GENERAL DECISION: FL20080037 02/08/2008 FL37 Date: February 8, 2008 General Decision Number: FL20080037 02/08/2008 Superseded General Decision Number: FL20070037 State: Florida Construction Types: Highway Counties: Broward and Palm Beach Counties in Florida. HIGHWAY CONSTRUCTION PROJECTS (excluding tunnels, building structures in rest area projects & railroad construction; bascule, suspension & spandrel arch bridges; bridges designed for commercial navigation; bridges involving marine constrcution; & other major bridges). Modification Number Publication Date 0 02/08/2008 SUFL1993-003 08/01/1993 Rates Fringes Bricklayer/Brickmason..........$ 9.50 Carpenter......................$ 10.20 Concrete Finisher..............$ 10.24 Electrician....................$ 14.73 Fence Erector..................$ 7.85 Form Setter....................$ 9.40 Grade Checker..................$ 7.25 Ironworkers: Reinforcing.................$ 12.53 Structural..................$ 12.00 Laborers: Air Tool Operators..........$ 10.19 Asphalt Rakers..............$ 7.99 Pipelayers..................$ 9.29 Unskilled...................$ 7.10 Painter........................$ 11.66 Power equipment operators: Asphalt Distributor.........$ 8.22 Asphalt Paving Machine......$ 9.84 Asphalt Screed..............$ 9.22 Backhoe.....................$ 10.27 Boom Auger Operator.........$ 9.89 Buldozer....................$ 9.43 Concrete Curb Machine Operator....................$ 10.31 Concrete Joint Saw Operator....................$ 11.07 Crane, Derrick, or Dragline....................$ 12.50 Earthmover..................$ 9.00 Forklift....................$ 7.75 Front End Loader............$ 9.26 Gradall.....................$ 10.69 Guardrail Erector...........$ 7.10 Guardrail Post Driver.......$ 7.79 Mechanic....................$ 8.94 Milling Machine Grade Checker.....................$ 7.39 Milling Machine Operator....$ 8.56 Motor Grader................$ 12.05 Mulching Machine............$ 7.25 Oiler, Greaseman............$ 9.29 Pavement Striping Machine.....................$ 8.94 Paving Striping Machine Nozzleman...................$ 7.69 Piledrivers: Leadsman..................$ 12.00 Operator..................$ 11.50 Power Subgrade Mixer........$ 9.46 Roller: Finish....................$ 8.54 Rough.....................$ 7.31 Self-prop. Rubber Tire....$ 8.31 Scraper.....................$ 8.22 Sign Erector................$ 11.33 Small Tool Operator.........$ 7.75 Tractors, Light.............$ 7.70 Trenching Machine...........$ 9.00 Widening Spreader Machine.....................$ 8.50 Traffic Controller TRAFFIC CONTROL SPECIALIST..................$ 7.66 TRAFFIC SIGNALIZATION Installers................$ 10.37 Mechanics.................$ 13.32 Truck drivers: Low-Boy.....................$ 8.51 Multi-Rear Axle.............$ 7.54 ---------------------------------------------------------------- WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental. ================================================================ Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)). ---------------------------------------------------------------- In the listing above, the "SU" designation means that rates listed under the identifier do not reflect collectively bargained wage and fringe benefit rates. Other designations indicate unions whose rates have been determined to be prevailing. ---------------------------------------------------------------- WAGE DETERMINATION APPEALS PROCESS 1.) Has there been an initial decision in the matter? This can be: * an existing published wage determination * a survey underlying a wage determination * a Wage and Hour Division letter setting forth a position on a wage determination matter * a conformance (additional classification and rate) ruling On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.) and 3.) should be followed. With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to: Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W. Washington, DC 20210 2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to: Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W. Washington, DC 20210 The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue. 3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to: Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W. Washington, DC 20210 4.) All decisions by the Administrative Review Board are final. ================================================================ END OF GENERAL DECISION