Previous Page Next Page Prior Version PDF Version Table of Content PGI 211.5

SUBPART 211.5---LIQUIDATED DAMAGES

(Revised December 19, 2006)

 

 



 211.503 Contract clauses.


211.503  Contract clauses.

 

      (b)  Use the clause at FAR 52.211-12, Liquidated Damages--Construction, in all construction contracts exceeding $550,000, except cost-plus-fixed-fee contracts or contracts where the contractor cannot control the pace of the work.  Use of the clause in contracts of $550,000 or less is optional.

 

 

 


Previous Page Next Page Prior Version PDF Version Table of Content PGI 211.5