This is the accessible text file for GAO report number GAO-03-706 
entitled 'Defense Inventory: Air Force Plans and Initiatives to 
Mitigate Spare Parts Shortages Need Better Implementation' which was 
released on June 27, 2003.

This text file was formatted by the U.S. General Accounting Office 
(GAO) to be accessible to users with visual impairments, as part of a 
longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov.

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately.

Report to the Chairman, Subcommittee on Defense, Committee on 
Appropriations, House of Representatives:

United States General Accounting Office:

GAO:

June 2003:

DEFENSE INVENTORY:

Air Force Plans and Initiatives to Mitigate Spare Parts Shortages Need 
Better Implementation:

GAO-03-706:

GAO Highlights:

Highlights of GAO-03-706, a report to the Chairman, Subcommittee on 
Defense, Committee on Appropriations, House of Representatives 

Why GAO Did This Study:

Despite reporting $10.5 billion in appropriations spent on spare parts 
since fiscal year 2000, the Air Force continues to report shortages of 
spare parts. The service has taken numerous actions to address these 
shortages.

GAO examined whether the Air Force’s strategic plan addresses the 
mitigation of spare parts shortages, whether key initiatives are 
likely to mitigate the shortages, and the impact on readiness 
identified from increased investments for spare parts.

What GAO Found:

The Air Force Strategic Plan generally provides an appropriate 
framework for mitigating spare parts shortages. However, one of two 
subordinate plans does not contain performance measures and targets 
linked to the strategic plan, and the other does not contain any 
performance targets. Therefore, the Air Force is not in a position to 
determine if the actions taken pursuant to its subordinate plans 
overcome spare parts shortages and provide assurance that it is 
getting the greatest readiness return on its spare parts investment.

Key logistics initiatives under the Spares Campaign and Depot 
Maintenance Reengineering and Transformation (DMRT) efforts may help 
to mitigate spare parts shortages, but the initiatives’ potential 
effectiveness is limited because of some key problems. First, the Air 
Force is not starting all identified initiatives that relate to the 
causes of shortages because it did not have needed personnel and 
funding. It assessed its logistics processes and identified more than 
80 initiatives to solve more than 300 deficiencies; 43 initiatives 
were to improve processes that affect spare parts shortages, with 
about half relating to depot maintenance and the other half to supply. 
As shown below, although all depot maintenance-related initiatives 
have been started, 12 of the supply related initiatives have not been 
started. Second, 23 of the 31 initiatives lack both output-related 
performance measures and targets. Without output-related measures and 
targets to assess the initiatives’ impact, the Air Force has little 
means of determining the extent to which it has successfully mitigated 
spare parts shortages and improved readiness. Third, the Air Force 
chose not to use the results of one of its initiatives, which 
identified a new total spares requirement as the basis for its fiscal 
year 2004 budget request. This decision resulted in a $578 million 
unfunded spare parts requirement. Finally, management problems—
including failure to articulate the need for change, a lack of top-
level commitment, and failure to address organizational issues—have 
hampered implementation of the initiatives. In February 2003, the Air 
Force established the Innovation and Transformation Directorate to 
address these problems, but its plans and priorities have not been 
set.

The Air Force can estimate the impact of increased funding on 
individual weapon systems’ supply availability and has done so. Based 
on its approximately $5.3 billion fiscal year 2004 spare parts budget 
request, the Air Force reported that aircraft supply availability 
would range from 73 to 100 percent. However, it cautioned that higher 
supply availability does not automatically result in higher mission 
capable rates because of other factors.

What GAO Recommends:

GAO recommends the Secretary of Defense

* incorporate Strategic Plan’s performance measures and targets 
relating to spare parts into its subordinate plans,

* start remaining initiatives to address the causes of parts shortages 
or show how they were incorporated into others, 

* adopt performance measures and targets to show impact of initiatives 
on parts shortages,

* direct the Innovation and Transformation Directorate to operate 
consistent with the Strategic Plan, and

* request funds in the Air Force budget consistent with results of its 
spare parts requirements determination process.

In its written comments on a draft of this report, the Department of 
Defense concurred with the intent of our recommendations, but not all 
actions.

[End of section]

Contents:

Letter:

Results in Brief:

Background:

Strategic Plan Has an Appropriate Framework but Is Not Adequately 
Supported by Subordinate Plans:

Initiatives Might Help Mitigate Spare Parts Shortages, but Their 
Potential Effectiveness Is Limited:

The Air Force Can Identify the Impact of More Funding on Supply 
Availability, but Not on Readiness:

Conclusions:

Recommendations for Executive Action:

Agency Comments and Our Evaluation:

Scope and Methodology:

Appendix I: Air Force Projected Aircraft Supply Availability Rates for 
Fiscal Year 2004:

Appendix II: Description and Estimated Completion Dates of Spares 
Campaign and Depot Maintenance Reengineering and Transformation 
Spare-Parts-Related Initiatives:

Appendix III: Not-Mission-Capable Supply Rate Targets by Weapon System:

Appendix IV: Comments from the Department of Defense:

Appendix V: GAO Contacts and Staff Acknowledgments:

Tables:

Table 1: Focus of Spares Campaign Review Teams:

Table 2: Summary of Initiatives Related to Spare Parts:

Table 3: Status of Spares Campaign Initiatives:

Table 4: Projected Air Force Aircraft Availability Rates:

Table 5: Spares Campaign Spare-Parts-Related Initiatives:

Table 6: Depot Maintenance Reengineering and Transformation Spare-
Parts-Related Initiatives:

Table 7: Not-Mission-Capable Supply Rate Targets by Weapon System:

Figure:

Figure 1: Relationship between Air Force Strategic Plan and Major 
Subordinate Plans:

Abbreviations:

DMRT: Depot Maintenance Reengineering and Transformation:

GPRA: Government Performance and Results Act of 1993:

United States General Accounting Office:

Washington, DC 20548:

June 27, 2003:

The Honorable Jerry Lewis Chairman, Subcommittee on Defense Committee 
on Appropriations House of Representatives:

Dear Mr. Chairman:

Since fiscal year 2000, the Air Force reportedly has spent 
approximately $10.5 billion from its annual operations and maintenance 
appropriations for spare parts, including additional supplemental 
funding totaling approximately $745 million.[Footnote 1] The Air Force 
has reportedly exceeded the Department of Defense's overall supply 
performance goal of having parts available 85 percent of the time when 
they are requested. Nevertheless, the Air Force continues to report 
spare parts shortages. While recognizing that spare parts shortages may 
never be eliminated, it is reasonable to expect the services to place a 
priority on efforts to mitigate (reduce) those shortages that adversely 
impact readiness. This priority should be inherent in their overall 
stewardship of funds they request from Congress and their 
accountability for making spare parts investment decisions that provide 
a good readiness return.[Footnote 2] In numerous reports, we have 
stated that DOD's inventory management is a high-risk area because of 
long-standing management weaknesses that could result in unnecessarily 
spending funds that could be directed to higher priorities, such as 
modernization or readiness.[Footnote 3]

This report is one in a series that responds to your request that we 
assist your committee in determining ways to improve the availability 
of spare parts.[Footnote 4] As agreed with your office, this report 
focuses on the following issues:

1. Does the Air Force's strategic plan address the mitigation of 
critical spare parts shortages--those that adversely affect 
readiness?[Footnote 5]

2. How likely will key Air Force initiatives mitigate critical spare 
parts shortages?

3. Does the Air Force have the ability to identify the impact on 
readiness of increased investments for spare parts?

To address these questions, we visited the Air Force Headquarters' 
Logistics Directorate and the Air Force Materiel Command, and we 
interviewed officials responsible for strategic planning, initiatives 
development and implementation, and requirements determination for 
spare parts funding. We also analyzed the strategic plans and key 
initiatives identified by the Air Force that address spare parts 
shortages and logistics support. We used the Government Performance and 
Results Act of 1993, prior GAO reports, and other key DOD documents as 
criteria to evaluate the Air Force's strategic plans and 
initiatives.[Footnote 6]

Results in Brief:

The Air Force Strategic Plan, issued between April 1998 and May 2000, 
generally provides an appropriate framework for mitigating critical 
spare parts shortages that affect readiness. However, its two 
subordinate logistics plans do not incorporate the same performance 
measures and targets, key elements of this framework. As a result, the 
Air Force is not in a position to determine if the actions taken 
pursuant to its subordinate plans mitigate the critical spare parts 
shortages, giving it the greatest readiness return on its spare parts 
investment. The Strategic Plan contains three long-term strategic 
goals, output-related performance measures, and performance targets. 
Goal 2 of the plan addresses two mission critical tasks that relate to 
mitigating spare parts shortages and identifies 19 performance 
measures, many specifically related to improving spare parts 
inventories. For example, one mission critical task is "to improve 
mission effectiveness while minimizing risk." To measure progress in 
implementing this task, the plan cites the need to track the percentage 
of time that aircraft cannot perform their mission because spare parts 
are not available. Moreover, the plan specifies performance targets for 
reducing the frequency at which this should occur, such as 9 percent 
for the F-15E and 22 percent for the B-1. Rather than use these 
performance measures and targets to guide its efforts, the Air Force in 
its subordinate Logistics Support Plan usually cited measures, such as 
the need to develop and apply combat support doctrine, without 
reference to a particular output that could be used to measure 
progress.[Footnote 7] Although the other subordinate logistics plan, 
the Supply Strategic Plan, cited output-related performance measures 
like those in Goal 2 of the Air Force Strategic Plan, it did not 
contain any performance targets against which to measure progress.

While key Air Force logistics initiatives that are intended to improve 
logistics processes might help mitigate spare parts shortages, their 
potential is limited for several reasons. First, the Air Force has not 
started 12 of the 43 initiatives it had identified as necessary to 
address the causes of spare parts shortages nor have they demonstrated 
that all key aspects of these 12 have been incorporated into other 
initiatives. According to the Air Force, it intends to reevaluate when 
and which of these initiatives should be started but has not specified 
a date for doing this. Without a commitment to implement all of the 
necessary initiatives, the Air Force is not assured that all the causes 
of shortages will be sufficiently addressed. Second, 23 of the 31 
initiatives implemented lack both performance measures and targets. 
Without output-related performance measures and targets to assess the 
initiatives' impact, the Air Force has little means of determining the 
extent to which it has successfully mitigated spare parts shortages and 
improved readiness. Third, the Air Force chose not to use the results 
of one of its initiatives, which compiled all of the service's spare 
parts requirements to identify a total requirement of approximately 
$5.9 billion. Instead, in its fiscal year 2004 budget request, the Air 
Force asked for approximately $5.3 billion and identified a $578 
million unfunded requirement, thereby raising questions about the 
validity of its new requirements computation process and its budget 
request. Finally, in 2002 an Air Force review team identified several 
management problems, which have hampered implementation of its 
initiatives. These problems include failure to clearly articulate the 
need for change, a lack of strong top-level commitment, and failure to 
address organizational issues. Although a directorate established in 
February 2003 is intended to address these issues, it has not 
established its plans or priorities. If concerns about these 
initiatives are not resolved, the Air Force cannot be assured that it 
has taken all the actions necessary to address the causes of spare 
parts shortages, measured the affect of its initiatives, and 
established effective management oversight.

The Air Force can estimate the impact of increased spare parts funding 
on individual weapon systems' supply availability and has done so. In 
its fiscal year 2004 budget request, the Air Force reported how its 
spare parts funding request would allow each of its major weapon 
systems to achieve a specified aircraft supply availability rate (see 
app. I for the rate for each aircraft).[Footnote 8] Based on its 
approximately $5.3 billion fiscal year 2004 budget request, the Air 
Force reported that aircraft supply availability would range from 73 
percent for the H-60 helicopter to 100 percent for the F-111 attack 
aircraft. This information came from the service's Funding/Availability 
Multi-Method Allocator for Spares model, which was developed to predict 
the affects of supply funding on mission capable rates. Using this 
model, the Air Force can also estimate how 1 percent increments in 
additional funding could increase spare parts availability. The Air 
Force cautioned, however, that increased supply availability does not 
automatically result in increased mission capable rates because other 
factors, such as maintenance and transportation can affect these rates.

Due to the critical impact of spare parts shortages on readiness as 
well as the Air Force's need to make good investment decisions, we are 
making recommendations to the Secretary of Defense aimed at ensuring 
that the Air Force Strategic Plan, subordinate plans, and initiatives 
have consistent performance measures and targets to show how successful 
the service has been at improving spare parts availability and 
readiness. We also recommend that the Air Force commit to starting the 
remaining initiatives that are aimed at addressing the causes of spare 
parts shortages or clearly identify how the initiatives are included in 
other initiatives already started. In addition, we recommend the Air 
Force request funds in its budget consistent with its spare parts 
requirements determination process. In written comments on a draft of 
this report, the Department of Defense concurred with the intent of our 
five recommendations, but not all actions cited in our second 
recommendation. In concurring with the second recommendation related to 
starting the remaining initiatives, the Department of Defense's 
position was that the initiatives were either already incorporated into 
other initiatives or overtaken by other events. Given the importance of 
overcoming causes of shortages that reduce the overall effectiveness of 
the Air Force's logistics efforts, the thrust of our recommendation is 
for the service to show clearly which initiatives have been 
incorporated into those already started and what events have overtaken 
the others to ensure that all causes of spare parts shortages 
identified by the Air Force are adequately addressed. Therefore, we 
continue to believe the actions prescribed in the recommendation are 
needed. In concurring with the funding recommendation, the Air Force 
stated that its 2004 budget request was developed consistent with its 
new requirements process, but its funding was constrained. This 
response confirms our statement that the Air Force has underfunded its 
spare parts requirements and thereby created the potential for a 
supplemental budget request or for additional shortages that could 
negatively affect readiness. The department's comments and our 
evaluation are on pages 17 and 18 of this report.

Background:

The Air Force recognized that reductions in spare parts inventories 
since the early 1990s have negatively affected aircraft readiness 
indicators such as mission capable rates, not-mission-capable supply, 
not-mission-capable maintenance, and cannibalizations.[Footnote 9] 
Recognizing the need to reverse this trend and that previous attempts 
to pinpoint specific spare parts shortages were piecemeal, temporary, 
and lacked adequate personnel to implement, the Air Force began a 5 to7 
year logistics transformation effort in 1999 aimed at improving the 
efficiency and economy of the entire logistics process to enhance 
support to the warfighter. Rather than focusing on fully eliminating 
specific spare parts shortages, the Air Force chose to focus on 
addressing the process disconnects that caused the shortages. This 
included an end-to-end look at all aspects of the logistics process 
including commercial supply chain management, supply, maintenance, 
transportation, logistics planning, and financial management. The 
Spares Campaign initiated in February 2001 and the Depot Maintenance 
Reengineering and Transformation (DMRT) effort started in July 2001 
were two key parts of the end-to-end review.[Footnote 10] In total, 
they identified the need for 84 initiatives, 43 of which related to 
spare parts.

The Spares Campaign focused on supply process deficiencies, and it was 
intended to improve parts supportability to weapon systems and reverse 
declining readiness related to spares management. This was considered 
a major transformation effort and included five teams that reviewed the 
processes needed to produce spares and identified disconnects and 
solutions that would improve mission capability and manage cost 
(see table 1).

Table 1: Focus of Spares Campaign Review Teams:

Spares campaign teams: Programming and financial management; Team 
focus: Reviewed how spares budgets are determined, funding obtained, 
and cost managed.

Spares campaign teams: Requirements determination; Team focus: Reviewed 
processes for identifying spares requirements.

Spares campaign teams: Requirements allocation, execution, and 
distribution; Team focus: Analyzed the processes and policies involved 
in getting spares and repair parts to depots and field locations.

Spares campaign teams: Spares command and control; Team focus: Studied 
management control of the spares processes.

Spares campaign teams: Supplier relationships; Team focus: Explored 
options for improving how the Air Force deals with suppliers of parts.

Source: U.S. Air Force.

[End of table]

Each team developed a flowchart showing how it believed processes 
related to its focus area should function and be managed to improve 
weapon system availability and cost management. The teams also 
identified disconnects or barriers preventing the processes from 
functioning as they should and recommended solutions to correct 
these disconnects. Twelve major deficiencies were noted, and more than 
190 corrective actions were identified, which resulted in 20 
initiatives, 19 of which were related to spare parts shortages. As of 
February 2003, 7 of 19 spare parts initiatives have been started.

The DMRT effort, focused on deficiencies in depot maintenance 
processes. Various teams identified disconnects and barriers in these 
processes, reviewed Air Force current initiatives that affected depot 
maintenance, and identified industry best practices and benchmarking, 
receiving input from Air Force management, major commands, and 
Air Logistics Centers. More than 300 barriers to depot maintenance 
operational and financial performance were identified and consolidated 
into more than 40 major issues organized around 8 overarching focus 
areas. This resulted in 64 initiatives, 24 of which were related to 
spare parts. All 24 of the spare parts related initiatives have been 
started. Table 2 below summarizes the status of the Spares Campaign and 
DMRT initiatives as of February 2003. Appendix II provides a 
description of the 31 Spares Campaign and DMRT initiatives that have 
been started and estimated completion dates.

Table 2: Summary of Initiatives Related to Spare Parts:

Spares campaign; Initiatives identified: 20; Initiatives related to 
spares: 19; Initiatives started: 7.

Depot maintenance reengineering and transformation; Initiatives 
identified: 64; Initiatives related to spares: 24; Initiatives started: 
24.

Totals; Initiatives identified: 84; Initiatives related to spares: 43; 
Initiatives started: 31.

Source: U.S. Air Force.

[End of table]

Strategic Plan Has an Appropriate Framework but Is Not Adequately 
Supported by Subordinate Plans:

The Air Force Strategic Plan is appropriately structured to provide a 
framework for mitigating spare parts shortages, but its two subordinate 
plans are not aligned with it in terms of performance measures. 
Consistent with sound management principles underlying the Government 
Performance and Results Act of 1993 (GPRA), the strategic plan includes 
a mission statement, long-term goals, and performance measures and 
targets, and some of these elements relate to spare parts shortages. 
However, the performance measures and targets in the subordinate plans 
are not consistent with those in the strategic plan or none are stated. 
This lack of alignment with the Air Force Strategic Plan's performance 
measures and targets means that the service cannot measure the 
contribution of the actions it takes in response to the subordinate 
plans toward overcoming spare parts shortages and be assured 
that implementing the subordinate plans will mitigate critical spare 
parts shortages and give the Air Force its greatest readiness return 
on investment.

Strategic Plan Complies with Most GPRA Requirements:

The Air Force Strategic Plan, issued between April 1998 and May 2000, 
generally includes an effective strategy consistent with GPRA 
guidelines, and it generally represents an effective framework for 
reducing spare parts shortages. The plan applies to the Air Force as a 
whole and contains a mission statement, strategic goals, and output-
related performance measures and targets. Specifically, the strategic 
plan has three goals: Goal 1 is to ensure a high quality force of 
people, Goal 2 is to enable commanders to respond to all types of 
crises, and Goal 3 is to prepare for an uncertain future by pursuing a 
modernization program. Each goal contains mission critical tasks (such 
as "Maximize the efficiency of operating and maintaining Air Force 
resources") along with related performance measures and targets for 
determining progress toward achieving its strategic goals.

Of the three strategic goals, Goal 2 addresses the mitigation of spare 
parts shortages. It has two mission critical tasks and 19 performance 
measures, many specifically related to improving spare parts 
inventories. One mission critical task, to "improve mission 
effectiveness while minimizing risk," cites the percentage of aircraft 
that cannot perform their mission because spare parts are not available 
as a performance measure. It also cites performance targets for each 
aircraft. For example, the target for the F-15E is 9 percent and for 
the B-1 it is 22 percent, meaning that percent of the aircraft cannot 
perform their mission because of spare parts shortages (see appendix 
III for the not mission capable supply rate targets). The second 
mission critical task, to "maximize the efficiency of operating and 
maintaining the Air Force resources," has the elapsed time between when 
a customer submits an order and receives the part as a performance 
measure.

Performance Measures and Targets in Subordinate Plans Are Not 
Consistent with Strategic Plan:

The major subordinate plans for implementing the Air Force Strategic 
Plan include goals similar to those in the strategic plan. However, 
their performance measures and targets are not linked to those in the 
strategic plan. The subordinate plans are the Logistics Support Plan 
and the Supply Strategic Plan (see fig. 1).

Figure 1: Relationship between Air Force Strategic Plan and Major 
Subordinate Plans:

[See PDF for image]

[End of figure]

The Logistics Support Plan was developed to provide authoritative, 
strategic direction and front-end guidance for Air Force logistics 
capabilities planning. It includes the same goals as the higher plan, 
and it contains objectives for accomplishing these goals. The plan does 
not include quantitative or qualitative output-related performance 
measures and targets that will yield the performance information needed 
to assess goal accomplishment at either the subordinate or strategic 
plan levels in order to measure results. Instead, it includes measures 
that will only yield information about whether or not a specific 
process was implemented. For example, the completion of combat support 
doctrine is the performance measure cited for accomplishing the 
objective to improve combat support to warfighters by developing and 
applying an Agile Combat Support doctrine. Another nonquantitative or 
qualitative performance measure was full fielding of identified total 
asset visibility capabilities for the objective to fully implement 
total asset visibility.

The Supply Strategic Plan was intended to (1) create an integrated 
process for Air Force supply planning, (2) establish the planning 
infrastructure to facilitate information exchange throughout Air Force 
Supply, and (3) improve Air Force Supply's measures of effectiveness. 
This plan contains five long-term goals that are consistent with the 
higher plan's goals, and it has 19 objectives, 71 tasks to accomplish 
these objectives, and a projected end-state for some of these 
tasks.[Footnote 11] Some end-states are similar to the strategic plan's 
output-related performance measures, but do not have corresponding 
performance targets. For example, one end-state discusses incidents of 
aircraft being not mission capable due to the lack of spare parts, but 
it does not specify a target (i.e., the desired percentage of 
incidences) against which to measure improvement. Other end-states did 
not discuss performance measures at all. For example, one end-state is 
completion of the new Air Force Supply Stockage Policy Guide and making 
it available to supply officers worldwide.

Without effective quantitative and qualitative measures that flow from 
the Strategic Plan structure to the subordinate plans, the Air Force 
cannot determine the extent to which the implementation of these plans 
is contributing to its overall strategic goal relating to overcoming 
spare parts shortages. Furthermore, the Air Force cannot be assured 
that implementing the subordinate plans will give them the greatest 
readiness return on their investment.

Initiatives Might Help Mitigate Spare Parts Shortages, but Their 
Potential Effectiveness Is Limited:

Key logistics initiatives being implemented by the Air Force may help 
to mitigate spare parts shortages, but their potential effectiveness is 
limited for several reasons. The Air Force has begun a major logistics 
transformation effort intended to improve the entire logistics process 
and identified numerous initiatives to improve its logistics process by 
addressing deficiencies, barriers, or disconnects. However, it has not 
implemented 12 of the 43 initiatives it identified as needed to address 
spare parts shortages nor demonstrated that all key aspects of these 
12 have been incorporated into other initiatives underway. In addition, 
23 of the 31 initiatives being implemented lack performance measures 
and targets. The Air Force also chose not to use the results of one of 
its initiatives, which identified a new consolidated requirement for 
spare parts; consequently, additional spare parts shortages could 
occur. Lastly, management problems identified by an Air Force review 
team in 2002 have hampered implementation of the initiatives, and its 
new directorate, established in February 2003, has not established a 
plan or priorities to address these problems.

Air Force Has Not Started All Initiatives:

In 2001, the Air Force identified 43 initiatives to improve processes 
related to spare parts shortages--19 as part of the Spares Campaign and 
24 as part of the DMRT. As of February 2003, 31 of the 43 initiatives 
have been started. The Air Force has started all 24 DMRT initiatives 
that relate to improving spare parts shortages, but has started only 7 
of the 19 initiatives that relate to spare parts shortages arising from 
the Spares Campaign. Table 3 shows the implementation status of Spares 
Campaign initiatives.

Table 3: Status of Spares Campaign Initiatives:

Initiatives: Improve depot-level repair throughput; Started: No; 
Not started: Yes.

Initiatives: Establish virtual single inventory control point; Started: 
Yes; Not started: No.

Initiatives: Improve spares budgeting; Started: Yes; Not started: 
No.

Initiatives: Improve item demand and repair workload forecasting; 
Started: Yes; Not started: No.

Initiatives: Develop alternative stockage policies to support 
warfighter; Started: No; Not started: Yes.

Initiatives: Ensure a competent and skilled workforce; Started: 
No; Not started: Yes.

Initiatives: Improve financial management; Started: Yes; Not started: 
No.

Initiatives: Create common operating view and improve data accuracy; 
Started: No; Not started: Yes.

Initiatives: Designate a single authority for spares management; 
Started: No; Not started: Yes.

Initiatives: Implement integrated supply chain management; Started: 
No; Not started: Yes.

Initiatives: Develop process to manage and reduce demands; Started: 
No; Not started: Yes.

Initiatives: Align supply chain management focus; Started: Yes; Not 
started: No.

Initiatives: Improve/restructure working capital fund; Started: 
No; Not started: Yes.

Initiatives: Develop appropriate metrics; Started: No; Not 
started: Yes.

Initiatives: Actively manage suppliers and supply base; Started: 
No; Not started: Yes.

Initiatives: Enable a single logistics proponent; Started: No; Not 
started: Yes.

Initiatives: Standardize use and role of regional supply squadrons; 
Started: Yes; Not started: No.

Initiatives: Adopt improved purchasing and supply chain management; 
Started: Yes; Not started: No.

Initiatives: Develop e-business strategy; Started: No; Not 
started: Yes.

Source: U. S. Air Force.

[End of table]

According to the Air Force, it chose to start the seven Spares Campaign 
initiatives that reflected its highest priorities, provided greatest 
impact to the logistics processes, and resulted in highest payback to 
the Air Force. The remaining 12 initiatives have not been started 
because the Air Force said it did not have the needed personnel and 
funding. Although the Air Force provided a document showing that some 
aspects of the remaining initiatives had been embedded into the Ten 
Focus Initiatives of the Spares Campaign, we could not verify that all 
of these initiatives had been started. Also, we could not validate that 
all of the deficiencies, disconnects, or barriers intended to be 
addressed by the remaining 12 initiatives were actually being 
addressed. Consequently, some of the process problems identified in the 
Spares Campaign that cause spare parts shortages may not be addressed, 
thereby reducing the overall effectiveness of the Air Force's efforts 
to mitigate spare parts shortages.

Most Initiatives Lack Output-Related Performance Measures and Targets:

Twenty-three of the 31 Air Force initiatives that have been started 
lack output-related performance measures and targets. One of the 23 
initiatives, the Material Policy initiative, has revision of all 
policies as its performance target. The other 22 initiatives were part 
of the DMRT effort and did not have any performance measure or any 
performance targets. Air Force officials said they are still trying to 
develop measures and targets for each of these initiatives. The other 
eight initiatives--such as the Weapon System Supply Chain Manager, 
Regional Supply Squadron, and Demand and Repair Workload Forecasting--
have output-related measures, including how effective they are in 
making weapon systems available, the amount of cannibalization done to 
keep aircraft available, and the amount of aircraft that are not 
mission capable due to supply or maintenance problems. Without 
quantitative or qualitative performance-related measures and targets 
relating to improving spare parts availability, the Air Force lacks the 
means to determine the extent to which these initiatives have improved 
readiness by reducing spare parts shortages.

Air Force Did Not Apply the Results of a Completed Initiative:

One Spares Campaign initiative recently established a new total 
requirement for spare parts, but the service chose not to request all 
the funds to meet the requirement. The Spares Campaign's Improve Spares 
Budgeting initiative created a Spares Requirement Review Board to 
identify a single, consolidated requirement for spare parts and 
consumable items. In the past, the Air Force had budgeted for spares 
based on annual flying-hour requirements with little consideration for 
the spares needed to meet non-flying-hour requirements, such as the 
pipeline or safety stock.[Footnote 12] As a result, the Air Force 
experienced parts shortages because demands for non-flying-hour spare 
parts had not been sufficiently budgeted. The review board compiled 
flying-hour and non-flying-hour requirements into a single, agreed upon 
requirement to be used for planning, programming, and budgeting.

The Air Force's new process yielded a new total spare parts requirement 
of approximately $5.9 billion for the fiscal year 2004 budget 
submission. However, in its fiscal year 2004 budget the service chose 
to only request $5.3 billion. After the service submitted its fiscal 
year 2004 budget, the Secretary of the Air Force reported $578 million 
in unfunded spares requirements: $166 million of this was for pipeline 
and other requirements, and $412 million was for the flying-hour 
program. The Air Force's decision to request less funding than 
identified in their most recent requirements determination process 
raises concerns. Either the Air Force's new spare parts requirements 
determination process is not a valid basis for future budget decisions, 
or by not requesting the full amount to meet the requirement, the Air 
Force has created the potential for additional spare parts shortages 
that could negatively affect readiness or has created the need for a 
supplemental budget request. Air Force officials said they took a risk 
that the $5.3 billion budget request would be sufficient based on the 
actual flying-hour cost experienced in fiscal year 2002. That year, 
they said, the flying-hour program was executed at a cheaper rate than 
budgeted.

Management Weaknesses Impeded Implementation of Initiatives:

The Air Force recently established a new directorate to address several 
management issues that it believes adversely affects its logistics 
transformation initiatives, but the extent to which this directorate 
will improve overall management of these initiatives is not clear. In 
2002, the Air Force formed a review team composed of retired general 
officers, senior executives, and industry leaders that assessed 
initiative implementation plans, identified problems with its logistics 
transformation efforts, and developed recommendations to solve these 
problems. The team concluded that a high risk of failure existed for 
the transformation efforts because (1) the Air Force is not clearly 
articulating throughout its organization the need for changes, (2) top-
level commitment to implementing initiatives is not as strong as needed 
as evidenced by schedule slippage and lack of funding for initiatives, 
and (3) clear roles and responsibilities concerning the Spares Campaign 
are not being addressed. One of the team's recommendations was to merge 
the Spares Campaign and DMRT efforts into a single, full-time logistics 
transformation program. In February 2003, the Air Force established the 
Innovation and Transformation Directorate, a new organization under the 
Logistics Division, which according to an Air Force briefing, 
consolidated the two efforts and placed oversight responsibility for 
all Air Force logistics transformation efforts on top-level leadership 
within one office.

According to the Air Force, some of the first steps for the new 
directorate will be to review existing Spares Campaign and DMRT 
initiatives, resolve deficiencies in the two efforts, set aggressive 
timelines, goals, objectives, and performance measures, and obtain 
senior leadership approval of their actions. However, according to Air 
Force officials, the plans and priorities of this new directorate had 
not been set as of April 2003. Without such plans, priorities, and 
senior leadership commitment guiding the Air Force's efforts to 
overcome these problems, the potential benefits from its initiatives to 
mitigate spare parts shortages that impact readiness may be delayed or 
possibly not achieved.

The Air Force Can Identify the Impact of More Funding on Supply 
Availability, but Not on Readiness:

The Air Force can show that additional funding for spare parts would 
improve aircraft supply availability if the funds were provided 
directly to the working capital fund. However, the Air Force does not 
link funding for spare parts directly to readiness because other 
factors also affect readiness. In its fiscal year 2004 budget request 
for spare parts funding, the Air Force included information on how 
spare parts funding in the working capital fund affected the supply 
availability for various types of aircraft (see app. I for projected 
aircraft availability rates).[Footnote 13] The budget request indicated 
that spare parts funding of approximately $5.3 billion would allow for 
aircraft supply availability ranging from 73 percent for the H-60 to 
100 percent for the F-111.

The Air Force drew this data from its Funding/Availability Multi-Method 
Allocator for Spares model, which estimates how many and which 
additional parts (i.e. supply availability) it can procure with 
different amounts of operating authority.[Footnote 14] The Air Force 
said that the model has some weaknesses, but it does provide a good 
mechanism for projecting aircraft supply availability. One weakness, 
according to DOD, is that while the model attempts to optimize supply 
parts availability, it is generally biased towards the purchase of low 
cost/high-demand items versus those critical spare parts that would 
most improve mission capable rates.

The Air Force can also use this model to show how additional funding 
could increase spare parts availability by estimating the cost of 
additional supply availability in 1 percent increments by weapon 
system. For example, in 2002 the cost for the F-15E to achieve an 88 
percent supply availability rate was approximately $237 million. To 
increase this availability 1 percent would have cost an additional $7 
million. Similarly, it cost the Air Force approximately $301 million 
for the C-5 to achieve an 82 percent supply availability rate. To 
achieve an additional 1 percent supply availability would have cost an 
additional $3.6 million.

According to the Air Force, additional supply availability results in 
improved stockage effectiveness and reduced customer wait time, 
back orders, and cannibalization rates, which all contribute to 
increased readiness. However, the Air Force cautioned that increased 
supply availability does not automatically result in increased mission 
capable (readiness) rates because other factors, such as maintenance 
and transportation, affect these rates. For example, if maintenance 
staffing levels at depots are inadequate, then even with 100 percent 
supply availability, mission capability will not be at its highest 
possible level.

Conclusions:

An Air Force strategic goal is to address problems that adversely 
affect mission accomplishment, such as critical spare parts shortages 
that reduce readiness. While it has a strategic plan that provides a 
good management framework, places emphasis on mitigating spare parts 
shortages, and cites performance measures and targets for assessing 
progress, the Air Force's potential for successful implementation of 
the plan is hindered by several problems. Subordinate plans have not 
adopted the Strategic Plan's readiness-related performance measures and 
targets; all identified initiatives to deal with the causes of spare 
parts shortages have not been started or key aspects clearly 
incorporated into other initiatives; and many of those that have been 
started lack effective performance measures and targets. Additionally, 
some management weaknesses could significantly impede successful 
initiative oversight and implementation. By not adopting specific 
performance measures and targets related to mitigating the critical 
spare parts shortages into subordinate plans and initiatives, following 
through on initiatives to address the causes of parts shortages and 
determine spare parts requirements, and resolving program management 
deficiencies, the Air Force has little assurance that its program 
emphasis and initiatives will improve spare-parts-related readiness. 
Furthermore, as part of its stewardship and accountability for funds, 
the Air Force will not be assured that the service's spare parts 
spending is yielding the best readiness return on investment.

Recommendations for Executive Action:

We are recommending that the Secretary of Defense direct the Secretary 
of the Air Force to take the following steps:

* Incorporate the Air Force Strategic Plan's performance measures and 
targets into the subordinate Logistics Support Plan and the Supply 
Strategic Plan.

* Commit to start those remaining initiatives needed to address the 
causes of spare parts shortages or clearly identify how the initiatives 
have been incorporated into those initiatives already underway.

* Adopt performance measures and targets for its initiatives that will 
show how their implementation will affect critical spare parts 
availability and readiness.

* Direct the new Innovation and Transformation Directorate to establish 
plans and priorities for improving management of logistics initiatives 
consistent with the Air Force Strategic Plan.

* Request spare parts funds in the Air Force's budget consistent with 
results of its spare parts requirements determination process.

Agency Comments and Our Evaluation:

In written comments on a draft of this report, the Department of 
Defense concurred with the intent of all five recommendations, but not 
all actions. The Department of Defense's written comments are reprinted 
in their entirety in appendix IV.

In concurring with our first, third, and fourth recommendations 
concerning incorporating and adopting performance measures and 
targets into subordinate plans and initiatives, the Department of 
Defense responded that the establishment of the Directorate of 
Innovation and Transformation, the directorate's efforts to develop a 
balanced scorecard and supporting metrics, and its draft campaign plans 
which spell out and track milestones for each initiative were 
consistent with the direction of the Strategic Plan.[Footnote 15] We 
believe that if the Department of Defense follows through with its 
plans for the new directorate, as laid out in its written response, 
these planned actions should meet the thrust of our recommendations.

The Department of Defense concurred with the intent of our second 
recommendation related to starting those remaining initiatives needed 
to address the causes of shortages, but not the specific actions. In 
its comments the Department of Defense stated the original 19 
initiatives have been either consolidated into the Ten Focus 
Initiatives or overtaken by other events making it unnecessary to 
separately track progress for each of the individual actions. Based on 
this action, the Department of Defense concluded that it had complied 
with this recommendation. We disagree that the department's actions 
fully respond to our recommendation. The thrust of our recommendation 
is that the Air Force identify which of the 12 remaining initiatives 
that were not started were incorporated into the Ten Focus Initiatives 
and what events have overtaken the others to ensure that all causes of 
spare parts shortages identified by the Air Force are being adequately 
addressed.

In concurring with our fifth recommendation that the Air Force request 
spare parts funds consistent with results of its spare parts 
requirements determination process, the Department of Defense responded 
that the Air Force's spare parts budget was developed consistent with 
the new requirements determination process, but the amount of funding 
requested was constrained. This response confirms our statement that 
the Air Force has underfunded its spare parts requirements and thereby 
created the potential for a supplemental budget request or for 
additional spare parts shortages that could negatively affect 
readiness.

Scope and Methodology:

To accomplish our three objectives, we visited the Air Force 
Headquarters' Logistics Directorate, in Washington, D.C., the Air Force 
Material Command, in Dayton, Ohio and contractor representatives at 
Bearing Point (formerly KPMG Consulting) in McLean, Virginia.

To determine whether the strategic plans address the mitigation of 
spare parts shortages, we reviewed the Air Force Strategic Plan, its 
two subordinate plans--Logistics Support Plan and Supply Strategic 
Plan--as well as other strategic planning documents and interviewed 
officials to determine whether these plans included key actions 
targeted at mitigating critical spare parts shortages and improving 
readiness. We also reviewed these plans to determine if performance 
measures and targets in the subordinate plans were similar and linked 
to those in the higher-level strategic plan. Additionally, we reviewed 
these plans to determine whether they included the elements of a 
strategic plan as defined by the GPRA.

To determine the likelihood of whether key initiatives would mitigate 
spare parts shortages to improve readiness, we interviewed Air Force 
officials to identify the initiatives that they believe will mitigate 
spare parts shortages and improve readiness. We obtained and reviewed 
documents related to the 31 spare-parts-related initiatives that have 
been started to determine the likelihood of whether they would mitigate 
spare parts shortages. We evaluated these initiatives to determine 
whether they included quantifiable and measurable performance targets 
as described by GPRA that would allow an assessment of how 
implementation of the initiatives would impact spare parts shortages. 
We also assessed whether these initiatives included all identified 
actions needed to overcome the causes of spare parts shortages. In 
addition, we obtained a briefing and discussed with Air Force officials 
the results of an Air Force review team's assessment of its logistics 
transformation efforts that identified management weaknesses.

To determine what impact the Air Force could identify from additional 
funding for spare parts, we interviewed officials and obtained 
documents related to the Air Force's fiscal year 2004 budget 
submission. We also discussed with Air Force budget officials their 
Funding/Availability Multi-Method Allocator for Spares model, which 
includes projected supply availability rates based on estimated funding 
amounts and was used to provide the budget information.[Footnote 16]

We performed our review from August 2002 to March 2003 in accordance 
with generally accepted government auditing standards.

We are sending copies of this report to the Secretary of Defense; 
the Secretary of the Air Force; the Director, Office of Management 
and Budget; and other interested congressional committees and parties. 
We will also make copies available to others upon request. In addition, 
the report will be available at no charge on the GAO Web site at http:/
/www.gao.gov.

Please contact me on (202) 512-8365 if you or your staff have any 
questions concerning this report. Major contributors to this report are 
included in appendix V.

Sincerely,

William M. Solis, 
Director 
Defense Capabilities and Management:

Signed by William M. Solis:

[End of section]

Appendix I: Air Force Projected Aircraft Supply Availability Rates for 
Fiscal Year 2004:

In response to a recommendation in the Inventory Management Study of 
the Office of the Secretary of Defense, the Air Force included supply 
availability rates for its weapons systems in its fiscal year 2004 
budget submission. As shown in table 4, the Air Force projected 
aircraft supply availability rates ranging from 73 percent to 100 
percent based on requested funding of approximately $5.3 billion.

Table 4: Projected Air Force Aircraft Availability Rates:

Aircraft: A-10; Budget request: (dollars in millions): 177.702; 
Availability rate (percent): 85.70.

Aircraft: B-1B; Budget request: (dollars in millions): 258.001; 
Availability rate (percent): 77.60.

Aircraft: B-2; Budget request: (dollars in millions): 109.886; 
Availability rate (percent): 93.60.

Aircraft: B-52; Budget request: (dollars in millions): 147.867; 
Availability rate (percent): 88.20.

Aircraft: C-5; Budget request: (dollars in millions): 371.571; 
Availability rate (percent): 81.30.

Aircraft: C-130; Budget request: (dollars in millions): 310.825; 
Availability rate (percent): 85.70.

Aircraft: C-135; Budget request: (dollars in millions): 367.465; 
Availability rate (percent): 89.40.

Aircraft: C-141; Budget request: (dollars in millions): 16.009; 
Availability rate (percent): 84.50.

Aircraft: E-3; Budget request: (dollars in millions): 82.819; 
Availability rate (percent): 89.90.

Aircraft: E-4; Budget request: (dollars in millions): 0.121; 
Availability rate (percent): 89.00.

Aircraft: E-8; Budget request: (dollars in millions): 0.000; 
Availability rate (percent): 95.10.

Aircraft: F-4; Budget request: (dollars in millions): 5.659; 
Availability rate (percent): 94.40.

Aircraft: F-15; Budget request: (dollars in millions): 572.037; 
Availability rate (percent): 89.30.

Aircraft: F-16; Budget request: (dollars in millions): 392.210; 
Availability rate (percent): 86.90.

Aircraft: F-111; Budget request: (dollars in millions): 0.26; 
Availability rate (percent): 100.00.

Aircraft: F-117; Budget request: (dollars in millions): 0.067; 
Availability rate (percent): 95.10.

Aircraft: H-1; Budget request: (dollars in millions): 9.413; 
Availability rate (percent): 100.00.

Aircraft: H-53; Budget request: (dollars in millions): 51.095; 
Availability rate (percent): 87.30.

Aircraft: H-60; Budget request: (dollars in millions): 5.101; 
Availability rate (percent): 73.20.

Aircraft: Trainers; Budget request: (dollars in millions): 64.592; 
Availability rate (percent): 95.00.

Aircraft: Other Aircraft; Budget request: (dollars in millions): 9.842; 
Availability rate (percent): 94.00.

Aircraft: Special Operations Forces; Budget request: (dollars in 
millions): 30.765; Availability rate (percent): 88.60.

Aircraft: Other[A]; Budget request: (dollars in millions): 2,358.843; 

Aircraft: Total; Budget request: (dollars in millions): $5,342.150; 

Source: U. S. Air Force.

[A] Engines, missiles, electronic warfare, etc. The Air Force does not 
compute supply availability for these items.

[End of table]

[End of section]

Appendix II: Description and Estimated Completion Dates of Spares 
Campaign and Depot Maintenance Reengineering and Transformation 
Spare-Parts-Related Initiatives:

Table 5: Spares Campaign Spare-Parts-Related Initiatives:

Initiative: 1. Establish virtual inventory control point; Description: 
Provide single visibility over buy and repair requirements and 
distribution.; Estimated completion date[A]: Feb. 2004.

Initiative: 2. Align supply chain manager focus (Weapon system supply 
chain manager); Description: Single weapons system manager to execute 
buy and repair priorities and other management decisions.; Estimated 
completion date[A]: Mar. 2003.

Initiative: 3. Standardize use and expand role of regional supply 
squadron; Description: Provides for supply management on a regional 
basis, visibility of items in region.; Estimated completion date[A]: 
Sept. 2004.

Initiative: 4. Improve financial management; Description: Tracks 
weapons system support against plans and budget; Estimated completion 
date[A]: Sept. 2002.

Initiative: 5. Improve demand & repair workload forecasting; 
Description: Predict more accurately number and type of items needing 
repair and number of new items.; Estimated completion date[A]: Sept. 
2007.

Initiative: 6. Improve spares budgeting (Spares requirement review 
board); Description: Consolidated requirements determination.; 
Estimated completion date[A]: Jan. 2003.

Initiative: 7. Adopt improved purchasing and supply chain management; 
Description: Implement commercial best practices into Air Force supply 
management.; Estimated completion date[A]: Mar. 2006.

Source: U. S. Air Force:

[A] This represents reported completion dates as of February 2003. The 
Innovation and Transformation Directorate plans to review each 
initiative and determine what further actions should be taken.

[End of table]

Table 6: Depot Maintenance Reengineering and Transformation Spare-
Parts-Related Initiatives:

Initiative: 8. Standard process improvement strategy; Description: 
Establish and implement a corporate strategy for directing, overseeing, 
coordinating, improving, and facilitating depot maintenance 
operations.; Estimated completion date[A]: Sept. 2003.

Initiative: 9. Maintenance training; Description: Develop a maintenance 
training organization as a single training entity for all depot 
maintenance training. Build maintenance orientation and technical 
training plans.; Estimated completion date[A]: Sept. 2003.

Initiative: 10. Maintenance first line supervisory training; 
Description: Establish program that will train first line supervisory 
candidates prior to assumption of duties.; Estimated completion 
date[A]: Oct. 2003.

Initiative: 11. Maintenance professional development; Description: 
Train and develop maintenance workers and leaders.; Estimated 
completion date[A]: Oct. 2002.

Initiative: 12. Awards/appraisal systems; Description: Establish 
performance plans that focus on cost, schedule, performance and quality 
goals. Motivate work force by establishing incentive programs, which 
instill a desire to excel.; Estimated completion date[A]: Sept. 2003.

Initiative: 13. Unresponsive hiring process; Description: Establish 
hiring authorities to appoint the best qualified candidates and 
streamline the staffing process (external & internal).; Estimated 
completion date[A]: June 2003.

Initiative: 14. Engineering hiring/retention; Description: Develop 
compensation packages competitive with the commercial market.; 
Estimated completion date[A]: Sept. 2004.

Initiative: 15. Multi-skilling; Description: Determine how to employ 
multi-skilling for best value implementation.; Estimated completion 
date[A]: Jan. 2003.

Initiative: 16. Supervisor's distractors; Description: Continue to 
assess impact of data systems on 1st level supervisor's time. Review 
regulatory mandates assigning additional duties to first levels.; 
Estimated completion date[A]: Feb. 2003.

Initiative: 17. Formalize the depot integrated infrastructure master 
plan; Description: Formalize the depot infrastructure strategic 
planning process.; Estimated completion date[A]: Sept. 2004.

Initiative: 18. Incentivize infrastructure investment in maintenance 
and repair; Description: Incentivize infrastructure investment in 
maintenance and repair.; Estimated completion date[A]: Sept. 2003.

Initiative: 19. Train the depot workforce in capital purchase program 
and economic analysis processes; Description: Train the depot workforce 
in capital purchase program and economic analysis.; Estimated 
completion date[A]: Apr. 2004.

Initiative: 20. Improve preventative/ predictive maintenance programs; 
Description: Improve preventative maintenance program.; Estimated 
completion date[A]: Oct. 2003.

Initiative: 21. Identify and remove impediments to facility and 
equipment maintenance system usage; Description: Remove impediments to 
broad use of facility and equipment maintenance system.; Estimated 
completion date[A]: May 2003.

Initiative: 22. Streamline maintenance & repair process and procedures; 
Description: Improve maintenance and repair facility project delivery 
process.; Estimated completion date[A]: June 2003.

Initiative: 23. Provide greater flexibility for implementing workload 
changes; Description: Provide greater flexibility for implementing 
workload changes.; Estimated completion date[A]: Oct. 2003.

Initiative: 24. Add surge requirements to infrastructure planning and 
programming; Description: Add surge requirements to infrastructure 
planning and programming.; Estimated completion date[A]: Sept. 2004.

Initiative: 25. Improve capital purchase program process; Description: 
Improve capital purchase program process.; Estimated completion 
date[A]: Apr. 2003.

Initiative: 26. Create a depot capital investment funding 
appropriation; Description: Create two depot capital investment funding 
appropriations lines--new system investments and recap of existing 
systems (legacy).; Estimated completion date[A]: Nov. 2002.

Initiative: 27. Information technology master plan; Description: 
Establish a comprehensive vision for managing information resources; 
Estimated completion date[A]: Sept. 2002.

Initiative: 28. Automated information technology initiative; 
Description: Insert devices used to automate data collection on the 
shop floor to enhance depot productivity.; Estimated completion 
date[A]: Mar. 2003.

Initiative: 29. Depot X; Description: Establish a lab environment 
across air logistics centers, which will enhance the ability to rapidly 
test solutions to meet user requirements/ enhancements across depot 
maintenance systems.; Estimated completion date[A]: Apr. 2003.

Initiative: 30. Improve stock level processes; Description: Improve 
stock levels for low demand items through policy changes.; Estimated 
completion date[A]: Sept. 2002.

Initiative: 31. Improve material support policies; Description: Clarify 
material support policies to better state objectives and establish 
standards.; Estimated completion date[A]: Jan. 2004.

Source: U. S. Air Force.

[A] This represents reported completion dates as of February 2003. The 
Innovation and Transformation Directorate plans to review each 
initiative and determine what further actions should be taken.

[End of table]

[End of section]

Appendix III: Not-Mission-Capable Supply Rate Targets by Weapon System:

Goal 2 of the Air Force Strategic Plan cites the percentage of aircraft 
that cannot perform their mission because spare parts are not 
available, referred to as not-mission-capable supply, as a performance 
measure. Table 5 provides the not-mission-capable supply rates for the 
Air Force's weapons systems.

Table 7: Not-Mission-Capable Supply Rate Targets by Weapon System:

Aircraft: A-10; Target (percent): 8.

Aircraft: B-1; Target (percent): 22.

Aircraft: B-52; Target (percent): 12.

Aircraft: C-5; Target (percent): 8.5.

Aircraft: C-130; Target (percent): 12.

Aircraft: C-141; Target (percent): 6.

Aircraft: C-17; Target (percent): 4.6.

Aircraft: E-3; Target (percent): 6.

Aircraft: F-15; Target (percent): 9.

Aircraft: F-15E; Target (percent): 9.

Aircraft: F-16; Target (percent): 8.

Aircraft: F-117; Target (percent): 7.

Aircraft: KC-135; Target (percent): 8.5.

Source: U. S Air Force:

Note: Not-mission-capable supply rate is the percentage of time a 
weapon system is down because parts are not available.

[End of table]

[End of section]

Appendix IV: Comments from the Department of Defense:

DEPUTY UNDER SECRETARY OF DEFENSE FOR LOGISTICS AND MATERIEL READINESS 
3500 DEFENSE PENTAGON WASHINGTON, DC 20301-3500:

JUN 24 2003:

Mr. William Solis, Director:

Defense Capabilities and Management U.S. General Accounting Office:

441 G Street, N.W. Washington, DC 20548:

Dear Mr. Solis:

This is the Department of Defense (DoD) response to the GAO draft GAO-
03-706, "DEFENSE INVENTORY: Air Force Plans and Initiatives to Mitigate 
Spare Parts Shortages Need Better Implementation," dated May 15, 2003 
(GAO Code 350249).. The DoD generally concurs with the intent of the 
recommendations.

Detailed comments on the draft report recommendations are included in 
the enclosure. The DoD appreciates the opportunity to comment on the 
draft report.

Sincerely,

Allen W. Beckett 
Principal Assistant:

Enclosure:

Signed for Allen W. Beckett Principal Assistant:

GAO CODE 350249/GAO-03-706:

"DEFENSE INVENTORY: AIR FORCE PLANS AND INITIATIVES TO MITIGATE SPARE 
PARTS SHORTAGES NEED BETTER IMPLEMENTATION":

DEPARTMENT OF DEFENSE COMMENTS TO THE RECOMMENDATIONS:

RECOMMENDATION 1: The GAO recommended that the Secretary of Defense 
direct the Secretary of the Air Force to incorporate the Air Force 
Strategic Plan's performance measures and targets into the subordinate 
Logistics Support Plan and the Supply Strategic Plan. (Page 16/Draft 
Report):

DoD RESPONSE: Concur with intent. Air Force Directorate of Innovation 
and Transformation (AF/ILI) is currently developing a balanced 
scorecard and supporting metrics to measure the performance of each of 
the Air Force (AF) Logistics Transformation initiatives. In addition, 
AF/ILI is reviewing both higher and lower level strategic plans to 
ensure initiatives and performance measures are in agreement throughout 
the tier of planning documents. For instance, a review of the AF 
Materiel Management Strategic Plan has been conducted and comments 
provided will be incorporated and initiatives will be updated. 
Therefore, no further direction is required and action consistent with 
this recommendation is complete.

RECOMMENDATION 2: The GAO recommended that the Secretary of Defense 
direct the Secretary of the Air Force to commit to start those 
remaining initiatives needed to address the causes of spare parts 
shortages or clearly identify how they have been incorporated into 
those initiatives already underway. (Page 16/Draft Report):

DoD RESPONSE: Concur with intent. The AF Spares Campaign has been 
refined into the Ten Focus Initiatives that are being tracked. The 
original 19 initiatives were developed through the periodic roll up of 
related problem sets under a number of themes and many of the issues 
were redundant in terms of problem or solution set. These initiatives 
were refined and either consolidated under the ten focus initiatives or 
were overtaken by other events. In either case, the Ten Focus 
Initiatives of the Spares Campaign correctly encompasses the entire 
supply chain process and adequately addresses areas requiring 
improvement. Therefore, it would be inefficient and unnecessary to 
track progress on individual actions from the original 19 initiatives 
separately. Action consistent with this recommendation is complete.

RECOMMENDATION 3: The GAO recommended that the Secretary of Defense 
direct:

the Secretary of the Air Force to adopt performance measures and 
targets for its initiatives that will show how their implementation 
will affect critical spare parts availability and readiness. (Page 16/
Draft Report):

DoD RESPONSE: Concur with intent. The establishment of the Directorate 
of Innovation and Transformation (AF/ILI) with the mandate to drive 
logistics transformation is consistent with the direction of the AF 
Strategic Plan. The key is weapon system availability and readiness, 
not parts availability. As part of the logistics transformation 
mandate, AF/ILI will measure all initiatives in terms of meeting the 
following weapon system availability (WSA) and cost stretch goals:

* 20 percent increase in aircraft availability within the next three 
years:

* Zero real Operation and Support (O&S) growth over the FY 04-09 Future 
Years Defense Plan (FYDP):

AF/ILI has also directed that all subordinate goals for each of the 
individual initiatives be tied to these overall targets. Therefore, no 
further direction is required and action consistent with this 
recommendation is complete.

RECOMMENDATION 4: The GAO recommended that the Secretary of Defense 
direct the Secretary of the Air Force to direct the new Innovation and 
Transformation Directorate to establish plans and priorities for 
improving management of logistics initiatives consistent with the Air 
Force Strategic plan. (Page 16/Draft Report):

DoD RESPONSE: Concur with intent. AF/ILI is committed to ensure that 
Air Force logistics initiatives plans and priorities are established 
and harmonized with the Air Force Strategic Plan. Campaign plans are 
currently in draft, which spell out and track milestones associated 
with each initiative to execution. Therefore no further direction is 
required and action consistent with this recommendation is complete.

RECOMMENDATION 5: The GAO recommended that the Secretary of Defense 
direct the Secretary of the Air Force to request spare parts funds in 
its budget consistent with results of its spare parts requirements 
determination process. (Page 16/Draft Report):

DoD RESPONSE: Concur with intent. The Air Force is committed to 
identifying the total spares requirement for funding and advocating 
full funding for the requirement. In the instance cited in the draft 
GAO report, the spares budget was projected consistent with the new 
requirements determination process; however, funding is constrained. No 
further direction is required and action consistent with this 
recommendation is complete.

[End of section]

Appendix V: GAO Contacts and Staff Acknowledgments:

GAO Contact:

Richard G. Payne, (757) 552-8119 Connie W. Sawyer, Jr., (757) 552-8140:

Acknowledgements:

In addition to the names above, Gina O. Ruidera, Alfonso Q. Garcia, 
Susan K. Woodward, and Barry L. Shillito also made significant 
contributions to this report.

FOOTNOTES

[1] These figures are based on the Air Force's fiscal year 2002 through 
2004 OP-31 Budget exhibits about which GAO recently reported concerns. 
U.S. General Accounting Office, Defense Inventory: Better Reporting on 
Spare Parts Spending Will Enhance Congressional Oversight, GAO-03-18 
(Washington, D.C.: October 2002).

[2] Office of Secretary of Defense, Inventory Management Study 
(Washington, D.C.: August 2002)

[3] U.S. General Accounting Office, Major Management Challenges and 
Program Risks: Department of Defense, GAO-03-98 (Washington, D.C.: 
January 2003) and U.S. General Accounting Office, Air Force Inventory: 
Parts Shortages Are Impacting Operations and Maintenance 
Effectiveness, GAO-01-587 (Washington, D.C.: June 27, 2001).

[4] U.S. General Accounting Office, Defense Inventory: The Department 
Needs a Focused Effort to Overcome Critical Spare Parts Shortages, GAO-
03-707 (Washington, D.C.: June 27, 2003); U.S. General Accounting 
Office, Defense Inventory: The Army Needs a Plan to Overcome Critical 
Spare Parts Shortages, GAO-03-705 (Washington, D.C.: June 27, 2003); 
U.S. General Accounting Office, Defense Inventory: Navy Logistics 
Strategy and Initiatives Need to Address Spare Parts Shortages, GAO-03-
708 (Washington, D.C.: June 27, 2003); U.S. General Accounting Office, 
Defense Inventory: Several Actions Are Needed to Further DLA's Efforts 
to Mitigate Shortages of Critical Parts, GAO-03-709 (forthcoming); and 
U.S. General Accounting Office, Defense Inventory: Air Force 
Item Manager Views of Repair Parts Issues Consistent With Issues 
Reported in the Past, GAO-03-684R (Washington, D.C.: May 21, 2003).

[5] In the Air Force, critical spare parts are those that would prevent 
a weapon system from accomplishing its assigned mission. For example, 
the Air Force routinely reports the top items that prevent an aircraft 
from being mission capable, such as hydraulic manifolds for the C-5.

[6] Pub. L. 103-62, Aug. 3, 1993.

[7] Output means the tabulation, calculation, or recording of activity 
or effort and can be expressed in a quantitative or qualitative manner.

[8] The Air Force defines aircraft supply availability as 1 minus the 
total not-mission capable supply rate. For example, a not-mission 
capable supply rate of 9.6 percent would equate to 90.4 percent 
aircraft supply availability.

[9] Mission capable rates indicate the percentage of aircraft that can 
perform at least one of its assigned missions. Not-mission-capable 
supply and not-mission-capable maintenance are indicators that aircraft 
cannot perform any of their assigned missions because of supply 
shortages and maintenance requirements, respectively. Cannibalizations 
represent the removal of a good part from one aircraft in order to 
install it on another aircraft.

[10] Originally called Depot Maintenance Review Team.

[11] An end-state is the desired outcome of the task.

[12] Pipeline represents the process flow from the source of 
procurement of a part to its point of use. Safety stocks represent the 
quantity of parts, in addition to amounts needed for day to day 
operations, required to be available to permit continuous operations 
should normal replacement systems become interrupted.

[13] The 2004 budget request included supply availability data 
consistent with modifications in the budget exhibit, see Office of 
Secretary of Defense, Inventory Management Study (Washington, D.C.: 
August 2002). 

[14] We did not independently verify the quality or validity of the Air 
Force's model to predict supply availability.

[15] The balanced scorecard links goals, strategies, objectives and 
measures to an organization's plan.

[16] We did not independently verify the quality or validity of the Air 
Force's model to predict supply availability.

GAO's Mission:

The General Accounting Office, the investigative arm of Congress, 
exists to support Congress in meeting its constitutional 
responsibilities and to help improve the performance and accountability 
of the federal government for the American people. GAO examines the use 
of public funds; evaluates federal programs and policies; and provides 
analyses, recommendations, and other assistance to help Congress make 
informed oversight, policy, and funding decisions. GAO's commitment to 
good government is reflected in its core values of accountability, 
integrity, and reliability.

Obtaining Copies of GAO Reports and Testimony:

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through the Internet. GAO's Web site ( www.gao.gov ) contains 
abstracts and full-text files of current reports and testimony and an 
expanding archive of older products. The Web site features a search 
engine to help you locate documents using key words and phrases. You 
can print these documents in their entirety, including charts and other 
graphics.

Each day, GAO issues a list of newly released reports, testimony, and 
correspondence. GAO posts this list, known as "Today's Reports," on its 
Web site daily. The list contains links to the full-text document 
files. To have GAO e-mail this list to you every afternoon, go to 
www.gao.gov and select "Subscribe to e-mail alerts" under the "Order 
GAO Products" heading.

Order by Mail or Phone:

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to:

U.S. General Accounting Office

441 G Street NW,

Room LM Washington,

D.C. 20548:

To order by Phone: 	

	Voice: (202) 512-6000:

	TDD: (202) 512-2537:

	Fax: (202) 512-6061:

To Report Fraud, Waste, and Abuse in Federal Programs:

Contact:

Web site: www.gao.gov/fraudnet/fraudnet.htm E-mail: fraudnet@gao.gov

Automated answering system: (800) 424-5454 or (202) 512-7470:

Public Affairs:

Jeff Nelligan, managing director, NelliganJ@gao.gov (202) 512-4800 U.S.

General Accounting Office, 441 G Street NW, Room 7149 Washington, D.C.

20548: