PGI 236.2—SPECIAL ASPECTS OF CONTRACTING FOR CONSTRUCTION

PGI 236.201  Evaluation of contractor performance.
(See DFARS 236.201 - Pop-up window, PGI Viewer mode)

      (c)(i)  Send each contractor performance evaluation report to the central data base immediately upon its completion.

                    (A)  The central data base—

                            (1)  Is operated by—

U.S. Army Corps of Engineers, Portland District

ATTN:  CENWP-CT-I

PO Box 2946

Portland, OR  97208-2946

Telephone:  (503) 808-4590.

                            (2)  Keeps reports on file for 6 years.

                    (B)  For computer access to the files, contact the Portland District for user log-on and procedures.

              (ii)  Use performance records when making responsibility determinations under FAR Subpart 9.1.

                    (A)  For each contract expected to exceed $1,000,000, retrieve all performance records on file in the central data base for all prospective contractors that have a reasonable chance of being selected for award.  The central data base will provide—

                            (1)  Overall current performance ratings;

                            (2)  Descriptions of contracts on which ratings are based (e.g., type of facility, contract value, applicable performance elements); and

                            (3)  A telephone number to obtain transcripts and documentation of pertinent evaluation details.

                    (B)  Consider using the performance records in the data base for lower value contracts and to assess a contractor's performance record for reasons other than an award decision, such as subcontractor approval and awards for excellence.

PGI 236.203  Government estimate of construction costs.
(See DFARS 236.203 - Pop-up window, PGI Viewer mode)

      (1)  Designate the Government estimate as “For Official Use Only,” unless the information is classified.  If it is, handle the estimate in accordance with security regulations.

      (2)  For sealed bid acquisitions—

              (i)  File a sealed copy of the Government estimate with the bids.  (In the case of two-step acquisitions, this is done in the second step.)

              (ii)  After the bids are read and recorded, remove the “For Official Use Only” designation and read and record the estimate as if it were a bid, in the same detail as the bids.

PGI 236.213  Special procedures for sealed bidding in construction contracting.
(See DFARS 236.213 - Pop-up window, PGI Viewer mode)

For additive or deductive items—

      (1)  Use a bid schedule with—

              (i)  A first or base bid item covering the work generally as specified; and

              (ii)  A list of priorities that contains one or more additive or deductive bid items that progressively add or omit specified features of the work in a stated order of priority.  (Normally, do not mix additive and deductive bid items in the same solicitation.)

      (2)  Before opening the bids, record in the contract file the amount of funds available for the project.

      (3)  Determine the low bidder and the items to be awarded in accordance with the procedures in the clause at 252.236-7007, Additive or Deductive Items.  

PGI 236.273  Construction in foreign countries.
(See DFARS 236.273 -
Pop-up window, PGI Viewer mode)

      (b)  When a technical working agreement with a foreign government is required for a construction contract—

              (i)  Consider inviting the Army Office of the Chief of Engineers, or the Naval Facilities Engineering Command, to participate in the negotiations.

              (ii)  The agreement should, as feasible and where not otherwise provided for in other agreements, cover all elements necessary for the construction that are required by laws, regulations, and customs of the United States and the foreign government, including—

                    (A)  Acquisition of all necessary rights;

                    (B)  Expeditious, duty-free importation of labor, material, and equipment;

                    (C)  Payment of taxes applicable to contractors, personnel, materials, and equipment;

                    (D)  Applicability of workers' compensation and other labor laws to citizens of the United States, the host country, and other countries;

                    (E)  Provision of utility services;

                    (F)  Disposition of surplus materials and equipment;

                    (G)  Handling of claims and litigation; and

                    (H)  Resolution of any other foreseeable problems that can be appropriately included in the agreement.