Nuclear Waste: Challenges and Savings Opportunities in DOE's High-Level Waste Cleanup Program

GAO-03-930T July 17, 2003
Highlights Page (PDF)   Full Report (PDF, 26 pages)   Accessible Text

Summary

The Department of Energy (DOE) oversees the treatment and disposal of 94 million gallons of highly radioactive nuclear waste from the nation's nuclear weapons program, currently at DOE sites in Washington, Idaho, and South Carolina. In 2002, DOE began an initiative to reduce the estimated $105-billion cost and 70-year time frame of this cleanup. GAO was asked to testify on the status of this initiative, the legal and technical challenges DOE faces in implementation, and any further opportunities to reduce costs or improve program management. GAO's testimony is based on a report (GAO-03-593) released at the hearing.

DOE's initiative for reducing the costs and time required for cleanup of high-level wastes is still evolving. DOE's main strategy for treating high-level waste continues to include separating and concentrating much of the radioactivity into a smaller volume for disposal in a geologic repository. Under the initiative, DOE sites are evaluating other approaches, such as disposing of more waste on site. DOE's current savings estimate for these approaches is $29 billion, but the estimate may not be reliable or complete. For example, the savings estimate does not adequately reflect uncertainties or take into account the timing of when savings will be realized. DOE faces significant legal and technical challenges to realize these savings. A key legal challenge involves DOE's process for deciding that some waste with relatively low concentrations of radioactivity can be treated and disposed of on-site. A recent court ruling invalidated this process, putting the accelerated schedule and potential savings in jeopardy. A key technical challenge is that DOE's approach relies on laboratory testing to confirm separation of the waste into high-level and low-activity portions. At the Hanford Site in Washington State, DOE plans to build a facility before conducting integrated testing of the waste separation technology--an approach that failed on a prior major project. DOE is exploring proposals, such as increasing the amount of high-level waste in each disposal canister, that if successful could save billions of dollars more than the current $29 billion estimate. However, considerable evaluation remains to be done. DOE also has opportunities to improve program management by fully addressing recurring weaknesses GAO has identified in DOE's management of cleanup projects, including the practice of incorporating technology into projects before it is sufficiently tested.