This is the accessible text file for GAO report number GAO-07-76 
entitled 'Global War on terrorism: Fiscal Year 2006 Obligation rates 
Are Within Funding Levels and Significant Multiyear Procurement Funds 
Will Likely Remain Available for Use in Fiscal Year 2007' which was 
released on November 13, 2006. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Report to Congressional Committees: 

United States Government Accountability Office: 

GAO: 

November 2006: 

Global War On Terrorism: 

Fiscal Year 2006 Obligation Rates Are Within Funding Levels and 
Significant Multiyear Procurement Funds Will Likely Remain Available 
for Use in Fiscal Year 2007: 

Global War on Terrorism: 

GAO-07-76: 

GAO Highlights: 

Highlights of GAO-07-76, a report to congressional committees 

Why GAO Did This Study: 

Because of broad congressional interest, GAO is examining the costs of 
military operations in support of the Global War on Terrorism (GWOT) 
under the Comptroller General’s authority to conduct evaluations on his 
own initiative. In September 2005, GAO reported the Department of 
Defense (DOD) cannot ensure reported GWOT obligations are complete, 
reliable, and accurate, and recommended improvements. In this report, 
GAO (1) compared supplemental and annual appropriations identified for 
GWOT in fiscal year 2006 to the military services’ reported obligations 
as of June 2006 and their cost projections for the remainder of the 
fiscal year, and (2) examined DOD’s efforts to improve the reliability 
of GWOT obligation data. 

For this engagement, GAO analyzed fiscal year 2006 GWOT related 
appropriations and reported obligations, and DOD’s corrective actions. 

What GAO Found: 

As of June 2006, which represents 9 months (75 percent) of fiscal year 
2006, the military services have reported obligating about $51.6 
billion (55 percent) of the $93.3 billion they received for GWOT in 
supplemental and annual appropriations for military personnel, 
operation and maintenance, and procurement. Our analysis of reported 
obligations and the military services’ forecasts of their likely costs 
for fiscal year 2006 suggest that the rates of obligation for military 
personnel and operation and maintenance are within fiscal year 2006 
GWOT funding levels and significant amounts of multiyear procurement 
funds will likely remain available for use in fiscal year 2007. The 
rates of obligation for military personnel are within funding levels 
for all military services except the Army, which plans to transfer 
about $591 million in funds from other appropriations accounts to cover 
its military personnel obligations. The rates of obligation for 
operation and maintenance are within funding levels for all military 
services. As of June, the military services reported obligating about 
85 percent of military personnel funds and 60 percent of operation and 
maintenance funds. For various reasons, most notably being that 
supplemental funds were not appropriated until June 2006, the military 
services do not expect to obligate a large portion of procurement 
funds, which generally are available for multiple years, and therefore 
these funds will remain available in fiscal year 2007. The military 
services received about 32 percent ($6.8 billion) of procurement 
funding in annual appropriations and 68 percent ($14.7 billion) in the 
supplemental appropriation. As of June, the military services reported 
obligating about 68 percent of the procurement funds received in the 
annual appropriation. 

DOD and the military services have taken specific steps intended to 
improve the accuracy and reliability of their reported GWOT obligation 
data. Some problems remain with transparency over certain costs and 
inaccuracies in reported obligations. In response to GAO’s prior 
recommendations, DOD now requires components to perform a monthly 
variance analysis to identify and explain significant changes in 
obligations and to attest to the accuracy of monthly obligation 
reports, and affirm it provides a fair representation of ongoing 
activities. Because these efforts are in the early stages of 
implementation, GAO has not fully evaluated their impact. Existing cost 
reporting procedures limit transparency of certain obligations because 
DOD continues to report large amounts in miscellaneous “other” 
categories. Also, DOD’s cost reports for fiscal year 2005 understated 
total GWOT obligations for that year because they did not initially 
include about $1.1 billion in obligations tied to the training and 
equipping of Afghan and Iraqi security forces. Without transparent and 
accurate cost reporting, Congress and DOD will continue to be unable to 
reliably know how much the war is costing, examine details on how 
appropriated funds are being spent, or have historical data useful in 
considering future funding needs. On the basis of GAO’s work, DOD 
updated its guidance on the reporting of obligations in miscellaneous 
“other” categories and revised its September 2005 cost-of-war report to 
more fully reflect past obligations. 

What GAO Recommends: 

Because significant multiyear procurement funds from fiscal year 2006 
will likely remain available, GAO suggests Congress require DOD provide 
year-end data on fund availability and plans for additional funds 
received or requested. DOD disagreed, noting, among other things, it 
had already justified its needs. To ensure appropriate transparency, 
GAO continues to believe Congress needs updated data on DOD’s plans. 

[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-07-76]. 

To view the full product, including the scope and methodology, click on 
the link above. For more information, contact Sharon Pickup at (202) 
512-9619 or pickups@gao.gov. 

[End of Section] 

Contents: 

Letter: 

Results in Brief: 

Background: 

Fiscal Year 2006 Rates of Obligations Are Within Funding Levels and 
Significant Multiyear Procurement Funds Will Likely Remain Available 
for Use in Fiscal Year 2007: 

DOD and the Military Services Have Taken Specific Steps Intended to 
Improve GWOT Cost Reporting Procedures and Data Reliability; Some 
Problems Remain: 

Conclusions: 

Matter for Congressional Consideration: 

Agency Comments and Our Evaluation: 

Appendix I: Scope and Methodology: 

Appendix II: DOD's Process for Reporting GWOT Obligations: 

Appendix III: Comments from the Department of Defense: 

Appendix IV: GAO Contact and Staff Acknowledgments: 

Tables: 

Table 1: Fiscal Year 2006 Appropriations Identified for GWOT for the 
Military Services: 

Table 2: DOD's Six Largest Obligation Categories from Fiscal Year 2001 
through Fiscal Year 2006 (June): 

Table 3: DOD Supplemental and Cost of War Execution Report for Fiscal 
Year 2006: 

Figures: 

Figure 1: Military Services' Fiscal Year 2006 Reported GWOT Military 
Personnel Obligations of Appropriations Identified for GWOT through 
June 2006: 

Figure 2: Military Services' Fiscal Year 2006 Reported GWOT Operation 
and Maintenance Obligations of Appropriations Identified for GWOT 
through June 2006: 

Figure 3: Military Services' Fiscal Year 2006 Reported GWOT Procurement 
Obligations of Appropriations Identified for GWOT through June 2006: 

United States Government Accountability Office: 
Washington, DC 20548: 

November 13, 2006: 

Congressional Committees: 

Since the September 11, 2001, terrorist attacks, Congress has provided 
the Department of Defense (DOD) with about $381 billion, as of June 
2006, in supplemental and annual appropriations for military operations 
both in the United States and overseas in support of the Global War on 
Terrorism (GWOT).[Footnote 1] DOD received about $114.4 billion in 
appropriations for GWOT in fiscal year 2006, $49 billion of which was 
received in its annual appropriation and $65.4 billion of which came 
through a supplemental appropriation. The portion of annual 
appropriations for GWOT, also known as "Title IX" or "bridge" 
funding,[Footnote 2] was provided to pay for ongoing military 
operations during the first part of the fiscal year. In June 2006, 
Congress passed a supplemental appropriation to provide funding for 
GWOT operations through the remainder of the fiscal year. Of the $114.4 
billion provided in fiscal year 2006, about $93.3 billion was 
appropriated to the military services for military personnel, operation 
and maintenance, and procurement. The remaining funds provided, about 
$21.1 billion, were for defensewide agencies; research, development, 
test, and evaluation; and military construction. In fiscal year 2006 
through June, DOD reported total obligations of about $63 billion for 
GWOT, including about $54 billion for Operation Iraqi Freedom (OIF) and 
about $9 billion for Operation Enduring Freedom (OEF). 

DOD compiles and reports obligations[Footnote 3] incurred to support 
GWOT in a monthly Supplemental and Cost of War Execution Report. This 
document is used by senior DOD leadership, along with other 
information, in evaluating the costs of the war and formulating future 
budget requests to fund GWOT. The document identifies the monthly and 
cumulative reported incremental GWOT obligations. DOD reports these 
obligations by appropriation, contingency operation,[Footnote 4] and 
military service or defense agency. According to Volume 12, Chapter 23 
of the DOD Financial Management Regulation, the monthly cost reports 
are typically compiled in the 45 days after the end of the reporting 
month in which the obligations are incurred.[Footnote 5] DOD has 
prepared monthly reports on the obligations incurred for its 
involvement in GWOT since fiscal year 2001. 

We have conducted a series of reviews under the Comptroller General's 
authority examining the reported obligations and funding for military 
operations in support of GWOT. In July 2004, we issued a report stating 
that large amounts of DOD's obligations were being reported in 
miscellaneous "other" categories, which provided little insight into 
how those funds had been spent.[Footnote 6] In September 2005, we 
issued a report identifying numerous reliability issues with DOD's 
reported GWOT obligation data, which make it difficult for DOD and 
Congress to know reliably how much the war is costing, examine details 
on how appropriated funding is being spent, or have historical data 
useful in considering future funding needs.[Footnote 7] Over the years, 
we have made a series of recommendations to the Secretary of Defense 
intended to improve the transparency and reliability of DOD's GWOT 
obligation data, including recommendations that DOD (1) revise the cost 
reporting guidance so that large amounts of reported obligations are 
not shown in "miscellaneous" categories, and (2) take steps to ensure 
that reported GWOT obligations are reliable. In response, the 
Department has implemented many of our previous recommendations. 

To assist Congress in its oversight role and to help it consider future 
GWOT funding needs, we prepared this report under the Comptroller 
General's authority to conduct evaluations on his own initiative. In it 
we assess the outlook of fiscal year 2006 reported GWOT obligations and 
funding based on data through June 2006, and determine DOD's progress 
in addressing problems we identified regarding the reliability of DOD's 
reported GWOT obligation data. We (1) compared supplemental and annual 
appropriations identified for GWOT in fiscal year 2006 to the military 
services' reported obligations as of June 2006 and their cost 
projections for the remainder of the fiscal year, and (2) examined the 
extent to which DOD has taken steps to improve its cost reporting 
procedures and the reliability of its reported GWOT obligation data. 

To compare the military services' reported obligations against 
available funding appropriated for GWOT in fiscal year 2006, we 
analyzed copies of DOD's monthly Supplemental and Cost of War Execution 
Report for October 2005 through June 2006 and reviewed applicable 
supplemental and annual appropriations and DOD reports on the transfer 
of funds between various appropriation accounts. We also interviewed 
key officials from the Office of the Under Secretary of Defense 
(Comptroller)[Footnote 8] and the Army, Navy, Marine Corps, and Air 
Force to determine if their projected GWOT obligations are within 
fiscal year 2006 funding levels. As previously reported, we found the 
data in DOD's monthly Supplemental and Cost of War Execution Report to 
be of questionable reliability. Consequently, we are unable to ensure 
that DOD's reported obligations for GWOT are complete, reliable, and 
accurate, and they should therefore be considered approximations. In 
addition, as recently as November 2005, DOD acknowledged that systemic 
weaknesses with its financial management systems and business 
operations continue to impair its financial information. To examine the 
steps DOD has taken to improve the reliability of its reported GWOT 
obligations, we interviewed key officials from the DOD Comptroller and 
the Army, Navy, Marine Corps, and Air Force to determine the extent to 
which our previous recommendations have been implemented. We also 
reviewed any new guidance issued by DOD regarding the analysis and 
reporting of obligations for contingencies. In addition, we performed 
limited testing of the reported GWOT obligations for military personnel 
and discussed with DOD and military service financial managers their 
specific processes and procedures used to ensure that reported GWOT 
obligation data provided by the subordinate commands are accurate and 
reliable. 

We performed our work from January 2006 through September 2006 in 
accordance with generally accepted government auditing standards. 

Results in Brief: 

As of June 2006, which represents 9 months (75 percent) of fiscal year 
2006, the military services reported obligating about $51.6 billion (55 
percent) of the $93.3 billion they received for GWOT in supplemental 
and annual appropriations for military personnel, operation and 
maintenance, and procurement. Our analysis of reported obligations and 
the military services' forecasts of their likely costs for fiscal year 
2006 suggest that the rates of obligation for military personnel and 
operation and maintenance are within fiscal year 2006 GWOT funding 
levels and significant amounts of multiyear procurement funds will 
likely remain available for use in fiscal year 2007. As of June, the 
military services reported obligating about 85 percent of military 
personnel funds and 60 percent of operation and maintenance funds. 
Fiscal year 2006 rates of obligation for military personnel for GWOT 
are within GWOT funding levels for all military services except the 
Army. According to military service officials, the Army experienced 
higher than anticipated obligations for military personnel due 
primarily to increased recruitment and retention incentives offered to 
assist in manning the force during GWOT and increased death gratuity 
benefits provided in the National Defense Authorization Act for fiscal 
year 2006. The Army expects to be able to cover these obligations by 
transferring about $591 million in funds from other appropriations 
accounts into the military personnel account under authority granted by 
Congress.[Footnote 9] In addition, the military services' rates of 
obligation for operation and maintenance for GWOT are within fiscal 
year 2006 GWOT funding levels for all military services. According to 
military service officials, operation and maintenance obligations in 
June 2006 were lower than anticipated due to reduced spending relating 
to contracts and certain operations bills. For example, the Army 
reduced spending on contracts for selected base closures and 
restructuring in Iraq because of the security environment and 
uncertainty regarding receipt of supplemental funding. Furthermore, for 
fiscal year 2006, GWOT-related procurement funds are expected to remain 
largely unobligated by the end of the fiscal year, and will remain 
available in fiscal year 2007. Procurement funds appropriated in one 
fiscal year may remain available in future fiscal years because they 
are available for obligation over multiple years. For fiscal year 2006, 
the military services received about 32 percent ($6.8 billion) of 
procurement funding in Title IX as part of the annual appropriation and 
68 percent ($14.7 billion) in the supplemental appropriation. As of 
June, the military services have spent about 68 percent of the 
procurement funds received through Title IX. Given the time required to 
negotiate new procurement contracts, military service officials stated 
that they were prevented from obligating much of their procurement 
funds received in the supplemental appropriation prior to the end of 
the fiscal year and therefore expect reported monthly procurement 
obligations to be higher in the last month of fiscal year 2006 and in 
early fiscal year 2007. However, given that at the time of this report 
DOD had only reported obligations through June 2006, we were unable to 
determine how much funding would remain at the end of the fiscal year. 
Since it is likely that much of the procurement funding from fiscal 
year 2006 will remain available in fiscal year 2007, knowledge of what 
those available amounts are and how DOD plans to spend them would 
assist congressional decision makers in determining DOD's future 
funding needs. 

DOD and the military services have taken specific steps intended to 
improve the accuracy and reliability of their reported GWOT obligation 
data. Some problems remain with transparency over certain costs and 
inaccuracies in reported obligations. In response to our previous 
recommendation to improve the accuracy and reliability of reported GWOT 
obligation data, in August 2005 the DOD Comptroller issued 
guidance[Footnote 10] to the secretaries of the military services and 
the directors of the defense agencies to help DOD components[Footnote 
11] more accurately and consistently report obligations for 
contingencies such as GWOT. This guidance directed DOD components to 
perform a monthly variance analysis to review and validate that their 
reported obligations are accurate and provide a fair representation of 
ongoing activities, and to include an explanation of variances that 
exceed a certain threshold. The DOD Comptroller also issued guidance 
directing submitting DOD components to attest to the accuracy of their 
monthly obligation data contained in DOD's Supplemental and Cost of War 
Execution Report and affirm that the report provides a fair 
representation of ongoing activities. Because these efforts are in the 
early stages of implementation, we have not fully evaluated their 
impact. The Army also made improvements to the accuracy of its imminent 
danger pay reporting shortly after the issuance of our September 2005 
report and DOD's guidance regarding the analysis of contingency 
operations costs. In addition to these efforts, further improvements 
are needed in the cost reporting process. For example, existing cost 
reporting procedures limit the visibility over or transparency of 
certain obligations because DOD continues to report large amounts of 
obligations in miscellaneous "other" categories. For example, in fiscal 
year 2005, about $12.8 billion (or 26 percent of all obligations) 
reported in the operation and maintenance account were in "other 
supplies and equipment" and "other services and miscellaneous 
contracts." This trend has continued in fiscal year 2006. Little has 
been done DOD-wide to further refine reporting of these miscellaneous 
obligations in DOD's cost-of-war reports, although the Army has taken 
some steps at the headquarters level to reduce the amounts reported in 
these "other" categories by revising its reporting methodology to 
redirect some of the obligations into reporting categories that more 
closely describe the obligations. Moreover, while the components have 
taken steps to improve their reporting of GWOT obligations, as required 
by DOD's financial management regulation, inaccuracies in DOD's 
reported obligations continue to exist. For example, we found that 
DOD's cost-of-war reports understated total GWOT obligations because 
they did not include about $1.1 billion in obligations for fiscal year 
2005 tied to the training and equipping of Afghan and Iraqi security 
forces. According to DOD officials, because the funds for these 
purposes became available later in the fiscal year, DOD did not have a 
reporting format in the cost-of-war reports for these obligations and 
planned to amend its September 2005 cost-of-war report at some point to 
reflect them. Without transparent and accurate reporting of GWOT 
obligations, the public, Congress, and DOD will continue to be unable 
to reliably know how much the war is costing, examine details on how 
appropriated funds are being spent, or have historical information 
useful in determining future funding needs. 

In a draft of this report, we made two recommendations to DOD to 
improve the transparency and accuracy of its cost reporting. DOD agreed 
with one recommendation to revise Volume 12, Chapter 23 of the DOD 
Financial Management Regulation to provide additional subcategories for 
"other supplies and equipment," "other services and miscellaneous 
contracts," and "other military personnel" to provide further breakdown 
of reported obligations in miscellaneous categories and, in fact, in 
October 2006, issued a revision to Chapter 23 to provide such 
breakdowns. We believe this meets the intent of our recommendation and 
removed the recommendation from the final report. DOD disagreed with 
the basis of a second recommendation to amend the September 2005 
version of DOD's Supplemental and Cost of War Execution Report to 
include the unreported Afghan and Iraqi security forces fund 
obligations for fiscal year 2005. In its comments, DOD stated that this 
information was provided to Congress in another report and therefore 
did not agree with our observation that the costs were "understated". 
DOD also stated it had revised its September 2005 cost-of-war report to 
reflect these obligations. However, since DOD has already issued and 
provided us with an amended September 2005 cost-of-war report including 
the about $1.1 billion in fiscal year 2005 obligations, we believe this 
fulfills the intent of our recommendation and removed the 
recommendation from the final report. DOD's comments and our evaluation 
of them can be found at the end of this report. DOD's comments are 
reprinted in appendix III. 

In addition, since it is likely significant multiyear procurement 
funding from fiscal year 2006 will remain available in fiscal year 
2007, we have included a matter for congressional consideration. 
Congress should consider requiring DOD to provide information on how 
much procurement funding remains available for obligation at the 
conclusion of the fiscal year and how the department intends to 
obligate this funding and any other procurement funding received or 
requested for GWOT in fiscal year 2007 and beyond. DOD also did not 
agree with our matter for congressional consideration, stating that it 
has plans for reconstituting forces deployed in the war on terror and 
that it is not reasonable to infer that these funds are available for 
other purposes. We do not believe that our report implies that any 
previously appropriated procurement funding is available for other 
purposes. On the contrary, we stated that significant multiyear funds 
will remain available at the end of fiscal year 2006 for procurement 
purposes. Given that DOD received more procurement funding with the 
enactment of the fiscal year 2007 defense appropriation and 
authorization bills and is expected to request more in a fiscal year 
2007 supplemental appropriation, we believe it is important that 
Congress have a complete picture of all funding DOD has available for 
procurement purposes when considering future appropriations requests 
from DOD and have retained the matter. 

Background: 

After the terrorist attacks of September 11, 2001, the President 
announced a Global War on Terrorism requiring the collective 
instruments of the entire federal government to counter the threat of 
terrorism. Military operations to combat terrorism began with Operation 
Noble Eagle, which is aimed at defending the United States homeland 
against terrorist attacks, and Operation Enduring Freedom (OEF), which 
takes place principally in and around Afghanistan, but also covers 
additional operations in the Horn of Africa, the Philippines, and 
elsewhere.[Footnote 12] In 2003, the United States began Operation 
Iraqi Freedom (OIF), which takes place principally in Iraq. These 
operations involve a wide variety of activities such as combating 
insurgents, training the military forces of other nations, and 
conducting small-scale reconstruction and humanitarian relief projects. 
DOD and the military services are responsible for carrying out these 
operations. 

To fund these operations in fiscal year 2006, Congress provided DOD 
with funding for GWOT as part of its annual appropriations, known as 
"Title IX" or "bridge" funding, and through supplemental 
appropriations. This funding totaled about $114.4 billion, of which 
about $93.3 billion went to the military services' three major 
appropriations accounts: military personnel, operation and maintenance, 
and procurement. The remaining funds provided, about $21.1 billion, 
were for defensewide agencies; research, development, test and 
evaluation; and military construction. As shown in table 1, the 
military services received about $15.9 billion for military personnel, 
about $55.9 billion for operation and maintenance, and about $21.5 
billion for procurement. 

Table 1: Fiscal Year 2006 Appropriations Identified for GWOT for the 
Military Services: 

Dollars in billions. 

Military Personnel: Title IX; 
Army: $ 5.1; 
Navy: $ 0.1; 
Marine Corps: $ 0.5; 
Air Force: $ 0.5; 
Totals: [Empty].  

Military personnel: Supplemental; 
Army: 6.8; 
Navy: 0.9; 
Marine Corps: 0.8; 
Air Force: 1.2; 
Totals: [Empty]. 

Military Personnel: Total; 
Army: 11.9; 
Navy: 1.0; 
Marine Corps: 1.3; 
Air Force: 1.7; 
Totals: $ 15.9.  

Operation and maintenance: Title IX; 
Army: 21.6; 
Navy: 1.8; 
Marine Corps: 1.9; 
Air Force: 2.5; 
Totals: [Empty]. 

Operations and maintenance: Supplemental; 
Army: 18.0; 
Navy: 2.8; 
Marine Corps: 1.7; 
Air Force: 5.6; 
Totals: [Empty]. 

Operations and maintenance: Total; 
Army: 39.6; 
Navy: 4.6; 
Marine Corps: 3.6; 
Air Force: 8.1; 
Totals: 55.9. 

Procurement: Title IX; 
Army: 4.6; 
Navy: 0.3; 
Marine Corps: 1.7; 
Air Force: 0.1; 
Totals: [Empty]. 

Procurement: Supplemental; 
Army: 9.0; 
Navy: 1.0; 
Marine Corps: 2.6; 
Air Force: 2.2; 
Totals: [Empty]. 

Procurement: Total; 
Army: 13.6; 
Navy: 1.3; 
Marine Corps: 4.3; 
Air Force: 2.3; 
Totals: 21.5. 

Grand total; 
Army: [Empty]; 
Navy: [Empty]; 
Marine Corps: [Empty]; 
Air Force: [Empty]; 
Totals: 93.3. 

Source: GAO analysis of Pub. L. No. 109-148 (2005) and Pub. L. No. 109- 
234 (2006). 

Note: Totals may not compare to those in the report due to rounding. 

[End of table] 

In addition to the funds appropriated to the military services, since 
2003 Congress has also appropriated funds to the Iraqi Freedom Fund 
(IFF), a special account providing funds available for 2 fiscal years 
and that can be transferred to the military services' appropriations 
accounts. DOD may transfer funds from the IFF to other accounts to 
cover additional expenses for ongoing military operations in Iraq, 
operations authorized by the Authorization for Use of Military 
Force,[Footnote 13] and other operations and related activities in 
support of GWOT. In fiscal year 2006 through June, DOD had transferred 
about $3.7 billion of the funds originally appropriated to the IFF into 
the military services' appropriations accounts, most of which were to 
cover the expenses for classified programs and to defeat improvised 
explosive devices. 

For fiscal year 2006 through June, DOD has reported total obligations 
of about $63 billion for GWOT, including about $54 billion for OIF and 
about $9 billion for OEF. DOD began the fiscal year operating under a 
continuing resolution[Footnote 14] and legislation providing the $49 
billion bridge funding was not passed until December 2005, causing the 
services to curtail spending early in the fiscal year. Additionally, 
military service officials stated they had anticipated receiving 
supplemental appropriations in May, but since this funding was not 
appropriated until June, the military services took steps to reduce 
costs until supplemental funds were received, including postponing 
payment of bills and delaying certain maintenance activities. Appendix 
II contains an explanation of DOD's process for reporting obligations. 

Between September 2001 and June 2006, Congress provided DOD with about 
$381 billion in supplemental and annual appropriations for military 
operations in support of GWOT. DOD reported total obligations[Footnote 
15] of about $287 billion for overseas GWOT-related activities from 
September 2001 through June 2006, including about $227 billion for 
operations in Iraq and about $60 billion for operations in Afghanistan, 
the Horn of Africa, the Philippines, and elsewhere. In addition to 
overseas obligations, DOD reported about $27.7 billion in obligations 
related to defense of the U.S. homeland from 2001 through June 2006. 

Fiscal Year 2006 Rates of Obligations Are Within Funding Levels and 
Significant Multiyear Procurement Funds Will Likely Remain Available 
for Use in Fiscal Year 2007: 

Our analysis of reported obligations and the military services' 
forecasts of their likely costs for fiscal year 2006 suggest that the 
rates of obligation for military personnel and operation and 
maintenance are within fiscal year 2006 GWOT funding levels and 
significant amounts of multiyear procurement funds will likely remain 
available for use in fiscal year 2007. As of June, the military 
services reported obligating about 85 percent of military personnel 
funds and 60 percent of operation and maintenance funds. Fiscal year 
2006 rates of obligation for military personnel for GWOT are within 
GWOT funding levels for all military services except the Army, due 
primarily to increased recruitment and retention incentives offered by 
the Army to assist in manning the force during GWOT and increased death 
gratuity benefits provided in the National Defense Authorization Act 
for fiscal year 2006. The military services' rates of obligation for 
operation and maintenance for GWOT are within fiscal year 2006 GWOT 
funding levels for all military services, although they curtailed 
spending in multiple categories due to uncertainty relating to receipt 
of supplemental funding. For fiscal year 2006, the GWOT procurement 
funds appropriated to the military services are largely expected to 
remain unobligated and will remain available in fiscal year 2007. 
Procurement funds may remain available in future fiscal years because 
they are available for obligation over multiple years. 

Fiscal Year 2006 Rates of Obligation for Military Personnel for GWOT 
Are Within GWOT Funding Levels for All Military Services Except the 
Army: 

Fiscal year 2006 rates of obligation for military personnel for GWOT 
are within GWOT funding levels for all military services except the 
Army. The Army experienced higher than anticipated obligations for 
military personnel due primarily to increased recruitment and retention 
incentives offered to assist in manning the force during GWOT and 
increased death gratuity benefits provided in the National Defense 
Authorization Act for fiscal year 2006. To avoid a problem in the last 
quarter of the fiscal year, the Army included a transfer action in the 
so-called fiscal year 2006 omnibus reprogramming request DOD submitted 
to Congress. This action transfers about $591 million in funds from 
various appropriation accounts to the Army's military personnel account 
and fund the Army's remaining military personnel needs for fiscal year 
2006. As figure 1 shows, after 9 months, or 75 percent of the fiscal 
year, the Army reported obligations of 91 percent, the Navy 63 percent, 
the Marine Corps 72 percent, and Air Force 68 percent of available GWOT 
appropriations. 

Figure 1: Military Services' Fiscal Year 2006 Reported GWOT Military 
Personnel Obligations of Appropriations Identified for GWOT through 
June 2006: 

[See PDF for image] 

Source: GAO analysis of DOD data. 

Notes: June 2006 represents 75 percent of the fiscal year and is an 
indication of where DOD would be if it had obligated its available 
funding equally each month throughout the fiscal year. Reported 
obligations include those from both the active and reserve components. 
We have previously assessed the reliability of DOD's obligations data 
and found that while the data we report reflect the data used by DOD to 
advise Congress on the cost of the war, they may not accurately reflect 
the true dollar value of GWOT obligations. 

[End of figure] 

Fiscal Year 2006 Rates of Obligation for Operation and Maintenance for 
GWOT Are Within Fiscal Year 2006 GWOT Funding Levels for All Military 
Services: 

The military services' rates of obligation for operation and 
maintenance for GWOT are within fiscal year 2006 GWOT funding levels 
for all military services. As shown in figure 2, after 9 months, or 75 
percent of the fiscal year, the Army reported obligations of 61 
percent, the Navy 49 percent, the Marine Corps 58 percent, and the Air 
Force 62 percent of available GWOT appropriations. The military 
services' reported GWOT operation and maintenance obligations are less 
than anticipated because they curtailed spending at the beginning of 
the year due to uncertainty relating to the receipt of supplemental 
funding. For example, sustainment contracts in Iraq, Afghanistan, and 
Kuwait were scaled back due to the unpredictability of fiscal year 2006 
funding. In addition, Army officials stated that contracts for selected 
base closures and restructuring in Iraq have been scaled back due to 
the security environment. As previously stated, the Navy is reporting 
lower than anticipated obligations for operation and maintenance 
because many Navy components took steps to reduce spending early in the 
fiscal year. For example, Navy officials stated that they withheld 
payment of certain operations bills, such as transportation, and 
deferred obligations for depot maintenance to stay within available 
funding as the military services awaited receipt of supplemental 
funding. 

Figure 2: Military Services' Fiscal Year 2006 Reported GWOT Operation 
and Maintenance Obligations of Appropriations Identified for GWOT 
through June 2006: 

[See PDF for image] 

Source: GAO analysis of DOD data. 

Notes: June 2006 represents 75 percent of the fiscal year and is an 
indication of where DOD would be if it had obligated its available 
funding equally each month throughout the fiscal year. Reported 
obligations include those from both the active and reserve components. 
We have previously assessed the reliability of DOD's obligations data 
and found that while the data we report reflect the data used by DOD to 
advise Congress on the cost of the war, they may not accurately reflect 
the true dollar value of GWOT obligations. 

[End of figure] 

GWOT Appropriations for Procurement in Fiscal Year 2006 Will Largely 
Remain Unobligated and Remain Available for Future Fiscal Years: 

For fiscal year 2006, the GWOT procurement funds appropriated to the 
military services are largely expected to remain unobligated and will 
remain available in future fiscal years. Procurement funds can remain 
available for future fiscal years because they generally are available 
for obligation over multiple years. For fiscal year 2006, the military 
services received about 32 percent ($6.8 billion) of procurement 
funding in Title IX as part of the annual appropriation and 68 percent 
($14.7 billion) in the supplemental appropriation. As of June the 
military services have spent about 68 percent of the procurement funds 
received through Title IX. 

We project that DOD's procurement obligations will remain low in fiscal 
year 2006 for two reasons. First, the majority of the fiscal year 2006 
procurement appropriations were provided in the GWOT supplemental 
appropriation, which the military services did not receive until June 
2006. Second, officials stated that supplemental funds had been 
expected in May 2006 but were not received until June 2006 and the time 
required to negotiate new procurement contracts may prevent the 
military services from obligating much of their procurement funds prior 
to the end of fiscal year 2006. As a result, significant procurement 
funds will remain available in fiscal year 2007. Figure 3 shows, the 
percentage of the total available GWOT procurement appropriations 
obligated through June 2006. According to military service officials, 
they expect higher procurement obligations late in fiscal year 2006 and 
into early fiscal year 2007. At the time of this report, DOD had only 
reported obligations through June 2006; therefore, we were unable to 
determine how much funding would remain at the end of the fiscal year. 
DOD received more procurement funding with the enactment of the fiscal 
year 2007 defense appropriation bill. Since it is likely that much of 
the procurement funding from fiscal year 2006 will remain available in 
fiscal year 2007, knowledge of what those available amounts are and how 
DOD plans to spend them would assist congressional decision makers in 
determining DOD's future funding needs. 

Figure 3: Military Services' Fiscal Year 2006 Reported GWOT Procurement 
Obligations of Appropriations Identified for GWOT through June 2006: 

[See PDF for image] 

Source: GAO analysis of DOD data. 

Notes: Reported obligations include those from both the active and 
reserve components. We have previously assessed the reliability of 
DOD's obligations data and found that while the data we report reflect 
the data used by DOD to advise Congress on the cost of the war, they 
may not accurately reflect the true dollar value of GWOT obligations. 

[End of figure] 

DOD and the Military Services Have Taken Specific Steps Intended to 
Improve GWOT Cost Reporting Procedures and Data Reliability; Some 
Problems Remain: 

DOD and the military services have taken specific steps intended to 
improve the accuracy and reliability of their reported GWOT obligation 
data. Some problems remain with transparency over certain costs and 
inaccuracies in reported obligations. The DOD Comptroller has 
established new monthly variance reporting and affirmation 
requirements, and the military services have improved the accuracy of 
some of their reported obligations. In addition to these efforts, 
further improvements are needed in the cost reporting process. For 
example, existing cost reporting procedures do not provide transparency 
and visibility over certain GWOT obligations because DOD and the 
military services continue to report large obligations in miscellaneous 
"other" categories that provide little insight on how those funds have 
been spent. We also continue to find inaccuracies in the overall 
reported GWOT obligations due to unreported obligations related to the 
training and equipping of Afghan and Iraqi security forces. Until DOD 
takes steps to address these problems, it will continue to be difficult 
for Congress and DOD to reliably know how much the war is costing, 
examine details on how appropriated funds are being spent, or have 
historical information useful to determine future funding needs. 

DOD and the Military Services Have Established New Monthly Variance 
Reporting and Affirmation Requirements, and Have Improved the Accuracy 
of Some Reported Obligation Data: 

The DOD Comptroller has established new monthly variance reporting and 
affirmation requirements intended to improve GWOT cost reporting 
procedures, and the military services have improved the accuracy of 
some reported obligations. Specifically, in response to our previous 
recommendation to improve the accuracy and reliability of reported GWOT 
obligation data, the DOD Comptroller, in August 2005, issued 
guidance[Footnote 16] to the secretaries of the military services and 
the directors of the defense agencies to help DOD components more 
accurately and consistently report obligations for contingencies such 
as GWOT. This guidance directed DOD components to perform a monthly 
variance analysis to review and validate that their reported 
obligations are accurate and provide a fair representation of ongoing 
activities, and to include an explanation of variances that exceed a 
certain threshold.[Footnote 17] Thresholds triggering the variance 
analysis review differ by cost category. 

DOD components were directed to use, to the fullest extent possible, 
actual obligation data as captured in the official accounting systems. 
When obligation data were not available in the accounting system, then 
an auditable alternative methodology was to be established providing 
explanation of all sources used to capture the data other than official 
accounting systems. For example, when using alternate data sources, 
DOD's variance analysis guidance requires each DOD component to provide 
detail on the type or description of the cost, the cost category 
impacted, an explanation of why data are not available from the 
accounting system, a description of the criteria or methodology used to 
calculate costs, and the mechanism used to track these costs. Each of 
the military services directed its major and subordinate commands to 
complete the monthly variance analysis, and submit the analysis to the 
command level, where financial management officials are expected to 
review obligations data for discrepancies. In early fiscal year 2006, 
DOD set up a task force under the leadership of the DOD Comptroller to 
develop and refine DOD's efforts to improve the reliability of its 
reported obligations, including the variance analyses. This task force 
includes representatives from each of the military services' financial 
management and comptroller offices, as well as representatives from 
Defense Finance and Accounting Service. 

DOD began including the variance analyses with the November 2005 DOD 
Supplemental and Cost of War Execution Report. In reviewing the 
variance analysis submissions since then, we have noted improvements in 
both the variance analysis submissions as well as the explanations 
provided on the use of alternate data sources. Military service 
officials stated that the variance analysis highlighted several 
problems and allowed them to correct the mistakes before submitting 
their reports to the DOD Comptroller for inclusion in the monthly DOD 
Supplemental and Cost of War Execution Report. In June 2006, DOD issued 
revised guidance[Footnote 18] for analyzing obligations for contingency 
operations based on the experiences of the DOD components with the 
variance analysis over the last several months. 

Because efforts to implement the variance analysis are still in the 
early stages, we have not fully evaluated the impact of this new 
initiative on cost reporting. However, in reviewing the June 2006 
variance submission, we identified two examples of where additional 
explanation could be provided. For example, in reviewing the Air 
Force's June 2006 variance report for military personnel obligations-- 
which includes imminent danger pay, hardship duty pay, and family 
separation pay--we found that the Air Force had used an alternative 
data source, but provided limited explanation as to the criteria and 
methodology it used to track these obligations. Our past work has shown 
significant problems with DOD's reported obligations data, in 
particular its military personnel obligations, including imminent 
danger pay. Upon discussion with Air Force officials, they recognized 
that their explanation could be expanded to provide further 
clarification. We also found problems with the explanations provided 
for variances in the Marine Corps' June 2006 operation and maintenance 
obligations for GWOT. For example, the Marine Corps reported that its 
obligations for transportation in support of OEF had decreased by 81 
percent, due to the refinement of transportation obligations in 
previous months. However, no further explanation is provided as to what 
types of refinements were made and how these refinements resulted in 
reductions in obligations. Similarly, the Marine Corps Reserve reported 
that its obligations for personnel support for OIF had changed by 900 
percent due to a realignment of expenses. However, no explanation is 
provided as to where the obligations were realigned and why the 
realignment was made. Marine Corps officials subsequently stated that 
the variance explanation for transportation was not fully addressed due 
to an administrative oversight and the variance explanation for 
personnel support was not provided because, in their view, the small 
obligations reported, totaling $1000, which is associated with the 
variance, did not warrant explanation. Because the variance analysis 
process is relatively new, we are not making recommendations at this 
time, but will continue to monitor this process in the future. 

Furthermore, to help ensure that the obligations for contingency 
operations being reported were as accurate as possible, DOD developed 
an affirmation process. In March 2006, the DOD Comptroller issued 
initial guidance[Footnote 19] directing submitting DOD components to 
attest to the accuracy of their monthly obligation data contained in 
DOD's Supplemental and Cost of War Execution Report and affirm that the 
report provides a fair representation of ongoing activities. The 
affirmation was to accompany the monthly GWOT cost report and would be 
provided to the Defense Finance and Accounting Service by the 
comptroller or financial manager of the associated DOD component. 
However, shortly thereafter, the DOD Comptroller instructed the 
military services to delay submission of their affirmation memos until 
revised guidance could be issued. Revised guidance was issued in late 
June 2006, to allow for further delegation of the affirmation 
authority. All other requirements for the affirmation were unchanged. 
Specifically, DOD's guidance now requires that each military service's 
Assistant Secretary for Financial Management & Comptroller, the Deputy, 
or the Director for Budget provide the affirmation. However, we note 
that it does not contain criteria or factors that could be considered 
during the review process. In discussions with military service 
officials, some military services are relying on the judgment of their 
major and subordinate commands that the costs are indeed accurate as a 
basis for their affirmation, while others have instituted additional 
management reviews of the reported costs. Because this affirmation 
process is new, we are making no recommendations regarding the process 
at this time, but will continue to monitor this process in the future. 

Finally, we found that the Army made improvements to the accuracy of 
its imminent danger pay reporting shortly after the issuance of our 
September 2005 report and DOD's guidance regarding the analysis of 
contingency operations costs. As part of our work last year, we 
conducted limited testing of military personnel obligations data and 
reported wide monthly swings in imminent danger pay with little 
correlation to the numbers of deployed personnel.[Footnote 20] Reported 
imminent danger pay obligations for GWOT should correlate to the 
approximate number of deployed forces in eligible areas.[Footnote 21] 
In our September 2005 report we noted a reporting discrepancy for DOD's 
reported imminent danger pay in fiscal year 2004. The reported 
obligations suggested that more than 1 million personnel were deployed 
in support of OIF and OEF, while according to DOD only about 221,300 
personnel from all the military services were deployed. DOD was able to 
identify the accounting error and provide a revised obligations figure. 
Our analysis of reported Army imminent danger pay for fiscal year 2006 
through May 2006 shows that the accuracy of these data improved, with 
reduced monthly swings and closer correlation to the actual number of 
deployed personnel. 

Cost Reporting Procedures Do Not Provide Visibility and Transparency 
over Certain Obligations: 

Existing cost reporting procedures do not provide visibility and 
transparency over certain obligations because DOD continues to obligate 
large amounts of funds in miscellaneous "other" categories that provide 
little insight on how those funds have been spent. For example, in 
fiscal year 2005, close to 26 percent of obligations reported in the 
operation and maintenance account were in "other supplies and 
equipment" and "other services and miscellaneous contracts."[Footnote 
22] This trend has continued in fiscal year 2006. As shown in table 2, 
from fiscal year 2001 through June of fiscal year 2006, DOD has 
reported operation and maintenance obligations in the cost reports of 
$26.5 billion for "other services and miscellaneous contracts" and 
obligations of $23.9 billion for "other supplies and equipment." During 
this time frame, DOD has reported military personnel obligations of 
about $15.7 billion for "other military personnel." 

Table 2: DOD's Six Largest Obligation Categories from Fiscal Year 2001 
through Fiscal Year 2006 (June): 

Dollars in thousands. 

Category: Reserve components called to active duty; 
FY 2005: $8,398,240; 
FY 2006 as of June: $6,033,225; 
Total FY 2001 to June 2006: $37,809,078. 

Category: Operation OPTEMPO (fuel, petroleum, oils, lubricants, and 
spare parts); 
FY 2005: 8,344,809; 
FY 2006 as of June: 7,964,114; 
Total FY 2001 to June 2006: 34,024,022. 

Category: Facilities/base support; 
FY 2005: 9,118,936; 
FY 2006 as of June: 5,982,880; 
Total FY 2001 to June 2006: 28,885,801. 

Category: Other services/miscellaneous contracts; 
FY 2005: 6,609,012; 
FY 2006 as of June: 2,979,547; 
Total FY 2001 to June 2006: 26,584,689. 

Category: Other supplies & equipment; 
FY 2005: 6,250,765; 
FY 2006 as of June: 3,901,483; 
Total FY 2001 to June 2006: 23,982,627. 

Category: Other military personnel; 
FY 2005: 2,541,957; 
FY 2006 as of June: 3,792,359; 
Total FY 2001 to June 2006: 15,775,832. 

Source: GAO's analysis of DOD's reported GWOT data. 

Note: The reported obligations in this chart include obligations for 
Operation Noble Eagle, Operation Enduring Freedom, and Operation Iraqi 
Freedom. 

[End of table] 

We have previously stated our concerns that while the miscellaneous 
"other" categories defined in DOD's Financial Management Regulation 
provide a uniform framework for capturing obligations, they do not 
provide the specificity or transparency needed for Congress and others 
to understand clearly how funds appropriated for contingency operations 
are being used, particularly since these categories involve billions of 
dollars in reported obligations. We have reported for several years, 
and as recently as July 2004, that large amounts of reported 
obligations for GWOT are in miscellaneous "other" categories in both 
the operation and maintenance and the military personnel 
accounts.[Footnote 23] For example, in our report on fiscal year 2003 
funding[Footnote 24] we pointed out that almost 35 percent of 
obligations reported in the operation and maintenance account were in 
"other supplies and equipment" and "other services and miscellaneous 
contracts." We previously recommended that DOD revise its cost 
reporting guidance so that the use of miscellaneous "other" categories 
is minimized when reporting obligations. 

In response to our recommendations, in January 2005, DOD expanded the 
cost categories for contingency operations in the DOD Financial 
Management Regulation to include an additional category for military 
personnel obligations related to active component end strength. These 
obligations had previously been recorded in the "other military 
personnel" category. However, DOD did not refine reporting of the other 
miscellaneous obligations in DOD's cost-of-war reports. On its own 
initiative, the Army has taken some steps to provide better 
transparency over the operation and maintenance obligations previously 
reported in the "other services and miscellaneous contracts" category. 
Specifically, it has revised its reporting methodology to redirect some 
of its contracting obligations into other reporting categories more 
directly tied to the contracted activity. For example, the Army is now 
reporting obligations for information technology contracts tied to 
DOD's Projects and Contracting Office[Footnote 25] under the command, 
control, communications, computers, and intelligence cost category. It 
has also begun reporting contract obligations associated with the 
special technical inspection and repair process at the Army's Aviation 
and Missile Command under the reporting category for intermediate level 
maintenance. However, the Navy, Marine Corps, and Air Force have yet to 
take similar steps. On the basis of our work, in October 2006 DOD 
updated its guidance on the reporting of obligations in miscellaneous 
"other" categories to more fully reflect these obligations. 

Inaccuracies in Reported GWOT Obligations Continue to Exist: 

We continue to find inaccuracies in the overall reported GWOT 
obligations. For example, DOD had not reported certain obligations tied 
to the training and equipping of Afghan and Iraqi security forces in 
fiscal year 2005. Based on our work, DOD has since taken corrective 
action. In September 2005, DOD issued an update to the DOD Financial 
Management Regulation governing contingency operations, adding an 
additional cost reporting category called "Other Support Costs," in the 
DOD Supplemental and Cost of War Execution Report.[Footnote 26] This 
"Other Support Costs" category includes obligations such as the 
reimbursement of coalition countries for logistical and military 
support, lift and sustainment for coalition partners during military 
operations, training and equipping the Afghan National Army and the 
Armed Forces of Iraq, and obligations tied to the Commander's Emergency 
Response Program. [Footnote 27] 

At the time of a draft of this report, DOD had not yet reported 
obligations tied to the training and equipping of Afghan and Iraqi 
security forces for fiscal year 2005. While DOD has begun reporting 
obligations incurred for these activities in fiscal year 2006, the DOD 
Comptroller's office had not amended its previously reported 
obligations for fiscal year 2005 to include these obligations. 
According to DOD officials, because the funds for these purposes became 
available later in the fiscal year, DOD did not have a reporting format 
in the cost-of-war reports for these obligations and planned to amend 
its September 2005 cost-of-war report at some point to reflect them. 
For example, DOD had not reported more than $1.1 billion in obligations 
tied to these categories, the majority of which is for the Armed Forces 
of Iraq. Excluding these obligations from the cost-of-war reports 
understates DOD's total GWOT obligations for fiscal year 2005, and 
limits Congress's visibility over DOD's total fiscal year 2006 GWOT 
requirements. However, in October 2006, DOD did amend the September 
2005 cost-of-war report to reflect the $1.1 billion in fiscal year 2005 
obligations. 

In reviewing the Army's fiscal year 2006 obligations to finance the 
training and equipping of the Afghan National Army, we found that the 
obligations reported by the Army in DOD's GWOT cost reports were being 
understated between the October 2005 and March 2006 cost reports, when 
compared to the Office of Management and Budget's (OMB) SF 133 Report 
on Budget Execution and Budgetary Resources[Footnote 28] for the same 
time period. In total, we found that the Army had understated 
obligations by almost $371 million. In discussions with the DOD 
Comptroller, we pointed out that the obligations data being reported to 
OMB were different from the data being reported to DOD for its GWOT 
cost-of-war report. According to DOD Comptroller officials, prior to 
fiscal year 2005 appropriations for the training and equipping of the 
Afghan National Army flowed to the Defense Security Cooperation Agency 
for obligation through the Foreign Military Sales program. After the 
Afghanistan Security Forces Fund was established in fiscal year 2005, 
the Defense Security Cooperation Agency began transferring the funds 
directly to the Foreign Military Sales program for use by the Army. 
Additionally, the DOD Comptroller noted that upon transfer from the 
Afghanistan Security Forces Fund, DOD and OMB consider these funds 
fully obligated, since the funds will not be spent elsewhere. However, 
the Defense Security Cooperation Agency and the Army were not reporting 
the transferred amounts as obligations, but were instead reporting the 
amount of funds disbursed through the Foreign Military Sales program. 
The Army's lower obligation data were appearing in DOD's Supplemental 
and Cost of War Execution Report from October 2005 through March 2006. 
Once this matter came to light, DOD Comptroller officials took action 
to reflect the accurate obligations against the Afghanistan Security 
Forces Fund. The April 2006 report reflects the corrected cumulative 
obligations through April 2006. 

Conclusions: 

While the military services expect increases in the amount of reported 
obligations for procurement in the last month of fiscal year 2006, much 
of this multiyear funding will remain available in fiscal year 2007. 
Since it is likely that much of the procurement funding from fiscal 
year 2006 will remain available in fiscal year 2007, knowledge of those 
amounts and how DOD plans to spend them would ensure congressional 
decision makers have additional information to use in determining DOD's 
future funding needs. While DOD has taken steps to improve its cost 
reporting procedures and the reliability of its reported GWOT 
obligation data, lack of transparency and inaccuracies in reported GWOT 
obligations continue to exist. The large obligations in miscellaneous 
categories do not provide decision makers with transparency over how 
those funds have been spent, while underreported obligations understate 
DOD's total GWOT obligations. Until DOD and the military services 
revise their cost reporting procedures to address these problems, it 
will continue to be difficult for the public, Congress, and DOD to 
reliably know how much the war is costing, examine details on how 
appropriated funds are being spent, or have historical information 
useful in determining future funding needs. 

Matter for Congressional Consideration: 

When conducting its deliberations over DOD's funding needs, Congress 
should consider requiring DOD to provide fiscal year-end information on 
how much procurement funding remains available for obligation at the 
conclusion of fiscal year 2006. Congress should also require DOD to 
provide a plan detailing how the department intends to obligate this 
funding and any other procurement funding received or requested for 
GWOT for fiscal year 2007 and beyond. 

Agency Comments and Our Evaluation: 

In written comments on a draft of this report, DOD agreed with one 
recommendation made in the draft report and disagreed with the second. 
DOD also provided technical comments and we have incorporated them in 
the report as appropriate. 

DOD agreed with our recommendation that Volume 12, Chapter 23 of the 
DOD Financial Management Regulation be revised to provide additional 
subcategories for "other supplies and equipment," "other services and 
miscellaneous contracts," and "other military personnel" to provide 
further breakdown of reported obligations in miscellaneous categories. 
DOD further stated that it has updated the DOD Financial Management 
Regulation to expand the cost categories of the data reported in its 
monthly Supplemental and Cost of War Execution Reports. This guidance, 
issued in October 2006, adds elements that expand these "other" cost 
categories into more descriptive subcategories that provide additional 
details on DOD's reported obligations for pay and allowances, permanent 
changes of station, temporary storage, supplies and equipment and 
contract services. We believe this meets the intent of our 
recommendation and removed the recommendation from the final report. 

DOD did not agree with the basis of our recommendation that it amend 
the September 2005 version of DOD's Supplemental and Cost of War 
Execution Report to include about $1.1 billion in unreported fiscal 
year 2005 obligations tied to the training and equipping of Afghan and 
Iraqi security forces. In its comments, DOD stated that this 
information was provided to Congress in an October 2005 report pursuant 
to Section 9010 of the Department of Defense Appropriations Act, 
2005[Footnote 29] and therefore did not agree with our observation that 
the fiscal year 2005 costs of the war were "understated" by $1.1 
billion. However, DOD stated it did amend the September 2005 cost-of- 
war report to include the $1.1 billion in fiscal year 2005 obligations, 
as we recommended, and noted this in their comments. We recognize that 
DOD did report some of these obligations to Congress in this October 
2005 report entitled Report on the Military Operations of the Armed 
Forces and the Reconstruction Activities of the Department of Defense 
in Iraq and Afghanistan. However, in reviewing the obligation figures 
included in this report, we note these figures do not match those 
reported in DOD's amended September 2005 cost-of-war report and the 
Office of Management and Budget's (OMB) SF 133 Report on Budget 
Execution and Budgetary Resources for fiscal year 2005. According to a 
DOD official, the figures in DOD's October 2005 report were preliminary 
and did not reflect all technical adjustments. Furthermore, this 
official stated that reports pursuant to Section 9010 no longer include 
obligations against the Afghan and Iraqi security forces funds because 
these obligation figures are being reported in DOD's monthly 
Supplemental and Cost of War Execution Reports. As we discuss in this 
report, DOD's monthly Supplemental and Cost of War Execution Report is 
used by senior DOD leadership, along with other information, in 
evaluating costs of the war and formulating future budget requests to 
fund GWOT. Since this document does provide historical data with which 
to evaluate the costs of the war and advise Congress, we believe it is 
important that DOD include all GWOT related obligations in these 
reports. Since DOD has already issued and provided us with an amended 
September 2005 cost-of-war report including the about $1.1 billion in 
fiscal year 2005 obligations, we believe this fulfills the intent of 
our recommendation and removed the recommendation from the final 
report. 

With respect to our suggestion that Congress consider requiring DOD to 
provide fiscal year-end information on how much procurement funding 
remains available for obligation at the conclusion of fiscal year 2006 
and require DOD to provide a plan detailing how the department intends 
to obligate this funding and any other procurement funding received or 
requested for GWOT in fiscal year 2007 and beyond, DOD commented that 
it has plans for reconstituting forces deployed in the war on terror 
and that it is not reasonable to infer that these funds are available 
for other purposes. DOD further stated that it had justified the 
procurement requirements to Congress and already provides reports that 
clearly state the status of obligations for all GWOT funds. We do not 
believe that our report implies that any previously appropriated 
procurement funding is available for other purposes. On the contrary, 
we stated that significant multiyear funds will remain available at the 
end of fiscal year 2006 for procurement purposes. Given that DOD 
received more procurement funding with the enactment of the fiscal year 
2007 defense appropriation bill and is expected to request more in a 
fiscal year 2007 supplemental appropriation, we believe it is important 
that Congress have a complete and up-to-date picture of all funding DOD 
has available for procurement purposes when considering future 
appropriations requests from DOD. 

We are sending copies of this report to other interested congressional 
committees; the Secretary of Defense; the Under Secretary of Defense 
(Comptroller); and the Director, Office of Management and Budget. 
Copies of this report will also be made available to others upon 
request. In addition, this report will be available at no charge on the 
GAO Web site at [Hyperlink, http://www.gao.gov]. 

If you have any questions regarding this report, please contact me at 
(202) 512-9619 or pickups@gao.gov. Contact points for our Offices of 
Congressional Relations and Public Affairs may be found on the last 
page of this report. GAO staff who made major contributions to this 
report are listed in appendix IV. 

Signed by: 

Sharon L. Pickup: 
Director, Defense Capabilities and Management: 

List of Congressional Committees: 

The Honorable John Warner: 
Chairman: 
The Honorable Carl Levin: 
Ranking Minority Member: 
Committee on Armed Services: 
United States Senate: 

The Honorable Judd Gregg: 
Chairman: 
The Honorable Kent Conrad: 
Ranking Minority Member: 
Committee on the Budget: 
United States Senate: 

The Honorable Ted Stevens: 
Chairman: 
The Honorable Daniel K. Inouye: 
Ranking Minority Member: 
Subcommittee on Defense: 
Committee on Appropriations: 
United States Senate: 

The Honorable Duncan L. Hunter: 
Chairman: 
The Honorable Ike Skelton: 
Ranking Minority Member: 
Committee on Armed Services: 
House of Representatives: 

The Honorable Jim Nussle: 
Chairman: 
The Honorable John M. Spratt, Jr. 
Ranking Minority Member: 
Committee on the Budget: 
House of Representatives: 

The Honorable C.W. Bill Young: 
Chairman: 
The Honorable John P. Murtha: 
Ranking Minority Member: 
Subcommittee on Defense: 
Committee on Appropriations: 
House of Representatives: 

[End of section] 

Appendix I: Scope and Methodology: 

To compare the military services' reported obligations against 
available funding appropriated for Global War on Terrorism (GWOT) in 
fiscal year 2006, we analyzed applicable annual and supplemental 
appropriations provided to the military services and Department of 
Defense (DOD) reports on GWOT obligations. To identify funding for the 
GWOT, we reviewed applicable annual and supplemental DOD appropriations 
in fiscal year 2006. We also reviewed DOD reports on the transfer or 
reprogramming of funds among various appropriation accounts or budget 
activities to support GWOT. To examine DOD's reported obligations, we 
obtained and analyzed copies of the October 2005 through June 2006 
monthly DOD Supplemental and Cost of War Execution Report from the 
Office of the Under Secretary of Defense (Comptroller) to identify 
reported obligations by operation and by appropriation account for the 
military services. We focused our review on the reported obligation of 
GWOT funds appropriated for military personnel, operation and 
maintenance, and procurement for the Army, Air Force, Navy, and Marine 
Corps, for both active and reserve forces, because they represented 
more than 80 percent of the funds obligated in fiscal year 2006. We 
excluded classified programs from our review because obligations for 
those programs are not reported in DOD's monthly Supplemental and Cost 
of War Execution Report. In addition, for fiscal year 2006, we reviewed 
the latest available obligation data and held discussions with the 
military services on the results of their midyear budget reviews. We 
compared the military services' reported obligations through June 2006, 
the latest available reported obligation data at the time of our 
review, to the supplemental appropriations provided to calculate the 
proportion of funds obligated through June. We then compared those 
proportions to the proportion of the fiscal year that has elapsed 
through June--which represents 75 percent of the fiscal year--to assess 
whether based on obligations through June funding is likely to be 
greater than, less than, or equal to obligations. We also interviewed 
key officials from the Office of the Under Secretary of Defense 
(Comptroller) and the Army, Navy, Marine Corps, and Air Force to 
determine if their projected GWOT obligations are within fiscal year 
2006 funding levels. We recognize that funds are not obligated equally 
each month throughout the fiscal year and that the supplemental 
appropriation funding was not received by the military services until 
June. 

GWOT obligations provided in this report are DOD's claimed obligations 
as reported in DOD's monthly Supplemental and Cost of War Execution 
Report. As previously reported, we found the data in DOD's monthly 
Supplemental and Cost of War Execution Reports to be of questionable 
reliability. Consequently, we are unable to ensure that DOD's reported 
obligations for GWOT are complete, reliable, and accurate, and they 
should therefore be considered approximations. In addition, as recently 
as November 2005, DOD acknowledged that systemic weaknesses with its 
financial management systems and business operations continue to impair 
its financial information. Despite the uncertainty about obligation 
data, we are reporting the information because it is the only way to 
approach an estimate of the costs of the war. Also, despite the 
uncertainty surrounding the true dollar figure for obligations, these 
data are used to advise Congress on the cost of the war. 

To examine the steps DOD has taken to improve the reliability of its 
reported GWOT obligations, we reviewed DOD Financial Management 
Regulation Volume 12, Chapter 23, which establishes DOD's policies and 
procedures for developing contingency budget estimates and cost 
reporting. We analyzed DOD's emergency supplemental budget requests for 
fiscal year 2006, and military service contingency operation financial 
management policies and procedures. We analyzed the fiscal year 2006 
GWOT cost reports and held discussions with the DOD Comptroller and 
military service financial management officials regarding the processes 
used to ensure that GWOT obligation data provided were accurate and 
reliable. We conducted limited testing of the Army's reported military 
personnel obligations, specifically imminent danger pay, and discussed 
our work with officials from the Army Budget Office and DOD 
Comptroller. We also obtained and reviewed information on DOD's budget 
estimates, supplemental requests, budget reprogramming and transfer 
documents, and other supporting documentation. Lastly, we reviewed 
previous GAO reports and testimonies and reports from other agencies 
regarding guidance and oversight of contingency operations costs in 
DOD's accounting systems. As of September 2006, we determined that 
problems with the completeness and accuracy of DOD's reported 
obligations continue and we discuss these problems throughout the 
report. 

We interviewed DOD representatives regarding GWOT obligations and 
funding for fiscal year 2006 and the reliability of cost reporting in 
the following locations: 

* Office of the Under Secretary of Defense (Comptroller), Washington, 
D.C. 

* U.S. Pacific Command, Camp H.M. Smith, Hawaii: 

* Defense Finance and Accounting Service Center, Denver, Colorado: 

* Headquarters, Department of the Army, Washington, D.C. 

* U.S. Army Installation Management Agency, Washington, D.C. 

* U.S. Army Installation Management Agency, Southeast Region, Fort 
McPherson, Georgia: 

* U.S. Army Installation Management Agency, Pacific Region, Fort 
Shafter, Hawaii: 

* Headquarters, U.S. Army Forces Command and Headquarters, Third Army 
(Army Central Command), Fort McPherson, Georgia: 

* Headquarters, U.S. Army Pacific, Fort Shafter, Hawaii: 

* Army Materiel Command, Fort Belvoir, Virginia: 

* Headquarters, 25th Infantry Division, Schofield Barracks, Hawaii: 

* U.S. Army Garrison, Schofield Barracks, Hawaii: 

* Headquarters, U.S. Marine Corps, Washington, D.C. 

* U.S. Marine Corps Forces Pacific, Camp H.M. Smith, Hawaii: 

* Marine Corps Central Command, MacDill AFB, Florida: 

* Department of the Navy, Headquarters, Washington, D.C. 

* Commander, U.S. Pacific Fleet, Pearl Harbor, Hawaii. 

* Military Sealift Command, Washington, D.C. 

* Department of the Air Force, Headquarters, Washington, D.C. 

* U.S. Air Forces Pacific, Hickam Air Force Base, Hawaii: 

* Air Force Air Combat Command, Langley Air Force Base, Virginia: 

* Air Force Air Mobility Command, Scott Air Force Base, Illinois: 

* U.S. Central Command Air Forces, Shaw Air Force Base, South Carolina: 

We performed our work from January 2006 through September 2006 in 
accordance with generally accepted government auditing standards. 

[End of section] 

Appendix II: DOD's Process for Reporting GWOT Obligations: 

Obligations are the foundation of all Global War on Terrorism (GWOT) 
cost reporting. The obligations incurred for military contingency 
operations are referred to as "incremental," which are costs that are 
directly attributable to the operation that would not have been 
incurred if it were not for the operation.[Footnote 30] The reported 
incremental obligations incurred for these military or contingency 
operations include the pay of mobilized reservists as well as the 
special pays and allowances for deployed personnel, such as imminent 
danger pay and foreign duty pay for those personnel serving in 
Operation Iraqi Freedom (OIF) and Operation Enduring Freedom (OEF); the 
cost of transporting personnel and materiel to the theater of operation 
and supporting them upon arrival; and the operational cost of equipment 
such as vehicles and aircraft, among many other obligations.[Footnote 
31] Obligations that are incurred regardless of whether there is a 
contingency operation, such as the base pay of active duty military 
personnel, are not considered incremental. 

When obligations are incurred, the military services enter them into 
their individual accounting systems. An obligation entry includes 
information on the funding source; the operational mission, such as 
OIF; and the category of cost, as determined by the individual military 
service. The Department of Defense's (DOD) financial management 
regulation direct the military services to capture contingency costs, 
which include GWOT obligations, within their existing accounting 
systems and at the lowest possible level of organization. 

To improve the consistency of contingency-cost reporting between the 
multiple military services and agencies, on October 1, 1998, DOD 
implemented a standard contingency cost-breakdown structure. This cost- 
breakdown structure was to facilitate future efforts to understand and 
interpret differences between estimated and actual obligations. 
Examples of cost categories include imminent danger or hostile fire 
pay, facilities/base support, airlift, vehicle procurement, and major 
military construction. Of the common cost categories and multiple 
subcategories listed in DOD financial management regulation, 55 cost 
categories are used to report DOD's monthly GWOT obligations. 

For GWOT cost reporting, individual obligation data that are coded as 
being in support of GWOT are recorded and sent through the military 
services' chain of command where they are aggregated at successively 
higher command levels. Each military service and defense agency 
compiles its reported obligations in the standard contingency cost 
breakdown structure, and sends them to the Defense Finance and 
Accounting Service (DFAS). DFAS aggregates the individual submissions 
into the monthly Supplemental and Cost of War Execution Report. DFAS 
publishes 10 versions of this report on a monthly basis, each of which 
specifies GWOT obligations by operation, appropriation, and appropriate 
DOD component.[Footnote 32] The monthly GWOT cost reports are then 
submitted to the DOD Comptroller for review and further 
dissemination.[Footnote 33] The versions of the report published for 
fiscal year 2006 are listed in table 3. 

Table 3: DOD Supplemental and Cost of War Execution Report for Fiscal 
Year 2006: 

Fiscal years: 
2006 Summary: 
2006 Appropriations. 
2005 Title IX Appropriation (Second Year Execution). 
2005 Iraq Security Forces Fund (Second Year Execution). 
2005 Coalition Support Fund (Second Year Execution). 
2005 Afghanistan Security Forces Fund (Second Year Execution). 
2005 Appropriations (Second Year Execution). 
2004 Title IX Appropriation (Third Year Execution). 
2004 Appropriations (Third Year Execution). 
2003 Appropriations (Fourth Year Execution). 

Source: Defense Finance and Accounting Service. 

[End of table] 

[End of section] 

Appendix III: Comments from the Department of Defense: 

Under Secretary Of Defense: 
1100 Defense Pentagon: 
Washington, DC 20301- 1100: 

Comptroller: 

The Honorable David M. Walker: 
Comptroller General: 
U.S. Government Accountability Office: 
Washington, DC 20548: 

Dear Mr. Walker: 

This is the Department of Defense (DoD) response to the Government 
Accountability Office (GAO) Draft Report GAO-07-76, titled "Global War 
On Terrorism: Fiscal Year 2006 Obligation Rates Are Within Funding 
Levels And Significant Multi-Year Procurement Funds Will Likely Remain 
Available For Use In Fiscal Year 2007." 

The Department of Defense does not concur with one of the 
recommendations for executive action and has taken appropriate action 
to address the second. Enclosed are specific comments on each issue. 
The Department did not "understate" the fiscal year (FY) 2005 cost of 
the war by $1.1 billion because these costs have been reported to 
Congress. The Department included this funding in its October 2005 
report to Congress to comply with Section 9010 of Public Law 10-287, 
the Department of Defense Appropriations Act, 2005. We also have 
provided an amended September FY 2005 Cost of War report including the 
$1.1 billion. The second item, providing additional detail for other 
costs, has also been addressed. We have updated the Department of 
Defense Financial Management Regulation to expand the cost categories 
of the data reported in the Cost of War reports. 

We also do not agree with the recommended matter for congressional 
action regarding procurement. The Department of Defense has plans for 
reconstituting forces deployed in the war on terror over the next 
several years. The majority of the FY 2006 Supplemental funds were 
appropriated in June 2006. These funds are designed to spend out over a 
maximum of 3 years in accordance with a reasonable plan for 
reconstituting forces. It is not reasonable to infer that these funds 
are available for other purposes. 

Thank you for the opportunity to provide the Department's response to 
GAO's recommendations. 

Signed by: 

Tina W. Jonas: 

Enclosure: 
As stated: 

Department of Defense Comments GAO-07-76: 

Subject: GAO Draft Report, titled "Global War On Terrorism: Fiscal Year 
2006 Obligation Rates Are Within Funding Levels And Significant Multi- 
Year Procurement Funds Will Likely Remain Available For Use In Fiscal 
Year 2007." 

Discussion: 

* The GAO report outlined two recommendations for executive action and 
one item for Congressional concern. 

* The Department of Defense nonconcurs with one item for executive 
action and concurs with comment on the other. 

* The findings help highlight problems for corrective action, such as 
insufficient detail for "Other" categories in the Cost Breakdown 
Structure (CBS). 

* The Department nonconcurs on the item for Congressional concern. 

Recommendation 1: The Secretary of Defense revise Volume 12, Chapter 23 
of the DoD Financial Management Regulation to provide additional 
subcategories for "other supplies and Equipment," "other services and 
miscellaneous contracts," and "other military personnel" to provide a 
further breakdown of reported obligation in miscellaneous categories. 

DoD Comment To Recommendation 1: Concur with comment. The Department 
has updated the DoD Financial Management Regulation to expand the 
accuracy of the data reported in the cost reports. The Cost of War 
reports now provide additional details in miscellaneous categories.  

* Pay and allowances: 

* Permanent change of station cost: 

* Costs for temporary storage: 

* Supplies and equipment: 

* Contract services: 

Recommendation 2: The Secretary of Defense should direct the Under 
Secretary of Defense (Comptroller) to amend the September 2005 version 
of DoD's Supplemental and Cost of War Execution reports to include the 
unreported Iraq and Afghan security forces fund obligations for fiscal 
year 2005. 

DoD Comment To Recommendation 2: Non concur. The Department did not 
"understate" the fiscal year (FY) 2005 cost of the war by $1.1 billion 
because these costs have been reported to Congress. The Department 
included this funding in its October 2005 report to Congress to comply 
with Section 9010 of Public Law 10-287, the Department of Defense 
Appropriations Act, 2005. We also have provided an amended September FY 
2005 Cost of War report including the $1.1 billion. 

Matter for Congressional Concern: When conducting its deliberations 
over DoD s funding needs for fiscal year 2007 and beyond, Congress 
should consider requiring DoD to provide fiscal yearend information on 
how much procurement funding remains available for obligation from 
fiscal year 2006. Congress should also require DoD to provide a plan 
detailing how the department intends to obligate these and any other 
procurement funding received or requested for GWOT. 

DoD Comment On Matter for Congressional Concern: Non concur. The 
Department of Defense justified the procurement requirements to 
Congress and is currently executing the approved program. The 
Department of Defense already provides reports that clearly state the 
status of obligations of all GWOT funds. 

[End of section] 

Appendix IV: GAO Contact and Staff Acknowledgments: 

GAO Contact: 

Sharon Pickup (202) 512-9619 or pickups@gao.gov: 

Acknowledgments: 

In addition to the contact named above, Ann Borseth, Assistant 
Director; Richard K. Geiger; Natalie Schneider; Kim Mayo; Renee S. 
Brown; and Lonnie McAllister made key contributions to this report. 

FOOTNOTES 

[1] For purposes of this report, GWOT refers to the ongoing military 
operations overseas. 

[2] Title IX is the section of the annual defense appropriation that 
outlines emergency spending provisions for operations in support of 
GWOT. 

[3] According to Department of Defense Financial Management Regulation, 
7000.14-R, vol. 1, Definitions, p. xvii (December 2001), obligations 
are incurred through actions such as orders placed, contracts awarded, 
services received, or similar transactions made by federal agencies 
during a given period that will require payments during the same or a 
future period. 

[4] DOD defines contingency operations to include small, medium, and 
large-scale campaign-level military operations, including support for 
peacekeeping operations, major humanitarian assistance efforts, 
noncombatant evacuation operations, and international disaster relief 
efforts. 

[5] Volume 12, Chapter 23 of DOD's Financial Management Regulation, 
7000.14R generally establishes financial policy and procedures related 
to DOD contingency operations. Volume 6A, Chapter 2 and Volume 3, 
Chapter 8 of the DOD Financial Management Regulation also include 
provisions to ensure the accuracy of cost reporting. 

[6] GAO, Military Operations: Fiscal Year 2004 Costs for the Global War 
on Terrorism Will Exceed Supplemental, Requiring DOD to Shift Funds 
from Other Uses, GAO-04-915 (Washington, D.C.: July 21, 2004). 

[7] GAO, Global War on Terrorism: DOD Needs to Improve the Reliability 
of Cost Data and Provide Additional Guidance to Control Costs, GAO-05-
882 (Washington, D.C.: Sept. 21, 2005). 

[8] For purposes of this report, we refer to the Office of the Under 
Secretary of Defense (Comptroller) as the DOD Comptroller. 

[9] DOD uses "transfer authority" to shift funds between appropriation 
accounts, for example, between military personnel and operation and 
maintenance. Transfer authority is granted by Congress to DOD usually 
pursuant to specific provisions in authorization or appropriation acts. 
The ability to shift funds within a specific appropriation account, 
like operation and maintenance, is referred to as "reprogramming." In 
general, DOD does not need statutory authority to reprogram funds 
within an account as long as the funds to be spent would be used for 
the same general purpose of the appropriation and the reprogramming 
does not violate any other specific statutory requirements or 
limitations. 

[10] DOD Comptroller, Memorandum: Analysis of Contingency Operation 
Costs (Aug. 30, 2005). 

[11] "Components" refers to all military services and DOD agencies. 

[12] From fiscal year 2001 through fiscal year 2004, military 
operations in defense of the homeland were funded through supplemental 
appropriations. Since fiscal year 2005, DOD has funded these operations 
through its regular annual budget. 

[13] Pub. L. No. 107-40 (Sept. 18, 2001). 

[14] A continuing resolution is a joint resolution enacted by Congress, 
providing budget authority for federal agencies and programs to 
continue in operation until the regular appropriations acts are 
enacted. 

[15] DOD's reported obligations do not include obligations for 
classified activities, which are not captured in DOD's monthly 
Supplemental and Cost of War Execution Report. However, on the basis of 
conference reports for various supplemental appropriations acts, the 
Congressional Budget Office estimates those costs are at least $25 
billion. 

[16] DOD Comptroller, Memorandum: Analysis of Contingency Operation 
Costs (Aug. 30, 2005). 

[17] The DOD components submit their monthly variance reports to the 
Defense Finance and Accounting Service along with their reported 
obligation data. 

[18] DOD Comptroller Memorandum: Revised Instructions for Analysis of 
Contingency Operation Costs (June 13, 2006). 

[19] DOD Comptroller Memorandum: Accuracy of Contingency Operation and 
Disaster Relief Cost Reports (Mar. 3, 2006). 

[20] GAO-05-882. 

[21] As of October 1, 2002, all military personnel--both Active and 
Reserve Component--in areas designated as eligible for imminent danger 
pay receive $225 per month. Such areas include, but are not limited to, 
the countries of Iraq, Afghanistan, Kuwait, Qatar, Bahrain, and Saudi 
Arabia. The monthly amount is payable in full without being prorated or 
reduced, for each month, during any part of which a service member 
qualifies and regardless of the actual period of time served on active 
or inactive duty during that month. 

[22] The percentage of reported obligations in this category includes 
obligations for Operation Noble Eagle, Operation Enduring Freedom, and 
Operation Iraqi Freedom. 

[23] GAO, Military Operations: Fiscal Year 2004 Costs for the Global 
War on Terrorism Will Exceed Supplemental, Requiring DOD to Shift Funds 
from Other Uses, GAO-04-915 (Washington, D.C.: July 21, 2004). 

[24] GAO, Military Operations: Fiscal Year 2003 Funding and Reported 
Obligations in Support of the Global War on Terrorism, GAO-04-668 
(Washington, D.C.: May 13, 2004). 

[25] In May 2004, the President signed National Security Presidential 
Directive 36, which established the Projects and Contracting Office as 
a temporary organization within DOD. The Projects and Contracting 
Office provides acquisition and project management support for the 
reconstruction effort in Iraq. 

[26] These "Other" costs are reported in up to 20 categories and are 
included as subsidiary reports to the Army's and the Defense Security 
Cooperation Agency's DOD Supplemental and Cost of War Execution Report. 

[27] The Commander's Emergency Response Program provides funds to 
military commanders for small-scale reconstruction and humanitarian 
relief projects in Iraq and Afghanistan. 

[28] The Office of Management and Budget's SF 133 Report on Budget 
Execution and Budgetary Resources fulfills the requirement in 31 U.S.C. 
§ 1511 - 1514 that the President review federal expenditures at least 
four times a year. The report provides a basis to determine obligation 
patterns and provide historical reference that can be used to help 
prepare the President's budget, program operating plans, and spend-out 
rate estimates. 

[29] Pub. L. No. 108-287 (Aug. 5, 2004). 

[30] Sections 230406 and 230902 of DOD's Financial Management 
Regulation 7000.14-R, Volume 12, Chapter 23 "Contingency Operations" 
(September 2005) provide additional information on incremental costs. 

[31] Service members who are assigned, deployed, or traveling on 
temporary duty to certain foreign areas are eligible for certain 
special pays and benefits, such as imminent danger pay. 37 USC § 310 
(a) (2) (D) (2006). 

[32] For fiscal year 2006, additional resources at DFAS were reassigned 
to assist in producing and reviewing DOD's monthly Supplemental and 
Cost of War Execution Report. 

[33] The DOD Comptroller has two full-time employees dedicated to 
reviewing the department's GWOT obligations reported in DOD's monthly 
Supplemental and Cost of War Execution Report. 

GAO's Mission: 

The Government Accountability Office, the investigative arm of 
Congress, exists to support Congress in meeting its constitutional 
responsibilities and to help improve the performance and accountability 
of the federal government for the American people. GAO examines the use 
of public funds; evaluates federal programs and policies; and provides 
analyses, recommendations, and other assistance to help Congress make 
informed oversight, policy, and funding decisions. GAO's commitment to 
good government is reflected in its core values of accountability, 
integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through the Internet. GAO's Web site ( www.gao.gov ) contains 
abstracts and full-text files of current reports and testimony and an 
expanding archive of older products. The Web site features a search 
engine to help you locate documents using key words and phrases. You 
can print these documents in their entirety, including charts and other 
graphics. 

Each day, GAO issues a list of newly released reports, testimony, and 
correspondence. GAO posts this list, known as "Today's Reports," on its 
Web site daily. The list contains links to the full-text document 
files. To have GAO e-mail this list to you every afternoon, go to 
www.gao.gov and select "Subscribe to e-mail alerts" under the "Order 
GAO Products" heading. 

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. Government Accountability Office 

441 G Street NW, Room LM 

Washington, D.C. 20548: 

To order by Phone: 

Voice: (202) 512-6000: 

TDD: (202) 512-2537: 

Fax: (202) 512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: www.gao.gov/fraudnet/fraudnet.htm 

E-mail: fraudnet@gao.gov 

Automated answering system: (800) 424-5454 or (202) 512-7470: 

Public Affairs: 

Jeff Nelligan, managing director, 

NelliganJ@gao.gov 

(202) 512-4800 

U.S. Government Accountability Office, 

441 G Street NW, Room 7149 

Washington, D.C. 20548: