This is the accessible text file for GAO report number GAO-03-686 
entitled 'Capitol Hill Anthrax Incident: EPA's Cleanup Was Successful; 
Opportunities Exist to Enhance Contract Oversight' which was released 
on June 17, 2003.

This text file was formatted by the U.S. General Accounting Office 
(GAO) to be accessible to users with visual impairments, as part of a 
longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov.

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately.

Report to the Chairman, Committee on Finance, U.S. Senate:

United States General Accounting Office:

GAO:

June 2003:

Capitol Hill Anthrax Incident:

EPA's Cleanup Was Successful; Opportunities Exist to Enhance Contract 
Oversight:

GAO-03-686:

GAO Highlights:

Highlights of GAO-03-686, a report to the Chairman, Committee on 
Finance, U.S. Senate

Why GAO Did This Study:

In September and October 2001, the first cases of anthrax bioterrorism 
occurred in the United States when letters containing anthrax were 
mailed to congressional leaders and members of the news media. As the 
cleanup of the Capitol Hill anthrax site progressed, EPA’s estimates 
of the cleanup costs steadily rose. GAO was asked to describe (1) the 
costs EPA incurred to conduct the cleanup and how it was funded, (2) 
the extent to which EPA awarded the cleanup contracts competitively, 
(3) EPA’s oversight of the contractors’ work and any suggested changes 
to EPA’s contracting practices, and (4) the extent to which EPA agreed 
to indemnify contractors against liability for potential damages 
related to the cleanup.

What GAO Found:

EPA spent about $27 million on the Capitol Hill anthrax cleanup, using 
funds from its Superfund program. From the outset, many uncertainties 
were associated with the cleanup effort, including how to remove 
anthrax from buildings. EPA revised its November 2001 estimate of $5 
million several times during the cleanup as the nature and extent of 
the contamination became fully known and the solutions to remove and 
properly dispose of the anthrax were agreed upon and carried out. To 
conduct the cleanup, EPA relied extensively on the existing 
competitively awarded Superfund contracts it routinely uses to address 
threats posed by the release of hazardous substances. Specifically, 
about 80 percent of the contract costs were incurred under 10 of EPA’s 
existing Superfund contracts.

EPA dedicated significant resources to overseeing the many contractors 
working on the Capitol Hill anthrax cleanup—including about 50 staff 
from nine regional offices experienced in leading and overseeing 
emergency environmental cleanups. Most often, these staff ensured that 
the contractors were on site and performing assigned tasks 
efficiently. EPA also assigned an administrative specialist to ensure 
that contract charges were accurate and reasonable. EPA’s assessment 
of its emergency responses to the anthrax incidents, which focused on 
or included the Capitol Hill site, concluded that, overall, the agency 
had used its contracts effectively but that it could improve some 
areas of its contracting support. In addition, GAO’s review of the 
Capitol Hill cleanup revealed inconsistencies in EPA’s cost oversight 
practices among regions. For example, EPA uses a computerized system 
for tracking contractor costs for hazardous substance removal 
contracts, but regions use the system inconsistently for the technical 
assessment contracts also used during emergency responses. Consistent 
use of the system would likely improve the quality of EPA’s nationwide 
contract data and enhance EPA’s oversight capabilities.

EPA agreed to indemnify two contractors with key roles in the 
fumigation of the Hart Senate Office Building with chlorine dioxide 
gas against liability that could have resulted if a third party had 
been injured by the contractors’ release of a harmful substance, 
including anthrax.  

What GAO Recommends:

To enhance EPA’s contract oversight, GAO recommends that the EPA 
Administrator require all EPA regions to more consistently use two 
contract oversight practices and to examine expanding the use of 
another.

EPA officials agreed to implement or consider implementing GAO’s 
recommendations.  Their comments and our response are discussed at the 
end of this report.

[End of section]

Contents:

Letter:

Results in Brief:

Background:

EPA Spent About $27 Million of its Superfund Money to Clean Up the 
Capitol Hill Anthrax Site:

EPA Competitively Awarded Most Major Contracts Used in the Anthrax 
Cleanup:

EPA Devoted Extensive Resources to Overseeing Contractors' Work, yet 
Some Contracting Changes Would Better Support EPA Cleanups:

EPA Negotiated Indemnification Agreements with Two Contractors to 
Address Their Liability Concerns:

Conclusions:

Recommendations for Executive Action:

Agency Comments and Our Response:

Scope and Methodology:

Appendix I: Contract Tasks and Roles:

Appendix II: GAO Contacts and Staff Acknowledgments:

Tables:

Table 1: EPA Estimated Contract and Government Agreement Cost Increases 
for the Capitol Hill Anthrax Cleanup:

Table 2: Competitively Awarded Superfund Contracts Used for the Capitol 
Hill Anthrax Cleanup:

Table 3: Noncompetitively Awarded EPA Contracts Used for the Capitol 
Hill Anthrax Cleanup:

Table 4: Agreements with Federal and State Agencies Used for the 
Capitol Hill Anthrax Cleanup:

Figures:

Figure 1: A Sample Is Inserted into a Vial in the Hart Senate Office 
Building:

Figure 2: Cleanup Personnel Use a HEPA Vacuum in a Congressional 
Office:

Figure 3: Breakout of EPA Contract and Government Agreement Costs:

Abbreviations:

CDM: Federal Programs Corporation:

CERCLA: Comprehensive Environmental Response, Compensation, and 
Liability Act:

EPA: Environmental Protection Agency:

HEPA: high efficiency particulate arresting:

NCP: National Oil and Hazardous Substance Pollution Contingency Plan:

United States General Accounting Office:

Washington, DC 20548:

June 4, 2003:

The Honorable Charles E. Grassley 
Chairman, 
Committee on Finance 
United States Senate:

Dear Chairman Grassley:

Anthrax is a naturally occurring bacterium that causes acute infectious 
disease and is potentially fatal.[Footnote 1] As you know, in September 
and October 2001, the first cases of anthrax bioterrorism occurred in 
the United States when letters containing a powdered form of anthrax 
were mailed to members of the news media and congressional leaders. On 
October 15, 2001, one of these letters, addressed to the former 
Majority Leader of the U. S. Senate, was opened in the Hart Senate 
Office Building in Washington, D.C. The letter had contaminated several 
congressional and other buildings along the mail delivery route and 
elsewhere, and approximately 30 congressional employees tested positive 
for anthrax exposure soon after. The Hart Senate Office Building is a 
10-million-cubic-foot building that houses the offices and staffs of 50 
senators. As a result of the anthrax contamination, the Hart Building 
and several others on Capitol Hill were closed.

In consultation with the leadership of the Congress, the U.S. Capitol 
Police Board--which oversees the security of the Capitol complex--
established a team led by an independent "incident commander" to 
coordinate the response to the anthrax incident among several federal 
and local agencies. The team determined that the congressional offices 
should be decontaminated and reopened as expeditiously as possible so 
that the operations of the legislative branch would not be impeded. The 
Environmental Protection Agency (EPA), which removes hazardous 
substances under its Superfund program, had a significant role in the 
cleanup.

As the cleanup of the Capitol Hill anthrax site progressed, EPA's 
estimates of its cost steadily increased. Consequently, you asked us to 
examine several aspects of EPA's cleanup. This report describes (1) the 
costs EPA incurred to conduct the Capitol Hill anthrax cleanup and how 
the costs were funded, (2) the extent to which EPA awarded the anthrax 
cleanup contracts competitively, (3) EPA's oversight of the work 
performed by contractors and any suggested changes to EPA's contracting 
processes, and (4) the extent to which EPA agreed to indemnify 
contractors against liability for potential damages related to the 
cleanup.

To conduct our work, we sought contracting documentation relevant to 
the anthrax cleanup from EPA. However, delays in receiving much of this 
documentation considerably extended the time necessary to complete our 
work. Factors contributing to the delay included the need to negotiate 
and then to implement a process established by the Capitol Police Board 
and EPA to address their respective concerns. The Capitol Police Board 
was concerned that the EPA documents might contain sensitive security 
information, and EPA thought that the documents might contain 
confidential business information that it was not authorized to release 
to the Capitol Police Board. As the first step in the process, EPA 
established a reading room for GAO staff to preliminarily review the 
documents. After this review, EPA screened the documents for 
confidential business information and gave them, with certain 
information redacted, to the Capitol Police Board so it could screen 
for security issues and redact sensitive information. After the EPA and 
Capitol Police Board reviews, which took more than 3 months, the 
documents were given to us. In part because of delays in obtaining this 
contracting information, we surveyed 63 EPA personnel the agency had 
identified as having provided contractor oversight for the cleanup to 
obtain information on their oversight roles. We received survey 
responses from 56 people, a response rate of 89 percent. Our scope and 
methodology for this review are presented at the end of this report.

Results in Brief:

EPA spent approximately $27 million to clean up anthrax contamination 
on Capitol Hill, using funding from its Superfund program. To conduct 
the anthrax contamination assessments and the actual decontamination, 
EPA retained the services of many more contractors than it would 
typically use for a single Superfund cleanup site. Specifically, EPA 
paid 27 contractors and three federal and state agencies about $25 
million for the Capitol Hill anthrax cleanup; the remaining $2 million 
covered EPA's personnel costs, including travel, primarily for the 
staff who supervised the contractors. In fiscal year 2002, the Congress 
appropriated about $23 million to replenish a substantial portion of 
the Superfund monies EPA had spent. From the outset in October 2001, 
many uncertainties were associated with the cleanup effort, including 
how to remove anthrax from buildings and how much the cleanup would 
cost. As the nature and extent of the contamination became fully known 
and the solutions to remove and properly dispose of the anthrax were 
agreed upon and carried out, EPA's November 2001 estimate of $5 million 
proved to be a fraction of what was actually needed to conduct the 
cleanup. With the dedication of substantial resources and funding to 
the cleanup, the objective of reopening the decontaminated Capitol Hill 
office buildings as soon as was safely possible was achieved in about 3 
months. In contrast, some other buildings that were also contaminated 
with anthrax in the fall of 2001, such as the Brentwood postal 
facility, remain closed as of May 2003.

Because EPA relied extensively on the existing competitively awarded 
Superfund contracts it routinely uses to address threats posed by the 
release or threatened release of hazardous substances, about 80 percent 
of the contract costs for the Capitol Hill anthrax cleanup were 
incurred under competitively awarded technical assessment or hazardous 
substance removal contracts. Specifically, EPA used 10 of its existing 
competitively awarded contracts and 2 new competitively awarded supply 
and security contracts for additional support. Most of the 15 contracts 
that were not competitively awarded were sole-source contracts for 
under $200,000 to obtain supplies and technical, laboratory, and 
security services or to support existing removal contracts. EPA's 
Office of Acquisition Management authorized the use of sole-source 
contracts for the cleanup on the basis that the emergency situation 
created an urgent and compelling need to obtain services and supplies 
without going through the generally more time-consuming competitive 
bidding process. For additional assistance, EPA also entered into 
agreements with the U.S. Coast Guard, the Department of the Army, and 
the State of Maryland Department of the Environment.

EPA dedicated significant staff resources to overseeing the many 
contractors working on the Capitol Hill anthrax cleanup to ensure that 
their assessment and cleanup work was appropriate and the charges were 
accurate and reasonable. About 150 EPA staff participated in the 
cleanup, including about 50 staff from nine regional offices--called 
on-scene coordinators--who have experience in leading and overseeing 
emergency environmental cleanup operations. The on-scene coordinators 
oversaw, and sometimes assisted with the work of, the contractors 
during shifts that ran 24 hours a day, 7 days a week, for about 3 
months. The tasks of the on-scene coordinators varied but most often 
included ensuring that the contractors were on-site and performing 
assigned tasks efficiently. In addition, EPA assigned an administrative 
specialist to ensure that contract charges were accurate and 
reasonable. This individual reviewed the daily charges for four removal 
contracts, which represented about 41 percent of the total contract 
costs. EPA has conducted four assessments of its emergency responses to 
the anthrax incidents, focusing on or including the Capitol Hill site. 
Overall, these assessments indicated that EPA used its contracting 
capabilities effectively, but they also identified areas in which EPA 
could improve contract support, and EPA has begun taking steps to do 
so. Moreover, our work on the Capitol Hill cleanup revealed areas in 
which oversight of contract costs was not consistent among the regions 
and might be improved. For example, while EPA uses a computerized 
system for tracking contractor costs for removal contracts, this system 
is used on a limited basis for technical contracts that are also used 
for cleanups. If the system--which provides up-to-date cost information 
organized in consistent categories, such as equipment and travel--were 
used consistently, the quality of EPA's nationwide contract data would 
be improved and its oversight capabilities would likely be enhanced. 
Toward this end, we are recommending that EPA require all the regions 
to more consistently use certain of the practices now used in only some 
regions.

EPA agreed to indemnify two contractors that had key roles in the 
fumigation of the Hart Senate Office Building with chlorine dioxide gas 
against liability that could have resulted if a third party had been 
injured by the contractors' release of a harmful substance, including 
anthrax and chlorine dioxide. Although one of the contractors worked at 
the site while negotiating with EPA for indemnification against such 
liability, the other contractor would not start removal procedures 
without first receiving indemnification. Following 4 weeks of 
negotiations, EPA reached agreement on indemnification with this 
contractor in November 2001. Because the negotiation process occurred 
at the same time that testing was being performed offsite to determine 
the proper decontamination methods to use at the Hart Senate Office 
Building, the month-long negotiation process did not delay the cleanup. 
However, it potentially could have done so. As a result, two of EPA's 
assessments of its responses to the 2001 terrorist attacks recommended 
expanding contractor indemnification to address counter-terrorism 
response activities.

Background:

The Capitol Hill anthrax incident occurred a month after the terrorist 
attacks on the World Trade Center and the Pentagon, while EPA and other 
federal agencies were continuing to respond to these attacks. The 
Capitol Police Board, which governs the U.S. Capitol Police Force, led 
the anthrax cleanup at the Capitol Hill site.[Footnote 2] Consisting at 
the time of our review of the House and Senate Sergeants-at-Arms and 
the Architect of the Capitol, the Board oversees the security of 
members of the Congress and the Capitol buildings, such as the 
congressional office buildings. The federal entities involved in the 
cleanup--including EPA, the Federal Emergency Management Agency, the 
Centers for Disease Control and Prevention, the U.S. Coast Guard, and 
the Department of the Army--reported to an incident commander who was 
appointed by the Capitol Police Board to make decisions on the day-to-
day activities of the cleanup. The period from October 20, 2001, to 
November 13, 2001, is characterized as the emergency phase, which 
focused on identifying the extent of anthrax contamination; this was 
followed by the remedial, or cleanup, phase.

Reporting to the Capitol Police Board's incident commander, EPA managed 
the decontamination aspects of the cleanup. EPA's activities at the 
Capitol Hill site included:

* working with other agencies and entities to evaluate the 
effectiveness of potential disinfectants and cleanup technologies,

* isolating areas to prevent the spread of contamination,

* sampling to determine and confirm the extent of contamination (see 
fig. 1),

* evaluating sampling results,

* removing critical items for special decontamination procedures, and:

* cleaning up the contaminated areas and disposing of decontaminated 
items.

Figure 1: A Sample Is Inserted into a Vial in the Hart Senate Office 
Building:

[See PDF for image]

[End of figure]

At the Capitol Hill site, EPA sampled both surfaces and air in the 
buildings for the presence of anthrax, using three types of surface 
samples (wet swabs and wipes for nonporous surfaces and high efficiency 
particulate arresting (HEPA) vacuuming for porous materials) and four 
types of air samples. Four methods were used to remove anthrax found in 
congressional buildings: fumigating with chlorine dioxide gas, an 
antimicrobial pesticide; disinfecting with a liquid form of chlorine 
dioxide; disinfecting with Sandia foam;[Footnote 3] and using HEPA 
vacuuming (see fig. 2). During the cleanup, chlorine dioxide gas was 
identified as the best available fumigant for decontaminating parts of 
the Hart Senate Office Building, as well as for fumigating mail and 
packages. EPA oversaw the use of chlorine dioxide gas during three 
fumigation events in the Hart building.

Figure 2: Cleanup Personnel Use a HEPA Vacuum in a Congressional 
Office:

[See PDF for image]

[End of figure]

In addition, contractors removed items from congressional offices that 
were critical to congressional operations or personal effects of 
significance. These items were bagged, tagged, and moved for off-site 
decontamination. Approximately 3,250 bags of critical items were 
transported to a company in Richmond, Virginia, for decontamination 
treatment using ethylene oxide. Approximately 4,000 packages and other 
mail were collected from the mail rooms in congressional office 
buildings and also transported off site for decontamination using 
chlorine dioxide gas. In addition, drums of mail were sent to a 
facility in Lima, Ohio, for irradiation treatment.

The Capitol Hill anthrax cleanup site included 26 buildings, most of 
them located in or near the Capitol Hill area of Washington, D.C. The 
buildings that required testing for anthrax contamination included 
congressional and judicial buildings; mail facilities; and other nearby 
buildings, such as the Library of Congress. Initial sampling was 
conducted along the route traveled by the letter opened in the Hart 
Building by tracing the route back to the Dirksen Senate Office 
Building (where the mail for the Senate is processed), to the P Street 
Warehouse (a restricted mail inspection facility overseen by the 
Capitol Police where congressional mail is inspected), and finally to 
the Brentwood postal facility (the U.S. Postal Service mail processing 
and distribution center for Washington, D.C.).[Footnote 4]

Samples from 7 of the 26 buildings were found to contain anthrax, which 
required that these 7 undergo more thorough sampling, followed by 
decontamination, and followed then by resampling to confirm that the 
anthrax had been eradicated. In total, approximately 10,000 samples 
were taken at the Capitol Hill site, about half of them from locations 
in the Hart Senate Office Building. EPA advised the Capitol Police 
Board's incident commander about the extent to which buildings needed 
to be cleaned to make them safe. EPA, along with the Centers for 
Disease Control and Prevention, the Agency for Toxic Substances and 
Disease Registry, the National Institute for Occupational Safety and 
Health, and other relevant authorities, determined that the cleanup 
standard that would be fully protective of public health and the 
environment was "no detectable, viable anthrax spores." The seven 
buildings that required decontamination were the Dirksen, Hart, and 
Russell Senate Office Buildings; the Ford and Longworth House Office 
Buildings; the U.S. Supreme Court Building; and the P Street Warehouse. 
Six of the seven buildings were cleared for reentry by the end of 
January 2002. The P Street Warehouse was cleared for reentry in March 
2002. According to the lead EPA on-scene coordinator, no one became 
sick as a result of exposure to anthrax or chemical agents used during 
decontamination.

EPA performed its work on the Capitol Hill anthrax cleanup under its 
Superfund program pursuant to the Comprehensive Environmental Response, 
Compensation, and Liability Act (CERCLA) and the National Oil and 
Hazardous Substance Pollution Contingency Plan (NCP). Provisions of 
CERCLA, as amended, promote a coordinated federal, state, and local 
response to mitigate situations at sites that may pose an imminent and 
substantial threat to public health or the environment. The NCP is the 
federal government's blueprint for responding to both oil spills and 
hazardous substance releases. It requires that an on-scene coordinator 
manage the federal response at the scene of a discharge of oil or a 
release of a hazardous substance that poses a threat to public health 
or the environment. The on-scene coordinator coordinates all federal 
efforts with, and provides support and information to, local, state, 
and regional response communities. Depending on where an incident 
occurs, the on-scene coordinator may be either an EPA or U.S. Coast 
Guard employee. EPA's Superfund work typically involves using agency 
personnel and contractors from 1 of 10 EPA regions located throughout 
the country that have experience with the hazardous substances involved 
in the incident and the methods required to remove them.

Removal actions are generally short-term, relatively inexpensive 
responses to releases or threats of releases of hazardous substances, 
pollutants, or contaminants that pose a danger to human health, 
welfare, or the environment. CERCLA generally limits the cost of a 
removal action to $2 million and the duration to 1 year. However, 
CERCLA exempts certain removal actions from these limitations, such as 
when continued response is required immediately to prevent, limit, or 
mitigate an emergency. EPA approved an emergency exemption to the $2-
million statutory limit for the Capitol Hill anthrax cleanup on 
November 5, 2001.

Typically, EPA provides one on-scene coordinator for a removal site to 
perform an initial assessment of the cleanup work needed, monitor the 
more detailed technical assessment and cleanup work being performed by 
EPA personnel and one or two contractors, and evaluate the results. 
However, the Capitol Hill site response was different from most 
hazardous materials emergency responses in its size and complexity, the 
nature of the contamination, and the requirement that the closed 
congressional buildings be reopened as soon as possible. As a result, 
EPA had to use a large number of on-scene coordinators, major 
contracts, and other federal agencies for assistance. In this case, 
EPA's Mid-Atlantic Regional Office (Region III) provided the lead on-
scene coordinator, who led the agency's cleanup efforts. Region III, 
along with eight other regions, also provided about 50 other on-scene 
coordinators. Further, unlike most EPA cleanups, the lead on-scene 
coordinator was not in charge of the overall operations but instead 
reported to the incident commander, who in turn reported to the Capitol 
Police Board and House and Senate leaders.

A substantial portion of the cleanup work at the Capitol Hill site was 
performed from October 2001 through January 2002, with most of the 
remaining work finished by April 2002. However, some additional costs 
have been incurred, and EPA personnel continued to work on activities 
related to the cleanup after April 2002. For example, the final 
disposal of items used at the cleanup continued after the buildings had 
been reopened. In addition, EPA conducted several internal reviews to 
identify lessons learned from this experience to help the agency 
prepare for responses to other potential biological or chemical weapons 
attacks.

EPA Spent About $27 Million of its Superfund Money to Clean Up the 
Capitol Hill Anthrax Site:

According to EPA, the agency expended about $27 million on the Capitol 
Hill anthrax cleanup, using Superfund program funding.[Footnote 5] 
Through fiscal year 2002 supplemental appropriations acts, the Congress 
provided EPA with additional funding for activities related to 
terrorism, and EPA allocated about $23 million of these funds to 
reimburse the Superfund program for expenditures associated with the 
Capitol Hill anthrax cleanup. Overall, EPA dedicated what it describes 
as unprecedented resources--contract staff and EPA personnel--to 
accomplish the cleanup of the anthrax site safely and effectively. 
Ninety-three percent of the $27 million in costs were incurred 
primarily by EPA contractors who, among other things, conducted 
technical assessments and performed the decontamination tasks at the 
various Capitol Hill sites; the remaining 7 percent of costs were 
incurred by EPA personnel, largely for planning and overseeing the work 
of the contractors in accordance with the direction provided by the 
Capitol Police Board.

Over the course of the cleanup, EPA revised its cost estimates several 
times as the nature and extent of the contamination became fully known 
and the solutions for removing and properly disposing of the anthrax 
were agreed upon and carried out. EPA's various cost estimates covered 
the contracts and government agreements and generally do not include 
the payroll and travel costs associated with EPA personnel assigned to 
the Capitol Hill site. In November 2001, EPA increased its initial 
estimate for the cleanup to $5 million--more than doubling the initial 
statutory limit of $2 million. EPA revised its estimate for the cleanup 
five more times to continue work necessary to control and mitigate the 
threat of release of anthrax to the environment and to properly dispose 
of pollutants and contaminants from the site. The last revision--an 
increase from $25 million to $28 million--occurred in June 2002. (See 
table 1.):

Table 1: EPA Estimated Contract and Government Agreement Cost Increases 
for the Capitol Hill Anthrax Cleanup:

Dollars in millions.

November 5, 2001; Amount of increase: a; New estimated contract cost: 
$5.

December 5, 2001; Amount of increase: $4; New estimated contract cost: 
9.

December 18, 2001; Amount of increase: 3; New estimated contract cost: 
12.

January 16, 2002; Amount of increase: 8; New estimated contract cost: 
20.

February 14, 2002; Amount of increase: 5; New estimated contract cost: 
25.

June 6, 2002; Amount of increase: 3; New estimated contract cost: 28.

Source: EPA.

[A] EPA first authorized spending in excess of the $2 million statutory 
limit in a November 5, 2001, action memorandum.

[End of table]

EPA adjusted its projections during the course of the cleanup as a 
result of a number of factors generally related to the uniqueness of 
the situation--the first use of anthrax as a terrorist weapon in this 
country. EPA had not addressed anthrax contamination in buildings 
previously and protocols for responding to contamination by anthrax or 
other biological agents did not exist. In addition, some scientific and 
technical information needed to properly plan and conduct the anthrax 
cleanup was not readily available; and EPA did not, at that time, have 
registered antimicrobial agents approved for use against anthrax. Also, 
EPA had not compared the costs of candidate decontamination methods. 
Further, much was--and still is--unknown about the properties of lab-
produced anthrax such as that used in this incident, which led to 
uncertainties about the health risks posed by the contamination and how 
it could spread. As a result, EPA and contractors had to develop plans 
for decontaminating large areas within buildings with limited practical 
knowledge; search for decontamination methods; assess their likely 
efficacy; implement them; and, at times, repeat the process if the 
methods did not work. Finally, EPA was one of a number of participants 
in the decisions made about the work to be done, the timing of the 
work, and the resources needed; it was not the primary decision maker 
as it would be in a typical Superfund cleanup.

As EPA and contractor staff were beginning their work at the Capitol 
Hill anthrax site, the limitations of existing knowledge about the 
health risks associated with anthrax--such as what amount of exposure 
could cause illness or death--were becoming more clear. That the 
Capitol Hill site was potentially riskier than initially believed 
became evident when workers in the postal facilities where anthrax-
laced letters were processed became ill; two of them subsequently died 
of inhalation anthrax. The scientific and medical information initially 
available to EPA and other agencies indicated that workers in postal 
facilities were not at risk of infection. Further, an elderly 
Connecticut woman--who may have been exposed to mail that had been 
contaminated with anthrax--died from anthrax inhalation, and a New York 
woman whose exposure to anthrax could not be linked to any mail or mail 
facilities also died.[Footnote 6]

To accomplish the cleanup safely in the midst of significant scientific 
and technical uncertainty and changing information about how anthrax 
spreads, EPA called on about 150 of its staff in headquarters and the 
regions, incurring agency payroll and travel costs of $1.9 
million[Footnote 7]--payroll costs amounted to $1.3 million and travel 
costs to about $600,000.[Footnote 8] According to our analysis of EPA's 
Office of the Chief Financial Officer records, the majority of payroll 
and travel costs were incurred by on-scene coordinators from EPA's 
regions who were overseeing and assisting on the cleanup. Further, EPA 
employed 27 contractors and obtained further support from three 
government agencies at a total cost of about $25 million to provide 
assessment and cleanup services. These costs are discussed in the next 
section.

Because of the magnitude and urgency of the health threat and the high 
priority placed on reopening the congressional buildings as soon as 
possible to mitigate disruptions to the functioning of the federal 
government, the Capitol Hill anthrax cleanup conducted by EPA and other 
federal agencies was accomplished fairly quickly, with the majority of 
contaminated buildings opened for business in about 3 months. Without 
the emphasis on reopening the buildings, for example, the cleanup site 
likely would not have been operated around the clock, 24/7, for months. 
In contrast, testing and decontamination of some buildings at other 
sites have taken much longer. For example, fumigation of the Brentwood 
postal facility was completed in March 2003, and this facility had not 
reopened as of May 2003. In addition, a news media building in Boca 
Raton, Florida, where the first letter containing anthrax was received 
in September 2001, remained closed as of May 2003.

EPA Competitively Awarded Most Major Contracts Used in the Anthrax 
Cleanup:

Almost all of the cleanup expenses-81 percent--paid to EPA's 27 
contractors and 3 government agencies were incurred under competitively 
awarded contracts. For example, $20.3 million of the approximately $25 
million total expenditures under contracts and government agreements 
were incurred under 10 existing, competitively awarded contracts that 
EPA routinely uses under the Superfund program to respond to releases 
or the threat of releases of hazardous substances, pollutants, or 
contaminants that may present imminent and substantial danger to the 
public health or welfare. Most of the contracts that were not 
competitively awarded cost less than $200,000 and provided supplies and 
technical services. For additional assistance, EPA also entered into 
agreements with two federal agencies and one state agency. (See fig. 
3.):

Figure 3: Breakout of EPA Contract and Government Agreement Costs:

[See PDF for image]

[A] The competitively awarded contracts include $20.3 million expended 
under 10 existing contracts and about $0.1 million under 2 contracts 
awarded during the cleanup.

[End of figure]

Competitively Awarded Superfund Contracts:

When responding to a release of hazardous substances, EPA first relies 
on its existing Superfund contracts. The Competition in Contracting Act 
of 1984 generally requires contracting agencies to obtain full and open 
competition through the use of competitive procedures, the dual 
purposes of which are to ensure that procurements are open to all 
responsible sources and to provide the government with the opportunity 
to receive fair and reasonable prices. In order to respond to 
emergencies involving releases of hazardous substances quickly, EPA 
issues competitively awarded multiyear Superfund contracts so that 
contractors with the necessary expertise are available on short notice 
when needed. The 10 EPA regions each negotiate and manage these 
Superfund contracts for work in their geographic area.

EPA generally uses two types of contracts in an emergency response:

* technical contracts provide technical assistance for EPA's site 
assessment and removal activities, and:

* removal contracts provide emergency, time-critical removal services.

EPA used 10 existing, competitively awarded Superfund contracts for 
most of the technical assessment and anthrax removal at the Capitol 
Hill site: 4 technical contracts, 4 removal contracts, 2 other 
contracts that provided specific technical services and support; and 
issued 2 additional contracts for security services and supplies that 
were competitively awarded. (See table 2.) The 10 existing contracts 
had been in place for up to 4 years when the anthrax incident 
occurred.[Footnote 9] While EPA's Region III issued the Superfund 
contracts that incurred the most costs for the Capitol Hill anthrax 
cleanup, contracts from other regions were also used to augment Region 
III contracting resources. The 10 existing Superfund contracts 
accounted for $20.3 million--or about 80 percent--of the total contract 
and government agreement costs for the Capitol Hill cleanup.

Table 2: Competitively Awarded Superfund Contracts Used for the Capitol 
Hill Anthrax Cleanup:

EPA Superfund contract: IT Corporation; Contract purpose: Removal; 
Obligated amount: $4,800,000; Expended amount[A]: $3,924,566.

EPA Superfund contract: Tetra Tech EM, Inc.; Contract purpose: 
Technical; Obligated amount: 4,497,205; Expended amount[A]: 4,397,083.

EPA Superfund contract: Earth Tech, Inc.; Contract purpose: Removal; 
Obligated amount: 3,751,700; Expended amount[A]: 3,380,143.

EPA Superfund contract: Environmental Quality Management, Inc.; 
Contract purpose: Removal; Obligated amount: 3,100,000; Expended 
amount[A]: 2,848,095.

EPA Superfund contract: CDM Federal Programs Corporation; Contract 
purpose: Support; Obligated amount: 2,500,000; Expended amount[A]: 
2,075,436.

EPA Superfund contract: Roy F. Weston, Inc.; Contract purpose: 
Technical; Obligated amount: 1,495,320; Expended amount[A]: 1,424,415.

EPA Superfund contract: Ecology & Environment, Inc.; Contract purpose: 
Technical; Obligated amount: 1,055,261; Expended amount[A]: 1,039,601.

EPA Superfund contract: Lockheed Martin; Contract purpose: Support; 
Obligated amount: 1,000,000; Expended amount[A]: 1,000,000.

EPA Superfund contract: Guardian Environmental Services, Inc.; Contract 
purpose: Removal; Obligated amount: 200,000; Expended amount[A]: 
116,184.

EPA Superfund contract: URS Operating Services, Inc.; Contract purpose: 
Technical; Obligated amount: 91,423; Expended amount[A]: 91,423.

EPA Superfund contract: MVM Security & Staffing Services; Contract 
purpose: Security services; Obligated amount: 87,562; Expended 
amount[A]: 87,562.

EPA Superfund contract: TSI, Inc.; Contract purpose: Supplies; 
Obligated amount: 7,520; Expended amount[A]: 7,520.

EPA Superfund contract: Total; Contract purpose: [Empty]; Obligated 
amount: $22,585,991; Expended amount[A]: $20,392,028.

Source: EPA's Office of the Chief Financial Officer.

[A] Expenditures as of March 14, 2003.

[End of table]

The four EPA technical contracts for the Capitol Hill anthrax cleanup, 
among other things, provided decontamination plans and sampled for 
anthrax in buildings. According to an EPA contracting official in 
Region III, technical contracts typically account for about 10 percent 
of total contract costs at a cleanup site. However, technical contracts 
costs for the Capitol Hill site totaled about $7 million--or about 28 
percent of the total contract costs.

The four EPA removal contracts for the Capitol Hill anthrax cleanup 
provided personnel, equipment, and materials to remove items from the 
site for safekeeping, decontaminate areas where anthrax was found, and 
dispose of contaminated items. These removal contracts also provided 
equipment and personnel to conduct sampling because of the large amount 
of samples that were required and the short time frames involved. The 
four EPA removal contract costs totaled about $10 million.

The other existing EPA contracts provided either specific technical 
services or support. One contract, which provides engineering and 
analytical services to EPA, monitored the air to ensure that 
potentially harmful decontamination chemicals were not released outside 
the area in which they were being used. Another contract, typically 
used for long-term Superfund cleanups known as remedial cleanups, 
provided additional technical support, including sampling analysis and 
data evaluation at the site. These two contracts totaled $3 million.

Noncompetitively Awarded Contracts:

Federal contracting laws that generally require EPA to use a 
competitive bidding process permit some exceptions to this requirement, 
including emergency situations where there is an unusual or compelling 
urgency for obtaining the necessary supplies or services. On this 
basis, in November 2001, EPA's Office of Acquisition Management gave 
the EPA contracting officers the authority to enter into contracts for 
the Capitol Hill anthrax site without using the normal competitive 
bidding process. Overall, EPA used 15 noncompetitively awarded 
contracts--that is, sole-source contracts--for supplies and for 
technical, removal, and laboratory services to support the cleanup of 
the Capitol Hill anthrax site. As shown in table 3, costs for three of 
the sole-source contracts exceeded $200,000, and many of them were for 
considerably less.

Table 3: Noncompetitively Awarded EPA Contracts Used for the Capitol 
Hill Anthrax Cleanup:

Contract: Kemron Environmental Services, Inc.[B]; Contract purpose: 
Removal; Obligated amount: $2,421,800; Expended amount[A]: $2,119,650.

Contract: HMHTTC Response Team, Inc.; Contract purpose: Removal; 
Obligated amount: 900,000; Expended amount[A]: 900,000.

Contract: Southwest Research Institute; Contract purpose: Laboratory; 
Obligated amount: 383,085; Expended amount[A]: 383,085.

Contract: University of California--Berkeley Sponsored Projects 
Office; Contract purpose: Technical; Obligated amount: 182,075; 
Expended amount[A]: 182,075.

Contract: Silva Consulting Services, LLC; Contract purpose: Technical; 
Obligated amount: 165,000; Expended amount[A]: 158,100.

Contract: Science Applications International Corporation[B]; Contract 
purpose: Technical; Obligated amount: 132,359; Expended amount[A]: 
28,630.

Contract: Biomarine, Inc.; Contract purpose: Supplies; Obligated 
amount: 81,147; Expended amount[A]: 65,647.

Contract: Envirofoam Technologies, Inc.; Contract purpose: Supplies; 
Obligated amount: 52,405; Expended amount[A]: 52,405.

Contract: Safeware, Inc.; Contract purpose: Supplies; Obligated amount: 
49,450; Expended amount[A]: 49,450.

Contract: Airgas Safety; Contract purpose: Supplies; Obligated amount: 
31,756; Expended amount[A]: 30,992.

Contract: Sabre Oxidation Technologies, Inc.; Contract purpose: 
Technical; Obligated amount: 21,950; Expended amount[A]: 19,850.

Contract: U.S. Art Company, Inc.; Contract purpose: Technical; 
Obligated amount: 12,842; Expended amount[A]: 12,842.

Contract: Mine Safety Appliances[B]; Contract purpose: Supplies; 
Obligated amount: 12,446; Expended amount[A]: 12,446.

Contract: Coastal Safety & Health Services, Inc.; Contract purpose: 
Supplies; Obligated amount: 11,025; Expended amount[A]: 11,025.

Contract: New Horizons Diagnostics Corporation; Contract purpose: 
Supplies; Obligated amount: 5,717; Expended amount[A]: 5,717.

Contract: Total; Contract purpose: [Empty]; Obligated amount: 
$4,463,057; Expended amount[A]: $4,031,914.

Source: EPA's Office of the Chief Financial Officer.

[A] Expenditures as of March 14, 2003.

[B] GSA federal supply schedule contract.

[End of table]

The largest noncompetitive contract used for the cleanup was with 
Kemron Environmental Services, Inc. Kemron provided EPA with HEPA 
vacuuming services, one of the four methods used to remove anthrax at 
the Capitol Hill site. EPA obtained the services of Kemron under the 
GSA federal supply schedule, relying on GSA's determination that the 
prices offered under the GSA contract were fair and 
reasonable.[Footnote 10] The second largest noncompetitive contract was 
with the removal contractor HMHTTC Response Team, which provided 
additional workers in December 2001 to relieve the removal contractors 
who had worked at the site since October. The other sole-source 
contract over $200,000 was with Southwest Research Institute, a 
laboratory that analyzed spore strips used to test for anthrax after 
the decontamination efforts. This particular laboratory was selected 
because it was familiar with the protocol developed by the technical 
consultant who developed the spore strips. In addition, according to 
EPA officials, the lab could handle the quantity of spore strips the 
cleanup generated, it promised a quick turnaround time, and the fee was 
reasonable.

The other noncompetitively awarded contracts used at the Capitol Hill 
site were for supplies needed for the contractors working at the site, 
such as respirators, air quality meters, and sampling kits, and for 
technical and removal and laboratory services. For example, one 
technical contractor, U.S. Art Company, Inc., provided advice regarding 
the removal and decontamination of art objects in the Capitol Hill 
buildings.

Appendix I provides details on the tasks performed under the 
competitively and noncompetitively awarded contracts.

Agreements with Government Agencies:

EPA obtained further support through two federal interagency agreements 
and one state agreement. EPA amended an existing interagency agreement 
with the U.S. Coast Guard to respond quickly to the Capitol Hill 
anthrax contamination. The U.S. Coast Guard National Strike Force 
provided tactical entry teams, specialized equipment, management 
support, and a deputy to the incident commander during the emergency 
phase of the cleanup. EPA also entered into a new interagency agreement 
with the U.S. Department of the Army for waste incineration services at 
Fort Detrick, Maryland. In addition, EPA used the State of Maryland 
Department of the Environment to review work plans and help coordinate 
EPA's removal and disposal of anthrax. (See table 4.):

Table 4: Agreements with Federal and State Agencies Used for the 
Capitol Hill Anthrax Cleanup:

Entity: U.S. Coast Guard; Obligated amount: $900,000; Expended 
amount[A]: $635,254.

Entity: Department of the Army-U.S. Medical Command; Obligated amount: 
274,141; Expended amount[A]: 241,141.

Entity: State of Maryland Department of the Environment; Obligated 
amount: 1,500; Expended amount[A]: 1,500.

Entity: Total; Obligated amount: $1,175,641; Expended amount[A]: 
$877,895.

Source: EPA's Office of the Chief Financial Officer.

[A] Expenditures as of March 14, 2003.

[End of table]

EPA Devoted Extensive Resources to Overseeing Contractors' Work, yet 
Some Contracting Changes Would Better Support EPA Cleanups:

EPA dedicated significant staff resources to overseeing the many 
contractors working on the Capitol Hill anthrax cleanup. Specifically, 
about 50 EPA staff ensured the contractors were on site and performing 
assigned tasks appropriately. In addition, EPA assigned an 
administrative specialist to ensure contract charges were accurate and 
reasonable. After the cleanup, EPA assessed its response to the Capitol 
Hill anthrax incident and concluded that, overall, it had effectively 
used its contracting resources. However, EPA also identified ways it 
could improve contract support for potential future emergency 
responses. Moreover, our review of the Capitol Hill anthrax incident 
revealed inconsistencies in oversight practices that could affect the 
quality of EPA's contract cost oversight, such as the extent to which 
regions use the computerized cost-tracking system, the extent to which 
they assign dedicated administrative specialists to cleanup sites to 
oversee costs, and regions' varying approaches to reviewing cost 
reports for technical contracts.

Staff Oversaw Contractors' Work to Ensure It Was Appropriate and 
Charges Were Accurate and Reasonable:

EPA used emergency technical assessment and hazardous substance removal 
contractors to conduct the cleanup and dedicated significant staff 
resources to overseeing their work. Reporting to the Capitol Police 
Board, EPA staff provided extensive technical expertise in anthrax 
detection and removal to ensure that the Capitol Hill cleanup protected 
public health and the environment. In all, according to EPA's Office of 
the Chief Financial Officer's payroll list, about 150 EPA staff 
participated in the anthrax cleanup, including about 50 staff from nine 
regional offices who are experienced in leading and overseeing 
emergency environmental cleanup operations--the on-scene coordinators-
-and several staff from EPA's Environmental Response Team who also have 
experience in emergency cleanup operations.[Footnote 11]

The on-scene coordinators oversaw, and sometimes assisted with, the 
work of the contractors during shifts that ran 24 hours a day, 7 days a 
week, for about 3 months. Fifty-six EPA staff whose responsibilities at 
the Capitol Hill site included overseeing contractors responded to our 
survey about the oversight activities they performed. They reported 
that their tasks varied but that the task they most frequently carried 
out was overseeing contractors.[Footnote 12] Specifically, the EPA 
respondents to our survey spent, on average,

* 53 percent of their time overseeing contractors;

* 18 percent researching and developing technical plans;

* 13 percent coordinating with other federal agencies on the 
administration of the cleanup; and:

* 14 percent on "other activities," such as conducting pilot studies 
for the decontamination effort, sampling for anthrax, and organizing 
and administering cleanup activities.

The EPA staff who reported overseeing contractors spent, on average, 54 
percent of their time observing contractors to ensure they were on site 
and working on assigned tasks efficiently. These staff also spent, on 
average, 17 percent of their time reviewing the results of contractors' 
work, and 8 percent of their time preparing daily or weekly work plans. 
Less frequently, staff who reported oversight activities also monitored 
delivery and quality of supplies, reviewed cost documents, and approved 
hours worked by contract personnel.

While EPA staff who reviewed cost documents spent, on average, 3 
percent of their time reviewing cost documents, one person--a site 
administrative officer--spent 100 percent of his time reviewing cost 
documents. As discussed in the following section, Region III generally 
uses site administrative officers to review both technical and removal 
contract costs in detail and to document these reviews before the on-
scene coordinator reviews and approves them, thereby easing the cost-
review workload of on-scene coordinators and allowing them to focus 
more on other cleanup management tasks and issues.

At the Capitol Hill anthrax site, the site administrative officer 
reviewed the daily charges for four of the six removal contracts, which 
represented about 41 percent of the total contract costs.[Footnote 13] 
These reviews involved verifying the hours the contractor staff worked 
by comparing the hours billed with the hours recorded in sign-in 
sheets; reviewing travel costs to ensure they were within federal 
guidelines and reviewing other expenditures of contractor staff, such 
as telephone charges to ensure they were allowable. The review work 
papers provide documentation of the cost reviews performed.

According to EPA officials, the technical contractors did not have 
sufficient staff on site to provide daily cost reports, and the site 
administrative officer, therefore, did not review the daily costs of 
the technical contracts at the Capitol Hill site. EPA requires reviews 
of the monthly cost reports from technical contractors before they are 
approved for payment by project officers in the regions; the reviews 
are generally performed by the on-scene coordinator at the site. 
However, we could not determine the extent to which the costs of the 
largest technical contract, which was managed by Region III, were 
reviewed by on-scene coordinators at the Capitol Hill site because the 
project officer responsible had retired, and EPA staff could not locate 
any documentation of reviews that had been requested or performed. As 
discussed further below, Region III implemented a new review process in 
2002 that requires such documentation.

EPA's Assessments of Its Response to the Capitol Hill Anthrax Incident 
Identified Contracting Issues, Which EPA Is Addressing:

EPA conducted four assessments that either focused on or included the 
Capitol Hill anthrax cleanup; the reports resulting from each follow:

* Regional Lessons Learned from the Capitol Hill Anthrax Response, 
March 2002;

* 60-Day Counter-Terrorism Contracting Assessment Final Report, May 
2002;

* Federal On-Scene Coordinator's After Action Report for the Capitol 
Hill Site, August 2002; and:

* Challenges Faced During the Environmental Protection Agency's 
Response to Anthrax and Recommendations for Enhancing Response 
Capabilities: A Lessons Learned Report, September 2002.[Footnote 14]

One of these reviews, the 60-day counter-terrorism contracting 
assessment report, focused exclusively on the capability of EPA's 
existing emergency response contracting network to respond to terrorist 
incidents, while the other three addressed a range of issues, such as 
operations and management, communications and coordination, health and 
safety, and the resources available to EPA. The overarching purpose of 
the four reviews was to derive lessons learned from EPA's responses to 
the anthrax incidents in order to improve the agency's ability to 
handle the kind of threats associated with large terrorist incidents. 
In this regard, while EPA concluded the cleanup was a success because 
the anthrax on Capitol Hill was removed efficiently and safely in the 
face of numerous and unprecedented challenges, the reports include a 
wide range of recommendations aimed at improving EPA's response 
capabilities. Regarding contracting, the four reviews found that the 
agency's emergency response contracting network met the response and 
procurement needs at the Capitol Hill site, but they also identified 
suggestions or recommendations for EPA to improve contract support for 
potential future responses. The lessons learned and recommendations 
included in the counter-terrorism contracting assessment report 
generally address the contracting issues that were identified in the 
broader reviews as well.

The counter-terrorism contracting assessment report developed 13 
recommendations, 9 of which it identified as the most urgent. These 
high-priority recommendations include the following:

* Facilitate counter-terrorism equipment acquisition and maintenance by 
compiling a national vendor database of sources of counter-terrorism 
equipment, supplies, and services.

* Create a strike team of headquarters and regional contracting 
officers and project officers that will be available for deployment 24/
7 in the event of an emergency to assist with emergency procurement 
needs.

* Increase the administrative support provided to on-scene coordinators 
during a major terrorism-related response by, for example, providing 
staff to review daily cost reports, review invoices, and process on-
site paperwork.

According to its April 21, 2003, status report of emergency response 
contracting activities, EPA has completed or is currently taking steps 
to address the contracting recommendations in the counter-terrorism 
contracting report. Regarding the three recommendations discussed 
above, EPA has done the following:

* EPA has developed counter-terrorism equipment warehouse contracts for 
most of its regions.

* EPA developed a final draft document on establishing a national 
contract support team and released it within EPA for review on April 
18, 2003.

* The workgroup addressing the need for administrative support for on-
scene coordinators is working on a list of specific administrative 
support tasks that are required.

The next section of this report discusses some other areas in which 
EPA's contracting oversight might be improved that we identified during 
our review of the Capitol Hill anthrax cleanup.

Certain Oversight Practices That Could Enhance EPA's Oversight Are Used 
in Some, but Not All, Regions:

As a result of the convergence of EPA staff from nine of its regions at 
the Capitol Hill site, regional differences in contractor oversight 
were highlighted. Three oversight differences concern contract cost 
data and the review of these costs. First, regions vary in the way they 
use a computerized contract cost-tracking system called the Removal 
Cost Management System. All regions use the system for removal 
contracts; however, some regions also use it for some technical 
contracts also used at cleanup sites. Second, some regions require that 
invoice reviews be documented before payments are made; other regions 
have no such requirement. Third, regarding cost reviews, some regions 
hire administrative specialists to conduct detailed daily on-site 
reviews of contract costs in support of the on-scene coordinator, while 
others only rely on the on-scene coordinator to both manage cleanups 
and review and approve the contract costs.[Footnote 15]

Computerized Cost-Tracking System:

In 1988, to better support Superfund program management, EPA developed 
a computerized cost-tracking system for cleanups so the agency could 
obtain consistent documentation from contractors at all sites in a 
timely and efficient manner. Specific anticipated benefits included 
timely tracking of total costs to ensure that cleanup projects would 
not exceed authorized amounts, more efficient invoice verification, and 
the ability to develop more accurate cost estimates for cleanups. The 
tracking system provides up-to-date cost information organized under 
the main categories of "personnel," "equipment," and "other field 
costs;" the system further breaks "other field costs" into such 
subcategories as materials and supplies, travel, lodging, per diem, and 
subcontracts. Thus, to the extent that regions require contractors to 
input daily contract costs into the system, EPA can readily monitor 
total costs as well as individual cost categories on a daily basis. 
Daily cost information supports oversight better than monthly 
information because it allows timely, on-site reviews of costs that can 
uncover inefficient or excessive use of labor and equipment.

While a 1989 memorandum requiring the use of the tracking system 
indicated that all site costs were to be input into the system, 
generally only the costs associated with removal contracts are entered 
daily into the system. For example, on the Capitol Hill anthrax 
cleanup, the expenditures ($10.2 million) for the four multi-year 
removal contracts were input into the system, but the expenditures ($7 
million) for the four multi-year technical contracts were not. 
According to EPA officials, part of the rationale for inputting removal 
contract costs into the system is that the type of contract used--"time 
and materials" contracts--requires more oversight than some other 
contract types, such as fixed-price contracts. That is, the removal 
contracts provide for specific labor rates but do not specify the 
number of hours that may be applied under the contracts. Most of the 
technical contracts currently used by the regions are cost 
reimbursement contracts and a few are fixed-priced contracts. Further, 
the fixed-priced contracts used by the regions will include a cost 
reimbursement portion that may cover activities such as contractor 
travel and subcontracts, according to a Region III contract official. 
For example, the cost reimbursement portion of one of the fixed-price 
technical contracts used for the Capitol Hill anthrax cleanup was 
substantial--about half of the contract cost of $4.4 million was 
invoiced under the cost reimbursement portion, according to a Region 
III contract official.[Footnote 16] As with work performed on a time-
and-materials basis, cost-reimbursement work requires appropriate 
surveillance during performance to provide reasonable assurance that 
efficient methods and effective cost controls are used. In addition, 
the technical contracts support work at numerous cleanup sites, and EPA 
also needs to track site-specific costs as well as total contract 
costs. However, because EPA does not consistently use the contractor 
cost-tracking system to track the costs incurred under its technical 
contracts, complete and consistent cost data on specific cleanup sites 
are not readily available.

Although EPA generally does not use the tracking system for technical 
contract costs, individual on-scene coordinators in some regions have 
required that these costs, as well as others, such as those incurred by 
state and federal agencies, be entered into the system. According to 
two such on-scene coordinators with whom we spoke, a key benefit of 
using the tracking system is that it gives them timely information on 
costs which helps them oversee and manage the work. According to an 
environmental engineer with EPA's Environmental Response Team, the 
benefits of using the tracking system for all of the contracts would 
include having consistent cost data about each cleanup site in one 
place, thereby enabling the agency to quickly respond to the numerous 
site-specific questions frequently asked by EPA management, the 
Congress, the Office of Management and Budget, the Federal Emergency 
Management Agency, and others. For example, using the tracking system 
one can quickly break out the expenditures into individual cost 
categories. The four Capitol Hill contracts entered into the tracking 
system include, in the aggregate, personnel costs of $2.8 million, 
lodging costs of $1.6 million, and per diem costs of $0.6 million. 
Using the tracking system, analyses of contract cost categories can be 
performed on individual contracts and individual sites. However, 
because technical contracts generally are not included in the tracking 
system, information on individual cost categories for the entire 
cleanup is incomplete.

Documentation of Invoice Reviews:

EPA's Contracts Management Manual describes responsibilities and 
procedures for processing contractors' invoices. Contract invoices are 
to be reviewed thoroughly for cost reasonableness and to be processed 
in a timely manner. While the guidance may be tailored to specific 
contracts and the use of checklists is optional, EPA's policy requires 
documentation to show that the appropriate reviews have been performed. 
The manual defines the roles of the various staff involved in reviewing 
and approving invoices. Among the key personnel in this process are the 
EPA staff who oversee the actual contract work[Footnote 17]--primarily 
on-scene coordinators in the case of the Capitol Hill anthrax site--and 
the project officer. In general, the staff who oversee the work are 
responsible for reviewing individual contract costs for reasonableness 
and informing the project officers of any problems with the costs, such 
as excess hours charged. The project officers are responsible for 
reviewing contract invoices for payment and completing and submitting 
invoice approval forms to EPA's financial management center for 
payment. The contract invoices for the removal and technical contracts 
are typically highly detailed and presented in varying formats.

Invoice reviews for removal contracts are generally more standardized 
across EPA than the invoice reviews for the technical contracts. 
Regions use varying invoice review approaches for the technical 
contracts. For example, beginning in November 2002, EPA Region III 
established a new process for reviewing invoices of technical 
contracts: the relevant EPA staff who oversaw or are overseeing the 
work at the sites receive monthly site-specific invoices from 
contractors, and the EPA staff are required to provide a written 
statement to the EPA project officer either indicating agreement with 
the costs or identifying questions about them. Region III revised its 
invoice review process after a new project officer with prior auditing 
experience was hired. This individual proposed the change to better 
ensure that invoices were reviewed by the on-site person familiar with 
the work that was performed--such as the on-scene coordinator--and that 
the review was documented before invoices were paid. Similarly, Regions 
V and IX send forms requiring responses to questions about the 
invoices, along with the monthly invoices, and require the work 
assignment managers overseeing the contract work to return the 
completed forms to the project officers.

However, before this change, and during the Capitol Hill anthrax 
cleanup, Region III did not require written certification of invoice 
reviews. Region III's earlier approach is similar to the one currently 
used in Region IV, where the project officer sends monthly invoices to 
the EPA work assignment managers for review and asks them to respond if 
they have concerns. Lacking a response from an EPA work assignment 
manager, the project officer approves the invoice for payment after a 
specified date. In these cases, the agency does not have documentation 
of the appropriate invoice reviews by the EPA staff who oversaw the 
contract work. Another variation is used in Region X: the project 
officer approves the monthly invoices without providing the EPA work 
assignment manager the opportunity to review them for reasonableness. 
As a result, the review is performed by an individual who did not 
oversee the work rather than by on-site staff who know the specifics of 
the work performed.

Dedicated Administrative Specialists to Review Costs:

EPA's on-scene coordinators generally are responsible for managing all 
aspects of emergency environmental cleanups: organizing, directing, and 
documenting cleanup actions.[Footnote 18] Specific tasks include 
conducting field investigations, monitoring on-scene activities, and 
overseeing the cleanup actions. The on-scene coordinator is also the 
individual with primary responsibility for ensuring that cleanup costs 
are managed and tracked as the cleanup progresses. The cost reviews 
that are required to ensure that EPA approves only reasonable and 
allowable costs are detailed and time-consuming. An EPA cost management 
principle for the Superfund program is that costs can be managed and 
documented most effectively from the cleanup site as they occur. 
However, EPA's Removal Cost Management Manual recognizes that the 
demands on the on-scene coordinator's time and attention are great and 
that, therefore, some cost management responsibilities have to be 
delegated to other on-site or off-site personnel.

To address this workload issue, Region III established an 
administrative position to provide on-site cost management support to 
its on-scene coordinators. As discussed earlier, one of Region III's 
site administrative officers[Footnote 19] worked on site at the Capitol 
Hill anthrax cleanup, supporting the lead on-scene coordinator 
essentially full-time from October 2001 through April 2002 and part-
time for several more months. As a result, the daily costs for four 
removal contracts were examined, contractor hours were traced back to 
sign-in sheets, and equipment deliveries and uses confirmed. The lead 
on-scene coordinator could not have conducted these detailed cost 
reviews because of other demands, and the other on-scene coordinators 
on site (many of whom were assigned to the site for only several weeks) 
also were involved overseeing the work being performed and would not 
have been able to conduct timely, detailed cost reviews.

Also, as discussed above, one of the lessons EPA learned from its 
assessments of its responses to the recent terrorist attacks, including 
the anthrax incidents, is that the agency needs to provide more 
administrative support to its on-scene coordinators who are responding 
to threats associated with terrorist incidents. The 60-Day Counter-
Terrorism Contracting Assessment Final Report specifically said that 
on-scene coordinators need increased support to review daily cost 
reports and invoices and to process paperwork on-site. Although EPA's 
Region III provides cost management support to its on-scene 
coordinators on a routine basis, most of the regions do not have 
positions dedicated to assist on-scene coordinators with their cost 
management responsibilities and, therefore, do not have trained support 
staff readily available to augment large or complex emergency cleanup 
efforts. Region III, which was responsible for the contracting for the 
Capitol Hill anthrax cleanup, has three such positions and was able to 
provide a site administrative officer to perform detailed cost reviews 
of removal contracts at the Capitol Hill site. Region II also has three 
similar positions. Five other regions we contacted do not have a 
similar position.[Footnote 20]

EPA Negotiated Indemnification Agreements with Two Contractors to 
Address Their Liability Concerns:

People in or near the contaminated Capitol Hill buildings could have 
been harmed by anthrax that was not successfully removed or by a 
release of the chemicals used to decontaminate the buildings. For 
example, the decontaminant used in the fumigation cleanup method--
chlorine dioxide gas--may irritate the respiratory tract at low 
concentrations and is fatal at high concentrations. In many cases, 
contractors can obtain pollution liability insurance to cover harm to 
third parties that may arise from cleanup activities; in other cases, 
the cost of such insurance may be prohibitive. In the case of the 
Capitol Hill anthrax cleanup, two contractors with key roles in the 
fumigation of the Hart Senate Office Building informed EPA that they 
were not able to obtain such insurance at a reasonable cost, and they 
requested indemnification. As discussed below, EPA agreed to provide 
the indemnification authorized by CERCLA to the two contractors, 
protecting them from the financial liability that could result if a 
third party were injured by the contractors' release of a harmful 
substance, including anthrax.

For example, numerous uncertainties about the use of chlorine dioxide 
gas for this task existed, and IT Corporation--which was tasked to 
fumigate the Hart office building using chlorine dioxide gas--would not 
start removal procedures without receiving indemnification from EPA 
against liability for damages. According to EPA officials, chlorine 
dioxide had not been used previously for removing anthrax or for 
fumigating such a large area. After EPA determined that IT Corporation 
and three of its subcontractors supplying the fumigation chemicals and 
technologies had diligently sought insurance and none was available at 
a reasonable price, in November 2001, the agency agreed to provide them 
with indemnification. Specifically, EPA agreed to compensate IT 
Corporation and its three subcontractors up to $90 million if they were 
deemed liable for damages caused by a negligent release of a hazardous 
substance, pollutant, or contaminant, including but not limited to 
anthrax and chlorine dioxide. According to EPA officials, the 
negotiations for the indemnification agreement were completed in about 
4 weeks. The indemnification does not cover liability for intentional 
misconduct or gross negligence. It appears that the cleanup was handled 
without harmful incidents occurring. According to EPA officials, 
neither IT Corporation nor the subcontractors have sought compensation 
under the indemnification agreement.

In December 2001, after the agreement with IT Corporation was in place, 
another contractor supporting the fumigation requested and obtained 
indemnification. CDM Federal Programs Corporation (CDM), whose 
responsibilities included placing the materials to test for the 
presence of anthrax during fumigation, received indemnification terms 
similar to those granted IT Corporation but with significantly lower 
compensation amounts. Specifically, EPA agreed to compensate CDM up to 
$1 million if it were deemed liable for damages caused by a negligent 
release of a hazardous substance, pollutant, or contaminant, including 
but not limited to anthrax. This indemnification also does not extend 
to liability arising from intentional misconduct or gross negligence. 
Negotiations for this agreement built on the previously negotiated 
agreement with IT Corporation, and, according to EPA officials, were 
accomplished in about a week. CDM was already working at the site when 
it requested indemnification and continued to work while the 
negotiations were in process.

Although IT Corporation required that an indemnification agreement be 
in place before it would begin the decontamination of the Hart 
building, the cleanup itself was not delayed because other issues 
needed to be resolved before IT Corporation started the fumigation 
process. For example, tests had to be conducted and then reviewed by 
EPA, the Capitol Police Board, and others to confirm that chlorine 
dioxide had the antimicrobial properties to effectively destroy 
anthrax. By the time open issues were resolved and the decontamination 
could begin, EPA had reached its agreement with IT Corporation and its 
subcontractors. However, in other emergency cleanups, such negotiations 
could delay the start of decontamination work. In this regard, EPA has 
concluded that in the future, a more expedient way to indemnify 
contractors for emergency situations such as anthrax incidents needs to 
be in place to prevent delays. In fact, two of the EPA reviews of its 
responses to the anthrax incidents recommended that EPA take steps to 
expand contractor liability indemnification to address counter-
terrorism response activities. Once Subtitle G of the recently enacted 
Homeland Security Act of 2002 is fully implemented, agency officials 
believe that their emergency response contractors will face little or 
no legal liability to injured third parties if the contractors use 
qualified antiterrorism technologies previously approved by the 
Secretary of Homeland Security. According to an EPA official, if this 
act had been in effect at the time of the anthrax cleanup, and the 
Department of Homeland Security had approved the chlorine dioxide 
technology, the contractor would not have needed any indemnification 
protection.

Conclusions:

In about 3 months and without harm to emergency response workers or 
congressional staff, EPA, the Capitol Police Board, and others planned 
and successfully conducted the first cleanup of office buildings 
contaminated by a lethal form of anthrax that had caused several deaths 
elsewhere. Moreover, EPA has taken the initiative to study its response 
actions to better prepare itself for other emergency cleanups, 
including other potential terrorism attacks, and has identified areas 
in which it could improve. Despite the success of the cleanup, our 
review identified certain inconsistencies in EPA's contractor cost 
oversight that may affect its quality. First, regarding tracking 
contract costs, because few regions use the cost-tracking system for 
technical as well as removal contracts, EPA does not have readily 
accessible, consistent contracting data on its cleanup sites. One 
result of this lack is that the agency was unable to readily respond to 
your questions about the costs of this cleanup, including the 
categories of expenditures--how much was spent on personnel, travel, 
equipment, and so on. In addition, EPA has less assurance that it is 
providing effective, consistent oversight of its contracts. Second, 
because EPA has not ensured that all of its regions document the 
reviews of contractor invoices conducted by cognizant on-site 
officials, the agency's ability to ensure that contractors' charges are 
accurate and reasonable is lessened. Finally, on-scene coordinators 
face many competing demands; therefore, their reviews of costs may be 
less timely than those that can be provided by a specialist working on 
site to support the on-scene coordinators' cost reviews. Such 
administrative support could provide EPA with better assurance that its 
payments to contractors are appropriately reviewed and adjusted on a 
routine basis. It could also be readily called upon to conduct these 
cost reviews during large and complex emergency cleanups, such as those 
that may stem from terrorism.

Recommendations for Executive Action:

To enhance its ability to ensure that the agency is providing effective 
and efficient contractor oversight, we recommend that the Administrator 
of EPA direct the Office of Solid Waste and Emergency Response to 
require:

* the regions to track and monitor both technical and removal contract 
cost data in the agency's computerized cost-tracking system and:

* the on-site staff who are responsible for reviewing contractor 
cleanup costs to certify that they have done so before the costs are 
approved for payment.

In addition, we recommend that the Administrator direct the Office of 
Solid Waste and Emergency Response to examine whether more or all of 
the regions should hire specialists--either EPA or contractor staff--to 
support the on-scene coordinators by providing timely, detailed reviews 
of contract costs. If EPA uses contractor staff for this purpose, the 
agency will need to provide appropriate contract oversight and ensure 
that potential conflicts of interest are identified and mitigated.

Agency Comments and Our Response:

We provided copies of our draft report to EPA for review and comment. 
In commenting on the draft, the Director of the Contract Management 
Center in the Office of Emergency and Remedial Response, Office of 
Solid Waste and Emergency Response, agreed to (1) consider adding the 
technical contracts to the computerized cost-tracking system as the 
agency awards the next round of these multiyear contracts and (2) 
ensure all regions coordinate with on-site staff for invoice reviews 
prior to approval. The Director also said that EPA is currently 
examining providing additional administrative support at cleanup sites 
and is considering using contractor support when in-house positions are 
not available.

One of the considerations the Director of the Contract Management 
Center cited regarding the inclusion of the technical contracts in the 
cost-tracking system is that reengineering the system to fit the 
different types of technical contracts that EPA uses might involve a 
considerable expense for the agency. Further, while she acknowledged 
that the cost tracking system may be particularly applicable when the 
technical contractors are involved in removal (cleanup) activities, she 
said the additional cost of using the system may not be justified in 
some cases, such as for finite work performed under a negotiated work 
plan or a fixed level of effort. However, we believe reengineering 
costs may not be a barrier to using the system for both technical and 
removal contracts. Specifically, the system is already being used to 
track the costs of some of EPA's technical contracts. Further, an EPA 
environmental engineer with extensive experience working with the 
tracking system told us that changes to the system would not be 
required to add technical contracts. In addition, effective oversight 
of both time-and-materials work and cost-reimbursement work is 
essential to ensure costs are reasonable and accurate. However, 
currently the tracking system is used to support the on-site review of 
the time-and-materials work done under the removal contracts but not 
for the contract-reimbursement work done under the technical contracts. 
We believe that the existing tracking system offers EPA an economical 
vehicle for enhancing both its contracting data and its contractor 
oversight by including the technical contracts in the cost tracking 
system as was envisioned when the system was developed.

Regarding our recommendation that the on-site staff responsible for 
reviewing contractor invoices certify that they have done so before the 
costs are approved for payment, the Director agreed to require all EPA 
regions to coordinate their invoice reviews with the on-site staff 
before approving invoices for payment. If EPA requires the reviewers in 
all the regions to certify their invoice reviews--as we recommend and 
as some EPA regions currently do--the agency will be fully responsive 
to our recommendation. Such a requirement will provide greater 
assurance that the invoices EPA approves are accurate and reasonable.

EPA told us that it is currently examining the issue of additional 
administrative support at cleanup sites by either EPA staff or 
contractors, and we have revised our recommendation to take into 
account concerns that would arise if EPA delegated its contract cost 
review function to contractors.

EPA agreed that the information the report provides on the 
indemnification agreements that the agency negotiated with two 
contractors is accurate but suggested that the report also discuss the 
limitations of the indemnification that EPA can provide under CERCLA. 
As our report accurately addresses the extent to which EPA agreed to 
indemnify contractors against liability for potential damages related 
to the cleanup, we believe that a broader discussion of indemnification 
issues is not necessary.

Scope and Methodology:

To determine the costs to EPA of removing anthrax from the Capitol Hill 
site, we obtained and reviewed cost information from the agency's 
Office of the Chief Financial Officer. We discussed cleanup estimates 
and contract costs for the Capitol Hill anthrax site with EPA financial 
and contract staff. We also obtained detailed cost information on four 
of EPA's removal contracts that was available from EPA's Removal Cost 
Management System, the database that tracks costs by site and cost 
categories. We were not able to obtain this level of detailed cost 
information for all contractors because EPA does not use this database 
for all the contractors who work at cleanup sites. To determine how 
EPA's costs for the cleanup were funded, we reviewed relevant EPA 
financial documentation and appropriations legislation that reimbursed 
the agency's Superfund program for expenditures associated with the 
resources used on the cleanup. We did not validate or verify these 
data.

To determine the extent to which the contracts used at the Capitol Hill 
anthrax site were competitively awarded, we reviewed EPA regional 
contract documents and discussed the competitive contract process EPA 
used with agency contract officials. We obtained and reviewed EPA 
noncompetitively awarded contract documents and the regulations that 
the agency is required to follow to justify awarding such contracts. We 
reviewed contracts and agency reports to identify the roles and tasks 
of the contractors that participated in the Capitol Hill anthrax 
cleanup and discussed specific contract roles and tasks with EPA 
officials who were responsible for the cleanup.

To describe the extent to which EPA oversaw contractors' work on the 
Capitol Hill anthrax cleanup to ensure it was done appropriately and 
the charges were reasonable, we interviewed Region III contract 
officials and the site administrative officer who oversaw four 
contracts during the cleanup. We also examined documentation of the 
oversight provided by reviewing Capitol Hill site contracting files. We 
reviewed documentation of, and talked with agency officials about, the 
current contract oversight practices EPA uses, including staff 
responsibilities for cost oversight and the use of the contractor cost 
tracking system. In addition, in part because of delays in obtaining 
contract information, we surveyed the 63 EPA personnel whom the agency 
identified as having provided contractor oversight to obtain 
information on their roles in overseeing the contractors' cleanup work 
for the Capitol Hill anthrax site. Using a Web-based survey, we 
received responses from 56 individuals, a response rate of 89 percent. 
We also interviewed nine EPA personnel who the survey identified as 
having spent considerable time at the cleanup site performing contract 
oversight. In addition, we reviewed four EPA assessments that either 
focused on or included the Capitol Hill anthrax cleanup and that 
identified contract oversight issues and recommendations. We obtained 
information on actions EPA has taken or is taking to respond to the 
recommendations addressing contracting issues.

To describe EPA's indemnification of contractors against liability for 
potential damages, we reviewed CERCLA provisions and EPA guidance 
governing indemnity authority, as well as contract modifications 
regarding indemnification that EPA made to two contracts used for the 
Capitol Hill anthrax cleanup. We also discussed with EPA officials how 
the indemnification process affected the Capitol Hill anthrax cleanup.

We conducted our review from June 2002 through May 2003 in accordance 
with generally accepted government auditing standards.

As agreed with your office, unless you publicly announce the contents 
of this report earlier, we plan no further distribution until 14 days 
after the report date. At that time, we will send copies of this report 
to the Administrator of EPA and other interested parties. We will make 
copies available to others upon request. In addition, the report will 
be available at no charge on GAO's Web site at http://www.gao.gov.

If you or your staff have any questions, please call me at (202) 512-
3841. Key contributors to this report are listed in appendix II.

Sincerely yours,

John B. Stephenson 
Director, 
Natural Resources and Environment:

Signed by John B. Stephenson:

[End of section]

Appendix I: Contract Tasks and Roles:

Competitively awarded contracts:

Contract: IT Corporation; Purpose: 
Removal; Task/role performed: Prepare 
buildings for decontamination. Conduct and support decontamination 
operations, including fumigation with chlorine dioxide gas. 
Decontaminate interior surfaces of buildings, other structures, cars, 
and other vessels. Provide for collection, containment, and 
transportation and disposal of contaminated materials from the site 
operations; Provide support to EPA sampling teams and other federal 
responders, including response technicians, to assist with 
decontamination activities.

Contract: Tetra Tech EM, Inc.; Purpose: 
Technical; Task/role performed: 
Provide the on-scene coordinator and incident commander 
fumigation design procedures, including details on fumigant delivery; 
concentration; operating conditions, such as temperature and humidity; 
fumigant containment and recovery; and monitoring of parameters. 
Provide detailed design for delivery of fumigant, equipment 
requirements and specifications, flow schematics, and detailed 
schedules and operating procedures to use during fumigation. Provide a 
chlorine dioxide specialist to assist EPA in overseeing the fumigation 
setup; Provide technical support to the on-scene coordinator in 
developing chronology of events at the site, including researching 
various files, documents, and logbooks in order to develop a 
comprehensive report; Monitor and assist with the oversight of the 
chlorine dioxide fumigation process. Assist with health and safety 
matters at the site, conduct sampling, assist and oversee off-gassing, 
inventory, and return items being treated; Support the on-scene 
coordinator in conducting presentations and briefings related to post-
treatment and design of chlorine dioxide use in the heating, 
ventilation, and air-conditioning system; Sample a small number of 
critical items (plastic, leather, and polyester) for ethylene oxide and 
its derivations to determine how the ethylene oxide and its derivatives 
are maintained in the materials and off-gas over time.

Contract: Earth Tech, Inc.; Purpose: 
Removal; Task/role performed: Provide 
decontamination services and other direct support to sampling teams. 
Decontaminate interior surfaces of buildings, other structures, and 
interior and exterior surfaces of cars and other vessels identified by 
the on-scene coordinator. Collect all expended cleaning agents and 
materials for treatment and/or disposal; Provide decontamination 
facilities and services for response personnel and their equipment. 
Inventory items--segregating clean and contaminated materials and 
salvageable and expendable items--and provide documentation of 
inventoried items; Propose a decontamination strategy for critical 
items (including personal items such as photographs, framed diplomas, 
and equipment). Decontaminate critical and salvageable items from the 
Capitol Complex, including setting up work zones for items to be 
decontaminated and for personnel decontamination. Return property after 
decontamination.; Provide contamination reduction and isolation 
facilities and operations that improve and ensure safe access to 
contaminated areas and items and prevent further spread of 
contamination.

Contract: Environmental Quality Management, Inc.; Purpose: 
Removal; Task/role performed: 
Provide personnel and equipment, 
including portable decontamination facility. Collect expended cleaning 
agents and materials for treatment and/or disposal. Dispose of 
materials or items that could not be decontaminated.

Contract: CDM Federal Programs Corporation; Purpose: 
Support; Task/role performed: 
Oversee preparation, handling, placement, and collection of 
spore strips used during fumigation with chlorine dioxide gas and 
ethylene oxide gas. Develop a procedure for spore strip emplacement; 
removal; and critical item tagging, tracking, and shipping; Provide 
sampling such as swipe and high efficiency particulate air (HEPA) 
vacuum (including efforts to collect, prepare, and ship samples), item 
decontamination, and minor remediation work; Support critical item 
degassing activities in Beltsville, Maryland. Maintain critical item 
inventories and coordinate the release and return of critical items to 
congressional staffers; Support chlorine dioxide decontamination of 
congressional mail packages.

Contract: Roy F. Weston, Inc.; Purpose: 
Technical; Task/role performed: 
Develop various documents/plans to be used during the 
response activities (e.g., standard operating procedures for sampling, 
decontamination, source reduction). Provide reconnaissance, photo 
documentation, and sampling of congressional office buildings; 
Provide technical support for the selection and implementation of 
decontamination procedures; building-specific plan development for 
anthrax remediation, including sampling plans, isolation plans, 
decontamination plans, and item recovery plans; and sampling support 
for anthrax analysis using HEPA and wipe sampling techniques; perform 
oversight of removal crews. Provide swab and HEPA sampling and 
decontamination support; Provide bag-and-tag operations of critical 
and salvageable items in congressional office buildings. Provide air 
monitoring operations during chlorine dioxide fumigation operations.

Contract: Ecology & Environment, Inc.; Purpose: 
Technical; Task/role performed: 
Develop sampling and decontamination plans, sample labels 
and chain-of-custodies, and maps to support sampling activities and to 
track sampling results; Perform sampling, monitoring, and 
decontamination of areas in the Capitol Hill complex. Conduct sampling 
tracking and handling activities, including preparing samples for 
shipping; Compile and review background data and organize site 
documentation files; Provide technical support to the operations 
section and support to the EPA Mobile Lab.

Contract: Lockheed Martin; Purpose: 
Support; Task/role performed: Assist 
in monitoring temperature and relative humidity inside office buildings 
and in monitoring chlorine dioxide, chlorine, wind speed and direction, 
temperature and relative humidity in surrounding area; Assist with 
development and evaluation of anthrax fumigation procedures using spore 
strips in a test facility and train other contractors in the handling 
and placement of spore strips in the office building; Provide 
ambient air monitoring for chlorine dioxide using tape meters and a 
portable meteorological tower to document that no chlorine dioxide is 
being emitted from the treatment area. Provide on-site assistance to 
ensure that spore strip sampling is being conducted properly and that 
data management is being performed accurately and completely.

Contract: Guardian Environmental Services, Inc.; Purpose: 
Removal; Task/role performed: 
Assist in the removal of items from 
the contaminated office suites in the congressional office buildings, 
including removal of contaminated office furniture, office equipment, 
and carpet. Construct isolation chambers, decontamination chambers, and 
other related structures.

Contract: URS Operating Services, Inc.; Purpose: 
Technical; Task/role performed: 
Provide sampling for anthrax in the Capitol Hill complex.

Contract: MVM Security & Staffing Services; Purpose: 
Security; Task/role performed: 
Provide security personnel to staff the single 
entrance/exit and to patrol perimeter of the storage location used for 
property removed from U.S. Senate offices during the cleanup to ensure 
that no unauthorized personnel enter the work area and assure that 
property items are not removed from the work area without approval of 
EPA.

Contract: TSI, Inc.; Purpose: 
Supplies; Task/role performed: 
Provide Porta Count plus respirator fit tester.

Contract: Noncompetitively awarded contracts.

Contract: Kemron Environmental Services, Inc.; Purpose: 
Technical; Task/role performed: 
Perform air sampling and perform HEPA vacuuming 
services; Remove critical items and documents, spray affected areas 
with chlorine dioxide, and perform cleaning and breakdown of work 
zones; Assist EPA in the evaluation of possible remediation of the 
heating, ventilation, and air-conditioning system, including 
evaluation of affected areas, and construction of critical barriers 
inside the ductwork to isolate affected areas from uncontaminated 
areas. After fumigation of the affected heating, ventilation, and air 
conditioning system, provide confirmatory sampling support, interior 
duct sampling, additional cleaning of the system (including post-
fumigation scrub down inside the ducts), and removal of duct 
insulation.

Contract: HMHTTC Response Team, Inc.; Purpose: 
Removal; Task/role performed: 
Perform cleanup activities, including construction and 
removal of isolation barriers, HEPA vacuuming operations, and 
application of liquid chlorine dioxide; Provide 24-hour support for 
decontamination and rescue operations at the Capitol Hill anthrax 
site.

Contract: Southwest Research Institute; Purpose: 
Laboratory work; Task/role performed: 
Provide analysis of spore strips placed in various locations 
during cleanup operations. Receive and perform daily observations of 
thousands of spore strips.

Contract: University of California--Berkeley Sponsored Projects 
Office; Purpose: Technical; Task/role 
performed: Participate in and support 
program plan development relating to spore sterilization technologies 
for remediation of federal facilities; Develop experimental and 
field test plans and methodologies for characterization/modeling spore 
killing processes and kinetics and factors that affect the efficacy of 
spore killing in field-scale applications; Establish laboratory 
systems for the measurement of gas phase sporicidal effects at federal 
office and mail facilities. Provide laboratory analytical support for 
measurement of gas phase sporicidal effects. Develop experimental and 
test plans and methodologies for assessing and validating spore killing 
processes; Determine the concentrations of chlorine dioxide needed 
to decontaminate anthrax on Capitol Hill. Prepare 31,500 test strips 
containing a bacillus similar to anthrax and send to Capitol Hill. The 
exposed strips will be sent to labs and results then will be sent to 
the University of California, Berkeley, to be included in a 
consolidated final report.

Contract: Silva Consulting Services, LLC; Purpose: 
Technical; Task/role performed: 
Maintain sample management system software in a 
private, secure environment on the Internet. Provide EPA personnel and 
designated contractor personnel secure, controlled access to the 
database. This system could generate a large variety of reports to 
address particular questions about sampling results.

Contract: Science Applications International Corporation; Purpose: 
Technical; Task/role performed: 
Provide consulting services to EPA on-
scene coordinator in environmental remediation of anthrax-contaminated 
buildings in the Capitol Hill complex. Support includes data 
interpretation of the spore strips used to test the efficacy of the 
kill of anthrax, data validation, review of documents, assistance in 
document preparation, and report writing. Coordinate efforts with the 
University of California, Berkeley.

Contract: Biomarine, Inc.; Purpose: 
Supplies; Task/role performed: 
Provide equipment that includes biopaks, facemasks, oxygen cylinders, 
gel tubes, foam scrubbers, coolant canister foam, flow restrictors, and 
biopak service and retrofit kits.

Contract: Envirofoam Technologies, Inc.; Purpose: 
Supplies; Task/role performed: 
Provide Sandia foam and backpack dispensing units.

Contract: Safeware, Inc.; Purpose: 
Supplies; Task/role performed: 
Provide respirators with battery and cartridge.

Contract: Airgas Safety; Purpose: 
Supplies; Task/role performed: 
Provide air purifying respirators.

Contract: Sabre Oxidation Technologies, Inc.; Purpose: 
Technical; Task/role performed: 
Provide engineering support during the assessment of 
the feasibility and design of the systems for fumigating air handling 
return system.

Contract: U.S. Art Company, Inc.; Purpose: 
Technical; Task/role performed: 
Provide training on proper procedures for handling, 
packaging, and decontaminating artifacts (paintings, sculptures, and 
other art forms) from the Hart Senate Office Building.

Contract: Mine Safety Appliances; Purpose: 
Supplies; Task/role performed: 
Provide self-contained breathing apparatus system.

Contract: Coastal Safety & Health Services, Inc.; Purpose: 
Supplies; Task/role performed: 
Provide indoor air quality meter.

Contract: New Horizons Diagnostics Corporation; Purpose: 
Supplies; Task/role performed: 
Provide anthrax detection kits.

Source: EPA.

[End of table]

[End of section]

Appendix II: GAO Contacts and Staff Acknowledgments:

GAO Contacts:

John B. Stephenson (202) 512-3841:

Christine Fishkin (202) 512-6895:

Staff Acknowledgments:

In addition to those named above, Heather Balent, Greg Carroll, Nancy 
Crothers, Richard Johnson, and Susan Lawes made key contributions to 
this report.


FOOTNOTES

[1] Technically, the term "anthrax" refers to the disease caused by the 
spore-forming bacterium, Bacillus anthracis, and not the bacterium or 
its spores. In this report, we use the term to refer to the bacterium 
and its spores to reflect terminology commonly used in the media and by 
the general public.

[2] The cleanup decisions were authorized by EPA in "action memoranda" 
the agency uses for Superfund response decisions.

[3] Sandia foam is a decontaminant that neutralizes chemical and 
biological agents.

[4] The Brentwood Processing and Distribution Center was renamed the 
Joseph Curseen, Jr., and Thomas Morris, Jr., Processing and 
Distribution Center in September 2002 in honor of two postal employees 
who died as a result of anthrax exposure at the facility. The facility 
is still commonly referred to as Brentwood.

[5] The expenditures reported are as of March 14, 2003, and were paid 
under total obligations of about $30 million. Obligations are contracts 
awarded, services received, and similar transactions during a given 
period that will require payment during the same or future period.

[6] Including the four fatalities discussed, the letters contaminated 
with anthrax caused 23 illnesses and resulted in five deaths.

[7] We did not validate the personnel costs reported by the Office of 
the Chief Financial Officer. These costs may be somewhat understated 
because documents we reviewed showed that at least five of the on-scene 
coordinators who worked at the Capitol Hill anthrax cleanup for 3 weeks 
or less were not identified by EPA as having their hours worked and/or 
transportation expenses assigned to the cleanup job.

[8] According to EPA officials, the agency decided to allocate direct 
personnel costs (salaries and travel expenses) to the anthrax cleanup 
but not indirect costs, such as contract management support, which it 
normally allocates to Superfund cleanups. Under the Superfund program, 
EPA seeks to recover costs from the responsible party or parties.

[9] Most of these contracts are for 5-year terms.

[10] Under the Federal Supply Schedule, GSA awards contracts to 
multiple companies supplying comparable products and services after 
determining that the prices negotiated were fair and reasonable. 
Federal agencies may use the supply schedule to purchase commercial 
services requiring a statement of work but are responsible for 
determining that the total contract prices are fair and reasonable, 
considering the level of effort and mix of labor skills needed to 
perform specific tasks. Agencies ordering services that require a 
statement of work are to transmit their requests for services to at 
least three contractors. However, EPA awarded this contract without 
soliciting bids from three contractors on the basis that there was an 
unusual and compelling need to obtain the services without delay. 

[11] The Environmental Response Team assists EPA regions and other 
federal agencies responding to environmental emergencies by providing a 
wide range of technical expertise and equipment.

[12] Forty-six of the survey respondents were on-scene coordinators.

[13] The site administrative officer did not review the costs 
associated with the other two removal contracts--a GSA federal supply 
contract and a noncompetitive contract awarded for a limited period of 
time--on a daily basis because the contractors had not input these into 
the computerized cost tracking system used for the review.

[14] This report focused largely on the Capitol Hill anthrax cleanup 
but also included EPA's roles in other anthrax incidents, such as at 
other federal facilities.

[15] Generally on-scene coordinators review and approve costs for 
removal contracts and review costs for technical contracts; project 
officers generally approve costs for technical contracts.

[16] This and the other Region III technical contract were negotiated 
as fixed-price contracts with cost reimbursement provisions. Under 
these contracts, contractors provide EPA with "dedicated teams" that 
provide technical assistance at set monthly rates for up to a 
predetermined amount of time; additional time may be provided at fixed 
hourly rates; and other specialized personnel and contractor travel and 
subcontracting are included among the items that are paid under the 
cost reimbursement provisions. 

[17] EPA staff overseeing the work are referred to as "work assignment 
managers" in the EPA manual.

[18] As discussed, at the Capitol Hill anthrax cleanup, EPA's lead on-
scene coordinator reported to the Capitol Police Board, and about 50 
on-scene coordinators worked at the site during the cleanup.

[19] Region III refers to this position as site administrative officer 
or field administrative specialist.

[20] We contacted regions II, III, IV, V, VIII, IX, and X.

GAO's Mission:

The General Accounting Office, the investigative arm of Congress, 
exists to support Congress in meeting its constitutional 
responsibilities and to help improve the performance and accountability 
of the federal government for the American people. GAO examines the use 
of public funds; evaluates federal programs and policies; and provides 
analyses, recommendations, and other assistance to help Congress make 
informed oversight, policy, and funding decisions. GAO's commitment to 
good government is reflected in its core values of accountability, 
integrity, and reliability.

Obtaining Copies of GAO Reports and Testimony:

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through the Internet. GAO's Web site ( www.gao.gov ) contains 
abstracts and full-text files of current reports and testimony and an 
expanding archive of older products. The Web site features a search 
engine to help you locate documents using key words and phrases. You 
can print these documents in their entirety, including charts and other 
graphics.

Each day, GAO issues a list of newly released reports, testimony, and 
correspondence. GAO posts this list, known as "Today's Reports," on its 
Web site daily. The list contains links to the full-text document 
files. To have GAO e-mail this list to you every afternoon, go to 
www.gao.gov and select "Subscribe to e-mail alerts" under the "Order 
GAO Products" heading.

Order by Mail or Phone:

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to:

U.S. General Accounting Office

441 G Street NW,

Room LM Washington,

D.C. 20548:

To order by Phone: 	

	Voice: (202) 512-6000:

	TDD: (202) 512-2537:

	Fax: (202) 512-6061:

To Report Fraud, Waste, and Abuse in Federal Programs:

Contact:

Web site: www.gao.gov/fraudnet/fraudnet.htm E-mail: fraudnet@gao.gov

Automated answering system: (800) 424-5454 or (202) 512-7470:

Public Affairs:

Jeff Nelligan, managing director, NelliganJ@gao.gov (202) 512-4800 U.S.

General Accounting Office, 441 G Street NW, Room 7149 Washington, D.C.

20548: