Hurricane Protection System Contract Information

Before doing business with the U.S. Army Corps of Engineers a business must register with the Central Contractor’s Register. http://www.ccr.gov/

The Federal Business Opportunities website FedBizOpps.gov is the single government point-of-entry for Federal government procurement opportunities over $25,000. Government buyers are able to publicize their business opportunities by posting information directly to FedBizOpps via the Internet. Through one portal - FedBizOpps (FBO) - commercial vendors seeking Federal markets for their products and services can search, monitor and retrieve opportunities solicited by the entire Federal contracting community.


Link to contracting opportunities:


Orleans Parish
Project Code Contract Contracting
Package
Contracting Estimates
(in millions)
Contract Awards
(Quarters based on calendar year)
LPV-101.02 Lakefront Levee OEB - 17th St. Canal to Topaz Unrestricted - Best Value 20-50 Q 4 2009
LPV-102.01 Lakefront Levee OEB - Topaz to Orleans Canal HUBZONE - MATOC 1.10 10 03 07
LPV-102.02 Lakefront Levee OEB - Topaz to Orleans Canal HUBZONE - MATOC 0-5 Q 2 2009
LPV-103.01 Lakefront Levee OEB - Orleans Canal to London Ave HUBZONE - MATOC 5.20 1 -03 07
LPV-103.01a Lakefront Levee OEB - Orleans Canal to London Ave - Phase 1A Unrestricted - Best Value 5-20 Q 2 2009
LPV-103.01a2 Lakefront Levee OEB - London Ave - to IHNC Unrestricted - Best Value 5-20 Q 1 2009
LPV-104.01 Lakefront Levee OEB - London Avenue Canal to IHNC HUBZONE - MATOC 1.29 07 13 07
LPV-104.01a Lakefront Levee OEB - London Avenue Canal to IHNC -Phase 1A HUBZONE - MATOC 5-20M Q 1 2009
LPV-104.02 Lakefront Levee OEB - London Ave Canal to IHNC Unrestricted - Best Value 20-50 Q 2 2009

LPV-105.01

 

Lakefront Airport Floodwalls Unrestricted - Best Value 50-100 Q 1 2010
LPV-105.02 T-wall existing alignment- Lakefront Airport - East Unrestricted -Best Value 20-50 Q 1 2010
LPV-106 Citrus Lakefront Levee (west of Paris Road) Unrestricted 100M+ Q 4 2009
LPV-107 Replace Gate at Lincoln Beach Floodwall HUBZONE 5-20 Q 4 2009
LPV-108 Raise Levee - Paris Rd to South Point Unrestricted 100+ Q 4 2008
LPV-109.01 New Orleans East Levee - Intermedate Levee Raise - South Point to GIWW Unrestricted - Best Value 100+ Q 4 2008
LPV-109.02a New Orleans East Levee - South Point - CSX RR (100YR) Unrestricted - Best Value 20-50 Q 4 2009
LPV-109.02b I-10 Floodwall & Crossing Unrestricted - Best Value 50-100 Q 3 2010
LPV-109.02c US 11 & US 90 Gates & Crossings Unrestricted - Best Value 20-50 Q 2 2009
LPV-110 New Orleans East Levee - Modify CSX Railroad Gate SDV 0-5 Q 4 2009
LPV-111.01 New Orleans East Back Levee - CSX RR to Michoud Canal Unrestricted - Best Value 100+ Q 4 2009
LPV-111.02 Raise wall at Pump Station #15 Unrestricted - Best Value 5-20 Q 1 2010
LPV - 113 Citrus Back Levee (Michoud Canal to Michoud Slip) to Auth. Elevation HZ -MATOC 5-20 Q 4 2008
LPV-115 Citrus Back Levee - Michoud Slip to IHNC Hired Labor $1.10 12-21-06
LPV-116 Eastbank IHNC- GIWW/MRGO to Almonaster Hired Labor $1.50 12-30-06
LPV-201 IHNC GIWW to Almonaster Hired Labor $0.10 12-30-06
LPV-142 Interim Measure - South Side of GIWW $1.2 6-10-07
NOE-9 Michoud Slip to Michoud Canal, Floodwall Scour Repair $21.7 6-3-06
OEB-02 Lake Pontch-17th St. Canal Floodwall Repair, Phase 2 $15.2 2-3-06
OEB-04 Lake Pontch-London Ave. Canal Breach at Mirabeau, Ph2 $12.02 2-10-06
OEB-06 Lake Pontch- London Ave. Breach at Robert E. Lee, Ph2 $9.85 2-24-06

IHNC Floodgates

Project Code Contract Contracting
Package
Contracting Estimates
(in millions)
Contract Awards
(Quarters based on calendar year)
IHNC-01 IHNC Flood Protection - Seabrook
Design Build
50-100
Q-2-2010
IHNC-02 IHNC Flood Protection - GIWW/MRGO Design Build $695 Apr 3 2008

Lake Pontchartrain & Vicinity

Project Code

Contract

Contracting
Package

Contracting Estimates
(in millions)

Contract Awards
(Quarters based on calendar year)

LPV-00.1

Reach 1 Lakefront Levee - Phase 1

8(a)

4.57

8/31/2006

LPV-00.2

Reach 1 Lakefront Levee - Phase 2

8(a)

0-5

Q2 2009

LPV-01.1

Reach 2 Lakefront Levee Phase 1

8(a)

0-5

Q 32008

LPV-02.1

Reach 3 Lakefront Levee - (3rd Lift) - Phase 1

8(a) MATOC

5.52

10/6/2006

LPV-02.2

Reach 3 Lakefront Levee - Phase 2

8(a) MATOC

0-5

Q-2-2009

LPV-03d.2

Airport Runway 10 Levee - Phase 1

Unrestricted

0-5

Q 3 2009

LPV-03a.1

West Return Floodwall - Vintage - Phase 1

8(a)

1.68

5/13/2006

LPV-03.2

West Return Floodwall - Vintage - Phase 2

Unrestricted

100M+

Q 1 2010

LPV-03b.1

West Return Floodwall - Airport I-wall - Phase 1

8(a)

0.59

9/16/2006

LPV-03c.1

West Return Floodwall - I- wall @ I-10 - Phase 1

HZ-MATOC

0.09

4/24/2007

LPV-09.1

Pump Station #1 (Bonnabel) Floodwall Tie-ins -Phase 1

HZ-MATOC

0.29

5/16/2007

LPV09.2

Pump Station #1 (Bonnabel) Modifications, Fronting Protection & Floodwall Tie-ins Phase 2

Unrestricted

20-50

Q 2 2009

LPV-10.1

Pumping Station #2 (Suburban) Floodwall Tie-ins -Phase 1

8(a) MATOC

1.19

9/22/2006

LPV-10.2

Pumping Station #2 (Suburban) Modifications, Fronting Protection, Positive Cut-off & Floodwall Tie-ins - Phase 2

Unrestricted

20 50

Q 2 2009

LPV-11.1

Pumping Station #3 (Elmwood) Floodwall Tie-ins -Phase 1

8(a)

1.39

9/22/2006

LPV-11.2

Pumping Station #3 (Elmwood) Modifications, Fronting Protection, Positive Cut-off & Floodwall Tie-ins - Phase 2

Unrestricted

20-50

Q 2 2009

LPV-12.2

Pumping Station #4 (Duncan) Modifications, Fronting Protection, Positive Cut-off & Floodwall Tie-ins - Phase 2

HUBZONE

20-50

Q 1 2009

LPV-13.1

Re-Curve I-Wall in Northwest Kenner - Phase 1

HUBZONE

1.01

5/2/2007

LPV-13.2

Re-Curve I-Wall in Northwest Kenner - Phase 2

HUBZONE

5-20

Q 3 2009

LPV-16.1

Floodwall and Gate at Bonnabel Launch - Phase 1

HUBZONE

0-5

5/21/2007

LPV-16.2

Floodwall and Gate at Bonnabel Launch - Phase 2

HUBZONE

0-5

Q 2 2009

LPV-17.2

Bridge abutment and floodwall tie-ins at Causeway Bridge - Phase 2

HUBZONE

0-5

Q 1 2010

LPV-18.2

Floodwall and Gate at Williams Blvd. Boat Launch - Phase 2

HUBZONE

0-5

Q 2 2009

LPV-09a2
Pump Station #1 Breakwater -Phase 1 Unrestricted 0-5
Q 1 2009

LPV-19.2

Reach 4 Lakefront Levee - Phase 2

HUBZONE

0-5

Q 2 2009

LPV-20.1

Reach 5 Lakefront Levee - Phase1

HUBZONE

0-5

Q 4 2008

LPV-20.2

Reach 5 Lakefront Levee - Phase 2

HUBZONE

5-20

Q 2 2009

Southeast Louisiana - Jefferson Parish

Project Code

Contract

Contracting
Package

Contracting Estimates
(in millions)

Contract Awards
(Quarters based on calendar year)

SELA-01

Soniat Canal - Veterans to Canal #3 & gap below Veterans

Unrestricted

24.02

11/16/2006

SELA-01a

Soniat Canal - West Napoleon to Lynette

Unrestricted

5-20

Q 2 2009

SELA-02

Westwego PS Diesel Engine

8(a) - MATOC

1.49

12/18/06

SELA-03

Westminster/Lincolnshire PS Backup Generators

8(a) - MATOC

8.85

12/29/06

SELA-04

Elmwood Canal Bridge @ Kawanee

8(a) - MATOC

5.84

1/30/07

SELA-04a

Elmwood Canal Bridge @ W. Esplanade

HZ - MATOC

13.08

2/26/2007

SELA-05

Grand Cross Canal @ Lapalco

HZ - MATOC

8.66

6/18/2007

SELA-06

Gardere Canal - Phase II

Unrestricted

31.35

1/12/2007

SELA-07

Pump to River Disc. Tubes ( Hickory Avenue Section)

SDV

8.45

8/14/2007

SELA-07A Pump to River Remaining Discharge Tubes 50-100M Q 3 2009
SELA-8 Soniat Canal - West Metairie to Lynette 20-50M Q 2 2009
SELA-9 Pump to the River PS and Intake Structure 50-100M Q 2 2010
SELA 10 Mayronne Canal 5-20M Q 2 2010

SELA-11

Cousins Canal - Phase II

8(a) - MATOC

9.00

9/27/2007

SELA 12 Two Mile Canal Phase 2 20-50M Q 2 2009
SELA 13 Justice and Oil Company Canals 5-20M Q 4 2009
SELA 14 Industry Canal 20-50M Q 4 2011
SELA 15 Trapp Canal 20-50M Q 2 2011
SELA 16 Bardere Canal - Phase III (Murphy Canal) 20-50M Q 3 2010

SELA-OG-1

Soniat Canal - West Napoleon to Veterans

 

20-50

7/25/2000

SELA-OG-2

Two Mile Canal Phase I

 

5-20

10/23/2003

SELA-OG-5

Whitney/Barataria Pump Station

 

5-20

12/15/1999

SELA-OG-6

Suburban Pump Station

 

5-20

12/14/1999

SELA-OG-7

Elmwood Pump Station

 

5.20

11/19/1999

Southeast Louisiana - Orleans Parish

Project Code

Contract

Contracting
Package

Contracting Estimates
(in millions)

Contract Awards
(Quarters based on calendar year)

SELA-18

Dryer Road PS intake Culvert

Unrestricted

20-50

Q 3 2008

SELA-19

Florida Avenue - Phase 1

Unrestricted

20-50

Q 4 2008

SELA-20

Florida Avenue - Phase 2

Unrestricted

50-100

Q 4 2008

SELA-21 Uptown Jeff Avenue - Phase 1 - Claiborne to Dryades   0-5 Q 3 2010
SELA-22 Uptown Jeff Avenue - Phase 1 - Dryades to Constance   0-5 Q 4 2010
SELA-23 Uptown Naploleon Avenue - Phase 1 - Constance to Carondelet   0-5 Q 1 2009
SELA 23a Uptown Naploleon Avenue - Phase 1 - Montecelle to Leonidas   0-5 Q 4 2009
SELA 23b Uptown Naploleon Avenue - Phase 1 - Leonidas to Lowerline   0-5 Q 1 2010

SELA-25

Florida Avenue - Phase 3

Unrestricted

20-50

Q 4 2009

SELA-OG-3

Dwyer Road - PS Improvements

 

20-50

9 21 2000

SELA-OG-4

Pritchard Place Pump Station

 

5-20

4 19 2001

Lake Cataouatche

Project Code

Contract

Contracting
Package

Contracting Estimates
(in millions)

Contract Awards
(Quarters based on calendar year)

WBV-15a.1

Lake Cataouatche PS to Segnette State Park-Phase 1

Unrestricted

$44.72

7/27/2007

WBV-15a.2

Lake Cataouatche PS to Segnette State Park-Phase 2

Unrestricted

5-20

Q-3-2009

WBV-15b.1

Lake Cataouatche PS Fronting Protection, Modifications

HUBZONE

4.86

8/31/2007

WBV-15b.2

Lake Cataouatche PS Fronting Protection, Modifications

HUBZONE

20-50

Q-2-2009

WBV-17a.1

Western Tie-In - Phase 1

Unrestricted

20-50

Q-3-2009

WBV-17a.2

Western Tie-In - Phase 2

Unrestricted

5-20

Q-3-2009

WBV-17b.1

Station 160+00 to Hwy 90- Phase 1

HUBZONE

14.62

03-19-2008

WBV-17b.2

Station 160+00 to Hwy 90- Phase 2

HUBZONE

0-5

Q-1-2009

WBV-18.1

Hwy 90 to Lake Cataouatche PS - Phase 1

Unrestricted

16.85

10/24/2006

WBV-18.2

Hwy 90 to Lake Cataouatche PS - Phase 2

Unrestricted

5-20

Q-2-2009

WBV-16.1

Segnette PS to New Westwego PS Floodwall - Phase 1

HUBZONE 

19.00

5/23/2007

WBV-16.2

Segnette PS to Company Canal Floodwall

SDV

20-50

Q 4-2009

WBV-16b

Segnette PS Fronting Protection & Modifications

  Unrestricted

20-50

Q 2 2009

WBV-19

Company Canal Floodwall

Unrestricted

20-50

WBV-24

Segnette State Park Floodwall

HUBZONE

100+

Q-1-2010

WBV-53

Priority Interim-Contract 2

Hired Labor

0.63

9/19/2006

WBV-71 Western Tie-In Levee (North-South) Unrestricted 0-5 M Q 4 2009
WBV-72 Western Tie-In Levee (East-West) Unrestricted 20-20M Q 2 2010
WBV-73 Western Tie-In Hwy Crossing Unrestricted 5-20M Q 4 2009
WBV-74 Western Tie-In Gated Closure Unrestricted 5-20M Q 1 2010
WBV-75 Western Tie-In RR Crossing Unrestricted 0-5M Q 1 2010

West Bank & Vincinity - West Algiers

WBV-01

Contract 1, Sectorgate to Boomtown Floodwall

Unrestricted

132.13

02/01/2008

WBV-02a

Contract 2a, Boomtown Floodwalls

Unrestricted

5-20

Q 3 2008

WBV-02b

Contract 2b, Boomtown to Hero PS Floodwalls

Unrestricted

56.10

3/26/2007

WBV-03a

Contract 3a, Hero PS to Algiers Canal Floodwall

Unrestricted

62.28

07/14/2008

WBV-03b

Contract 3b, Hero PS to Algiers Canal Floodwall

Unrestricted

5-20

Q 4 2008

WBV-04.2

Belle Chasse Hwy to Hero Cutoff-Reach1-Phase 2

HUBZONE

0-5

Q 2 2009

WBV-05.2

Belle Chasse Hwy to Hero Cutoff-Reach 2 - Phase 2

HUBZONE

5-20

Q 2 2009

WBV-06.2

Belle Chasse Hwy to Hero Cutoff-Reach 3 & 4 - Phase 2

HZ-MATOC

20-50

Q 2 2009

WBV-06a.1

Belle Chasse Hwy to Hero Cutoff (West)

HZ-MATOC

9.62

01-04-2008

WBV-06a.2

Belle Chasse Hwy to Hero Cutoff (West) - Phase 2

50-100

Q 1-2011

WBV-07

Planters PS Fronting Protection and Modifications

HZ-MATOC

20-50

Q 2 2008

WBV-08

S&WB PS #13 Fronting Protection and Modifications

HZ-MATOC

20-50

Q 4 2008

WBV-38.1

Cousins PS- Phase 1

Unrestricted

18.78

9/16/2006

WBV-38.2

Cousins PS- Phase 2

Unrestricted

20-50

Q 2-2009

WBV-46.1

Sector gate Complex - Phase 1

Unrestricted

35.69

12/16/2003

WBV-46.2

Sector gate complex- Phase 2

Unrestricted

5-20

Q 2-2009

WBV-47.1

Algiers Lock to Belle Chasse Hwy (West)- Phase 1

Unrestricted

5-20

Q 2 2009

WBV-47.2

Algiers Lock to Belle Chasse Hwy (West)- Phase 1

Unrestricted

20-50

Q 3 2010

WBV-39b.1

Cousins Discharge Channel Floodwalls - Phase 1

Hired Labor

1.05

6/17/2007

WBV-39b.2

Cousins Discharge Channel Floodwalls - Phase 2

Unrestricted

5-20

Q 4 2009

WBV-44

Whitney Barataria PS Fronting Protection and Modifications

Unrestricted

20-50

Q1 2009

WBV-52

Priority Interim-Contract 1

Hired Labor

0.20

9/19/2006

WBV-59 '07 Priority Interim-Contract 2 Estelle PS to Lapalco HUBZONE 3.17 7-13-2007
WBV-60
'07 Priority Interim-Contract 3 Westego Floodwall
8(a)
8.12 12 07 2007
WBV-61
'07 Priority Interim-Contract 4 Segnette Park Floodwall 8(a) 7.70 11 20 2007
WBV-62
Priority Interim-Contract 5 Old and New Estelle PS andPS #13 8(a) - MATOC 2.69 04 27 2007
WBV-63a
'07 Priority Interim-Contract 6 Misc WB Pump Station and Utility Crossing 8(a) - MATOC 0.99 04 26 2007
WBV-63b '07 Priority Interim-Contract 7 Misc WB Pump Station and Utility Crossing 8(a) - MATOC 0.67 06 21 2007
WBV-63b.1
'07 Priority Interim-Contract 7b Misc WB Pump Station and Utility Crossing 8(a) 3.5 07 03 2007
WBV-63c '07 Priority Interim-Contract 8 Misc WB Pump Station and Utility Crossing 8(a) - MATOC 4.35 05 23 2007

West Bank & Vincinity - Belle Chasse


Project Code

Contract

Contracting
Package

Contracting Estimates
(in millions)

Contract Awards
(Quarters based on calendar year)

WBV-09a

Hero Canal to Oakville -Levees

HZ-MATOC

5-20

Q1 2010

WBV-09b Hero Canal to Oakville - Structures HZ-MATOC
0-5
Q 4 2009

WBV-10

Belle Chasse PS #1 (Plaquemines PS) Fronting Protection and Modifications-Phase 1

Unrestricted

20-50

Q 4 2008

WBV-11

Belle Chasse PS #2 Fronting Protection and Modifications

Unrestricted

5-20

Q 4 2008

WBV-12

Hero Canal Reach 1, 2nd Enlgt

Unrestricted

50-100

Q 1 2010

WBV-13

S&WB PS #11Fronting Protection and Modifications

HZ-MATOC

20-50

Q 2 2008

WBV-48.1

Belle Chasse Hwy to Algiers Lock (East) - Phase 1

Unrestricted

4.99

8/8/2005

WBV-48.2

Belle Chasse Hwy to Algiers Lock (East) - Phase 2

Unrestricted

20-50

Q 1 2010

WBV-49.1

Hero Levee to Belle Chasse Hwy (East)- Phase 1

Unrestricted

0-5

Q 1 2009

WBV-49.2

Hero Levee to Belle Chasse Hwy (East)- Phase 2

Unrestricted

50-100

Q 2 2011

West Bank & Vincinity - Westwego to Harvey Canal

Project Code

Contract

Contracting
Package

Contracting Estimates
(in millions)

Contract Awards
(Quarters based on calendar year)

WBV-14a.1

Harvey Canal West Bank Levee, Phase 1

HZ-MATOC

1.77

04/15/2008

WBV-14a.2

Harvey Canal West Bank Levee, Phase 2

HZ-MATOC

5-20

Q 1 2010

WBV-14b.1

Orleans Village to Hwy 45, Levee-Phase 1

HZ-MATOC

3.00

8/28/2007

WBV-14b.2

Orleans Village to Hwy 45 Levee- Phase 2

HZ-MATOC

5-20

Q 2 2009

WBV-14c.1

New Westwego PS to Orleans Village , 3rd Enlgt-Phase 1H

HZ-MATOC

8.98

03/14/2008

WBV-14c.2

New Westwego PS to Orleans Village- Phase 2

HZ-MATOC

5-20

Q 2 2009

WBV-14e.1

V-line Levee, east of Vertex- Phase 1

HZ-MATOC

8.01

06/06/2008

WBV-14e.2

V-line levee, east of vertex- Phase 2

HZ-MATOC

20-50

Q 3 2009

WBV-14f.2

Hwy 45 levee- Phase 2

HZ-MATOC

0-5

Q 1 2009

WBV-14d

V-line Floodwall

HUBZONE

50-100

Q 1 2009

WBV-14g2

Estelle PS Vicinity Floodwalls

 

50-100 Q 2 2009
WBV-19
Company Canal Floodwall Unrestricted 20-50M Q

WBV-20

New Westwego PS fronting Protection and Modifications

Unrestricted

5-20

Q 1 2009

WBV-21

Old Westwego PS Fronting Protection and Modifications

Unrestricted

0-5

Q 2 2009

WBV-22

Westwego Floodwall

Unrestricted

20-50

Q 3 -2009

WBV-23

New Estelle PS Fronting Protection and Modifications

HUBZONE

5-20

Q 1 2009

WBV-30

Westminster PS Fronting Protection and Modifications

Unrestricted

5-20

Q 1 2009

WBV-33

Old Estelle PS Fronting Protection and Modifications

HUBZONE

20-50

Q 1 2009

WBV-37

Ames PS fronting Protection and Modifications

8(a)

20-50

Q 2 2009

WBV-43

Mt. Kennedy PS fronting protection and Modifications

8(a)

5-20

Q 1 2009

WBV-54

Priority Interim- Contract 3

Hired Labor

0.10

9/19/2006

WBV-55

Priority Interim- Contract 4

Hired Labor

0.60

9/19/2006

WBV-56

Priority Interim-Contract 5

Hired Labor

0.20

9/19/2006

St. Bernard Parish

Project Code Contract Contracting
Package
Contracting Estimates
(in millions)
Contract Awards
(Quarters based on calendar year)
LPV-142
Interim Measure - South Side of GIWW
0-5
06-10-2007
Chalmette Loop Levee - Bayou Bienvenue and Bayou Dupre
Unrestricted
20-50
Q 2 2009
LPV-145 Chalmette Loop Levee - Bayou Bienvenue to Bayou Dupre HUBZONE 100+ Q 3 2009
LPV-146 Chalmette Loop Levee - Bayou Dupre to Hwy 46 HUBZONE 100+ Q 2 2009
LPV 147 Chalmette Loop Levee - Bayou Road Floodgate and Hwy 46 ramp Unrestricted - Best Value 20 - 50 Q 4 2009
LPV-148.01 Chalmette Loop Levee - Hwy 46 to River (Verret to Caernarvon) Unrestricted - Best Value 41.82 10-31-2007
LPV 148.02 Chalmette Loop Levee - Hwy 46 to River (Verret to Caernarvon) Unrestricted - Best Value 20 - 50 Q 2 2009
LPV 149 Chalmette Loop Levee -(Verret to Caernarvon Structures Unrestricted - Best Value 5-20 Q 2 2010
NF-01 Grand Isle Non Federal 8(a) 0-5 Q 03 2009
GI-01 Grand Isle Federal Levee HUBZONE 12.50 04/08/2008

Plaquemines Parish

Project Code

Contract

Contracting
Package

Contracting Estimates
(in millions)

Contract Awards
(Quarters based on calendar year)

NOV - 01

Reach C Hurricane Protection - Phoenix to Davant

Unrestricted

20-50

Q 1 2010

NOV - 02

Reach C Hurricane Protection - Davant to Bohemia

Small Business

20-50

Q 4 2009

NOV - 05

West Bank - St. Jude - City Price Upper Reach A

Small Business

5-20

Q 1 2010

NOV - 06

West Bank - Reach A (City Price to Empire)

8(a)

5-20

Q 1 2010

NOV - 07

West Bank - Reach B-1 (Empire to Ft Jackson)

HUBZONE

20-50

Q 1 2010

NOV - 08

West Bank - Reach B-2 (Ft. Jackson to Venice)

8(a)

5-20

Q 1 2010

NOV - 09

West Bank MRL

8(a)

5-20

Q 1 2010

NOV -10

West Bank MRL - St Jude to Port Sulphur

Small Business

5-20

Q 1 2010

NOV -11

West Bank MRL - Port Sulphur to Fort Jackson Sta 285 to 357 Buras to Fort Jackson

Unrestricted - Best Value

5-20

Q 3 2010

NOV - 12

West Bank MRL - Fort Jackson to Venice

Unrestricted - Best Value

0-5

Q 1 2010

NOV - 13

West Bank - Empire Floodgate

Unrestricted - Best Value

0-5

Q 1 2010

NOV - 14

West Bank - Empire Lock

Unrestricted - Best Value

0-5

Q 1 2010

NOV - 15

West Bank - Floodwall Repairs Duvic P/S, Grand Laird P/S, Pt Michel, Childress

HUBZONE

5-20

Q 1 2010

NOV -15.01
Interim Measures at Duvic and Grand Liard Pump Stations
Hired Labor
4.00
08-08-07

NF-02

Braithwaite to Scarsdale Non Federal

HUBZONE

16

15 Jun 06

NOV-NF-W-04

Oakville to LaReusitte

Small Bussiness

50-100

Q 1 2010

NOV-NF-W-05

LaReusitte to Myrtle Grove

Unrestricted -

100+

Q 1 2010

NOV-NF-W-06

Myrtle Grove to St.Jude

8(a)

100+

Q 1 2010

 

Project Code

Contract

Contracting
Package

Contracting Estimates
(in millions)

Contract Awards
(Quarters based on calendar year)

P-13

Landside Levee Enlargement Port Sulphur Area

 

5-20

10 Feb 06

P-14

Landside Levee Enlargement Empire/Buras Area

 

18.2

26 Jan 06

P-15

Empire Floodgate Repair Phase 1 & 2

 

4.6

20 Jan 06

P-17

Landside Levee Enlargement Buras Area

 

3.5

3 Feb 06

P-24

Landside Levee Enlargement Port Sulphur Area

 

9.0

30 Jan 06

St. Charles Parish

Project Code

Contract

Contracting
Package

Contracting Estimates
(in millions)

Contract Awards
(Quarters based on
calendar year)

LPV-04.1

Levee - Reach 1A, 1B & 2A- Phase 1

HZ - MATOC

12.93

6/28/2007

LPV-04.2

Levee - Reach 1A, 1B & 2A- Phase 2

Unrestricted

20-50

Q3 2009

LPV-05.1

Levee - Reach 2B (2nd Lift)- Phase 1

8(a) - MATOC

4.66

9/14/2006

LPV-05.2

Levee - Reach 2B- Phase 2

HUBZONE

20-50

Q 3 2009

LPV-06.1

Floodwall Tie-ins- & Bayou Trepagnier Drainage Structure – Phase 1

8(a) - MATOC

0.98

3/3/2007

LPV-06a.2

Bonnet Carre Floodwall - Phase 2

Unrestricted

0-5

Q 3 2009

LPV-06b.2

Shell Pipeline Floodwall - Phase 2

Unrestricted

0-5

Q3 2009

LPV-06c.2

Goodhope Floodwall - Phase 2

Unrestricted

5-20

Q 3 2009

LPV-06d.2

Koch - Gateway Floodwall - Phase 2

Unrestricted

0-5

Q 3 2009

LPV-06e.1

Floodwall Under I-310 - Phase 1

Unrestricted

0.47

4/2720/07

LPV-06e.2

Floodwall Under I-310 - Phase 2

Unrestricted

5-20

Q3 2009

LPV-06f.2

Canadian National Railroad Gate - Phase 2

Unrestricted

5-20

Q 3 2009

LPV-07.1

St. Charles Drainage Structure Tie-In – Phase I

8(a) - MATOC

0.85

9-26-2007

LPV-07b.2

Cross Bayou Drainage Structure - Phase 2

Unrestricted

5-20

Q4 2009

LPV-07c.2

St. Rose Drainage Structure - Phase 2

Unrestricted

5-20

Q 1 2009

LPV-07d.2

Almeidia Drainage Structure - Phase 2

Unrestricted

0-5

Q1 2009

LPV-07e.2

Walker Drainage Structure - Phase 2

Unrestricted

0-5

Q1 2009

Lafouche Parish - Golden Meadow

Project Code

Contract

Contracting
Package

Contracting Estimates
(in millions)

Contract Awards
(Quarters based on calendar year)

LGM-00

Section D; South Berm and Mitigation Levee

8(a) -MATOC

1.73

11/21/2006

LGM-01

C North 3rd Lift

8(a) -MATOC

5-20

Q 3 2008

LGM-02

D North 3rd Lift

8(a) -MATOC

2.88

11/21/2006

Existing Pump Station Repair

Project Code Contract Contracting
Package
Contracting Estimates
(in millions)
Contract Awards
(Quarters based on calendar year)
Roofing Repairs 8(a) 1.9 22-Aug-06
OPS-02 Motor Rewinds P.S. 2,3,5 & 7 Service 4.07 15-May-06
OPS-03 Motors Rewinds P.S. 1 & 6 Service 3.3 15-May-06
OPS-05 Horizontal Pump Bearings Supply 1.11 01 Dec 06
OPS-06a Bearings - PS 1, 14, 15, 16, I-10 Service 3.22 1-Dec-06
OPS-06b OPS-06b Bearings - PS 4, 6, 10, 12, 19 Service 2.96 1-Dec-06
OPS-07a Frequency Changers Carrollton Building Service 3.42 22-Nov-06
OPS-07b OPS-07b - Frequency Changers Station 17 (D) Service 3.34 22-Nov-06
OPS-08 Electrical-Mechanical Repairs 8(a) 3.25 19 Jun-07
OPS-09 Building and Structural Repairs HUBZONE 1.55 12 Oct 07
OPS-10 Discharge Line SDV 1.85 1 Aug 07
OPS-11 Elaine Pump Station Repair 8(a) 0-5 Q 3 2008
JPS-01 Roofing Repairs Bonnabel Smplfd. Constr. 0.1 10 May 06
JPS-02 Roofing Repairs Duncan Smplfd. Constr. 0.1 11 -May 06
JPS-03a Roofing Siding Repairs 8(a) 0.1 17 Jul 06
JPS-03b Roofing Siding Repairs 8(a) 0.1 17 Jul 06
JPS-03c Roofing Siding Repairs 8(a) 0.1 17 Jul 06
JPS-04 Misc Repairs # 1
8(a)
0.1
8-Nov-06
JPS-05 Misc Repairs # 2 8(a) 0.1 30-Oct-06
JPS-06 Misc Repairs # 3 8(a) 0.1 2-Nov-06
SBPS-01 Design Build Contract Rebuild 2,3,and 5 Design Build 17.90 17-May-07
SBPS-02 Electric/Mechanical and Misc Repairs 8(a) 0.79 25 Jan 07
SBPS-03 Generators for PS#1 and 4 8(a) 0.1 27 Jul 06
SBPS-04 Gate Package 8(a) 0.5 28 Sep 06
SBPS-05 Roofing Repairs Smplfd. Constr. 0.1 14 Apr 06
PPS-01a Hayes, Esplalh, Bellevue, Scarsdale Unrestricted 5-20 19 Jun 08
PPS-01b Gainard Woods 1+2, Sunrise 1+2, Triumph 8(a) 0-5 Q 3 2008
PPS-01c Diamond and Wpalh 8(a) 0-5 Q 4 2008
PPS-01d Belle Chasse 1+2, Ollie, Grand Deliard, Dvvic 8(a) 0-5 Q 4 2008
PPS-02 Electric Services 8(a) 0.70 25 Aug 06

Existing Pump Station - Stormproofing

Project Code

Contract

Contracting
Package

Contracting Estimates
(in millions)

Contract Awards
(Quarters based on calendar year)

JPS-01

Jefferson Parish Pump Stations

HZ-MATOC

5-20

Q 2 2009

JPS-02

Jefferson Parish Pump Stations

HZ-MATOC

20-50

Q 2 2009

Five Safe Rooms
HZ-MATOC
17.16
12 18 2007
Seven Pump Station Automation
HZ-MATOC
5-20
Q-3-2008

OSP-01

Orleans Parish Pump Stations

Unrestricted

5-20

Q 3 2008

OPS-02

Orleans Parish Pump Stations

8(a)

50-100

Q 3 2008

PSG-01

PS #6 Emergency Generator

8(a)

2.5

31-Oct-06

PSG-02

PS #6 Fuel Tanks

Supply

0.2

12-Sep-06

Existing East Bank Outfall Canals

Project Code Contract Contracting
Package
Contracting Estimates
(in millions)
Contract Awards
(Quarters based on calendar year)
Lake Pontchartrain-Interim Closure Structure at 17th Street Canal
U
62.57
27-Jan-06
OEB 10 Lake Pontchartrain-Interim Closure Structure at London Ave Canal U 40.31 27-Jan-06
OEB 11 Lake Pontchartrain-Interim Closure Structure at Orleans Ave Canal U 47.70 3-Feb-06
OEB 12 Temporary Pump Supply 07 - 17th St. Canal Supply 20-50 22-Dec-06
OEB 13 Temporary Pump Supply 07 - London Ave Canal Supply 5-20 22-Dec-06
OEB 14 Temporary Pump Installation 07 - 17th St. Canal Design Build 5-20 31-Jan-06
OEB 15 Temporary Pump Installation 07 - London Ave Canal Design Build 20-50 31-Jan-06
SCADA-01 SCADA system for 17th, London and Orleans Avenue Canals Design Build 5.43 19-Apr-06

Permanent Canal Closure and Pump Stations (PCCP)

Project Code Contract Contracting
Package
Contracting Estimates
(in millions)
Contract Awards
(Quarters based on calendar year)
PCCP-01
Outfall Canal Closures
Design Build
100 +
Q 1 2010
Revision Date : October 15, 2008