This is the accessible text file for GAO report number GAO-03-1014T 
entitled 'Capitol Visitor Center: Current Status of Schedule and 
Estimated Cost' which was released on July 15, 2003.

This text file was formatted by the U.S. General Accounting Office 
(GAO) to be accessible to users with visual impairments, as part of a 
longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov.

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately.

United States General Accounting Office:

GAO:

Testimony:

Before the Subcommittee on Legislative, Committee on Appropriations, 
House of Representatives:

For Release on Delivery:

Expected at 1:30 p.m. EDT Tuesday, July 15, 2003:

CAPITOL VISITOR CENTER:

Current Status of Schedule and Estimated Cost:

Statement of David M. Walker, Comptroller General of the United States:

GAO-03-1014T:

GAO Highlights:

Highlights of GAO-03-1014T, a testimony before the Subcommittee on 
Legislative, Committee on Appropriations, House of Representatives. 

Why GAO Did This Study:

GAO has been providing ongoing assistance to the Capitol Preservation 
Commission and the Senate and House Appropriations Committees in their 
monitoring and oversight of the Capitol Visitor Center construction 
project. Given the current decisions facing the Congress, this 
testimony covers (1) management of the project, (2) the estimated cost 
for the project, (3) the status of the project’s schedule, and (4) 
actions that Congress and the AOC should consider taking to address 
funding gaps and other current project issues and risks. 

What GAO Found:

Recognizing the need for a new facility to provide greater security 
for all persons working in or visiting the United States Capitol and 
to enhance the educational experience of visitors who have come to 
learn about Congress and the Capitol building, Congress authorized the 
Architect of the Capitol (AOC) to build a new Capitol Visitor Center. 
The three-story, underground facility, located on the East side of the 
Capitol, is designed to be a seamless addition to the Capitol complex 
when completed without detracting from the appearance of the Capitol 
or its historic landscaping. 

Earlier this spring, GAO and the AOC determined that the estimated 
budget amount of $303.5 million for the Capitol Visitor Center (CVC) 
“base project” was no longer current. Based on GAO’s recommendation, 
the AOC hired a contractor to help analyze and update the cost 
estimate for completion of the base project. GAO’s review of the 
contractor’s “base cost” estimate analysis identified $7 million in 
adjustments, therefore increasing the contractor’s $344.3 million 
estimate to $351.3 million. GAO also conducted a supplemental analysis 
to identify potential future costs due to additional risks and 
uncertainties not included in the updated estimates. The result of 
this supplemental analysis disclosed that these risks and 
uncertainties could raise the estimated cost to between $380 million 
and $395 million. These potential additional costs do not need to be 
added to the base project budget now; however, a number of actions 
need to be taken to mitigate known risks. 

The AOC’s May 2003 status report indicates the project is on schedule 
for substantial completion of the plaza deck in January 2005, 
substantial completion of the CVC in September 2005, and final 
completion and opening to the public in December 2005. However, the 
project is currently experiencing delays and until the AOC compiles a 
fully integrated schedule, there will not be adequate information to 
determine whether the estimated completion dates are likely to be met.

What GAO Recommends:

We propose that the Architect of the Capitol and Congress consider 
taking actions to  

* address the gap between the $303.5 million current funding for the 
“base project” and the updated estimates; 

* consider how best to address costs associated with risks and 
uncertainties not included in updated “base cost” estimates;

* continue to resolve scope, requirements, estimated costs, and 
funding sources for unresolved items;

* implement controls for the approval of changes and use of 
contingency funds;

* continue to resolve contingency tracking and reporting issues; and

* expeditiously develop a comprehensive, integrated master project 
schedule.

www.gao.gov/cgi-bin/getrpt?GAO-03-1014T.

To view the full product, including the scope and methodology, click 
on the link above. For more information, contact Jeanette Franzel 
(202) 512-9471 or franzelj@gao.gov or Bernard L. Ungar at (202) 
512-4232.

[End of section]

Mr. Chairman and Members of the Subcommittee:

Recognizing the need for a new facility to provide greater security for 
all persons working in or visiting the United States Capitol and to 
enhance the educational experience of visitors who have come to learn 
about Congress and the Capitol building, Congress authorized the 
Architect of the Capitol (AOC) to build a new visitor center for the 
Capitol. The three-story, underground facility, located on the East 
side of the Capitol, is designed to be a seamless addition to the 
Capitol complex when completed without detracting from the appearance 
of the Capitol or its historic landscaping. It is the largest project 
on the Capitol grounds in over 140 years. According to current plans, 
when complete it will include theaters, an auditorium, exhibit space, a 
service tunnel for truck loading and deliveries, storage, and space for 
use by the House and Senate.

In response to requests from members of the Capitol Preservation 
Commission (CPC) and the conference report to the Omnibus Consolidated 
and Emergency Appropriations Act, 1999 (House Conference Report 105-
825), GAO has been providing ongoing assistance to the CPC and the 
Senate and House appropriations committees in their monitoring and 
oversight of the Capitol Visitor Center (CVC) project. While we have 
provided a wide range of assistance as the project has evolved, today, 
given the current decisions facing the Congress, I will focus on (1) 
management of the project, (2) the estimated cost for the project, (3) 
the status of the project's schedule, and (4) actions that Congress and 
the AOC should consider taking to address funding gaps and other 
current project issues and risks.

Management of the Project:

Shortly after we began to monitor progress on the CVC project, we made 
a number of suggestions to the AOC aimed at ensuring effective 
management of the project based on our previous work reviewing 
construction projects in all three branches of government. AOC 
generally agreed with our suggestions and took the following actions.

The AOC hired a construction management firm, Gilbane, for day-to-day 
detailed management of the project. Gilbane has provided project 
management, including supervision of contractors' work, schedule and 
cost monitoring, procurement of general conditions construction work, 
and monitoring and protection of the Capitol building from potential 
impact of construction. Recently, Gilbane has been working to implement 
a cost tracking system that conforms to the AOC's approved budget line 
items for the CVC.

Recognizing the impact that construction of the CVC would have on day-
to-day congressional operations, AOC established a communication/
outreach effort specifically dedicated to meeting the ongoing need of 
providing Congress with information regarding the project's impact on 
congressional operations, as well as progress toward completion of the 
CVC.

To supplement its in-house capability, AOC also entered into an 
agreement with the General Services Administration (GSA) to provide 
services related to management of the Sequence 1 and 2 procurements. 
Under the agreement, GSA managed the procurement process, while the AOC 
(the source selection authority) awarded and now administers the 
contracts.

While these positive steps have been taken, there are a number of other 
actions needed to strengthen project management that are outlined in 
the following sections, including developing risk mitigation strategies 
and improving tracking and reporting.

Estimated Cost for the Project:

Earlier this spring, we and the AOC determined that the estimated 
budget amount of $303.5 million for the CVC "base project"[Footnote 1] 
was no longer current. The estimate was limited due to uncertainties 
related to the preliminary nature of the design work, unknown scope of 
pre-construction requirements, and security adjustments to the design 
after the events of September 11, 2001. In addition, it was already 
evident that the expected cost of a number of line items in the 
estimate, such as utility relocation, tree preservation, temporary 
visitor screening facilities, and historic preservation, would be 
exceeded.

Based on GAO's recommendation, the AOC and Gilbane updated the project 
cost estimates as of March 20, 2003. The AOC then contracted with 
Tishman Construction Corporation (Tishman) to review the March 20, 2003 
estimate and perform a cost analysis based on information currently 
available. We reviewed the methodology, assumptions, and support for 
the analysis, dated May 16, 2003, including contingencies, scope items 
not included in the estimates, and risks and uncertainties.[Footnote 2] 
We also conducted a supplemental analysis to identify potential future 
costs due to additional risks and uncertainties not included in the 
updated estimates.

While we identified limitations to Tishman's analysis, our review found 
that Tishman's analysis was generally reasonable given the scope and 
assumptions provided by the AOC to Tishman. However, based on 
information available to us as of June 16, 2003, we identified cost 
adjustments to Tishman's analysis of the base project, totaling $7 
million, that we believe need to be made. These adjustments would 
increase Tishman's estimated cost at completion for the base project 
from $344.3 million to $351.3 million.

Due to the nature of the uncertainties still surrounding the project's 
estimated cost to complete and the limitations of information available 
at this time, there will likely be events occurring in the future that 
could further materially affect the project's cost at completion. For 
example, additional risks and uncertainties, which cannot be predicted 
with certainty at this time, were not priced as part of Tishman's 
analysis or as part of our adjusted figure. The result of this 
supplemental analysis disclosed that these additional risks and 
uncertainties could potentially raise the estimated cost at completion 
of the base project to between $380 million and $395 million. (See the 
list of additional risks and uncertainties below.) These potential 
additional costs of between $30 million and $45 million do not need to 
be added to the base project budget at this time; however, a number of 
actions need to be taken to mitigate known risks.

Additional Risks and Uncertainties That Could Affect Project Cost or 
Utilization:

Unforeseen conditions, including potential underground complications:

Potential for scope creep due to lack of a finalized and approved 
design program in some areas:

Cost overruns on "design-to-budget" scope, e.g., exhibitions and 
technical security:

Cost and schedule impacts due to contractor coordination issues:

Project delays and subsequent contractor claims:

Delays due to unique situations--e.g., government functions, terrorist 
alerts, state funerals:

Unanticipated client requests:

Inaugural support:

Unknown operator requirements (gift shop, kitchen, theater, 
exhibitions):

Capitol Building settlement or other damage:

Impact of cost allocations to the House and Senate expansion space on 
the CVC base budget:

In order to arrive at the potential estimated cost of $380 million to 
$395 million, which includes the additional risks and uncertainties, we 
used the CVC project team's lowest, most likely, and highest cost 
estimates for 37 project elements (e.g., structure/site, East Front 
structure, Library of Congress tunnel) and a simulation analysis to 
calculate different combinations of the project team's estimates that 
factored in risks and uncertainties. Some of the larger risks and 
uncertainties include unforeseen conditions (including potential 
underground obstructions); building settlement; contractor 
coordination issues, especially as they relate to any delays 
experienced; and the lack of an approved design program in some areas.

While it is not possible to eliminate all risks and uncertainties, 
certain steps can and should be taken to lessen their potential impact 
on the final cost of the project. Research by the Construction Industry 
Institute (CII) shows project scope is the major determinant of the 
cost of a project.[Footnote 3] Tishman noted that the reasonableness of 
AOC's and Gilbane's March 20, 2003, estimate could not be determined 
for several items because detailed requirements for those items have 
not been fully determined or approved by the CPC. CII research also 
shows that the lack of scope definition is the root cause of cost 
overruns, late completion dates, excessive rework, unnecessary disputes 
among project participants, and other problems associated with 
construction projects.[Footnote 4] While we did not identify any scope 
or quality changes to date that have not been brought to the CPC's 
attention, we are concerned that allowances for the "design to budget" 
items (for example, the exhibition space and technical security) may 
not be sufficient to cover the expected scope and quality. We believe 
there is a continual need for the AOC to align customer expectations 
with the project's scope, quality, and cost considerations. The Tishman 
analysis noted that the percentage of pending changes to date compared 
to the Sequence 1 contract cost is already above industry norms and 
that there is the potential for scope creep. As a result, it will be 
important for the AOC to implement controls for the advance and formal 
approval of any scope changes.

It is general practice when performing budget estimates for 
construction projects to carry a contingency allowance to cover such 
issues as unforeseen field conditions and design and price changes. The 
Tishman analysis evaluated the adequacy of the estimated contingency 
amounts and increased the amounts in several areas. Based on the 
information we gathered, we also increased the estimates for 
contingencies in certain areas. As the project moves forward, it is 
important that the AOC implement controls for using these contingency 
funds. Furthermore, we understand that the method to be used for 
tracking and reporting on contingency balances remains unresolved.

There are also items not in the base project that need to be resolved. 
For example, the requirements, estimated costs, and funding sources for 
wayfinding signage,[Footnote 5] additional furniture, fixtures, and 
equipment, and artwork have not been fully determined. In addition, the 
method for operating and maintaining the CVC has not yet been 
determined. Consequently, neither the updated estimates nor our 
supplemental analysis include provisions for these items.

Although not considered part of the base project, the $70 million 
already appropriated for the House and Senate expansion space may not 
be sufficient to make the space fully functional. Our review noted that 
substantial funds have already been allocated from the House and Senate 
expansion space budgets. Also, substantial risk exists because the 
design for the House and Senate expansion space is not complete, and it 
is assumed that the expansion space will be "designed to budget." 
However, to the extent that the future design and requirements exceed 
the remaining budget amounts, additional funds may be needed.

Status of the Project's Schedule:

To expedite the project schedule and maintain the option for use of 
some portion of the CVC for the inaugural events of January 20, 2005, 
the AOC divided the project into the following stages, rather than bid 
the total project after completion of all design work:

Pre-construction (largely complete):

Pre-construction work includes utility relocations, historic 
preservation efforts, tree care, and temporary visitor facilities. 
These efforts were conducted in advance of building construction to 
expedite the start of the construction contractor work. The work is 
basically completed, with the exception of ongoing tree preservation.

Construction (in process):

The construction contract for structural/foundation work, referred to 
as Sequence 1, was awarded to Centex Construction in June 2002 and, 
assuming no delays, is scheduled to be substantially complete in Spring 
2004. As discussed below, the Sequence 1 contractor has experienced 
delays and the AOC is working with the contractor to determine the 
impact of these delays to the project.

The construction contract for the project interface with the East Front 
of the Capitol, known as Sequence 1C, was awarded on July 11, 2003. 
Assuming no delays, this work is scheduled to be complete in Summer 
2004.

The construction contract for mechanical, electrical, plumbing and 
interior finishes work, referred to as Sequence 2, was awarded on April 
18, 2003 to Manhattan Construction. Assuming no delays, completion of 
the construction work is scheduled for December 2005. However, as 
discussed below, current delays in Sequence 1 could impact the Sequence 
2 schedule.

Senate and House Expansion Space (in design phase):

The design of these spaces is scheduled to be completed late in 2003. 
The construction of these spaces is scheduled to begin in the summer of 
2004, with completion in 2006.

Exhibits (in design phase):

The final phase of the project will involve the fabrication and 
installation of the exhibits. Because installation involves climate 
requirements only available in completed space, this contract is 
scheduled to be awarded and begin in late 2003, with projected 
completion in December 2005.

The AOC's May 2003 status report indicates the project is on schedule 
for substantial completion of the plaza deck in January 2005, 
substantial completion of the CVC in September 2005, and final 
completion and opening to the public in December 2005. The project, 
however, is currently experiencing delays and the AOC is working with 
Gilbane to develop a fully integrated schedule. Until the AOC develops 
a fully integrated schedule, it will be difficult to determine whether 
the estimated completion dates are likely to be met. A fully integrated 
schedule would combine schedules for all of the interrelated CVC 
projects, activities, and long-lead-time procurements (e.g. Sequence 1, 
Sequence 2, East Front interface, west refrigeration plant expansion, 
2005 inauguration) into one coordinated schedule. (The Sequence 2 full 
schedule is currently not available but is due from Manhattan in 
August.) According to Gilbane's June 5, 2003, report, the Sequence 1 
contractor's May update shows a 134-workday[Footnote 6] delay to the 
completion of Sequence 1. The AOC and contractor are negotiating the 
potential impact of any delays on the project schedule and budget. The 
AOC has indicated that current Sequence 1 delays have possibly led to a 
40 workday overlap between the Sequence 1 and Sequence 2 schedules. 
Although Gilbane and the AOC are working with Centex and Manhattan to 
mitigate the impact of the 40 workday overlap to the schedule, it is 
currently unclear what the total effect of the current Sequence 1 
delays will be to the final project completion date or costs. Because 
the project is still in the early stages of construction, there is risk 
of additional delays. We included an additional $2 million in 
contingency in our adjustments to the Tishman estimated cost-to-
complete for possible delay and acceleration costs.

Matters for AOC and Congressional Consideration:

Although the AOC has already initiated some actions to address some 
issues, we identified the following specific matters for the AOC's and 
your consideration:

Expeditiously address the current funding gap between the $303.5 
million provided for the base project and the updated estimates.

Consider how best to address the potential costs associated with the 
risks and uncertainties not specifically included in the updated 
estimates for the base project.

Ask the AOC to develop a plan to mitigate risk factors, to the extent 
practicable, and implement recommendations made by Tishman in the May 
16, 2003, report including, but not limited to:

revalidate the program of requirements for each cost element,

identify, contract for, and begin coordination of all operator 
requirements with existing design and construction efforts,

identify and involve the exhibit and audio visual equipment operators 
as soon as possible, and:

institute a proactive schedule management and tracking system related 
to potential contractor delay claims.

Determine whether to establish and fund a reserve account for any 
additional amounts above the current estimates to cover future costs 
due to risks and uncertainties that cannot be priced or estimated at 
the current time and establish procedures for timely release of the 
funds to the CVC project.

Continue to resolve the scope, requirements, estimated costs, and 
funding sources for unresolved items in the base project, such as 
fitout of the CVC administration, guide service, first aid and gift 
shop spaces.

Continue to resolve the scope, requirements, estimated costs, and 
funding sources for the items not in the base project, including the 
House and Senate expansion space.

Implement controls for the approval of changes and AOC's use of 
contingency funds.

Continue to resolve contingency tracking and reporting issues to 
achieve a single and standardized budget and reporting format.

Expeditiously develop a comprehensive, integrated master project 
schedule.

We will continue our monitoring efforts throughout construction. I will 
be happy to answer any questions at this time.

For further information regarding this testimony, please contact 
Jeanette M. Franzel at (202) 512-9471 or Bernard L. Ungar at (202) 512-
4232.

(194320):

FOOTNOTES

[1] The base project includes a finished visitor center shell and core, 
an extended loading dock service tunnel, exterior finishes, 
improvements to the East Plaza, construction of unfinished House and 
Senate expansion space, exhibits, technical security systems, and a 
connecting tunnel to the Library of Congress. The base project does not 
include other items funded by other sources, such as finishing the 
House and Senate expansion space and certain security-related 
enhancements. 

[2] Although we performed procedures to review the methodology, 
assumptions, and support behind the latest cost analysis for the CVC 
project, we did not conduct an audit. 

[3] Construction Industry Institute, Project Change Management, Special 
Publication 43-1 (Austin, Tex.: November 1994).

[4] Construction Industry Institute, Improving Early Estimates, 
Implementation Resource 131-2 (Austin, Tex.: September 1998).

[5] Code-required signage is included in the estimated cost of the base 
project.

[6] The current contractor schedule indicates a 5 day workweek. 
Therefore, 134 workdays is equivalent to 187 calendar days, or 
approximately 6 months.