This is the accessible text file for GAO report number GAO-09-189R 
entitled 'Defense Acquisitions: Status of the Safety, Performance, and 
Reliability of the Expeditionary Fire Support System' which was 
released on November 18, 2008.

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

GAO-09-189R: 

United States Government Accountability Office: 
Washington, DC 20548: 

November 18, 2008: 

The Honorable Carl Levin:
Chairman:
Committee on Armed Services:
United States Senate: 

Subject: Defense Acquisitions: Status of the Safety, Performance, and 
Reliability of the Expeditionary Fire Support System: 

The Expeditionary Fire Support System (EFSS)--which consists of two 
kinds of motorized vehicles, a 120-mm mortar, an ammunition trailer, 
and fire direction equipment--is being developed to meet the United 
States Marine Corps' need for a weapon system that can be carried 
inside the MV-22 Osprey to support assault operations. The Marine Corps 
Operational Test and Evaluation Activity (MCOTEA), the independent test 
agency for the Marines, conducted initial operational testing and 
evaluation of the EFSS from May to July 2007, and reported in September 
2007, among other things, that it experienced several safety, 
performance, reliability, and mechanical problems. We briefed you on 
these and other issues related to the EFSS in September 2007. 

Subsequently, at your request, the Marine Corps delayed full-rate 
production of the EFSS until after GAO reported on the system. In 
December 2007, we issued our report,[Footnote 1] which described the 
system's safety, performance, reliability, and mechanical problems. 
MCOTEA retested the system in February and March 2008, focusing on 
determining whether the problems identified in 2007 were resolved. It 
reported its analysis of the test results in May 2008. 

In October 2008, you asked us to provide you with a brief assessment of 
the Marine Corps' conclusions regarding whether the concerns we 
reported have been addressed. To do so, we reviewed MCOTEA's May 2008 
Independent Evaluation Report from the EFSS' Follow-on Operational Test 
and Evaluation as well as documentation of the system's insensitive 
munition certification[Footnote 2], and compared the results with the 
concerns we reported in 2007. We also reviewed documentation of EFSS' 
full-rate production decision. We interviewed EFSS program officials, a 
Marine Corps Combat Development Command official, and the MCOTEA 
official who oversaw EFSS testing to obtain their perspectives 
regarding whether and how the previously reported concerns were 
addressed. We conducted this performance audit from October 2008 
through November 2008 in accordance with generally accepted government 
auditing standards. Those standards require that we plan and perform 
the audit to obtain sufficient, appropriate evidence to provide a 
reasonable basis for our findings and conclusions based on our audit 
objectives. We believe that the evidence obtained provides a reasonable 
basis for our findings and conclusions based on our audit objectives. 

Results in Brief: 

Based on the May 2008 independent test report, most of the EFSS' 
safety, performance, reliability, and mechanical issues we reported in 
2007 have been addressed through a combination of design changes and 
increased training. While some issues remain, MCOTEA did not judge them 
to be serious. The test report indicates that the EFSS' major safety 
issue we previously reported on--the system's inability to tow the 
ammunition trailer safely--has been addressed. The 2008 report also 
indicates that most of the performance issues we reported from the 2007 
initial operational testing have been addressed. For example, follow-on 
testing showed that the system met all requirements associated with 
timed events, except the maximum rate of fire requirement, and resolved 
problems with the mortar's sight. Because the maximum rate of fire was 
frequently, but not consistently achieved, MCOTEA did not report it as 
a serious shortcoming and a Marine Corps requirements official stated 
that it was not a problem. EFSS vehicles are still not capable of 
securely carrying all required equipment, but Marine Corps officials 
attributed this problem to the space constraints imposed by the need to 
fit the system inside the V-22 Osprey, rather than to a design problem. 
The 2008 follow-on testing indicated that all of the reliability issues 
we reported in 2007 have been addressed, including issues related to 
the mortar's need for maintenance, transport barrel clamp weakness, and 
inconsistent vehicle configuration. The mechanical issues we reported 
on in 2007 appear to have been addressed, although not all of them 
could be directly tested during the 2008 follow-on test events. 
Although most of EFSS's earlier problems have been addressed, MCOTEA 
reiterated in its 2008 test report that the EFSS is a survivable 
platform provided it is used within its concept of employment and that 
employing the EFSS outside of the concept of employment would present a 
significant survivability liability to the operators given its limited 
protection. 

Background: 

The EFSS is designed to use its M327 120-mm rifled mortar to provide 
mobile fire support for expeditionary forces. The EFSS includes two 
kinds of prime mover vehicles and a trailer, in addition to the mortar. 
One vehicle tows the mortar, while the other tows the trailer that 
carries ammunition for the mortar. MCOTEA reported that the EFSS has a 
capability that is not currently fielded in the operating forces. It 
provides greater range and lethality than the mortars currently in use 
by the Marine Corps and it can be internally transported via assault 
support aircraft, in particular, the MV-22 Osprey. 

MCOTEA conducted initial and follow-on operational testing and 
evaluation for the EFSS to ensure that the system meets its mission 
essential tasks as well as the criteria of Operational Effectiveness 
and Operational Suitability by providing effective fire support and 
proving its reliability, availability, and maintainability. The Initial 
Operational Test and Evaluation, which we reported on in 2007, was 
conducted in three phases: amphibious, desert, and high-altitude 
operations. Follow-on testing was conducted in two phases: cold weather 
at the Cold Regions Test Center, Fort Greely, Alaska, from February 17, 
2008, through March 2, 2008, and desert terrain at the Marine Corps Air 
Ground Combat Center, Twentynine Palms, California, from March 6-9, 
2008. Data from both the initial testing and the follow-on testing were 
used by the Marine Corps Operational Test and Evaluation Activity to 
prepare the May 2008 Independent Evaluation Report for the Follow-on 
Operational Test and Evaluation. 

On June 2, 2008, the Marine Corps Systems Command approved the EFSS 
program to move forward with full-rate production of the system. In 
addition, the Command approved full fielding of the system once certain 
conditions have been met.[Footnote 3] The program office reported that 
the request for proposal for full-rate production for fiscal year 2009 
has been issued, but they have not yet entered into a contract. 

Most EFSS Safety, Performance, Reliability, and Mechanical Issues 
Identified in 2007 Have Been Addressed: 

In the 2008 follow-on testing, MCOTEA determined that the EFSS is 
operationally effective and operationally suitable. The test report 
indicates that most of the safety, performance, and reliability issues 
identified in 2007 initial operational testing have been addressed. 
Substantial design changes were made to the system in response to 
issues identified in initial operational testing and the test unit 
participants received substantially more training in the use of the 
system than in previous tests. The Operational Test Project Officer 
stated that the prime mover was "like a completely different vehicle" 
and the director of the follow-on testing reported that the system 
"proved it can operate in extreme conditions with close to normal 
response times." Although substantial improvements have been made to 
the EFSS, it remains critical that the system be employed within its 
concept of employment in order to be survivable. Table 1 summarizes the 
status of these issues based on the 2008 testing. 

Table 1: Comparison of Selected Results from 2007 and 2008 EFSS 
Testing: 

Issue: Safety; 
Factors Limiting EFSS Capability as Reported by GAO in 2007: Ammunition 
trailer risked injury to crewmember; 
Status Based on 2008 Test Results: Addressed. 

Issue: Performance; 
Factors Limiting EFSS Capability as Reported by GAO in 2007: Measures 
associated with timed events were not met, including: rate of fire, 
first round response, shift out of traverse, emplacement, and 
displacement; 
Status Based on 2008 Test Results: Addressed except maximum rate of 
fire was not consistently met. 

Issue: Performance; 
Factors Limiting EFSS Capability as Reported by GAO in 2007: Mortar 
sight difficult to use; 
Status Based on 2008 Test Results: Addressed[A]. 

Issue: Performance; 
Factors Limiting EFSS Capability as Reported by GAO in 2007: Shock 
mount problems; 
Status Based on 2008 Test Results: Minor problems persist. 

Issue: Performance; 
Factors Limiting EFSS Capability as Reported by GAO in 2007: Vehicles 
carry required equipment, but not securely; 
Status Based on 2008 Test Results: Not addressed, but officials report 
this is due to the vehicles' size requirements. 

Issue: Reliability; 
Factors Limiting EFSS Capability as Reported by GAO in 2007: The 
mortar's mean rounds between operational mission failure did not meet 
the threshold; 
Status Based on 2008 Test Results: Addressed. 

Issue: Reliability; 
Factors Limiting EFSS Capability as Reported by GAO in 2007: Transport 
barrel clamps contributed to brake damage; 
Status Based on 2008 Test Results: Addressed. 

Issue: Reliability; 
Factors Limiting EFSS Capability as Reported by GAO in 2007: Vehicle 
physical configuration not considered to be production representative; 
Status Based on 2008 Test Results: Addressed. 

Issue: Mechanical failures; 
Factors Limiting EFSS Capability as Reported by GAO in 2007: Problems 
with Central Tire Inflation System; 
Status Based on 2008 Test Results: Addressed. 

Issue: Mechanical failures; 
Factors Limiting EFSS Capability as Reported by GAO in 2007: Cooling 
system insufficient during operations; 
Status Based on 2008 Test Results: Considered by MCOTEA to be 
addressed[B]. 

Issue: Mechanical failures; 
Factors Limiting EFSS Capability as Reported by GAO in 2007: Vehicles 
had difficulty starting at high altitude; 
Status Based on 2008 Test Results: Considered by MCOTEA to be 
addressed[B]. 

Source: GAO analysis based on Marine Corps Operational Test and 
Evaluation Activity's Expeditionary Fire Support System Follow-on Test 
and Evaluation Independent Evaluation Report (May 2008) and GAO, 
Defense Acquisitions: Status of the Expeditionary Fire Support System, 
GAO-08-331R (Washington, D.C., Dec. 21, 2007). 

[A] MCOTEA reported that the operators could use the mortar sight 
without significant problem, but the mortar does require additional 
training for the operators. 

[B] Although the EFSS was not retested under these conditions in follow-
on testing, the Operational Test Project Officer stated that he was 
satisfied with the changes because testing for a system with the same 
cooling and starting components resulted in satisfactory operation in 
high heat and at an elevation of over 8,000 feet. 

[End of table] 

Safety: 

The 2008 follow-on test report indicates that the EFSS's major safety 
issue identified in initial operational testing--the system's inability 
to tow the ammunition trailer safely, which posed a risk of injury to 
the crewmember riding in rear seat of vehicle--has been addressed. 
Three incidents involving the trailer occurred during the 2007 test 
events. Prior to the 2008 follow-on test design changes were made, 
including lengthening the tongue on the ammunition trailer to increase 
the trailer's stability, redesigning the ammunition trailer's brakes, 
and lowering tire pressure. In addition, a cage and roll bar were 
installed on the rear of the prime mover to protect the Marine riding 
in the third seat and safe towing speeds were emphasized during 
testing. The test report indicated that throughout the follow-on 
testing, the Marines operated the prime mover and trailer in accordance 
with training standards and no incidents occurred to indicate the 
trailer would pose a hazard to the operators. In addition, in 2007 we 
reported that the EFSS mortar had not yet completed insensitive 
munition certification--a certification that a munition will not 
detonate under any condition other than its intended mission. The 
program office reported and provided documentation in October 2008, 
that this certification is now complete. 

Performance: 

The report from follow-on testing indicates that most of the 
performance issues identified in initial operational testing have been 
addressed. In follow-on testing, the EFSS successfully and consistently 
met requirements for almost all timed events that MCOTEA retested due 
to performance deficiencies in initial operational testing. Marine 
Corps officials attributed this improvement primarily to more thorough 
training and the test unit's higher level of performance. During 
initial operational testing, the EFSS did not meet the critical 
requirement related to maximum rate of fire. It also did not meet some 
non-critical requirements for timed events, which involved sustained 
rate of fire, first-round response, shift out of traverse, and 
emplacement and displacement. Although required times were achieved on 
occasion for these events, the preponderance of observed times took 
longer than required. These events were all retested in 2008, during 
which the test unit successfully and consistently performed those timed 
events except for the events related to rate of fire. MCOTEA assessed 
the sustained rate of fire requirement as met.[Footnote 4] However, the 
maximum rate of fire critical requirement was not met. Although the 
test unit frequently achieved the maximum rate of fire of 4 rounds per 
minute, the average for all trials was 3.5 rounds per minute. MCOTEA 
did not report the rate of fire results as a serious shortcoming and a 
Marine Corps requirements official stated that he did not see the 
system's maximum rate of fire as a problem because the maximum rate of 
fire was shown in testing to be achievable. 

The 2008 test report also indicates that performance issues associated 
with the mortar were largely addressed. Initial testing in 2007 found 
that the mortar sight was difficult for operators to use and its 
declinations were difficult to read in low light. The program office 
reported that, in order to help address these difficulties, the sight's 
eyepiece was lengthened and a better training package was developed to 
help users learn how to use the sight more effectively. MCOTEA reported 
in 2008 that operators could use the mortar sight without significant 
problems. In addition, in initial operational testing, the shock mount 
used to protect the sight from firing vibration caused issues with 
boresight verification. The shock mount was redesigned and officials 
stated that most of the problems associated with it were resolved. 
However, the test report indicated that the shock mount still posed 
some challenges with verification of the boresight. The EFSS program 
manager stated that a modification has been made to the shock mount 
latching mechanism to address the problems caused by the shock mount. 

The remaining performance issue is the limited storage space offered by 
the system, which may not be resolvable given the system's need to be 
small enough to be transported inside a V-22 tilt-rotor aircraft. Both 
the 2007 and 2008 test reports found that the EFSS vehicles were 
capable of carrying all required equipment, but not securely. The 
reports stated that section and personal equipment were loaded and 
carried haphazardly due to insufficient storage space. Because space 
inside the vehicle is limited, the Marines need to tie down their gear 
on a "gypsy rack" or on other parts of the prime movers. A Marine Corps 
requirements official stated that this limitation will be a challenge 
in terms of packing equipment, but several officials, including the 
Test Director stated that it is a function of the need to fit the 
system inside the V-22. 

Reliability: 

Follow-on testing indicated that all of the reliability issues 
identified in initial operational testing had been addressed. In 
initial operational testing, the mortar's mean rounds between 
operational mission failure did not meet the threshold. However, in 
follow-on testing the achieved availability for the launcher was met, 
meaning it did not experience a large amount of down time for 
maintenance relative to the amount of operating time. In addition, 
initial operational testing indicated that the EFSS' transport barrel 
clamps were not stout enough to prevent its mortar tube from rotating, 
which contributed to brake damage on one mortar during movement. This 
issue has been addressed--the transport barrel clamp has been augmented 
with a stop block and follow-on testing indicates that the augmentation 
effectively prevents the mortar tube from rotating during travel. 
Lastly, initial operational testing showed that each prime mover 
vehicle's physical configuration was different--the vehicles were not 
considered to be production representative. Spare and repair parts were 
also nonstandard, and the test team could not interchange parts between 
vehicles on several occasions. MCOTEA's EFSS Operational Test Project 
Officer stated that in follow-on testing, the vehicles' physical 
configuration was consistent and the system appeared to be production 
representative. Although substandard spare and repair parts continued 
to be an issue in follow-on testing, the program office stated that a 
complete spare parts package will be produced and will undergo quality 
inspection for delivery with the full-rate production systems. 

Mechanical Issues: 

The mechanical issues we reported on in 2007 appear to have been 
addressed, although not all of them could be directly tested during the 
2008 follow-on test events. Initial testing indicated that the 
compressor for the air ride system and Central Tire Inflation System 
was not robust enough to support all the air-powered systems on the 
vehicle. However, for follow-on testing, the system's operators were 
properly trained to use the systems, which operated satisfactorily. 
Substantial engineering changes were made in response to other 
mechanical issues raised in initial operational testing and the 
Operational Test Project Officer indicated he was satisfied with those 
changes. The 2007 testing indicated that EFSS' cooling system was not 
able to cool the engine and transmission sufficiently during 
operations. In addition, the same tests indicated that the vehicles did 
not start reliably in the mornings during high-altitude operations. To 
address these and other issues, the radiator and cooling system have 
been redesigned and expanded. The program office described these 
changes as significant. No cooling issues occurred during follow-on 
testing although desert temperatures were not considered high enough to 
challenge the system. The Operational Test Project Officer indicated 
that he was satisfied with the changes because testing for another 
Marine Corps system with the same cooling system resulted in 
satisfactory operation in high heat and at an elevation of over 8,000 
feet. 

Other Considerations: 

The Marine Corps' 2008 test report pointed out that the EFSS would 
enhance the capabilities of the Marine Corps' artillery community 
because it has a capability not currently fielded in the operating 
forces, but stated that the platform is only survivable[Footnote 5] 
when used within its concept of employment. MCOTEA reported that the 
system provides greater range and lethality than the 60 and 81 
millimeter mortars currently in use and the entire EFSS can be 
internally transported via assault support aircraft, particularly the 
MV-22 Osprey. The EFSS's 2008 follow-on test report, like the initial 
test report, indicated that the EFSS is a survivable platform provided 
it is used within its concept of employment. The EFSS concept of 
employment indicates that the EFSS will be flown in via MV-22 Osprey or 
helicopter. Once on the ground, most Marines would travel by foot, with 
the EFSS accompanying them at comparable speeds and at an equivalent 
distance. The system's concept of employment does not suggest 
employment in areas with asymmetric threats such as the urban areas of 
Iraq or Afghanistan. Both test reports stated that employing the EFSS 
outside of the concept of employment would present a significant 
survivability liability to the operators given its limited protection. 

Agency Comments and Our Evaluation: 

We provided a draft of this report to Department of Defense officials 
for review and comment and they chose to provide only technical 
comments, which were incorporated as appropriate. 

We are sending copies of this report to the Secretary of Defense, the 
Commandant of the Marine Corps, and interested congressional 
committees. We will also make copies available to others upon request. 
In addition, the report will be available at no charge on GAO's Web 
site at [hyperlink, http://www.gao.gov]. If you have any questions 
concerning this report, please contact me at (202) 512-4841. Key 
contributors to this assignment are David Best, Laura Holliday, and 
Greg Campbell. 

Signed by: 

Paul Francis, Director: 
Acquisition and Sourcing Management: 

[End of section] 

Footnotes: 

[1] GAO, Defense Acquisitions: Status of the Expeditionary Fire Support 
System, [hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-08-331R] 
(Washington, D.C., Dec. 21, 2007). 

[2] Certification that a munition will not detonate under any condition 
other than its intended mission. 

[3] These conditions include: verification that safety testing has been 
successfully completed and that manuals and training protocols address 
all necessary operating cautions and safety procedures, validation of 
the production process for ammunition manufacturing, and certification 
that support equipment and special tools have been provided and 
required technical manuals have been made available. 

[4] Sustained rate of fire was not directly evaluated because the 
entire basic load of ammunition was not fired--the assessment of the 
sustained rate of fire was derived from the maximum rate of fire 
evaluation. 

[5] According to DOD, survivability is a concept that includes all 
aspects of protecting personnel, weapons, and supplies while 
simultaneously deceiving the enemy. 

[End of section] 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Phone: 

The price of each GAO publication reflects GAO’s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO’s Web site, 
[hyperlink, http://www.gao.gov/ordering.htm]. 

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional 
information. 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Ralph Dawn, Managing Director, dawnr@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: