project monitoring and control: 

These processes provide oversight of the contractor's and the project 
office's performance, in order to allow appropriate corrective actions 
if actual performance deviates significantly from the plan. Key 
activities in tracking both the contractor's and the project office's 
performance include the selection of performance measures, 
communicating status, taking corrective actions, and determining 
progress. 

The project team is responsible for ensuring that the contractor's 
performance stays within cost and schedule thresholds for each phase of 
the DRIS contract. Therefore, the project team plans to provide 
contract tracking and oversight through: 

* earned value management reports, 
* contractor performance reports, 
* program management reviews, 
* monthly status reports. 

During Phase 1, the project team plans to determine the detailed 
requirements for these activities. 

Contract and Project Monitoring and Control (continued): 

However, the project office has not yet selected detailed performance 
measures for tracking the contractor or its own internal progress (such 
as progress against planned milestones, number of risks opened and 
closed, number and frequency of changes to requirements, and frequency 
of quality assurance reviews), in part because there is no Census 
policy requiring that these measures be implemented. Without such 
performance measures, the team cannot perform the other key activities 
of communicating status, taking corrective actions, and determining 
progress. 

As a result, the project office's view into when performance deviates 
from plans or when key activities are showing troubling trends is 
limited. This can lead to unexpected cost increases, schedule delays, 
and performance shortfalls. 

Process and Product Quality Assurance: 

This process area provides staff and management with objective insight 
into processes and associated work products. This includes the 
objective evaluation of project processes and products against approved 
descriptions and standards. Key activities include developing a quality 
assurance plan, assigning resources to quality assurance activities, 
and implementing quality assurance activities. Through quality 
assurance, the project team is able to identify and document 
noncompliance issues and provide appropriate feedback to project staff. 

The DRIS project team has identified several approaches that it plans 
to use to oversee the quality of deliverables and services produced by 
the contractor. These include: 

* requirements traceability and walkthroughs, 
* design walkthroughs, 
* peer reviews, 
* random inspections, 
* formal software quality assurance audits conducted by independent 
staff in the contractors' company. 

The project team plans to assign technical monitors to monitor, assess, 
document, and report on the contractor's performance. The team also 
expects the contractor to perform its own quality control methods to 
ensure that DRIS meets the government's requirements. The contractor's 
quality assurance plan is due in June 2006. 

However, the project team has not yet established a quality assurance 
plan, assigned resources, or implemented a quality assurance process. 
Specifically, the team has not yet determined how they will use the 
planned inspections, reviews, and walkthroughs to evaluate product 
quality. The delay in implementing this process is due in part to a 
lack of Census policy requiring these processes be in place prior to or 
soon after contract award. As a result, the project team is not able to 
ensure that it will be able to identify and document any noncompliance 
issues and take appropriate corrective actions. 

Executive Oversight and Governance: 

Office of Management and Budget and GAO guidance call for agencies to 
establish IT investment management boards comprised of key executives 
to regularly track the progress of major systems acquisitions. These 
boards should have documented policies and procedures for management 
oversight of IT projects and systems, and should be able to adequately 
oversee the project's progress toward cost and schedule milestones and 
their risks. The board should also employ early warning systems that 
enable it to take corrective actions at the first sign of cost, 
schedule, and performance slippages. 

The DRIS project received executive level oversight during early 
project planning: 

* the project was presented to key executives from the Department of 
Commerce IT Review Board and the Census Information Technology 
Governing Board (these boards include executive level managers from all 
bureau directorates, including the chief information officer and the 
chief financial officer), 

* the project team established an acquisition review team consisting of 
key information technology, acquisition, legal and program managers 
from the Census Bureau and the Department of Commerce to review and 
approve acquisition documents, 

* the project manager participated in meetings with Commerce and Census 
Bureau executives, and 

* the project team worked with senior acquisition officials to develop 
acquisition planning and solicitation documents. 

Executive-level oversight for DRIS is to continue as follows: 

* The DRIS project manager is reporting progress directly to the chief 
of the Decennial Systems and Contracts Management Office. 

* The DRIS Program Office is reporting weekly on the status of the DRIS 
project to Decennial Management Division officials. 

* The DRIS Program Office is expected to participate in quarterly 
reviews with the Commerce Information Technology Review Board, Census 
Bureau managers, and the Associate Director for Decennial Census 
Leadership Team. 

* Commerce and Census executive-level IT governing boards expect to 
review the DRIS project as part of its annual preparation for meeting 
OMB requirements, under the 2010 Testing, Evaluation, and System Design 
program. 

However, in June 2005, we reported that the Census Bureau's executive 
oversight of IT projects was incomplete. [NOTE 6] Specifically, we 
noted that the bureau lacked: 

* written procedures outlining the IT investment board's operations and 
ensuring consistent investment management and decision making practices 
and: 

* written policies and procedures for monitoring the progress of its IT 
projects and systems. 

As a result, we reported that the bureau lacks assurance that 
investment oversight and decision making is being performed in a 
consistent and repeatable manner, and that consistent and appropriate 
actions will be taken when cost, schedule, and performance expectations 
are not met. We recommended that the bureau develop and implement these 
policies and procedures. The bureau agreed to implement these 
recommendations, and expects to do so by the end of July 2006. 

Until these efforts are completed, the bureau cannot ensure that it is 
providing effective and consistent oversight for the DRIS project. 

NOTES: 

[5] While there have not been any contract modifications to date, the 
project team expects to modify the contract to reflect the revised 
schedule. 

[6] GAO-05-661. 

DRIS: 

Conclusions: 

While the DRIS project team has initiated important steps in 
establishing a sound and capable project management office, it has not 
yet completed important activities it needs to adequately manage this 
acquisition. Incomplete project plans, requirements, and risk 
management activities increase the risks that this project will 
encounter problems in meeting cost and schedule expectations. Given 
that the contract was awarded in October and is currently under way, it 
is critical that the DRIS project office expeditiously put in place key 
elements of a sound acquisition management capability. 

One of the root causes of the project's delay in completing key 
management activities is that the Census Bureau lacks organizational 
policies for managing major acquisitions. As a result, the success of 
major acquisitions such as DRIS and FDCA are extremely dependent on the 
knowledge, skills, and qualifications of the project teams. Without a 
minimum set of required steps and processes, Census acquisitions are at 
increased risk of being run in an ad hoc and chaotic manner-potentially 
resulting in increased project costs, delayed schedules, and 
performance shortfalls. 

DRIS: 

Recommendations: 

To ensure that the bureau adequately manages the DRIS project, we 
recommend that the project office take the following six actions: 

* complete the DRIS project plan and obtain stakeholders' commitment to 
the plan before initiating further development work, 

* obtain validation and management and customer approval of DRIS 
requirements, 

* staff teams and perform planned requirements management activities, 

* develop mitigation plans with milestones for key activities, and 
regularly brief senior managers on important risks, 

* establish performance measures and monitor results for contractor and 
project office activities, and: 

* implement a quality assurance process by establishing 
responsibilities for assuring product quality, and defining how 
inspections, reviews, and walkthroughs will be used to measure quality. 

Further, to ensure that the bureau improves its ability to manage this 
and other acquisitions, we recommend that the Director of the Census 
Bureau immediately establish and enforce a system acquisition 
management policy that incorporates best practices in system and 
software acquisition management (including those highlighted in this 
briefing). 

FDCA: 

Overview, Status, and Plans: 

The Field Data Collection Automation (FDCA) program is expected to 
provide automation support for field data collection operations for the 
2010 Census. Specific requirements include: 

* office automation for the twelve regional census centers, the Puerto 
Rico area office, and more than 450 local census offices, 

* the telecommunications infrastructure for headquarters, regional, and 
local offices, 

* mobile computing devices for field workers, 

* integration with other 2010 Census systems (e.g., DRIS and 
headquarters processing systems), and: 

* development, deployment, technical support, de-installation, and 
disposal services. 

Automating field data collection activities is expected to help reduce 
overall 2010 Census costs as well as improve data quality and 
operational efficiency. 

Mobile computing devices are a key technology component of FDCA. Census 
plans to have field-based enumerators use nearly 500,000 mobile 
computing devices to support the following decennial census functions: 

* case management and automated payroll for enumerators, 

* address canvassing (visiting households to update address lists and 
collect global positioning system coordinates to update maps), 

* non-response follow-up (visiting households to obtain information 
from those that did not provide responses via mail, Internet, or 
phone), 

* assignment updating to avoid unnecessary follow-up on late responses, 

* data transmission, and: 

* conducting additional interviews at a sample of households in order 
to help measure census undercounts or overcounts. 

In fiscal year 2002, the bureau conducted market research on purchasing 
mobile computing devices and then purchased and tested these devices 
during the 2004 census test. After encountering technical problems and 
realizing that they lacked resources and expertise to manage the 
project in-house, bureau officials decided to use an integration 
contractor to help develop and manage the FDCA project. 

The bureau has: 

* established a FDCA project office in January 2005, 
* held an industry symposium in February 2005, 
* issued a draft RFP and a pre-solicitation notice in April 2005, 
requesting that vendors submit examples of previous experience with 
projects similar to FDCA and describe the challenges facing the FDCA 
project. (Based on these proposals, the bureau then invited five 
vendors to develop and test prototypes for address canvassing. Of the 
five, three vendors chose to do so), 
* released the final RFP in June 2005, and: 
* conducted a technical exchange period from October to December 2005, 
during which the three vendors developed prototypes and the FDCA 
project team evaluated draft proposals. 

Project officials acknowledge that the FDCA schedule is ambitious. Key 
near-term activities include: 

Final proposals and prototypes due: January 20, 2006: 

Final evaluation: Feb. 6-Mar. 17, 2006: 

Source evaluation board review/decision: March 20-30, 2006: 

Contract award: March 31, 2006: 

Integrated baseline review: March 31-May 31, 2006: 

Dress rehearsal offices open: January 2007 (FDCA office automation 
ready): 

Dress rehearsal address canvassing: April-May 2007 (using FDCA mobile 
computing devices): 

The FDCA contract is expected to be a cost-reimbursement contract with 
multiple incentives. Cost estimates for FDCA are considered procurement 
sensitive. 

The FDCA RFP calls for a baseline planning period and three execution 
periods as follows: 

Baseline planning period: March 2006-May 2006: 

* involves the project team and contractor reaching agreement on 
schedule, cost, quality, scope, and technical performance measurement 
for the first contract execution period. 

Execution period 1: June 2006-December 2008: 

* includes activities leading up to and during the 2008 dress 
rehearsal: 

Execution period 2: January 2009-September 2011: 

* includes activities leading up to and during the 2010 Census: 

Execution period 3: August 2010-December 2011: 

* includes activities to wrap up operations after the completion of the 
2010 Census: 

FDCA: 

Summary - Acquisition Management Capabilities: 

Summary of the status of FDCA acquisition management capabilities. 

[See PDF for image] 

[End of table] 

FDCA: 

Acquisition Management Capabilities: 

Project and acquisition planning: 

Effective project planning involves establishing and maintaining plans 
defining project scope and activities, including overall budget and 
schedule, key deliverables, and milestones for key deliverables. 
Project planning also involves ensuring that the project team has the 
skills and knowledge needed to manage the project and obtaining 
stakeholder commitment to the project plan. Effective acquisition 
planning involves developing an acquisition strategy that includes 
objectives, projected costs and schedules, and risks. 

Regarding project and acquisition planning, the FDCA project office 
has: 

* defined the overall project scope and obtained an independent 
government cost estimate, 

* developed a project management plan that documents objectives and 
high-level plans for managing the acquisition, 

* established a project team with experience and certification in 
project management; 

* involved stakeholders in planning, and: 

* developed a high-level acquisition strategy that includes objectives, 
projected costs, and schedules. 

However, the office has not yet: 

* established an overall project schedule (including deliverables and 
milestones) for the project team and for the contractor for each 
contract execution period, or: 

* obtained stakeholder commitment to a comprehensive project management 
plan that includes the project's estimated costs, budget, and 
schedules. 

Bureau officials expect the project's costs and many management 
processes to be finalized shortly after the contract is awarded in 
early 2006, and they plan to work with the contractor to complete a 
master product schedule and integrated baseline review during the 
initial baseline planning period. By that time, Decennial Management 
Division (DMD) officials also plan to have the schedule for key dress 
rehearsal activities complete so that it can be considered during the 
integrated baseline review. 

In commenting on a draft of this briefing, bureau officials reiterated 
that they have an independent government cost estimate, an overall 
budget that they did not share with us due to its sensitivity, and an 
overall schedule for census activities. Officials also noted that they 
do not believe they can finalize cost, budget, deliverables, and 
milestones until after the contract is awarded because they are 
contracting for a solution-not a set of services or specific products. 

While we acknowledge the various activities that the bureau has 
undertaken to begin planning the FDCA project and the fact that a 
project plan will continue to evolve as the program proceeds, the FDCA 
project management plan does not provide stakeholders and other 
reviewers a comprehensive overview of the project's estimates of costs, 
schedules, and deliverables. Such a plan is often used to form a 
baseline for the program and to obtain buy in from stakeholders. 

Until the bureau completes key activities, including establishing 
budgets and schedules and documenting stakeholder commitment to its 
plans, it lacks assurance that reasonable plans for the project have 
been developed, and faces increased risk that the project may not 
achieve expected cost, schedule, and technical performance goals. 

Solicitation: 

This activity includes identifying the needs within a particular 
acquisition, developing and implementing a solicitation plan, preparing 
for the evaluation of responses, issuing a solicitation package, 
evaluating responses, conducting supporting negotiations, and making 
recommendations for award of the contract. 

The project office has: 

* identified needs for the FDCA acquisition, 

* developed criteria for evaluating vendor proposals, 

* generated the solicitation package, 

* developed a source selection plan, and: 

* conducted training on the evaluation process. 

In addition, the project office has begun evaluating proposals, has 
completed a technical exchange process, and plans to obtain 
recommendations from the Source Selection Board for the award of the 
contract in March 2006. 

Requirements Development and Management: 

Requirements development involves eliciting, analyzing, and validating 
customer and stakeholder needs and expectations. Requirements 
management involves establishing an agreed-upon set of requirements, 
ensuring traceability between operational and product requirements, and 
managing any changes to the requirements in collaboration with 
stakeholders. 

To develop and manage requirements, 

* DMD developed draft operational requirements for the 2010 Decennial 
Census, 

* the project office and DMD developed FDCA-specific functional 
requirements (listed in the RFP) with participation from stakeholders, 

* the project office selected automated tools for tracking requirements 
in the RFP and proposed changes to those requirements, 

* the project office drafted a requirements management plan, and: 

* DMD developed a detailed change control process for managing 
requirements for all 2010 decennial systems, including FDCA. 

Further, DMD plans to staff the implementation planning teams 
responsible for managing changes to requirements, and initiate 
requirements management activities after the FDCA contract is awarded. 

However, DMD has not yet: 

* validated and approved a baseline set of operational requirements, 
or: 

* ensured traceability between its operational requirements and the 
FDCA RFP. 

DMD officials attribute the delay in finalizing operational 
requirements primarily to the challenge of managing the magnitude and 
scope of the census and its unique environment. Until the bureau 
finalizes its operational requirements for the census and ensures that 
the FDCA RFP is consistent with the baseline requirements, the project 
will be at risk of later changes to the requirements, potentially 
affecting its ambitious development and implementation schedule. This 
is especially important given the acknowledged programmatic risk that 
there could be late changes in census scope. 

Risk Management: 

An effective risk management process identifies potential problems 
before they occur, so that risk-handling activities may be planned and 
invoked as needed across the life of the product and project in order 
to mitigate adverse impacts on achieving objectives. Key activities 
include identifying and analyzing risks, assigning resources, 
developing risk mitigation plans and milestones for key mitigation 
deliverables, briefing senior-level managers on high-priority risks, 
and tracking risks to closure. 

The project office has: 

* developed a draft risk management process and: 

* identified a number of high-level risks for the FDCA project, 
including: 

- an ambitious schedule; 
- system design faults; 
- late changes in project scope; 
- GPS signal not available; 
- maturity of FDCA contract management; 
- continuity of funding. 

To manage selected schedule and technical risks, the project office 
has: 

* adopted an approach calling for pre-award prototype development to 
address widely acknowledged schedule and technical risks, 

* incorporated an assessment of risk in its evaluation of vendor 
proposals, evaluated vendors' approaches to risk management in their 
responses to scenarios provided by the FDCA project team, and: 

* briefed senior management on these risks. 

However, the team has not yet implemented its risk management process. 
Specifically, the project team has not yet: 

* revisited or analyzed the identified risks, 
* begun prioritizing and tracking project risks, 
* assigned resources to manage risks, or: 
* documented risk mitigation plans. 

Bureau officials reiterated that they have managed FDCA risks 
throughout the pre-award process and plan to continue to do so after 
the contract is awarded, though not in the more formal manner outlined 
in our study of best practices. 

While we acknowledge that the program office continues to work to 
address key risks, ad hoc risk management activities are not a 
substitute for a more formal process where risks are routinely 
identified, prioritized, and mitigated. Until the project team 
implements an effective risk management process, it will lack a 
mechanism to address known and unknown problems. Without such a 
process, potential problems are more likely to become actual problems 
and have adverse effects on objectives-including FDCA cost, schedule, 
and performance. 

Contract Tracking and Oversight/Project Monitoring and Control: 

These processes provide oversight of the contractor's and the project 
office's performance, in order to allow appropriate corrective actions 
if actual performance deviates significantly from the plan. Key 
activities in tracking both the contractor's and the project office's 
performance include the selection of performance measures, 
communicating status, taking corrective actions, and determining 
progress. 

The project team has: 

* incorporated requirements in the RFP for earned value management and 
other status reporting by the contractor, 

* hired staff with contract surveillance experience, 

* provided training on contract surveillance to selected project staff, 
and: 

* planned to oversee the contractor using checklists, reports, site 
visits, vendor deficit tracking, and risk assessment. 

However, the project team has not yet: 

* developed detailed procedures and metrics for contract monitoring, 
or: 

* developed a full set of performance measures for internal project 
office performance, or begun tracking this performance. 

Project officials acknowledged the need for additional planning for 
these processes and activities, but do not plan to fully implement many 
aspects of these processes until after contract award. In commenting on 
a draft of this briefing, bureau officials stated that there would be 
little value in establishing metrics in advance of having a FDCA 
solution and that they plan to work with the winning vendor to 
establish meaningful metrics. Officials also stated that they have 
already begun tracking internal office performance and noted that they 
have already submitted earned value management metrics for the program 
office to the Department of Commerce. 

Given the importance of monitoring program office and contractor 
performance, best practices show that it is not too soon to begin 
identifying performance measures and developing a process for 
monitoring and managing both the program office and contractor's 
performance. Further, earned value management metrics are valuable, but 
do not comprise a comprehensive set of metrics for monitoring a 
program. The program office may identify and track other performance 
measures, including metrics for changes in risks and requirements. 
Moving forward, it will be important for the project team to establish 
strong project monitoring and control over internal performance as well 
as solid processes for tracking and overseeing the FDCA contractor's 
progress. Until it does so, the project faces increased risk of delays 
in identifying problems and taking appropriate corrective actions. 

Process and Product Quality Assurance: 

This process area provides staff and management with objective insight 
into processes and associated work products. This includes the 
objective evaluation of project processes and products against approved 
descriptions and standards. Key activities include developing a quality 
assurance plan, assigning resources to quality assurance activities, 
and implementing quality assurance activities. Through quality 
assurance, the project team is able to identify and document 
noncompliance issues and provide appropriate feedback to project staff. 

The project team has: 

* drafted plans for quality assurance, contract surveillance, and award 
fee determination that call for inspections, random sampling, periodic 
surveillance, customer feedback, and monitoring, 
* provided selected staff with training on quality assurance and 
surveillance planning, 
* begun planning to prepare staff for their roles in quality assurance, 
* assigned a quality assurance manager, and: 
* developed plans for a principal technical monitor and 12-15 technical 
monitors to evaluate contractor work products and processes. 

The project team plans to implement these quality assurance practices 
after contract award. 

Executive Oversight and Governance: 

The Office of Management and Budget and GAO guidance call for agencies 
to establish IT investment management boards comprised of key 
executives to regularly track the progress of major systems 
acquisitions. These boards should have documented policies and 
procedures for management oversight of IT projects and systems, and 
should be able to adequately oversee the project's progress toward cost 
and schedule milestones and their risks. The board should also employ 
early warning systems that enable it to take corrective actions at the 
first sign of cost, schedule, and performance slippages. 

The FDCA project received executive-level oversight during early 
project planning. 

* The project was presented to key executives from the Department of 
Commerce's IT Review Board and the Census Information Technology 
Governing Board. 

* The project manager participated in meetings with Commerce and Census 
Bureau executives. 

* The project reported to a FDCA steering committee comprised of 
executives from key bureau directorates. 

* The project team worked closely with senior acquisition officials to 
develop acquisition planning and solicitation documents. 

Executive-level oversight of FDCA is expected to continue: 

* the FDCA Program Office is expected to report weekly on the status of 
the FDCA project to Decennial Management Division officials, 
* the FDCA Program Office is expected to participate in quarterly 
reviews with the Commerce Information Technology Review Board and 
bureau managers, and 
* Commerce and Census executive-level IT governing boards expect to 
review the FDCA project as part of its annual budgetary planning, under 
the 2010 Testing, Evaluation, and System Design program. 

As previously noted, we reported in June 2005 on weaknesses in the 
bureau's executive oversight of IT projects. Specifically, we reported 
that, because the bureau did not have written procedures on how 
executive oversight was to be performed, it had less assurance that 
investment oversight and decision making was performed in a consistent 
and reasonable manner. Without clear, documented, and consistent 
governance procedures, the bureau cannot ensure that it is effectively 
and consistently overseeing these investments. 

FDCA: 

Conclusions and Recommendations: 

While the FDCA project team has initiated important steps in 
establishing a capable project management office, it has not yet 
completed important activities it needs to adequately manage this 
acquisition. For example, the bureau has not yet implemented needed 
processes for managing risks or measuring project performance. Without 
these processes in place, the bureau remains at increased risk of not 
developing and delivering FDCA on time and within budget. The project 
may also be at risk of falling short of promised functionality. Given 
the immovable deadline for performing the decennial census, the bureau 
faces greater risk of cost overruns or limited system functionality. 

To ensure that the bureau adequately manages the FDCA project, we 
recommend that the FDCA program office take the following four actions: 

* obtain stakeholder commitment to a project plan that includes 
estimated project costs and schedules, including deliverables and 
milestones, 

* obtain validation and approval of baseline requirements, 

* identify, prioritize, and assign responsibilities for risks, and 
develop and implement risk mitigation plans and actions, and: 

* develop internal and contractor performance measures and prepare to 
track project cost, schedule, and performance. 

Agency Comments and Our Evaluation: 

In providing oral and email comments on a draft of this briefing, 
Census Bureau officials, including the Associate Director for the 
Decennial Census and the Assistant Director for Decennial Information 
Technology and Geographic Systems, generally agreed with our 
recommendations and stated that time constraints and budgets have 
driven the bureau to proceed with its acquisitions before all of the 
recommended activities have been completed. Officials stated that they 
plan to complete these activities as soon as possible. 

Bureau officials also stated that they intend to rely on the DRIS and 
FDCA contractors to help refine requirements, project plans, and 
performance measures. However, our experience in reviewing major system 
acquisitions over the last several years has shown that it is important 
for the government to exercise strong leadership in managing 
requirements, plans, and measures. 

Bureau officials also offered technical corrections which we have 
incorporated as appropriate. 

[End of section] 

Appendix II: Objectives, Scope, and Methodology: 

For both the Decennial Response Integration System and Field Data 
Collection Automation program acquisitions, our objectives were to (1) 
provide an overview, status, and plans (including costs, schedule, and 
deliverables) and (2) determine if the bureau has capabilities in place 
to successfully manage and oversee the acquisitions. 

To provide each project's overview, status, and plans, we analyzed 
current project documents, including plans, acquisition documents, and 
deliverables; we also interviewed project officials. 

To determine if the bureau had capabilities in place to successfully 
manage and oversee the acquisitions, we identified sound IT systems 
acquisition and management processes from industry standards, including 
those developed by the Software Engineering Institute, and compared 
them to the Census Bureau's practices for the selected acquisitions. We 
evaluated the following processes: 

* project and acquisition planning; 

* solicitation; 

* requirements development and management; 

* risk management; 

* contract tracking and oversight/project monitoring and control; 

* process and product quality assurance; and: 

* executive oversight and governance. 

In each of the process areas listed above, we evaluated project 
documentation and interviewed project officials to determine the status 
of the bureau's efforts. We obtained comments from bureau officials, 
including the Associate Director for the Decennial Census and the 
Assistant Director for Decennial Information Technology and Geographic 
Systems, on a draft of the briefing in attachment I. We conducted our 
review between July 2005 and January 2006 at Census Bureau headquarters 
in Suitland, Maryland, in accordance with generally accepted government 
auditing standards. 

(310847): 

FOOTNOTES 

[1] 13 U.S.C. 141 (a) and (b). 

[2] GAO, Information Technology Management: Census Bureau Has 
Implemented Many Key Practices, but Additional Actions Are Needed, GAO- 
05-661 (Washington, D.C.: June 16, 2005). 

[3] Earned value management is a project management tool that 
integrates the investment scope of work with schedule and cost elements 
for investment planning and control. This method compares the value of 
work accomplished during a given period with that of the work expected 
in the period. Differences in expectations are measured in both cost 
and schedule variances. 

[4] For more information see GAO, Decennial Census: Overview of 
Historical Census Issues, GAO/GGD-98-103 (Washington, D.C.: May 1, 
1998). 

[5] An integrated baseline review is a joint assessment by the 
contractor and the project team of the technical plans for a work 
segment as well as the adequacy of the budgets, resources, and 
schedules estimated to complete that work. This review results in a 
detailed plan for work activities, costs, and schedules that is used as 
the basis for tracking the earned value of the contractor's 
deliverables. 

[6] GAO, 2010 Census: Planning and Testing Activities Are Making 
Progress, GAO-06-465T (Washington, D.C.: March 1, 2006). 

[7] GAO, Internal Revenue Service: Assessment of Fiscal Year 2006 
Budget Request and Interim Results of the 2005 Filing Season, GAO-05- 
416T (Washington, D.C.: April 7, 2005); and GAO, Business Systems 
Modernization: Internal Revenue Service's Fiscal Year 2005 Expenditure 
Plan, GAO-05-774 (Washington, D.C.: July 22, 2005).