This is the accessible text file for GAO report number GAO-04-634T 
entitled 'Chemical Weapons: Destruction Schedule Delays and Cost Growth 
Continue to Challenge Program Management' which was released on April 
01, 2004.

This text file was formatted by the U.S. General Accounting Office 
(GAO) to be accessible to users with visual impairments, as part of a 
longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov.

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately.

Testimony:

Before the Subcommittee on Terrorism, Unconventional Threats and 
Capabilities, Committee on Armed Services, House of Representatives:

United States General Accounting Office:

GAO:

For Release on Delivery Expected at 10:00 a.m. EST:

Thursday, April 1, 2004:

Chemical Weapons:

Destruction Schedule Delays and Cost Growth Continue to Challenge 
Program Management:

Statement of Raymond J Decker, Director, Defense Capabilities and 
Management:

GAO-04-634T:

GAO Highlights:

Highlights of GAO-04-634T, testimony to the Subcommittee on Terrorism, 
Unconventional Threats and Capabilities, Committee on Armed Services, 
House of Representatives 

Why GAO Did This Study:

Since its inception in 1985, the Chemical Demilitarization (Chem Demil) 
Program has been charged with destroying the nation’s large chemical 
weapons stockpile of over 31,000 tons of agent. The program started 
destroying the stockpile in 1990. As of March 2004, the program had 
destroyed over 27 percent of the stockpile. The program has recently 
reorganized into the Chemical Materials Agency (CMA) to manage seven of 
the nine sites. There are five sites using incineration to destroy the 
agent and two bulk agent only sites using neutralization. The Assembled 
Chemical Weapons Alternatives (ACWA) Program, in the Department of 
Defense (DOD), manages two sites using neutralization to destroy agent 
in weapons.

This testimony updates GAO’s September 2003 report and October 2003 
testimony. As requested, it focuses on the following issues: (1) 
changes in the status of schedule milestones and costs at the sites, 
(2) recent developments that impact the Chemical Weapons Convention 
(CWC) deadlines, (3) the challenges associated with managing the 
program, and (4) an update on the status of the Chemical Stockpile 
Emergency Preparedness Program (CSEPP).

What GAO Found:

Since GAO testified in October 2003, the Chem-Demil Program continues 
to fall behind its schedule milestones, which were last extended in 
2001. In the last 6 months, very little agent has been destroyed. While 
one site has closed, no new sites have started destroying agent (two 
were scheduled to start by March 2004). The delays stem from incidents 
during operations, environmental permitting issues, concerns about 
emergency preparedness, and unfunded requirements. If these delays 
persist, GAO continues to believe that program costs will rise 
substantially higher than the October 2003 estimate of more than $25 
billion. These rising costs have led to the need to reallocate funds 
within the program’s fiscal year 2005 budget.
 
Due to schedule delays, the United States will not meet the CWC April 
2004 deadline to destroy 45 percent of the stockpile. Although it has 
received an extension for this task to December 2007, it is 
questionable if the program will meet this deadline. DOD has said it 
will ask for an extension of the final deadline to destroy 100 percent 
of the stockpile beyond 2007. Unless the program resolves the problems 
causing program delays, the United States risks not meeting this 
deadline, if extended.

One positive development in the program is that the leadership has been 
stabilized for over a year since the program was reorganized. However, 
several long-standing organizational and strategic planning issues 
remain. One problem is that the program's new management structure is 
complex, with multiple lines of authority within the Army and the 
separation of ACWA from the rest of the program. These complexities 
raise concerns about the roles and responsibilities of the different 
parts of the program. Program officials also told us that they are 
developing strategic and risk mitigation plans, as GAO recommended.

Since GAO testified in October, there continues to be improvement in 
the preparation of state and local communities to respond to chemical 
emergencies. As of January 2004, 6 of 10 states near the stockpiles 
report they are fully prepared. This is a marked improvement from the 
status we reported in 2001 when three states reported they were far 
from being prepared. However, CSEPP costs continue to rise because some 
states have expanded their preparedness requests beyond their approved 
budgets. 

www.gao.gov/cgi-bin/getrpt?GAO-04-634T.

To view the full product, including the scope and methodology, click on 
the link above. For more information, contact Raymond J. Decker at 
(202) 512-6020 or deckerrj@gao.gov.

[End of section]

Mr. Chairman and Members of the Subcommittee:

I appreciate the opportunity to participate in this hearing today on 
the Department of Defense's (DOD) Chemical Demilitarization (Chem-
Demil) Program. Since its inception in 1985, this program has been 
charged with destroying the nation's large chemical weapons stockpile, 
second only to Russia's in terms of its size. After years of planning 
and building new facilities, the program started destroying the 
stockpile in 1990. Since 1990, we have issued more than 25 reports on 
the Chem-Demil Program. Nearly half of the reviews have raised 
questions about the program's growing costs, its inability to meet its 
schedule milestones, and its management weaknesses.

As you requested, my statement updates GAO's testimony from October 
2003 and focuses on the following issues: (1) changes in the status of 
schedule milestones and costs at the sites, (2) recent developments 
that impact the Chemical Weapons Convention (CWC) deadlines, (3) the 
challenges associated with managing the program, and (4) an update on 
the status of the Chemical Stockpile Emergency Preparedness Program 
(CSEPP).

As of March 2004, the Chem-Demil Program had destroyed an estimated 
8,691 tons (27.6 percent) of the total 31,500 tons of the original 
agent stockpile stored at nine sites in the United States and the 
Pacific Ocean at Johnston Atoll. Since our testimony in October 2003, 
the program has destroyed very little additional agent (about 1.5 
percent). Of the four sites that have begun agent destruction 
operations, Johnston Atoll has destroyed its entire stockpile and is 
closed; Tooele, Utah, has reduced its stockpile by about 47.1 percent; 
Anniston, Alabama, has destroyed 5.1 percent of its stockpile; and 
Aberdeen, Maryland, has destroyed 7.9 percent of its stockpile. Current 
schedule estimates show that the Army will not complete destruction of 
the entire stockpile until after the year 2012.

For this testimony, we conducted work that included discussions with 
officials from DOD, the Army, and FEMA. We also drew on the work we 
conducted for our September 2003 report[Footnote 1] and October 2003 
testimony.[Footnote 2] We performed our work in March 2004 in 
accordance with generally accepted government auditing standards.

Summary:

In summary, we found the following:

* Since we testified in October 2003, the Chem-Demil Program continues 
to fall behind its schedule milestones, which were extended in 2001. 
These schedule delays led to increased program costs and very little 
agent destruction over the last 6 months. We testified that four 
incineration sites and one bulk agent site would miss their scheduled 
milestones. However, since then, one of the incineration sites has 
closed and an additional bulk agent site has missed its scheduled 
milestone, resulting in five sites remaining behind approved 
destruction schedules. The remaining three sites--two Assembled 
Chemical Weapons Alternatives (ACWA) sites and one incineration site 
have not yet missed schedule milestones, but they too have experienced 
delays. The delays stem from ongoing incidents during operations, 
environmental permitting issues, concerns about emergency 
preparedness, and unfunded requirements. If these delays persist, we 
continue to believe that program costs will rise substantially higher 
than the October 2003 estimate of more than $25 billion. These rising 
costs have led to the need to reallocate funds within the program's 
fiscal year 2005 budget.

* Because of schedule delays, the United States will not meet CWC's 
April 2004 deadline to destroy 45 percent of the chemical stockpile. 
The United States asked the governing body of the convention for and 
received an extension for this deadline to December 2007. Although it 
has received an extension for this task, it is questionable if the 
program will meet this deadline. Moreover, DOD has said it will ask for 
an extension of the final deadline to destroy 100 percent of the 
stockpile beyond 2007. Unless the Chem-Demil Program is able to resolve 
the problems that have caused schedule delays to destroy the stockpile, 
the United States also risks not meeting CWC's deadline to destroy the 
entire stockpile, if extended to 2012.[Footnote 3]

* We previously testified that despite efforts to improve the 
management and reorganize the Chem-Demil Program, the program has 
suffered from several long-standing and unresolved management, 
organizational, and strategic planning issues. Recently, under the new 
organization, the leadership of the program has stabilized. However, 
the program's complex management structure, with multiple lines of 
authority within the Army and the separation of program components 
between the Army and DOD, raises concerns about the roles and 
responsibilities of the different parts of the program. For example, 
DOD manages two of the program's nine sites separately from the Army's 
management of the other sites. In addition, the absence of an 
overarching, comprehensive management strategy has resulted in a 
program without a clear road map to closely guide and integrate all of 
its activities and monitor its performance. Neither DOD nor the Army 
has adopted a comprehensive risk management approach that could help 
mitigate potential problems that affect program schedules, costs, and 
safety by anticipating problems and developing proactive plans. Program 
officials also told us that they are developing strategic and risk 
mitigation plans, as we have recommended.

* Since our October 2003 testimony, states and communities have 
continued to improve their emergency preparedness to respond to 
chemical incidents. Based on the states' self-assessments and FEMA's 
reviews, 6 of the 10 states near the eight storage sites are fully 
prepared and the remaining 4 are close to being fully prepared. In 
addition, in response to recommendations in our 2001 report,[Footnote 
4] FEMA and the Army have implemented a number of actions to improve 
technical assistance and guidance, training, and compliance measures to 
assess preparedness. However, despite these accomplishments, CSEPP 
costs continue to rise because some state and local communities have 
expanded their emergency preparedness requests beyond their approved 
budgets. The requests for fiscal years 2004 and 2005 exceeded approved 
budgets by a total of $88 million. In a few communities, these requests 
have grown as the sites have moved closer to the agent operations 
phase. These unfunded requirements have caused further delays in 
overall program operations because funds have to be diverted from other 
sites approved budgets to pay for these communities' requirements. To 
date, CSEPP has spent a total of $723 million in local communities.

Most Sites Will Miss Schedule Milestones Due to Programís Inability to 
Anticipate and Influence†Issues:

Since our October 2003 testimony, the Chem-Demil Program continues to 
struggle to meet its schedule milestones and remain within its cost 
estimates. These schedule delays led to increased program costs and 
very little agent has been destroyed over the last 6 months. We 
testified then that most incineration sites would miss their scheduled 
milestones established in 2001. At that time Anniston, Umatilla, and 
Pine Bluff had missed their 2001 milestones to begin agent destruction 
operations and Johnston Atoll had missed its milestone for shutting 
down the facility. However, since then, three of these sites have 
experienced further delays. Table 1 shows the delays at Umatilla, Pine 
Bluff, and Johnston Atoll incineration sites since October 2003. The 
delays stem from incidents during operations, environmental permitting 
issues, emergency preparedness, and unfunded requirements. If these 
delays persist, we continue to believe that program costs will rise 
substantially higher than the October 2003 estimate of more than $25 
billion. These rising costs have led to the need to reallocate funds 
within the program's fiscal year 2005 budget.

Table 1: Delays in Meeting Schedule Milestones, by Incineration Site:

Site: Umatilla; 
Next schedule milestone: Operations; 
October 2003 estimate to begin next milestone: Mar. 2004; 
Current estimates to begin next phase[A]: July 2004; 
Difference between 2003 status and current estimate (no. of months): 
+4.

Site: Pine Bluff; 
Next schedule milestone: Operations; 
October 2003 estimate to begin next milestone: Apr. 2004; 
Current estimates to begin next phase[A]: July 2004; 
Difference between 2003 status and current estimate (no. of months): 
+3.

Site: Johnston Atoll; 
Next schedule milestone: End of closure; 
October 2003 estimate to begin next milestone: Nov. 2003; 
Current estimates to begin next phase[A]: Dec. 2003; 
Difference between 2003 status and current estimate (no. of months): 
+1. 

Sources: DOD and the U.S. Army.

[A] Actual date that Johnston Atoll closed and program manager's 
official estimates for Pine Bluff and Umatilla to start operations.

[End of table]

As of March 2004, the two bulk-agent only sites, Aberdeen and Newport, 
have experienced delays and Aberdeen has missed its scheduled milestone 
for draining the agent from the ton containers. In 2002, DOD approved 
using an accelerated method that was expected to increase the rate of 
destruction at these two sites. The Army estimated that this process 
would reduce the scheduled end of operations at both sites by 5 years, 
from 2008 to 2003 at Aberdeen and from 2009 to 2004 at Newport. 
However, Aberdeen has encountered unanticipated problems with the 
processing of the mustard agent in the ton containers and has extended 
its planned completion date from October 2003 to December of 2004. The 
program has exceeded the 6-month period it estimated would be needed 
for accelerated destruction of the agent. Additionally, the site has 
only drained 152 of the 1,817-ton containers as of March 2004. Even if 
finished by December 2004, this time frame only covers the first stage 
of the operation to remove the mustard agent from the containers. An 
added problem, the hardening and congealing of residual agent in the 
ton containers, will require a second stage of operation to remove the 
residual agent. In addition, Newport has faced construction delays and 
community resistance to offsite treatment of waste byproducts. As a 
result of these delays, Newport extended its planned start date for 
agent operations twice: first from October 2003 to February 2004, and 
again to August 2004. However, the current plan to ship the waste to a 
treatment facility in New Jersey from Indiana has not been finalized 
and faces opposition from residents, workers, and environmental groups. 
DOD has not programmed funds to treat the waste on-site or to store it 
there until a disposal location has been finalized.

At the two ACWA sites, Pueblo, Colorado, and Blue Grass, Kentucky, DOD 
directed that they pursue accelerated destruction methods. According to 
program officials, the initial accelerated approaches proposed by the 
contractors exceeded DOD programmed funding and have to be reevaluated. 
Until the plans are approved, final schedule milestones cannot be set. 
This means both projects have been delayed while additional design work 
is completed.

These delays and schedule extensions[Footnote 5] have contributed 
directly to program cost growth, according to program officials. As a 
result, DOD's total program cost estimate grew from $15 billion to 
$24 billion between 1998 and 2001. (See fig. 1.) Because of delays 
encountered since the 2001 revisions, the Army is now in the process of 
developing new milestones that will extend beyond those adopted in 
2001. According to a DOD official, the program will use events that 
have occurred since 2001 in presenting new cost estimates to DOD for 
preparation of the fiscal year 2006 budget submission. Program 
officials told us that they estimate new costs had increased by 
$1.4 billion as of October 2003, and this estimate is certainly going 
to rise further, given the information we obtained on schedule delays 
from fiscal year 2005 budget documents and from program officials.

Figure 1: Comparison of 1998, 2001, and 2003 Cumulative Program 
Cost Estimates:

[See PDF for image]

[End of figure]

As an example of the impact schedule delays have on the program, DOD's 
fiscal year 2005 budget request includes a realignment of $147 million 
from the ACWA program to the rest of the program. Additional 
requirements have been identified that will likely delay the schedule 
further if future realignments are necessary.

Schedule Delays Required CWC Extension of Deadlines:

Although the United States met the first two chemical weapons treaty 
deadlines, the continuing delays in the schedule jeopardize its ability 
to meet the final two deadlines. (See table 2.) The program will not 
meet the April 2004 CWC deadline to destroy 45 percent of the 
stockpile. Although it has received an extension for this task to 
December 2007, it is questionable if the program will meet this 
deadline. Unless the Chem-Demil Program is able to resolve the problems 
that have caused schedule delays to destroy the stockpile, the United 
States will likely risk not meeting the deadline, if extended to 2012, 
to eliminate 100 percent of the stockpile.

Table 2: CWC Deadlines:

Required percentage of agent destroyed: 1; 
Deadlines for destruction: April 29, 2000; 
Date United States met deadline: September 1997.

Required percentage of agent destroyed: 20; 
Deadlines for destruction: April 29, 2002; 
Date United States met deadline: July 2001.

Required percentage of agent destroyed: 45; 
Deadlines for destruction: April 29, 2004; 
Date United States met deadline: Will not meet.

Required percentage of agent destroyed: 100; 
Deadlines for destruction: April 29, 2007; 
Date United States met deadline: Will not meet.

Sources: CWC and U.S. Army.

[End of table]

Long-standing Management and Strategic Planning Weaknesses Hamper 
Program Progress:

Despite recent efforts to improve the management and change the 
organization of the Chem-Demil Program, the program continues to falter 
because several long-standing management, organizational, and 
strategic planning weaknesses remain unresolved. While the program has 
lacked sustained leadership in the recent past, this situation has 
stabilized. However, the program's complex structure, with its many 
lines of authority within the Army and between the Army and DOD, raises 
questions about the roles and responsibilities of its various offices. 
In addition, the program lacks strategic and risk management plans to 
guide and integrate its activities.

Program Management Structure Remains Complex:

Although the program has experienced turbulence in key leadership 
positions in the recent past, the current leadership has been in place 
for more than a year, and these leaders have a substantial history of 
involvement with the program. The new leadership team is clarifying its 
roles, responsibilities, decision-making authority, and 
accountability.

However, despite the recent reorganization, this change has not 
streamlined the program's complex organization, as we documented in our 
2003 report.[Footnote 6] The establishment of the Chemical Materials 
Agency (CMA) in January 2003 has left the Director reporting to two 
different senior Army organizations. The reorganization has also 
divided the responsibility for various program phases between two 
offices within CMA. One organization, the Program Manager for the 
Elimination of Chemical Weapons, will manage the first three phases 
(design, construction, and systemization) for each site, and a newly 
created organization, the Director of Operations, will manage the final 
two phases (operations and closure). Moreover, the reorganization did 
not address the relationship between the Assembled Chemical Weapons 
Alternatives (ACWA) program and the Army's CMA since DOD manages ACWA 
separately from the Army, as congressionally directed.

Program Lacks Strategic and Risk Management Plans:

In response to our recommendations in our September 2003 report, 
according to DOD officials, the Army is developing a strategic plan to 
address the goals, objectives, and performance measures of the program. 
DOD says it is now in the process of developing a risk management plan. 
In the past, because the program had used a crisis management approach, 
it was forced to react to, rather than control issues. We believe a 
risk management approach would allow DOD and the Army to proactively 
anticipate and address potential problems that could adversely affect 
program schedule, costs, and safety.

Emergency Preparedness Program Is Improving, but Costs Are Rising:

FEMA and the Army continue to provide assistance to state and local 
communities to improve their emergency preparedness. Since our October 
2003 testimony, states and communities have continued to improve their 
emergency preparedness to respond to chemical incidents. Additionally, 
FEMA has provided software and training to state and local communities 
to help them simplify development of CSEPP financial reporting 
documents. FEMA also has published a Recovery Workbook.[Footnote 7] The 
workbook fills a void in state and local guidance for emergency 
responders to follow in the event of a chemical emergency. FEMA also 
expanded its capability assessment readiness tool to assist local 
communities in quantifying benchmark scores. In January 2004, FEMA 
reported to Congress that these achievements have aided CSEPP 
communities in reaching 95 percent of their benchmark compliance. Six 
of 10 states near the eight storage sites reported that they are fully 
prepared and the remaining 4 reported being close to fully prepared.

Despite these accomplishments, CSEPP costs continue to rise because, 
according to Army and FEMA officials, some state and local communities 
continue to identify additional emergency requirements that exceed 
DOD's programmed funding. This situation occurs because of the open 
interpretation of "maximum protection" concept that governs CSEPP. 
These unfunded requests have two effects. First, they cause the 
benchmarks showing how prepared each community is to change from fully 
compliant to not compliant from year to year. Second, they cause funds 
to be transferred from destruction activities to CSEPP and result in 
further delays in the destruction schedule. Army and FEMA officials 
explain that the states often identify and expand their requirements, 
especially as destruction facilities move closer to the start of the 
operations phase. For example, the states of Colorado, Alabama, and 
Oregon have requested additional funds for infrastructure support, 
including roads and bridges that exceed their CSEPP budgets. These 
requests follow a pattern that occurred at Anniston in 2001 when it 
received $40.5 million for additional CSEPP items. Currently, the 
communities around the Umatilla facility are demanding that substantial 
additional funding be provided as the onset of operations comes closer. 
Programwide, new requirements continue to exceed approved CSEPP funding 
levels. FEMA has little control over the additional funding requests 
made by the states. As of October 2003, FEMA had identified total $88 
million in unfunded CSEPP requirements for fiscal years 2004 and 2005. 
As of fiscal year 2004, the total cost for CSEPP has risen to $723.1 
million. Funding for individual states ranges from $9.7 million to 
$259.6 million for the period of 1989 to 2004. (See table 3.):

Table 3: CSEPP Funding by State, Fiscal Years 1989-2004:

State: Alabama; Fiscal years 1989-2004: $259,612,223; 
Percent of total spending: 35.9.

State: Arkansas; Fiscal years 1989-2004: 80,311,665; 
Percent of total spending: 11.1.

State: Colorado; Fiscal years 1989-2004: 30,233,930; 
Percent of total spending: 4.2.

State: Illinois; Fiscal years 1989-2004: 9,724,039; 
Percent of total spending: 1.3.

State: Indiana; Fiscal years 1989-2004: 46,201,152; 
Percent of total spending: 6.4.

State: Kentucky; Fiscal years 1989-2004: 60,055,596; 
Percent of total spending: 8.3.

State: Maryland; Fiscal years 1989-2004: 30,472,755; 
Percent of total spending: 4.2.

State: Oregon; Fiscal years 1989-2004: 93,484,394; 
Percent of total spending: 12.9.

State: Utah; Fiscal years 1989-2004: 74,596,336; 
Percent of total spending: 10.3.

State: Washington; Fiscal years 1989-2004: 38,388,929; 
Percent of total spending: 5.3.

Total; Fiscal years 1989-2004: $723,071,019; 
Percent of total spending: 100.0.

Source: FEMA data. The Army and FEMA have recently recognized the 
Confederated Tribes of the Umatilla Indian Reservation as a separate 
funding entity. The confederated tribes have received $2.5 million to 
date.

[End of table]

Mr. Chairman, this concludes my statement. I would be pleased to 
respond to any questions that you or Members of the Subcommittee may 
have.

Contacts and Acknowledgments For future questions regarding this 
testimony, please contact me at (202) 512-6020. Individuals making key 
contributions to this testimony include Donald Snyder, Rodell Anderson, 
Bonita Oden, John Buehler, Nancy Benco, Rick Yeh, Susan Mason, and Mike 
Zola.

FOOTNOTES

[1] U.S. General Accounting Office, Chemical Weapons: Sustained 
Leadership, Along with Key Strategic Management Tools, Is Needed to 
Guide DOD's Destruction Program, GAO-03-1031 (Washington, D.C.: Sept. 
5, 2003).

[2] U.S. General Accounting Office, Chemical Weapons: Better Management 
Tools Needed to Guide DOD's Stockpile Destruction Program, GAO-04-221T 
(Washington, D.C.: Oct. 30, 2003).

[3] The CWC allows extensions of up to 5 years to the 2007 deadline.

[4] Chemical Weapons: FEMA and Army Must Be Proactive in Preparing 
States for Emergencies, GAO-01-850 (Washington, D.C.: Aug. 13, 2001).

[5] Schedule extensions or slippages are caused primarily by actual 
destruction rates being lower than planned.

[6] GAO-03-1031.

[7] U.S. General Accounting Office, Chemical Weapons: FEMA and Army 
Must Be Proactive in Preparing States for Emergencies, GAO-01-850 
(Washington, D.C.: Aug. 13, 2001). Recovery plans refer to support 
activities that occur following a chemical event. The primary purpose 
is to protect the public health and safety while returning the 
community to normal conditions.