This is the accessible text file for GAO report number GAO-05-34 
entitled 'Space Shuttle: Costs for Hubble Servicing Mission and 
Implementation of Safety Recommendations Not Yet Definitive' which was 
released on December 17, 2004.

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov.

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately.

Report to the Subcommittee on VA/HUD-Independent Agencies, Committee on 
Appropriations, U.S. Senate:

United States Government Accountability Office:

GAO:

November 2004:

Space Shuttle:

Costs for Hubble Servicing Mission and Implementation of Safety 
Recommendations Not Yet Definitive:

GAO-05-34:

GAO Highlights:

Highlights of GAO-05-34, a report to the Subcommittee on VA/HUD-
Independent Agencies, Committee on Appropriations, U.S. Senate: 

Why GAO Did This Study:

Hubble’s continued operation has been dependent on manned servicing 
missions using the National Aeronautics and Space Administration’s 
(NASA) shuttle fleet. The fleet was grounded in early 2003 following 
the loss of the Space Shuttle Columbia, as NASA focused its efforts on 
responding to recommendations made by the Columbia Accident 
Investigation Board (CAIB). In January 2004, NASA announced its 
decision to cancel the final planned Hubble servicing mission, 
primarily because of safety concerns. Without some type of servicing 
mission, NASA anticipates that Hubble will cease to support scientific 
investigations by the end of the decade.

NASA’s decision not to service the Hubble prompted debate about 
potential alternatives to prolong Hubble’s mission and the respective 
costs of these alternatives. This report addresses the basis of NASA’s 
cost estimates to (1) service Hubble using the shuttle and (2) 
implement recommendations made by the CAIB. GAO is continuing its work 
on the Subcommittee’s request that GAO examine the potential cost of a 
robotic servicing mission to the Hubble Telescope.

What GAO Found:

Although a shuttle servicing mission is one of the options for 
servicing the Hubble Space Telescope, to date, NASA does not have a 
definitive estimate of the potential cost. At our request, NASA 
prepared an estimate of the funding needed for a shuttle servicing 
mission to the Hubble. NASA estimates the cost at between $1.7 billion 
to $2.4 billion. However, documentary support for portions of the 
estimate is insufficient. For example, NASA officials told us that the 
Hubble project’s sustaining engineering costs run $9 to 10 million per 
month, but they were unable to produce a calculation or documents to 
support the estimate because they do not track these costs by servicing 
mission. Additionally, the agency has acknowledged that many 
uncertainties, such as the lack of a design solution for autonomous 
inspection and repair of the shuttle, could change the estimate.

At the same time, NASA has yet to develop a definitive cost estimate 
for implementing all of the CAIB’s recommendations but has developed a 
budget estimate for safely returning the shuttle to flight—a subset of 
activities recommended by the CAIB as needed to return the shuttle to 
full operations. NASA currently estimates return to flight costs will 
exceed $2 billion, but that estimate will likely be refined as the 
agency continues to define technical concepts. NASA provided support 
for portions of the estimate, but we found the support to be 
insufficient—either because key documents were missing or the estimates 
lacked sufficient detail. Further, NASA cautions that return to flight 
costs will remain uncertain until the first return to flight shuttle 
mission, which is scheduled to go to the International Space Station in 
spring 2005.

Hubble Space Telescope: 

[See PDF for image]

[End of figure] 

What GAO Recommends:
 
GAO is not making recommendations in this report.

www.gao.gov/cgi-bin/getrpt?GAO-05-34.

To view the full product, including the scope and methodology, click on 
the link above. For more information, contact Allen Li at (202) 
512-4841 or lia@gao.gov.

[End of section]

Contents:

Letter:

Results in Brief:

Background:

NASA's Cost Estimate for a Hubble Servicing Mission Using the Shuttle 
Is Not Definitive:

Estimate for Implementing CAIB Recommendations Is Not Fully Developed:

Agency Comments and Our Evaluation:

Appendix I: Scope and Methodology:

Appendix II: Comments from the National Aeronautics and Space 
Administration:

Appendix III: GAO Contact and Staff Acknowledgments:

Tables:

Table 1: Budget Estimate for Shuttle Servicing of Hubble:

Table 2: Return to Flight Budget Estimates as of July 2004:

Table 3: Return to Flight Budget Estimate Review Status as of 
July 2004:

Abbreviations:

CAIB: Columbia Accident Investigation Board:

NASA: National Aeronautics and Space Administration:

PRCB: Program Requirements Control Board:

UCA: undefinitized contract actions:

United States Government Accountability Office:

Washington, DC 20548:

November 19, 2004:

The Honorable Christopher S. Bond: 
Chairman: 
The Honorable Barbara A. Mikulski: 
Ranking Member: 
Subcommittee on VA/HUD-Independent Agencies: 
Committee on Appropriations:
United States Senate:

For more than a decade, the National Aeronautics and Space 
Administration's (NASA) Hubble Space Telescope has provided unique 
images of the universe and has given scientists critical data needed to 
help understand a number of space mysteries. Hubble's continued 
operation has been dependent on NASA's space shuttle fleet, which 
carried crewmembers to the telescope to perform periodic maintenance 
and upgrades. The grounding of the shuttle fleet following the tragic 
loss of Space Shuttle Columbia in February 2003 put these missions to 
Hubble on hold, and in January 2004, NASA announced its decision to 
cancel the fifth and final planned Hubble servicing mission. With no 
future servicing missions, NASA anticipates that Hubble will cease to 
support scientific investigations by the end of the decade.

NASA said that its decision to cancel the servicing mission was based 
largely on concerns about shuttle safety--specifically, the need to 
implement recommendations made by the Columbia Accident Investigation 
Board (CAIB) for safely returning the space shuttle to flight.[Footnote 
1] NASA also recognized that a Hubble servicing mission would 
necessitate further changes both to shuttle hardware and operational 
procedures. However, NASA's decision has prompted considerable debate. 
Congressional members, scientists, and space policy experts have called 
for an examination of alternatives to prolong Hubble's mission, such as 
the possibility of servicing Hubble robotically. The CAIB Chairman 
suggested that only a study of the benefits and risks of a shuttle 
servicing mission to extend Hubble's life could determine whether it is 
worth the risks.

This report addresses the basis for NASA's cost estimates to 
(1) service the Hubble Telescope by using the shuttle and (2) implement 
the CAIB's recommendations, including those recommendations directly 
related to safely returning the shuttle to flight. We are continuing 
our work on your request that we examine the potential cost of a 
robotic servicing mission to the Hubble Telescope.

To assess the basis for NASA's Hubble servicing mission cost estimate, 
we examined NASA's rationale for its decision to cancel the final 
planned shuttle servicing mission, analyzed available funding 
estimates, and requested analytical and documentary support for 
selected high-dollar items to identify the sufficiency of support. In 
reviewing the basis for NASA's cost estimate for implementing the 
CAIB's recommendations, we analyzed available funding estimates and 
requested analytical and documentary support for selected high dollar 
portions of the estimate to determine the sufficiency of such support. 
We performed our review from March through September 2004 in accordance 
with generally accepted government auditing standards. For a complete 
description of our scope and methodology, see appendix I.

Results in Brief:

Definitive cost estimates to facilitate decisions regarding options for 
servicing the Hubble are critical. However, NASA has not yet developed 
such an estimate for one of the options--a shuttle servicing mission. 
At our request, NASA prepared an estimate of the funding needed for a 
shuttle servicing mission to Hubble. However, NASA could not provide 
documented support for key portions of the estimate, stating that there 
are many uncertainties that could change the estimate, such as the lack 
of a design solution for two safety-related requirements--autonomous 
inspection and repair and crew rescue mission capabilities.

Similarly, NASA does not have a definitive cost estimate for 
implementing all of the CAIB recommendations. The agency has been 
focusing primarily on those recommendations it considers necessary to 
return the shuttle fleet to flight. NASA's current estimate for 
implementing those recommendations is more than $2 billion. NASA 
provided us with documentary support for portions of the estimate, but 
we found some of the support to be insufficient. In NASA's view, the 
estimate for returning the shuttle fleet to flight will remain 
uncertain until the first shuttle mission to the International Space 
Station.

In written comments, which are reprinted in appendix II, NASA stated 
that the agency believes that both the estimate and the methodology 
used in calculating the costs of reinstating the servicing mission are 
sound and accurate given the level of definition of the mission at this 
point in time. However, the agency agreed that some portions of the 
servicing mission activities lacked the design maturity required to 
estimate the costs according to NASA accepted and established 
procedures.

Background:

Since it was launched in 1990, the Hubble Space Telescope has sent 
back images of space that have made a significant contribution to our 
understanding of the universe. The telescope uses pointing precision, 
powerful optics, and state-of-the-art instruments to explore the 
visible, ultraviolet, and near-infrared regions of the electromagnetic 
spectrum. To keep it at the forefront of astronomical research and 
extend its operational life, Hubble's instruments have been upgraded 
through a series of shuttle servicing missions. The fifth and final 
planned servicing mission was intended to install new science 
instruments, replace the telescope's insulation, and replace the 
batteries and gyroscopes. According to NASA, the lifetime of the 
observatory on orbit is ultimately limited by battery life, which may 
extend into the 2007-2008 time frame, but scientific operations are 
limited by the gyroscopes that stabilize the telescope--whose lifetimes 
are more difficult to predict. NASA forecasts that the Hubble will 
likely have fewer than three operating gyroscopes by mid-2006, and 
fewer than two by mid-2007.

In response to congressional concerns about NASA's decision to cancel 
the servicing mission, NASA requested that the National Research 
Council[Footnote 2] conduct an independent assessment of options for 
extending the life of the Hubble Space Telescope. In May 2004, the 
Council established a committee to assess the viability of a shuttle 
servicing mission, evaluate robotic and ground operations to extend the 
life of the telescope as a valuable scientific tool, assess telescope 
component failures and their impact, and provide an overall risk-
benefit assessment of servicing options. In an interim report issued in 
July 2004, the committee urged NASA to commit to a Hubble servicing 
mission that accomplishes the objectives of the canceled servicing 
mission and to take no actions that would preclude using a space 
shuttle to carry out this mission. According to a NASA official, the 
agency is not actively pursuing the shuttle servicing option but is not 
precluding it.

NASA is currently evaluating the feasibility of performing robotic 
servicing of the Hubble Telescope. To facilitate the evaluation, the 
agency has formulated a robotic mission concept, which includes a 
vehicle comprised of a robotic servicing module and another module that 
can be used to eventually de-orbit the telescope. The potential task 
list of activities for robotic servicing includes replacing the 
gyroscopes and batteries, installing new science instruments, and de-
orbiting the observatory at the end of its life. According to a NASA 
official, contracts to facilitate the robotic mission were recently 
awarded for work to begin on October 1, 2004.

The CAIB concluded that the Columbia accident was caused by 
both physical and organizational failures. The Board's 15 return to 
flight recommendations necessary to implement before the shuttle fleet 
can return to flight primarily address the physical causes of the 
accident and include eliminating external tank debris shedding and 
developing a capability to inspect and make emergency repairs to the 
orbiter's thermal protection system. NASA publishes periodic updates to 
its plan for returning the shuttle to flight to demonstrate the 
agency's progress in implementing the CAIB recommendations. The most 
recent update is dated August 27, 2004. This update identifies the 
first shuttle flight as occurring in spring 2005.

NASA's Cost Estimate for a Hubble Servicing Mission Using the Shuttle 
Is Not Definitive:

NASA does not currently have a definitive cost estimate for servicing 
the Hubble Telescope using the shuttle. The agency focused on safety 
concerns related to a servicing mission by the space shuttle in 
deciding not to proceed, and did not develop a cost estimate. At our 
request NASA prepared an estimate of the funding needed for a Hubble 
servicing mission by the space shuttle. NASA could not provide 
documented support for its estimate. The agency recognizes that there 
are many uncertainties that could change the estimate. NASA has now 
begun to explore the costs and benefits of various servicing 
alternatives, including robotic servicing, which should enable NASA to 
make a more informed decision regarding Hubble's future.

At our request NASA began development of an estimate of the funding 
needed for a shuttle servicing mission to the Hubble. The estimate 
provided captures additional funds over and above NASA's fiscal year 
2005 budget request that would be required to reinsert the mission in 
the shuttle flight manifest for launch in March 2007. The estimate does 
not include funding already expended to support the canceled servicing 
mission and develop the science instruments. NASA has determined that 
the additional funds needed to perform a shuttle servicing mission for 
Hubble would be in the range of $1.7 billion to $2.4 billion. According 
to NASA, this estimate is based on what it might cost, but it does not 
take into account the technical, safety, and schedule risks that could 
increase the cost and/or undermine the viability of the mission. For 
example, NASA cites uncertainties related to two safety-related 
requirements: inspection and repair and crew rescue mission 
capabilities that would be autonomous of the International Space 
Station and for which NASA currently has not formulated a design 
solution.[Footnote 3] In addition, NASA cautions that it did not 
examine whether design solutions could be accomplished in time to 
service Hubble before it ceases operations. Table 1 shows NASA's budget 
estimate phased by fiscal year (FY) for shuttle servicing of the Hubble 
Space Telescope, including ranges for some of the estimates.

Table 1: Budget Estimate for Shuttle Servicing of Hubble:

Real year dollars in millions[A].

Sustaining engineering for Hubble project; 
Fiscal year: 2005: $115; 
Fiscal year: 2006: $141; 
Fiscal year: 2007: $105; 
Fiscal year: 2008: $26; 
Fiscal year: 2009: $30; 
Budget to Complete: $40; 
Total[A]: $457.

Delay de-orbit mission until 2012; 
Fiscal year: 2007: $(69); 
Fiscal year: 2008: $(136); 
Fiscal year: 2009: $79; 
Budget to Complete: $166; 
Total[A]: $40.

Extend Hubble operations to 2012; 
Budget to Complete: $117; 
Total[A]: $117.

Shuttle services unique to servicing mission and extravehicular 
activity[B]; 
Fiscal year: $2006: $18; 
Fiscal year: 2007: $15; 
Total[A]: $33.

Payload processing; 
Fiscal year: 2005: $7; 
Fiscal year: 2006: $7; 
Fiscal year: 2007: $13; 
Fiscal year: 2008: $10; 
Fiscal year: 2009: $7; 
Total[A]: $43.

Autonomous inspection and repair capability; 
Fiscal year: 2004: $116- 134; 
Fiscal year: 2005: $74-86; 
Fiscal year: 2006: $52-60; 
Fiscal year: 2007: $18-21; 
Total[A]: $260-300.

Autonomous rescue mission capability; 
Fiscal year: 2004: $85-98; 
Fiscal year: 2005: $116-134; 
Fiscal year: 2006: $61-71; 
Fiscal year: 2007: $31- 36; 
Total[A]: $293-338.

Rescue mission unique requirements and ground operations; 
Fiscal year: 2006: $1; 
Fiscal year: 2007: $22; 
Total[A]: $22.

International Space Station Program impact (3-month delay); 
Fiscal year: 2006: $(5); 
Fiscal year: 2007: $(15); 
Fiscal year: 2008: $(13); 
Fiscal year: 2009: $(4); 
Budget to Complete: $50; 
Total[A]: $13.

Delay shuttle phase-out 3 months; 
Fiscal year: 2007: $9- 0; 
Fiscal year: 2008: $17-72; 
Fiscal year: 2009: $26-249; 
Budget to Complete: $350-757; 
Total[A]: $401-1,078.

Total[A]; 
Fiscal year: 2004: $200-231; 
Fiscal year: 2005: $312-341; 
Fiscal year: 2006: $275-293; 
Fiscal year: 2007: $128-127; 
Fiscal year: 2008: $(95)-(41); 
Fiscal year: 2009: $137-361; 
Budget to Complete: $723-1,130; 
Total[A]: $1,679-2,441. 

Source: NASA.

Note: Estimates are in full cost. The concept of full cost ties all 
agency costs (including civil service personnel costs) to major 
activities. This includes costs that are directly related to a specific 
project, such as contractor-supplied hardware, and indirect costs such 
as administrative costs, rents, utilities, and travel costs that cannot 
be directly identified with a specific project but which can be 
allocated based on direct labor hours, square footage, or other 
methods.

[A] In some cases, totals do not add because of rounding.

[B] Extravehicular activity is a space walk.

[End of table]

While we did not independently verify each component of NASA's 
estimate, we requested that NASA provide the analytical basis and 
documentary support for selected portions of the estimate, primarily 
those with large dollar values. NASA could not provide the requested 
information. For example, NASA officials told us that the Hubble 
project's sustaining engineering costs run $9 to 10 million per month, 
but they were unable to produce a calculation or documents to support 
the estimate because they do not track these costs by servicing 
mission. We also requested the basis of estimate for the costs to delay 
shuttle phase-out and for tools development for vehicle inspection and 
repair without the International Space Station (a component of 
extravehicular activity above). In response, NASA provided the 
assumptions upon which the estimates were based and stated that the 
estimates were based on information provided by Johnson Space Center 
and Kennedy Space Center subject matter experts. NASA also added that 
rigorous cost estimating techniques could not be applied to the tools 
development estimate because a rescue mission currently is only a 
concept. No analytical or documentary support was provided. In 
estimating the cost for the autonomous inspection and repair and rescue 
mission capabilities, NASA used a 30 to 50 percent uncertainty factor 
because of the very high uncertainty in the cost of developing and 
conducting a mission that is not adequately defined--i.e., NASA's 
estimate of $425 million plus 50 percent equals the $638 million upper 
range shown in the table above for these two items added together. As 
with the other estimates for which we requested analytical and 
documentary support, NASA was not able to provide it because the agency 
could not do a risk analysis without a design solution, according to a 
NASA official. The lack of documented support for portions of NASA's 
estimate increases the risk of variation to the estimate. Further, NASA 
recognizes that there are many uncertainties that could change the 
current estimate.

The 2004 NASA Cost Estimating Handbook states that cost analysts should 
document the results of cost estimates during the entire cost 
estimating process and that the documentation should provide sufficient 
information on how the estimate was developed so that independent cost 
analysts could reproduce the estimate. According to the handbook, the 
value of the documentation and analysis is in providing an 
understanding of the cost elements so that decision-makers can make 
informed decisions.

Recently, we also reported that dependable cost estimates are essential 
for establishing priorities and making informed investment decisions in 
the face of limited budgets.[Footnote 4] Without this knowledge, a 
program's estimated cost could be understated and thereby subject to 
underfunding and cost overruns, putting programs at risk of being 
reduced in scope or requiring additional funding to meet their 
objectives.

Since we began our review, attention has focused on alternatives to a 
shuttle mission, such as robotic servicing of Hubble. NASA has formed a 
team to evaluate Hubble servicing alternatives, including cost 
information. This analysis should enable NASA to make a more informed 
decision about Hubble's future and facilitate NASA's evaluation of the 
feasibility of robotic servicing options.

Estimate for Implementing CAIB Recommendations Is Not Fully Developed:

Currently, NASA has developed budget estimates for implementing the 
CAIB recommendations required to return the space shuttle to flight but 
not for all of the CAIB recommendations. NASA provided us with 
documentary support for portions of the return to flight estimate, but 
we found it to be insufficient. According to NASA, the agency's cost 
for returning the shuttle to flight, which is slightly over $2 billion, 
will remain uncertain until the completion of the first shuttle 
missions to the International Space Station in fiscal year 2005.

NASA's return to flight activities involve enhancing the shuttle's 
external tank, thermal protection system, solid rocket boosters, and 
imagery system to address the physical cause of the Columbia accident-
-a piece of insulating foam that separated from the external tank and 
struck a reinforced carbon-carbon panel on the leading edge of the 
orbiter's left wing. To address this cause, NASA is working to 
eliminate all external tank debris shedding. Efforts are also in place 
to improve the orbiter's thermal protection system, which includes heat 
resistant tiles, blankets, and reinforced carbon-carbon panels on the 
leading edge of the wing and nose cap of the shuttle, to increase the 
orbiter's ability to sustain minor debris damage. NASA is also 
redesigning the method for catching bolts that break apart when the 
external tank and solid rocket boosters separate as well as providing 
the capability to obtain and downlink images after the separation. NASA 
and the United States Air Force are working to improve the use of 
ground cameras for viewing launch activities. Table 2 shows NASA's 
budget estimates for return-to-flight activities.

Table 2: Return to Flight Budget Estimates as of July 2004:

Real year dollars in millions[A].

Orbiter reinforced carbon-carbon inspections; 
Fiscal year: 2003: $2; 
Fiscal year: 2004: $38; 
Fiscal year: 2005: $7.

On-orbit thermal protection system inspection and extravehicular 
activity tile repair; 
Fiscal year: 2003: $20; 
Fiscal year: 2004: $68; 
Fiscal year: 2005: $130.

Orbiter workforce; 
Fiscal year: 2003: $0; 
Fiscal year: 2004: $5; 
Fiscal year: 2005: $37.

Orbiter thermal protection system hardening; 
Fiscal year: 2003: $0; 
Fiscal year: 2004: $28; 
Fiscal year: 2005: $34.

Orbiter certification/verification; 
Fiscal year: 2003: $0; 
Fiscal year: 2004: $47; 
Fiscal year: 2005: $26.

Orbiter other; 
Fiscal year: 2003: $0; 
Fiscal year: 2004: $15; 
Fiscal year: 2005: $16.

External tank items (camera, bipod ramp, etc.); 
Fiscal year: 2003: $11; 
Fiscal year: 2004: $114; 
Fiscal year: 2005: $94.

Solid rocket booster items (bolt catcher, camera, etc.); 
Fiscal year: 2003: $1; 
Fiscal year: 2004: $8; 
Fiscal year: 2005: $26.

Ground camera ascent imagery upgrade; 
Fiscal year: 2003: $8; 
Fiscal year: 2004: $40; 
Fiscal year: 2005: $58.

Kennedy Space Center ground operations workforce; 
Fiscal year: 2003: $0; 
Fiscal year: 2004: $32; 
Fiscal year: 2005: $36.

Other (system integration, hardware processing and operations systems 
verification, and space shuttle main engine technical assessment); 
Fiscal year: 2003: $0; 
Fiscal year: 2004: $67; 
Fiscal year: 2005: $177.

Stafford-Covey team; 
Fiscal year: 2004: $3; 
Fiscal year: 2005: $1.

Total[B]; 
Fiscal year: 2003: $42; 
Fiscal year: 2004: $465; 
Fiscal year: 2005: $643; 
Fiscal year: 2006-2009[A]: $1,067; 
Total[B]: $2,217.

Source: NASA.

Note: According to NASA, not all elements of full cost have been 
distributed to return to flight activities.

[A] Fiscal years 2006-2009 are NASA preliminary estimates, and a cost 
breakout by activity is not available.

[B] In some cases, totals do not add because of rounding.

[End of table]

However, the majority of NASA's budget estimates for returning the 
shuttle to flight are not fully developed--including those for fiscal 
year 2005--as indicated by the agency's internal approval process. The 
Program Requirements Control Board (PRCB) is responsible for directing 
studies of identified problems, formulating alternative solutions, 
selecting the best solution, and developing overall estimates.
[Footnote 5] According to NASA, actions approved with PRCB directives 
have mature estimates, while those with control board actions in 
process--that is currently under review but with no issued directives 
yet--are less mature. Both the content and estimates for return to 
flight work that have not yet been reviewed by the control board are 
very preliminary and subject to considerable variation. Table 3 shows 
the status of control board review of NASA return to flight budget 
estimates and the percent of the total estimate at each level of 
review.

Table 3: Return to Flight Budget Estimate Review Status as of July 
2004:

Real year dollars in millions.

Control board review complete; directive issued; 
Fiscal year: 2003: $31; 
Fiscal year: 2004: $319; 
Fiscal year: 2005: $117; 
Fiscal year: 2006: $53; 
Fiscal year: 2007: $47; 
Fiscal year: 2008: $49; 
Fiscal year: 2009: $39; 
Total[A]: $655; 
Percent of total[A]: 29%.

Been to control board; directive not yet issued; 
Fiscal year: 2003: $11; 
Fiscal year: 2004: $146; 
Fiscal year: 2005: $217; 
Fiscal year: 2006: $117; 
Fiscal year: 2007: $125; 
Fiscal year: 2008: $134; 
Fiscal year: 2009: $109; 
Total[A]: $859; 
Percent of total[A]: 39%.

In review process; 
Fiscal year: 2005: $309; 
Fiscal year: 2006: $162; 
Fiscal year: 2007: $84; 
Fiscal year: 2008: $79; 
Fiscal year: 2009: $70; 
Total[A]: $704; 
Percent of total[A]: 32%.

Total Return to Flight activities[A]; 
Fiscal year: 2003: $42; 
Fiscal year: 2004: $465; 
Fiscal year: 2005: $643; 
Fiscal year: 2006: $331; 
Fiscal year: 2007: $257; 
Fiscal year: 2008: $261; 
Fiscal year: 2009: $218; 
Total[A]: $2,217; 
Percent of total[A]: 100%.

Source: NASA.

Note: According to NASA, not all elements of full cost have been 
distributed to return to flight activities.

[A] In some cases, totals do not add because of rounding. 

[End of table]

NASA provided us with the PRCB directives and in some cases, 
attachments which the agency believes support the estimate.[Footnote 6] 
However, we did not find this support to be sufficient. According to 
NASA's cost estimating handbook, estimates should be documented with 
sufficient detail to be reproducible by an independent analyst. 
Nevertheless, in many cases, there were no documents attached to the 
directive, and in cases where documents were attached to the 
directives, the documents generally provided high-level estimates with 
little detail and no documentation to show how NASA arrived at the 
estimate. For example, a request for $1.8 million to fund the network 
to support external tank camera transmissions indicated that 
$1.516 million of the amount would be needed for Goddard Space Flight 
Center to provide the necessary equipment at receiving stations, labor, 
subcontractor costs, and travel and that the remaining $290,000 would 
be needed for improvements to the receiving antennas ($104,000) and 
recurring costs ($62,000 per flight) for three trucks and the 
associated transponder time. However, the documents did not show how 
the requester for the $1.8 million arrived at the estimates. NASA 
officials told us that the reason for this was that the managers 
approving the directives trusted their employees to accurately 
calculate the estimate and maintain the support. In addition, our 
review of the documents indicated and NASA confirmed that quite a few 
of the estimates were based on undefinitized contract actions (UCA)--
that is, unnegotiated contract changes. Under these actions, NASA 
officials can authorize work to begin before NASA and the contractor 
agree on a final estimated cost and fee. As we have stated in our high-
risk series, relying on unnegotiated changes is risky because it 
increases the potential for unanticipated cost growth.[Footnote 7] 
This, in turn, may force the agency to divert scarce budget resources 
intended for other important programs. As of July 31, 2004, NASA 
records showed 17 UCAs related to return to flight with not-to-exceed 
amounts totaling $147.5 million. NASA's estimate for the entire effort 
under these UCAs totals about $325 million, or 15 percent of NASA's 
current $2.2 billion return to flight estimate.

In June 2004, NASA established additional requirements for funding 
requests submitted to the PRCB. Under the new policy, an independent 
cost estimate must be developed for requests greater than $25 million, 
and a program-level cost evaluation must be completed for requests over 
$1 million. The program-level evaluation consists of a set of standard 
questions to document the rationale and background for cost-related 
questions. The responses to the questions are initially assessed by a 
cost analyst but are reviewed by the Space Shuttle Program Business 
Manager before submission to the PRCB.

NASA provided us with two examples of requests falling under the new 
requirements. Both of the examples had better support than those with 
PRCB directives, but documentary support was still not apparent. For 
example, the funding request for a debris radar indicated that the 
estimate was based on a partnering agreement with the Navy and the 
Navy's use of the technology. However, the program-level evaluation 
pointed out that no detailed cost backup was provided. The other 
example, which was a funding request to change the processes currently 
in place for the Space Shuttle Program's problem reporting and 
corrective action system, was very well supported in terms of analysis, 
as the requester prepared detailed spreadsheets calculating the funding 
requirements according to a breakdown of the work to be performed, 
cited sources for labor rates, and provided assumptions underlying the 
calculations. However, as pointed out in the program evaluation of the 
request, there was no support provided for the estimate other than the 
initiator's knowledge of the change. We believe that future compliance 
with NASA's new policy establishing additional requirements for funding 
requests and the inclusion of documentary support could potentially 
result in more credible return to flight budget estimates.

According to NASA, estimates for fiscal year 2005 and beyond will be 
refined as the Space Shuttle Program comes to closure on return to 
flight technical solutions and the return to flight plan is finalized. 
NASA expects that by late fall of 2004, a better understanding of the 
fiscal year 2005 financial situation will be developed. However, NASA 
cautions that the total cost of returning the shuttle to flight will 
remain uncertain until completion of the first shuttle missions to the 
space station, scheduled to begin in spring 2005.

Agency Comments and Our Evaluation:

In written comments on a draft of this report, the NASA Deputy 
Administrator stated that the agency believes that both the estimate 
and methodology used in the calculation of costs for reinstating the 
Hubble Space Telescope servicing mission are sound and accurate, given 
the level of definition at this point in time. Notwithstanding that 
belief, the agency agreed that portions of the servicing mission 
activities lacked the design maturity required to estimate the costs 
according to accepted and established NASA procedures.

Specifically, NASA agrees that the Hubble Space Telescope work 
breakdown structure was not constructed to collect program costs. At 
the same time, NASA believes it is erroneous to suggest that NASA has 
no valid basis for the numbers provided, citing the "Servicing Mission 
4 Resources Management Plan," which describes the effort required for 
completion of a servicing mission. According to NASA, although the 
program's accounting system does not capture sustaining engineering 
costs in GAO's preferred format, the Servicing Mission 4 Resources 
Management Plan details mission schedules and staffing, and applying 
contractor and civil service rates to that staffing level can 
accurately reflect the effort required to execute a servicing mission. 
We requested this type of analysis and documentary support, but NASA 
representatives did not offer such a calculation. Rather, the officials 
stated that the sustaining engineering costs were based on management's 
assessment of contractor financial data and in-house service pool 
charges and that these activities could not be traced back to source 
documentation. Without adequate supporting data, we cannot assess the 
accuracy and reliability of such information.

NASA acknowledged that the agency does not have a technical design from 
which to derive the cost for the on-orbit inspection and repair of the 
shuttle independent of support from the International Space Station. In 
the case of the unsupported cost estimate for delaying the phase out of 
the space shuttle in order to complete a manned Hubble servicing 
mission, NASA stated that it used approved budget projections for the 
operating years affected by the insertion of the Hubble servicing 
mission and prorated the extension of the service life. According to 
NASA, a range was added to the estimate to account for uncertainties 
and retention of critical skills. The estimates were presented as a 
rough order of magnitude. NASA stated that it provided its assumptions 
to demonstrate the reasonableness of the estimates. Nevertheless, in 
spite of the uncertainties in the estimate, which we recognized in our 
report, NASA guidance states that cost estimates should be documented 
during the entire cost estimating process and that the documentation 
should provide sufficient information on how an estimate was developed 
to be reproducible by independent cost analysts. NASA did not provide 
us with this type of documentation. Without adequate supporting data, 
we cannot assess the accuracy and reliability of such information. We 
do not agree that the use of approved budget projections is a reliable 
cost estimating methodology, particularly given the long-term budget 
implications of the extension of the space shuttle's service life.

NASA believes that the examples it provided of the actions to implement 
several of the CAIB recommendations attest to the rigor of the process 
and approved procedures NASA utilized to validate the costs. According 
to NASA, the estimates will mature as the technical solutions mature, 
but the estimates were not refined at the time of our review. The 
agency believes the outstanding technical issues necessary to return to 
flight are beginning to be resolved. However, the examples that NASA 
provided were in support of estimates that the agency considers mature. 
We requested support for high dollar portions of NASA's estimate, which 
the agency did not provide. However, NASA selectively provided examples 
of what it considered to be mature estimates. We reviewed the examples 
but found that most of them contained insufficient documentation to 
assess the reliability of the estimates. In many cases, there were no 
documents in the approval packages to support the estimates, and in 
cases where there were documents, they generally provided high-level 
estimates with little detail and no documentation to show how NASA 
arrived at the estimates. We believe that because of its difficulty 
providing reliable cost estimates, NASA cannot provide the Congress 
assurance that its budget request for the shuttle program for fiscal 
year 2006 will be sufficient and that shortfalls would not need to be 
met through reductions in other NASA programs.

NASA stated that it believes the use of UCAs is both reasonable and 
necessary for return to flight activities. We agree that UCAs may be 
justified to facilitate work outside the scope of existing contracts to 
expedite the return to flight activities. However, the use of UCAs 
appears to be a growing trend and is a risky contract management 
practice because it increases the potential for unanticipated cost 
growth. In the past, we cited the agency's use of UCAs as one of the 
reasons we retained contract management as a high-risk designation for 
NASA to focus management attention on problem areas that involve 
substantial resources.[Footnote 8]

Finally, NASA agrees that cost estimates for significant development 
activities should be appropriately documented. According to NASA, 
additional requirements for cost estimates and internal controls 
recently established by the program represent a step in ensuring the 
appropriate documentation is developed as solutions are identified. As 
stated in our report, we believe that future compliance with this new 
policy could potentially result in more credible budget estimates.

In a broader context, reliable and supportable cost estimating 
processes are important tools for managing programs. Without this 
knowledge, a program's estimated cost could be understated and thereby 
subject to underfunding and cost overruns, putting programs at risk of 
being reduced in scope or requiring additional funding to meet their 
objectives. Further, without adequate financial and nonfinancial data, 
programs cannot easily track an acquisition's progress and assess 
actions to be taken before it incurs significant cost increases and 
schedule delays.

As agreed with your offices, unless you announce its contents earlier, 
we will not distribute this report further until 30 days from its date. 
At that time, we will send copies to the NASA Administrator and 
interested congressional committees. We will make copies available to 
others upon request. In addition, the report will be available at no 
charge on the GAO Web site at http://www.gao.gov.

If you or your staff have any questions concerning this report, please 
contact me at (202) 512-4841 or lia@gao.gov. Key contributors to this 
report are acknowledged in appendix III.

Signed by: 

Allen Li: 
Director: 
Acquisition and Sourcing Management:

[End of section]

Appendix I: Scope and Methodology:

To assess the basis for NASA's Hubble servicing mission cost estimate, 
we analyzed NASA's estimate of the funding needed for a shuttle 
servicing mission and supporting documentation, and we reviewed NASA 
documents explaining the rationale for the decision and identifying 
alternatives to shuttle servicing. We interviewed program and project 
officials to clarify our understanding of the available cost 
information and NASA's rationale for the decision. To test the 
sufficiency of the support for the estimates provided by NASA, we 
requested the analytical basis and documentary support for selected 
portions of the estimates, primarily those with large dollar values. In 
addition, we compared NASA's decision-making process with relevant 
Office of Management and Budget and NASA guidance on information and 
analyses recommended to enable decision-makers to select the best 
alternative.

To determine the basis for NASA's cost estimate for implementing all of 
the CAIB recommendations, we reviewed the CAIB report (volume 1), 
NASA's return to flight implementation plan and budget estimates, and 
agency documentation discussing the return to flight budget estimate. 
We interviewed program officials to obtain a better understanding of 
NASA's plans for returning the space shuttle to flight, the status of 
that effort, and the estimated cost. To test the sufficiency of the 
support for NASA's return to flight estimate, we requested the 
analytical basis and documentary support for selected high dollar 
portions of the estimate.

To accomplish our work, we visited NASA Headquarters, Washington, D.C; 
and Goddard Space Flight Center, Maryland.

We performed our review from March through September 2004 in accordance 
with generally accepted government auditing standards.

[End of section]

Appendix II: Comments from the National Aeronautics and Space 
Administration:

Department of Health & Human Services: 
Office of Inspector General: 

NOV 22 2004:

Ms. Leslie G. Aronovitz: 
Director, Health Care-Program Administration and Integrity Issues: 
United States Government Accountability Office: 
Washington, D.C. 20548:

Dear Ms. Aronovitz:

Enclosed are the Department's comments on your draft report entitled, 
"Medicare-Advisory Opinions As A Means of Clarifying Program 
Requirements" (GAO-05-129). The comments represent the tentative 
position of the Department and are subject to reevaluation when the 
final version of this report is received.

The Department provided several technical comments directly to your 
staff.

The Department appreciates the opportunity to comment on this draft 
report before its publication. 

Sincerely,

Signed by: 

Daniel R. Levinson: 
Acting Inspector General:

Enclosure:

The Office of Inspector General (OIG) is transmitting the Department's 
response to this draft report in our capacity as the Department's 
designated focal point and coordinator for Government Accountability 
Office reports. OIG has not conducted an independent assessment of 
these comments and therefore expresses no opinion on them.

COMMENTS BY THE DEPARTMENT OF HEALTH AND HUMAN SERVICES (HHS) ON THE 
U.S. GOVERNMENT ACCOUNTABILITY OFFICE'S (GAO) DRAFT REPORT ENTITLED 
"MEDICARE: ADVISORY OPINIONS AS A MEANS OF CLARIFYING PROGRAM 
REQUIREMENTS (GAO-05-129):

The HHS appreciates the opportunity to review and comment on GAO's 
draft report. We appreciate GAO's efforts to assess the role that a 
broader advisory opinion process might play in clarifying Medicare 
regulations.

In its concluding observations on page 21, the draft observes that the 
Medicare program and its implementing regulations are "inherently 
complex," and we agree. We do currently engage in numerous efforts to 
assist stakeholders' understanding of the program's complexities, the 
most important of which are described below. Included among these 
efforts are targeted advisory opinion processes conducted by our Office 
of Inspector General (OIG) and also within our Office of General 
Counsel. As the draft also acknowledges, however, advisory opinion 
processes are limited in their ability to provide quick answers to 
pressing problems. We agree.

We believe that an enhanced and more formal process of developing 
advisory opinions would not be a successful pursuit at this time. We 
believe such a process would be costly and just as slow as the current 
processes, which have been streamlined to the extent possible, given 
the large volume of pertinent guidance, which is constantly (and 
necessarily) in flux. Given the complexity and broad scope of the 
Medicare program, an enhanced effort to provide advisory opinions would 
require a far larger professional staff than is available under current 
resource constraints. It is also important to note that current HHS 
opinions specifically state that they are limited in scope to the 
specific arrangement described in the request and have "no 
applicability to other arrangements, even those which appear similar in 
nature or scope" and "may not be introduced into evidence in any matter 
involving an entity or individual that is not a requestor of this 
opinion." We believe that the usefulness of a broader set of opinions 
would be similarly constrained.

Additionally, the GAO draft states that the presence of user fees is 
among the critical factors in making currently operational advisory-
opinion processes effective. It is important to note that fees 
collected for our advisory opinions are not paid to or retained by HHS, 
and thus do not offset the costs of the staff time allocated to this 
work.

We cite the following as important existing sources of the guidance 
needed by Medicare stakeholders:

The Center for Medicare and Medicaid Services (CMS)'s customized 
provider web pages allow physicians, hospitals, ambulances, and other 
providers quick access to relevant Medicare information. These web 
pages, found on www.cms.hhs.gov/providers, have associated Listservs 
that ensure providers will get new information as it becomes available.

CMS has a Medicare Coverage Database on the CMS website, 
www.cms.hhs.gov, that contains all I national and local coverage policy 
and articles produced by contractors that provide additional coverage 
guidance. CMS has also implemented a new web page, allowing for easier 
provider and public access to recent Administrator decisions regarding 
the Provider Reimbursement Review Board and issued by the Office of the 
Attorney Advisor.

CMS publishes a Quarterly Provider Update on the first business day of 
each quarter on the CMS web site to inform the public about regulations 
and major policies currently under development during this quarter; 
regulations and major policies completed or cancelled; and new/revised 
manual instructions. This Update, makes it easier for providers, 
suppliers, and the general public to be aware of impending program 
changes.

In fiscal year 2004, CMS implemented an On-Line Manual System, located 
at www.cms.hhs.gov/manuals, to consolidate and update its manuals, 
policy and billing instructions, eliminate duplicate policy across 
manuals, and establish a single source to obtain information on the 
Medicare and Medicaid programs. Additionally, a related Monthly 
Bulletin is communicated to Medicare Contractors via email and is 
posted on the CMS On-Line Manual System.

In 2001, CMS began an initiative to improve provider communications 
when the agency required contractors to institute toll-free phone 
service to answer inquiries from providers who bill for services under 
fee-for-service Medicare. CMS also now issues nationally consistent 
provider education materials to accompany contractor instructions that 
implement new or revised policy. "Medlearn Matters ... Information for 
Medicare Providers" contains educational articles, written in 
consultation with clinicians, billing experts, and other medical 
professionals, and tailored in content and language to the specific 
provider types who are affected by the program change. These articles 
explain in plain English content of the program instructions, and, more 
importantly, the specific impact that the change has on the affected 
providers. The articles are housed in one central, easily accessible 
location (www.cms.hhs.gov/medlearn/matters).

CMS has held fourteen individual Open Door Forums and town hall 
meetings for physicians to discuss new initiatives. CMS has also 
established a provider partnership network with provider associations 
and organizations, whereby providers give input on products and CMS 
information tools, and assist in the dissemination of CMS information. 

[End of section]

Appendix III: GAO Contact and Staff Acknowledgments:

GAO Contact:

Allen Li (202) 512-4841:

Acknowledgments:

Staff making key contributions to this report were Jerry Herley, Erin 
Schoening, Karen Sloan, and Jonathan Watkins.

FOOTNOTES

[1] The CAIB was created by NASA to investigate the February 1, 2003, 
loss of the space shuttle Columbia.

[2] The National Research Council is part of the National Academies, 
which also comprise the National Academy of Sciences, National Academy 
of Engineering, and Institute of Medicine. They are private, nonprofit 
institutions that provide science, technology, and health policy advice 
under a congressional charter. The Research Council was organized by 
the National Academy of Sciences in 1916 to associate the broad 
community of science and technology with the Academy's purposes of 
further knowledge and advising the federal government.

[3] Although the autonomous inspection and repair capability of the 
shuttle's thermal protection system is a CAIB requirement for all 
shuttle missions, the currently planned method depends on International 
Space Station assets, such as the International Space Station's robotic 
arm to stabilize a spacewalk crew making repairs to the shuttle. A 
Hubble mission would not have this asset available; therefore, NASA 
would have to develop an alternate method for stabilizing a 
crewmember making repairs. The second requirement--NASA's requirement 
for a crew rescue shuttle--would apply to all shuttle flights, but 
according to NASA, the agency would need to dedicate two shuttles to a 
Hubble servicing mission because of the shorter amount of time to react 
to an emergency because the crew would not have the benefit of the 
International Space Station as a safe haven. The agency contends that 
the second (rescue) shuttle for the Hubble servicing mission would need 
to be on the adjacent launch pad in countdown mode at the same time the 
first shuttle is launched. The rescue shuttle capability would require 
the development of a second generation boom to be used to transfer the 
crew from the stricken orbiter and an enhanced camera to process 
imagery in time to support a go-no go rescue mission decision. In 
addition, a crew return kit would be needed to provide seats on the 
rescue shuttle for the rescued crew, and a special crew would have to 
be trained for the rescue mission.

[4] GAO, NASA: Lack of Disciplined Cost-Estimating Processes Hinders 
Effective Program Management, GAO-04-642 (Washington, D.C.: May 28, 
2004).

[5] The membership of the PRCB includes the Space Shuttle Program 
Manager, Deputy Manager, all Project and Element Managers, Safety and 
Mission Assurance personnel, and the Team Leader of the return to 
flight Planning Team.

[6] We attempted to obtain analytical and documentary support for the 
return to flight estimates on two occasions. First, in May 2004, we 
requested support for three high-dollar items for which we were told 
the estimates ranged from strong to weak to a mixture. In response to 
this request, NASA told us that the detailed bases of estimate for the 
activities were being developed and that NASA would report on return to 
flight expenses to Congress and GAO in a few weeks. Then, several weeks 
later when NASA released the July 28 return to flight update, we 
requested support for the three largest estimates, two of which were 
the same items for which we requested support in May. In response, NASA 
provided the PRCB directives and backup documents underlying the 
estimates that the agency considers to be mature. After we reviewed 
these documents and concluded that the support was not adequate, NASA 
offered to select some additional examples to show that the estimates 
were credible.

[7] GAO, NASA: Major Management Challenges and Program Risks, GAO-03-
849T (Washington, D.C.: June 12, 2003); GAO, High-Risk Series: An 
Update, GAO-03-119 (Washington, D.C.: January 2003); GAO, Major 
Management Challenges and Program Risks: National Aeronautics and Space 
Administration, GAO-03-114 (Washington, D.C.: January 2003); GAO, High-
Risk Series: An Update, GAO-01-263 (Washington, D.C.: January 2001); 
and GAO, Major Management Challenges and Program Risks: National 
Aeronautics and Space Administration, GAO-01-258 (Washington, D.C.: 
January 2001).

[8] High-Risk Series: An Update (GAO-01-263, January 2001).

GAO's Mission:

The Government Accountability Office, the investigative arm of 
Congress, exists to support Congress in meeting its constitutional 
responsibilities and to help improve the performance and accountability 
of the federal government for the American people. GAO examines the use 
of public funds; evaluates federal programs and policies; and provides 
analyses, recommendations, and other assistance to help Congress make 
informed oversight, policy, and funding decisions. GAO's commitment to 
good government is reflected in its core values of accountability, 
integrity, and reliability.

Obtaining Copies of GAO Reports and Testimony:

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through the Internet. GAO's Web site ( www.gao.gov ) contains 
abstracts and full-text files of current reports and testimony and an 
expanding archive of older products. The Web site features a search 
engine to help you locate documents using key words and phrases. You 
can print these documents in their entirety, including charts and other 
graphics.

Each day, GAO issues a list of newly released reports, testimony, and 
correspondence. GAO posts this list, known as "Today's Reports," on its 
Web site daily. The list contains links to the full-text document 
files. To have GAO e-mail this list to you every afternoon, go to 
www.gao.gov and select "Subscribe to e-mail alerts" under the "Order 
GAO Products" heading.

Order by Mail or Phone:

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to:

U.S. Government Accountability Office

441 G Street NW, Room LM

Washington, D.C. 20548:

To order by Phone:

	

Voice: (202) 512-6000:

TDD: (202) 512-2537:

Fax: (202) 512-6061:

To Report Fraud, Waste, and Abuse in Federal Programs:

Contact:

Web site: www.gao.gov/fraudnet/fraudnet.htm

E-mail: fraudnet@gao.gov

Automated answering system: (800) 424-5454 or (202) 512-7470:

Public Affairs:

Jeff Nelligan, managing director,

NelliganJ@gao.gov

(202) 512-4800

U.S. Government Accountability Office,

441 G Street NW, Room 7149

Washington, D.C. 20548: