                     TITLE 2--GRANTS AND AGREEMENTS
 
   CHAPTER II--OFFICE OF MANAGEMENT AND BUDGET CIRCULARS AND GUIDANCE
 
PART 215_UNIFORM ADMINISTRATIVE REQUIREMENTS FOR GRANTS AND AGREEMENTS WITH 
 
                    Subpart C_Post Award Requirements
 
Sec. 215.25  Revision of budget and program plans.

    (a) The budget plan is the financial expression of the project or 
program as approved during the award process. It may include either the 
Federal and non-Federal share, or only the Federal share, depending upon 
Federal awarding agency requirements. It shall be related to performance 
for program evaluation purposes whenever appropriate.
    (b) Recipients are required to report deviations from budget and 
program plans, and request prior approvals for budget and program plan 
revisions, in accordance with this section.
    (c) For nonconstruction awards, recipients shall request prior 
approvals from Federal awarding agencies for one or more of the 
following program or budget related reasons.
    (1) Change in the scope or the objective of the project or program 
(even if there is no associated budget revision requiring prior written 
approval).
    (2) Change in a key person specified in the application or award 
document.
    (3) The absence for more than three months, or a 25 percent 
reduction in time devoted to the project, by the approved project 
director or principal investigator.
    (4) The need for additional Federal funding.
    (5) The transfer of amounts budgeted for indirect costs to absorb 
increases in direct costs, or vice versa, if approval is required by the 
Federal awarding agency.
    (6) The inclusion, unless waived by the Federal awarding agency, of 
costs that require prior approval in accordance with OMB Circular A-21, 
``Cost Principles for Educational Institutions,'' and OMB Circular A-
122, ``Cost Principles for Non-Profit Organizations,'' or 45 CFR part 74 
Appendix E, ``Principles for Determining Costs Applicable to Research 
and Development under Grants and Contracts with Hospitals,'' or 48 CFR 
part 31, ``Contract Cost Principles and Procedures,'' as applicable.
    (7) The transfer of funds allotted for training allowances (direct 
payment to trainees) to other categories of expense.
    (8) Unless described in the application and funded in the approved 
awards, the subaward, transfer or contracting out of any work under an 
award. This provision does not apply to the purchase of supplies, 
material, equipment or general support services.
    (d) No other prior approval requirements for specific items may be 
imposed unless a deviation has been approved by OMB.
    (e) Except for requirements listed in paragraphs (c)(1) and (c)(4) 
of this section, Federal awarding agencies are authorized, at their 
option, to waive cost-related and administrative prior written approvals 
required by OMB Circulars A-21 and A-122. Such waivers may include 
authorizing recipients to do any one or more of the following.
    (1) Incur pre-award costs 90 calendar days prior to award or more 
than 90 calendar days with the prior approval of the Federal awarding 
agency. All pre-award costs are incurred at the recipient's risk (i.e., 
the Federal awarding agency is under no obligation to reimburse such 
costs if for any reason the recipient does not receive an award or if 
the award is less than anticipated and inadequate to cover such costs).
    (2) Initiate a one-time extension of the expiration date of the 
award of up to 12 months unless one or more of the following conditions 
apply. For one-time extensions, the recipient must notify the Federal 
awarding agency in writing with the supporting reasons and revised 
expiration date at least 10

[[Page 22]]

days before the expiration date specified in the award. This one-time 
extension may not be exercised merely for the purpose of using 
unobligated balances.
    (i) The terms and conditions of award prohibit the extension.
    (ii) The extension requires additional Federal funds.
    (iii) The extension involves any change in the approved objectives 
or scope of the project.
    (3) Carry forward unobligated balances to subsequent funding 
periods.
    (4) For awards that support research, unless the Federal awarding 
agency provides otherwise in the award or in the agency's regulations, 
the prior approval requirements described in this paragraph (e) are 
automatically waived (i.e., recipients need not obtain such prior 
approvals) unless one of the conditions included in paragraph (e)(2) 
applies.
    (f) The Federal awarding agency may, at its option, restrict the 
transfer of funds among direct cost categories or programs, functions 
and activities for awards in which the Federal share of the project 
exceeds $100,000 and the cumulative amount of such transfers exceeds or 
is expected to exceed 10 percent of the total budget as last approved by 
the Federal awarding agency. No Federal awarding agency shall permit a 
transfer that would cause any Federal appropriation or part thereof to 
be used for purposes other than those consistent with the original 
intent of the appropriation.
    (g) All other changes to nonconstruction budgets, except for the 
changes described in paragraph (j) of this section, do not require prior 
approval.
    (h) For construction awards, recipients shall request prior written 
approval promptly from Federal awarding agencies for budget revisions 
whenever paragraphs (h)(1), (2) or (3) of this section apply.
    (1) The revision results from changes in the scope or the objective 
of the project or program.
    (2) The need arises for additional Federal funds to complete the 
project.
    (3) A revision is desired which involves specific costs for which 
prior written approval requirements may be imposed consistent with 
applicable OMB cost principles listed in Sec. 215.27.
    (i) No other prior approval requirements for specific items may be 
imposed unless a deviation has been approved by OMB.
    (j) When a Federal awarding agency makes an award that provides 
support for both construction and nonconstruction work, the Federal 
awarding agency may require the recipient to request prior approval from 
the Federal awarding agency before making any fund or budget transfers 
between the two types of work supported.
    (k) For both construction and nonconstruction awards, Federal 
awarding agencies shall require recipients to notify the Federal 
awarding agency in writing promptly whenever the amount of Federal 
authorized funds is expected to exceed the needs of the recipient for 
the project period by more than $5000 or five percent of the Federal 
award, whichever is greater. This notification shall not be required if 
an application for additional funding is submitted for a continuation 
award.
    (l) When requesting approval for budget revisions, recipients shall 
use the budget forms that were used in the application unless the 
Federal awarding agency indicates a letter of request suffices.
    (m) Within 30 calendar days from the date of receipt of the request 
for budget revisions, Federal awarding agencies shall review the request 
and notify the recipient whether the budget revisions have been 
approved. If the revision is still under consideration at the end of 30 
calendar days, the Federal awarding agency shall inform the recipient in 
writing of the date when the recipient may expect the decision.