Force Structure: Actions Needed to Improve Estimates and Oversight of Costs for Transforming Army to a Modular Force

GAO-05-926 September 29, 2005
Highlights Page (PDF)   Full Report (PDF, 42 pages)   Accessible Text   Recommendations (HTML)

Summary

In 2004, the Army began transforming its force into modular brigade-based units, thus expanding the number of units available for deployment and creating new command and support units. The Army is transforming while engaged in the Global War on Terrorism and developing other high-cost capabilities. This prompted congressional concern about the affordability of Army plans. Thus, under the Comptroller General's statutory authority, GAO examined the Army's restructuring. This report addresses (1) the extent of change in costs and areas of uncertainty that could affect those costs, (2) the Army's plan for funding modularity and factors that may affect affordability, and (3) whether the Army has an adequate approach to track modularity obligations.

The Army's cost estimates for its modular force are evolving and have increased substantially, and uncertainty exists that will likely increase costs further. In March 2005, the Army estimated it will need $48 billion to fund modularity through 2011, a 71 percent increase from its 2004 estimate of $28 billion. However, this latest estimate does not include $27.5 billion in personnel and construction costs the Army and GAO identified, bringing potential known costs to $75.5 billion. Uncertainties remain in this estimate related to force design, equipment, facilities, and personnel, which could increase costs or require the Army to reduce capabilities. Until the Army provides a more reliable estimate of its modularity costs, DOD and Congress will not be well positioned to weigh competing requests for funding. The Army's funding plan, which it uses as the basis for developing funding requests, relies on annual and supplemental appropriations and may present future affordability challenges. Uncertainty in cost estimates noted above, reliance on business engineering efficiencies that historically have been difficult for DOD to achieve, and likely cost growth from another high-cost program--Future Combat Systems--collectively pose the risk of making this plan unaffordable. Also, the Army will be creating most of the modular units before it has the funding to support them While the Army can generally identify overall equipment purchases, it lacks an approach for tracking most modularity obligations and thus cannot provide a reliable picture of past spending or future funding needs. Army officials said they had not established a framework to track personnel and equipment obligations in part due to the difficulty of defining whether such expenses were incurred specifically for modularity or to support the force in general. However, we note the Army has made such distinctions in its past funding requests, including identifying specific amounts needed for equipment, and will require such data to develop and justify future requests.



Recommendations

Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Implemented" or "Not implemented" based on our follow up work.

Director:
Team:
Phone:
Sharon L. Pickup
Government Accountability Office: Defense Capabilities and Management
(202) 512-9619


Matters for Congressional Consideration


Recommendation: The Congress may wish to consider requiring the Secretary of Defense to provide a plan for overseeing spending of funds provided for modularity.

Status: In process

Comments: When we determine what steps the Congress has taken, we will provide updated information.

Recommendations for Executive Action


Recommendation: To improve information available to decision makers on the cost of the Army's plan for modularity, the Secretary of Defense should direct the Secretary of the Army to provide Congress a detailed plan estimating the costs of modularity sufficient to provide Congress reasonable assurance that estimated costs reflect total costs of modularity as designed and tested. Such a plan should be prepared annually and submitted as part of justification material supporting DOD's budget request, until the modular force is fully implemented. It should include a clear definition of what costs the Army does and does not consider to be related to the modular transformation.

Agency Affected: Department of Defense

Status: In process

Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.

Recommendation: To improve information available to decision makers on the cost of the Army's plan for modularity, the Secretary of Defense should direct the Secretary of the Army to provide Congress a detailed plan estimating the costs of modularity sufficient to provide Congress reasonable assurance that estimated costs reflect total costs of modularity as designed and tested. Such a plan should be prepared annually and submitted as part of justification material supporting DOD's budget request, until the modular force is fully implemented. It should include estimates for equipment, facilities and personnel.

Agency Affected: Department of Defense

Status: In process

Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.

Recommendation: To improve information available to decision makers on the cost of the Army's plan for modularity, the Secretary of Defense should direct the Secretary of the Army to provide Congress a detailed plan estimating the costs of modularity sufficient to provide Congress reasonable assurance that estimated costs reflect total costs of modularity as designed and tested. Such a plan should be prepared annually and submitted as part of justification material supporting DOD's budget request, until the modular force is fully implemented. It should include identification of uncertainties in the plan due to pending force structure design decisions or other decisions that may affect costs, and updates to the plan as these decisions are made.

Agency Affected: Department of Defense

Status: In process

Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.

Recommendation: To improve information available to decision makers on the cost of the Army's plan for modularity, the Secretary of Defense should direct the Secretary of the Army to provide Congress a detailed plan estimating the costs of modularity sufficient to provide Congress reasonable assurance that estimated costs reflect total costs of modularity as designed and tested. Such a plan should be prepared annually and submitted as part of justification material supporting DOD's budget request, until the modular force is fully implemented. It should include a report on obligations related to the modular force made the previous fiscal year.

Agency Affected: Department of Defense

Status: In process

Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.

Recommendation: To improve information available to decision makers on the cost of the Army's plan for modularity, the Secretary of Defense should direct the Secretary of the Army to provide Congress a detailed plan estimating the costs of modularity sufficient to provide Congress reasonable assurance that estimated costs reflect total costs of modularity as designed and tested. Such a plan should be prepared annually and submitted as part of justification material supporting DOD's budget request, until the modular force is fully implemented. It should include divergences from the plan as stated in the prior year's report, and contributing factors.

Agency Affected: Department of Defense

Status: In process

Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.

Recommendation: To facilitate his oversight of the program and collecting the data for Congress mentioned above, the Secretary of Defense should direct the Secretary of the Army in coordination with the Undersecretary of Defense (Comptroller) to develop a plan for overseeing the costs related to the Army's transformation to a modular force. This plan should include an approach for tracking modular transformation costs that clearly identifies obligations for the modular force.

Agency Affected: Department of Defense

Status: In process

Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.