Global Nuclear Energy Partnership: DOE Should Reassess Its Approach to Designing and Building Spent Nuclear Fuel Recycling Facilities

GAO-08-483 April 22, 2008
Highlights Page (PDF)   Full Report (PDF, 55 pages)   Accessible Text   Recommendations (HTML)

Summary

The Department of Energy (DOE) proposes under the Global Nuclear Energy Partnership (GNEP) to build facilities to begin recycling the nation's commercial spent nuclear fuel. GNEP's objectives include reducing radioactive waste disposed of in a geologic repository and mitigating the nuclear proliferation risks of existing recycling technologies. DOE originally planned a small engineering-scale demonstration of advanced recycling technologies being developed by DOE national laboratories. While DOE has not ruled out this approach, the current GNEP strategic plan favors working with industry to demonstrate the latest commercially available technology in full-scale facilities and to do so in a way that will attract industry investment. DOE has funded four industry groups to prepare proposals for full-scale facilities. DOE officials expect the Secretary of Energy to decide on an approach to GNEP by the end of 2008. GAO evaluated the extent to which DOE would address GNEP's objectives under (1) its original engineering-scale approach and (2) the accelerated approach to building full-scale facilities. GAO analyzed DOE plans and industry proposals and interviewed DOE and industry officials concerning the pros and cons of both approaches.

DOE's original approach of building engineering-scale facilities would meet GNEP's objectives if the advanced technologies on which it focused can be successfully developed and commercialized. The advanced technologies would reduce waste to a greater degree than existing technologies by recycling radioactive material that a geologic repository has limited capacity to accommodate. The advanced technologies would also mitigate proliferation risks relative to existing technologies by increasing the difficulty of theft or diversion of weapons-usable nuclear material from recycling facilities. Nonetheless, DOE's engineering-scale approach had two shortcomings. First, it lacked industry participation, potentially reducing the prospects for eventual commercialization of the technologies. In particular, the approach included some technologies that may introduce unnecessary costs and technical challenges while creating waste management challenges; industry representatives have questioned whether such technologies could be commercialized. Second, DOE's schedule called for building one of the recycling facilities (a reprocessing plant for separating reusable materials from spent nuclear fuel and fabricating recycled fuel) before conducting R&D on recycled fuel that would help determine the plant's design requirements. This schedule unnecessarily increased the risk that the spent fuel would be separated in a form that cannot be recycled. The other two facilities DOE had planned to build (an advanced reactor for using recycled fuel and an R&D facility) would allow DOE to conduct R&D that existing DOE facilities have limited capability to support. DOE's accelerated approach of building full-scale facilities would likely require using unproven evolutions of existing technologies that would reduce radioactive waste and mitigate proliferation risks to a much lesser degree than anticipated from more advanced technologies. Two of the four industry groups that have received funding under GNEP proposed evolutionary technologies for recycling spent fuel in existing reactors even though the GNEP strategic plan ruled out such technologies. While the evolutionary technologies could allow DOE to begin recycling a large amount of spent fuel sooner than under its original approach, fully meeting GNEP's waste reduction and nonproliferation objectives would require a later transition to more advanced technologies. Two other industry groups proposed technologies that would address GNEP's waste reduction and nonproliferation objectives by using technologies that are not mature enough to allow DOE to accelerate construction of full-scale recycling facilities. Under any of the proposals, DOE is unlikely to attract enough industry investment to avoid the need for a large amount of government funding for full-scale facilities. For example, the industry groups have proposed that DOE fund an advanced reactor, which DOE and industry officials expect would at least initially be more expensive than existing reactors to build and operate and thus not be commercially competitive. DOE acknowledges the limitations of its accelerated approach but cites other benefits, such as the potential to exert more immediate international influence on nonproliferation issues.



Recommendations

Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Implemented" or "Not implemented" based on our follow up work.

Director:
Team:
Phone:
Eugene E. Aloise
Government Accountability Office: Natural Resources and Environment
(202) 512-6870


Recommendations for Executive Action


Recommendation: The Secretary of Energy should direct the Office of Nuclear Energy to reassess its preference for an accelerated approach to implementing GNEP through construction of commercial-scale facilities using spent nuclear fuel recycling technologies that industry can offer in DOE's time frame. The reassessment should consider the time and government resources required to support both the initial spent nuclear fuel recycling facilities and research and development (R&D) on more advanced recycling technologies that fully meet GNEP's objectives.

Agency Affected: Department of Energy

Status: In process

Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.

Recommendation: If DOE decides to pursue design and construction of engineering-scale facilities for demonstrating advanced technologies, the Secretary of Energy should revise the schedule for an engineering-scale reprocessing plant so that the plant is built after an R&D facility and advanced reactor have conducted sufficient testing and development of recycled fuel to ensure that the output of the reprocessing plant can be fabricated into recycled fuel and used in an advanced reactor. The revised schedule should also allow for the R&D facility to test and demonstrate advanced reprocessing and safeguards technologies that would be used in the reprocessing plant.

Agency Affected: Department of Energy

Status: In process

Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.

Recommendation: If DOE decides to pursue design and construction of engineering-scale facilities for demonstrating advanced technologies, the Secretary of Energy should direct the Office of Nuclear Energy to work with industry to the extent possible on advanced spent nuclear fuel recycling technologies in order to obtain industry's expertise and input on future commercialization of such technologies.

Agency Affected: Department of Energy

Status: In process

Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.