Kennedy Center: Improvements Needed to Strengthen the Management and Oversight of the Construction Process

GAO-03-823 September 5, 2003
Highlights Page (PDF)   Full Report (PDF, 25 pages)   Accessible Text   Recommendations (HTML)

Summary

In the mid-1990s, John F. Kennedy Center for the Performing Arts (Kennedy Center) officials recognized a need for additional parking and better site access. As a precursor to a planned project to construct an 8-acre plaza and two additional buildings at the site, the Kennedy Center is currently in the process of constructing a garage expansion and site improvement project. GAO did this study because of congressional concerns over project delays and costs as well as challenges that the Kennedy Center faces as it pursues this major construction effort. GAO's objectives were to (1) compare the garage expansion and site improvement project's current costs, time frames, and scope with the estimates provided to congressional stakeholders in 1997 and 1998 and (2) identify what challenges the Kennedy Center faces in managing large construction projects.

As of July 2003, Kennedy Center officials estimated that the garage expansion and site improvement project would cost $88 million, the garage expansion will be completed in December 2003, the site improvements will be completed in summer 2004, and the project will include 525 parking spaces and various traffic flow improvements. These estimates vary substantially from estimates that Kennedy Center officials provided to congressional stakeholders in 1997 and 1998. At that time, Kennedy Center officials estimated that the project would cost $28 million, would be completed by August 2000, and would include between 900 and 1,000 parking spaces. According to Kennedy Center officials, the initial estimates were preliminary in nature and were based on some unrealistic assumptions. They acknowledged that they should have done a better job of informing Congress of the preliminary nature of the estimates and the subsequent events in the project's planning and bidding phases that affected the costs, time frames, and scope. Kennedy Center officials said that they now hold monthly meetings with Congress about the status of ongoing projects. The Kennedy Center faces certain challenges in managing large construction projects. Specifically, the Kennedy Center lacks (1) adequate policies and procedures to guide the planning and management of the construction process, (2) some timely construction data on schedules and costs for effectively overseeing construction projects and measuring results, and (3) key human capital resources and expertise that would be highly beneficial in managing the construction process. Kennedy Center officials are now working to address these challenges. Although making improvements in these areas is no guarantee of project success, these types of improvements would strengthen the construction program and reduce risk by providing greater effectiveness in managing and overseeing projects and measuring results.



Recommendations

Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Implemented" or "Not implemented" based on our follow up work.

Director:
Team:
Phone:
No director on record
No team on record
No phone on record


Recommendations for Executive Action


Recommendation: To help improve the Kennedy Center's ability to manage and oversee its construction program, the President of the Kennedy Center, in conjunction with the Chairman of the Board of Trustees, should develop comprehensive project management policies and procedures to guide the planning and execution of the construction process.

Agency Affected: Smithsonian Institution: John F. Kennedy Center for the Performing Arts

Status: Implemented

Comments: The Kennedy Center drafted a policy and procedure manual for the Project Management Office in 2004 that outlines the roles and responsibilities for project management staff and defines standard operating procedures for managing projects such as estimating design and construction costs.

Recommendation: To help improve the Kennedy Center's ability to manage and oversee its construction program, the President of the Kennedy Center, in conjunction with the Chairman of the Board of Trustees, should ensure development and use of timely data to oversee construction projects and measure results.

Agency Affected: Smithsonian Institution: John F. Kennedy Center for the Performing Arts

Status: Not Implemented

Comments: The Kennedy Center agreed to start pursuing monthly project management reports and detailed information at weekly progress meetings.

Recommendation: To help improve the Kennedy Center's ability to manage and oversee its construction program, the President of the Kennedy Center, in conjunction with the Chairman of the Board of Trustees, should ensure that the needs for human capital expertise are met.

Agency Affected: Smithsonian Institution: John F. Kennedy Center for the Performing Arts

Status: Implemented

Comments: The Kennedy Center generally agreed with the recommendation. Since the report was issued, the center has hired a Contracts Chief and a Director of Capital Projects to lead the Project Management Office.