This is the accessible text file for GAO report number GAO-07-1040 
entitled 'Military Base Realignments and Closures: Plan Needed to 
Monitor Challenges For Completing More Than 100 Armed Forces Reserve 
Centers' which was released on September 13, 2007. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Report to Congressional Addressees: 

United States Government Accountability Office: 

GAO: 

September 2007: 

Military base realignments and closures: 

Plan Needed to Monitor Challenges for Completing More Than 100 Armed 
Forces Reserve Centers: 

Military Base Realignments and Closures: 

GAO-07-1040: 

GAO Highlights: 

Highlights of GAO-07-1040, a report to congressional addressees. 

Why GAO Did This Study: 

The Army is implementing 44 base realignment and closure (BRAC) 
recommendations to construct 125 new Armed Forces Reserve Centers 
(AFRC) and close 387 existing reserve components facilities. The 
Department of Defense (DOD) expects the new AFRCs to increase 
recruiting and retention and create greater efficiencies by fostering 
jointness and consolidating functions. GAO (1) assessed the extent 
DOD’s cost and savings estimates to implement the recommendations have 
changed from BRAC Commission projections and (2) determined the extent 
the Army has identified potential challenges that could affect BRAC 
implementation and has developed a plan to address these challenges. 

GAO analyzed DOD’s publicly available BRAC budget data and interviewed 
officials at Army offices, including Reserve Command, National Guard 
Bureau, and the National Guard in five states. This report, prepared 
under the Comptroller General’s authority to initiate evaluations, is 
one of a series related to the BRAC 2005 round. 

What GAO Found: 

Since the BRAC Commission issued its projections in 2005, DOD’s cost 
estimates for implementing the reserve component recommendations have 
increased at the same time savings estimates have decreased. 
Implementation cost estimates increased from $2.9 billion to $3.2 
billion—a 13 percent or $363 million increase in constant 
dollars—mostly due to higher military construction cost estimates. 
Annual recurring savings estimates decreased from $323 million to $288 
million—an 11 percent decrease in constant dollars. However, GAO 
analysis suggests that these savings could be significantly less than 
currently estimated because over 90 percent of these savings are 
associated with eliminating positions currently held by military 
personnel without corresponding decreases in end strength in the force 
structure. GAO and the BRAC Commission have previously reported that 
military personnel eliminations are not a true source of savings 
because DOD does not expect to reduce end strength correspondingly but 
rather intends to reassign or shift these personnel to vacant positions 
in other areas. Although GAO agrees that transferring personnel to 
vacant positions may enhance capabilities and allows DOD to redirect 
freed-up resources to another area of need, GAO does not believe that 
such transfers produce a tangible dollar savings that DOD can apply to 
fund other defense priorities outside the military personnel accounts 
because these personnel will remain in the end strength—continuing to 
receive salaries and benefits. However, DOD’s treatment of military 
personnel savings represents a long-standing difference of opinion 
between DOD and GAO. 

The Army has identified several potential challenges in implementing 
the 44 reserve component recommendations. These include completing many 
construction projects in a compressed time frame, realizing 
efficiencies based on limited testing of new military construction 
processes, potential increasing land and supporting infrastructure 
costs, and changing force structure and mission requirements that may 
affect facility capacity. The Army has started construction on 5 of the 
125 AFRC projects, and the extent these challenges might occur remains 
uncertain until the Army receives and evaluates more AFRC construction 
proposals and more AFRCs are built. However, because the Army does not 
have a plan to routinely bring together the various key stakeholders 
involved in the construction of these facilities, including the state 
Army National Guard when appropriate, the extent the Army is able to 
monitor and quickly address potential challenges is unclear. Best 
practices suggest that involving stakeholders in planning can help 
create a clearer understanding among the stakeholders of competing 
demands, the limited resources available, and how those demands and 
resources require continuous balancing. Without a plan that brings 
together key stakeholders, it could be more difficult for the Army to 
monitor for implementation challenges and work through alternatives to 
mitigate them in a timely manner. 

What GAO Recommends: 

GAO is recommending that the Secretary of Defense direct the Army to 
develop a plan for bringing together various stakeholders to monitor 
and address potential challenges. DOD partially concurred with GAO’s 
recommendation. 

[hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-07-1040]. 

To view the full product, including the scope and methodology, click on 
the link above. For more information, contact Brian Lepore at (202) 512-
4523 or leporeb@gao.gov. 

[End of section] 

Contents: 

Letter: 

Results in Brief: 

Background: 

Cost Estimates Have Increased from BRAC Commission's Projections While 
Savings Estimates Decreased: 

Potential Challenges Exist to Implement Army's BRAC Recommendations 
Affecting Its Reserve Components: 

Conclusions: 

Recommendation for Executive Action: 

Agency Comments and Our Evaluation: 

Appendix I: Scope and Methodology: 

Appendix II: Comments from the Department of Defense: 

Appendix III: GAO Contact and Staff Acknowledgments: 

Related GAO Products: 

Table: 

Table 1: Comparison of BRAC Cost and Savings Estimates: 

Figures: 

Figure 1: Armed Forces Reserve Center, Greenville, North Carolina: 

Figure 2: Locations Where the Army Plans to Construct New Armed Forces 
Reserve Centers by September 15, 2011: 

Figure 3: Army's Rescheduling of AFRC Project Construction Starts 
(Fiscal Years 2006 through 2011): 

Abbreviations: 

AFRC: Armed Forces Reserve Center: 
BRAC: base realignment and closure: 
DOD: Department of Defense: 
OSD: Office of the Secretary of Defense: 

[End of section] 

United States Government Accountability Office: 

Washington, DC 20548: 

September 13, 2007: 

Congressional Addressees: 

On May 13, 2005, the Department of Defense (DOD) made public its 
recommendations for base realignment and closure (BRAC) as part of an 
effort to reduce excess infrastructure and costs, further 
transformation, and foster jointness. After performing its own 
analysis, the BRAC Commission[Footnote 1] forwarded the recommendations 
to the President for approval. These recommendations were accepted in 
their entirety by the President and Congress, and became effective on 
November 9, 2005. The BRAC Commission directed 56 BRAC 2005 
recommendations to the Army, of which 44 pertained to the reserve 
components.[Footnote 2] These 44 recommendations represent more than 
500 individual actions representing over 60 percent of the BRAC actions 
for all the services and primarily direct the Army National Guard and 
Army Reserve to construct 125 new Armed Forces Reserve Centers (AFRC) 
and close 387 existing facilities. DOD expects the new AFRCs will 
increase recruiting and retention and create greater efficiencies and 
improved effectiveness by fostering jointness and consolidating 
functions. Moreover, the Army reported to the BRAC Commission that 
these new AFRCs will increase military value and improve the readiness 
and ability of the reserve components to train and deploy in support of 
current and future contingency operations. At the same time the Army is 
to construct these AFRCs, it is also undertaking a massive worldwide 
restationing initiative that involves the implementation of other 
significant Army BRAC recommendations; the relocation of about 50,000 
soldiers and their families from Germany and Korea to the United 
States; the transformation of an Army force structure based on a 
division organization to more rapidly deployable, brigade-based units; 
and an increase in the Army's authorized end strength by 74,000 over 
the next 5 years. By statute, DOD must complete the recommendations for 
closing or realigning bases made in the BRAC 2005 round within a 6-year 
time frame ending September 15, 2011--6 years from the date the 
President submitted to Congress his approval of the commission's 
recommendation.[Footnote 3] As a result, the ability to quickly 
identify and mitigate challenges that could arise is imperative to the 
Army's success in managing the construction of 125 AFRCs, 
implementation of over 500 actions, and meeting the BRAC statutory 2011 
deadline. 

This report is one in a series of reports that detail the progress DOD 
has made in implementing the base closures and realignments included in 
the BRAC 2005 round. Because of the broad congressional interest in the 
BRAC process, we performed our work under the Comptroller General's 
authority to conduct evaluations under his own initiative.[Footnote 4] 
In this report, we assessed the extent to which (1) BRAC cost and 
savings estimates for the Army reserve component recommendations have 
changed from BRAC Commission projections and (2) the Army has 
identified potential challenges that could affect the implementation of 
the recommendations and has developed a plan to address these 
challenges. This report is addressed to you to facilitate your 
oversight role for the Army's infrastructure and BRAC implementation 
issues. 

To accomplish these objectives, we assessed the changes to the cost and 
savings estimates reported in the BRAC Commission report and the Army's 
BRAC budget justification materials provided to Congress in support of 
the President's fiscal year 2008 budget request. All cost and savings 
estimates have been adjusted for inflation and are presented in fiscal 
year 2005 constant dollars. In addition, we interviewed key officials 
involved in implementing the recommendations to understand the 
potential challenges the Army faces in completing the recommendations 
by the end of the 6-year statutory completion period. We performed our 
work at the Office of the Secretary of Defense's (OSD) BRAC Office, 
Office of the Assistant Secretary of Defense for Reserve Affairs, 
Office of the Assistant Secretary of the Army for Installations and 
Environment, Army's Office of the Assistant Chief of Staff for 
Installation Management, National Guard Bureau, Office of the Chief 
Army Reserve, Army Reserve Command, and U.S. Army Corps of Engineers. 
We also interviewed National Guard officials in five states and 
officials in two Army Reserve regional readiness commands most affected 
by the BRAC 2005 recommendations. We found DOD's data to be 
sufficiently reliable for the purposes of this report and for making 
broad estimated cost and savings comparisons. We conducted our work 
from June 2006 through June 2007 in accordance with generally accepted 
government auditing standards. Further details on our scope and 
methodology can be found in appendix I. 

Results in Brief: 

DOD's cost estimates for implementing the Army reserve component 
recommendations have increased compared with those projected by the 
BRAC 2005 Commission while the savings estimates have decreased. Based 
on data in DOD's fiscal year 2008 President's budget submission, 
estimated costs to implement the recommendations have increased from 
$2.9 billion to $3.2 billion in constant fiscal year 2005 dollars--a 13 
percent or $363 million increase--mostly because of higher military 
construction cost estimates. Furthermore, we calculated that the annual 
recurring savings projected to accrue starting in 2012 decreased by 11 
percent, to $288 million. Moreover, our analysis suggests that these 
annual recurring savings could be significantly less than what is 
projected in the fiscal year 2008 budget submission because more than 
90 percent of these savings are associated with eliminating positions 
currently held by military personnel without corresponding force 
structure end-strength reductions. We have previously reported, and the 
BRAC Commission agreed, that military personnel position eliminations 
are not a true source of savings because DOD does not expect to reduce 
end strength correspondingly but rather intends to reassign or shift 
these personnel to vacant positions in other areas. DOD's assumption 
behind the military personnel savings is that transferring military 
personnel to vacant positions allows DOD to obtain new and additional 
capabilities without having to request additional appropriations to 
hire personnel for these positions. Although we agree that transferring 
personnel to vacant positions may enhance capabilities and allows DOD 
to redirect freed-up resources to another area of need, we do not 
believe that such transfers produce a tangible dollar savings that DOD 
can apply to fund other defense priorities outside the military 
personnel accounts because these personnel will remain in the end 
strength--continuing to receive salaries and benefits. In fact, the 
Army plans to increase its reserve component's end-strength 
authorization by about 9,000 military members over the next 5 years. 
Not recognizing that these dollar savings cannot be readily applied 
elsewhere could create a false sense of the savings available for use 
in other areas outside the military personnel account, such as 
modernization. However, DOD's treatment of military personnel savings 
represents a long-standing difference of opinion between DOD and us. 

The Army has identified several potential challenges that could affect 
its ability to successfully construct all 125 AFRCs within the current 
$3 billion estimate and by the 2011 statutory deadline;[Footnote 5] 
however, it is unclear whether the Army will be able to successfully 
address these challenges because the Army does not have a plan that 
routinely brings together the various stakeholders, including the state 
Army National Guard when appropriate, to help them monitor for 
implementation challenges and to quickly take steps to mitigate those 
challenges should they occur. Although the Army has started 
construction on only 5 out of 125 AFRCs (3 Reserve-led and 2 Guard-led) 
and none were completed at the time we completed the work for this 
report, reserve component officials told us that the more significant 
challenges that could affect BRAC implementation are the following: 

* Completing construction of all AFRCs in compressed time frame: The 
Army rescheduled the construction for many AFRC projects to start later 
in the BRAC implementation period, thus increasing the number of 
projects to be managed in a more compressed time frame. This compressed 
construction time frame, in turn, reduces the time available to 
mitigate unforeseen problems that may arise and increases the risk that 
the AFRC projects and BRAC-recommended realignments may not be 
completed by the 2011 statutory deadline. 

* Realizing efficiencies from new military construction processes that 
have undergone limited testing: The Army recently transformed its 
military construction process in an effort to reduce costs and build 
facilities faster. Because these new processes have undergone limited 
testing, it remains uncertain whether these efficiencies will be 
realized although the Army has already included these projected 
efficiency savings in its BRAC budget estimates for fiscal years 2006 
through 2011. 

* Potential increasing land and supporting infrastructure costs: Cost 
estimates for land and supporting infrastructure could be higher 
because for many AFRCs earlier estimates were too low. Also, supporting 
infrastructure, such as access roads and utilities, are lacking because 
of the remoteness of some AFRC sites, which officials told us could 
increase costs. 

* Changing force structure and mission requirements for units slated to 
occupy AFRCs: Future force structure and mission requirements could 
change the composition and requirements of some units relocating into 
new AFRCs. As a result, Army National Guard officials told us that some 
new centers may not fully meet the personnel and equipment requirements 
of certain types of newly-formed units, such as the fires brigades 
being created by Army modularity.[Footnote 6] 

It is unclear whether the Army will be able to successfully address 
these challenges if they arise because the Army does not have a plan 
that routinely brings together the various stakeholders, including the 
state Army National Guard when appropriate, as a group to help them 
monitor for potential challenges and develop plans to mitigate the 
challenges should they occur. Effective development of such a plan for 
BRAC implementation would better enable the Army to measure progress 
toward its goals and identify strategies to meet goals that were not 
met because of implementation challenges. Reserve component officials 
further noted that this issue is important given that so many 
stakeholders with varying viewpoints and perspectives on the potential 
challenges are involved in the construction of the 125 AFRCs. Although 
the construction of these reserve centers is guided by 44 separate 
business plans that describe required actions, their timing, and 
resources, both Army National Guard and Reserve Command officials told 
us that these plans do not provide the information needed to quickly 
develop plans to mitigate these challenges should they occur. In 
addition, Army officials told us that should some of these challenges 
occur, they might have to adapt by choosing one or more of the 
following alternatives: (1) requesting more BRAC funds, (2) reducing 
the scope of a construction project, (3) expanding the use of 
alternative, less expensive construction materials, (4) requesting 
additional funds from the regular military construction appropriations, 
or (5) using funds as allowable from operation and maintenance 
appropriations. Finally, National Guard officials said they could 
exercise additional alternatives, such as using state funds, seeking 
assistance from state congressional delegations, or allowing temporary 
overcrowding of the AFRCs. However, the extent to which challenges will 
occur and alternatives will be used remains uncertain until the Army 
receives and evaluates more AFRC construction proposals and more 
centers are built. 

To better ensure that BRAC 2005 recommendations affecting the Army's 
reserve components and interests of the states are effectively managed 
and any potential adverse effects are quickly identified, we are making 
a recommendation to the Secretary of Defense to direct the Secretary of 
the Army to develop a plan for routinely bringing together the various 
stakeholders as a group, to include the state Army National Guard when 
appropriate, to monitor for and develop steps to mitigate 
implementation challenges should they occur. Without a plan that 
involves bringing together the stakeholders to help monitor for 
challenges and work through alternatives, early identification of 
challenges and development of steps to mitigate them in a timely manner 
becomes more difficult. Best practices suggest that involving 
stakeholders in planning can help create a clearer understanding among 
the stakeholders of competing demands, the limited resources available, 
and how those demands and resources require continuous balancing. 

In commenting on a draft of this report, DOD partially concurred with 
our recommendation. While stating that we appropriately highlighted 
BRAC implementation challenges due to transformation, modularity, 
mission changes, and construction factors affecting BRAC military 
construction projects, to include changes to initial BRAC cost savings 
projections and military construction time frames, DOD believes that we 
overlooked the existence of various groups, forums, or plans that the 
Army has in place to assist with BRAC execution and management. 
Although we were aware of these groups, forums, and plans during the 
course of our work, we nonetheless found that these venues were not 
adequately meeting the needs of many reserve component and state-level 
stakeholders. For example, during our review many Army National Guard 
and Reserve officials still expressed confusion and frustration over 
how to respond to certain challenges associated with the construction 
of the 125 new AFRCs despite the existence of these various venues. 
Moreover, these AFRCs are to be in 38 states and because local 
circumstances may vary, it is unclear how planning groups that exclude 
the states will be positioned to effectively mitigate the risks that 
may be unique to a given location. Consequently, we still believe that 
the Army would benefit from routinely bringing together the reserve 
component and state-level stakeholders who are playing a vital role in 
the planning of the actual design and construction of the AFRCs so that 
challenges and issues can be effectively mitigated before the AFRCs are 
built and subsequently require potential modification. As a result, we 
continue to believe that our recommendation has merit. However, to 
clarify our intent, we modified our recommendation to specifically 
include state National Guard stakeholders when appropriate. DOD's 
written comments are reprinted in appendix II. DOD also provided 
technical comments, which we have incorporated into this report as 
appropriate. 

Background: 

The BRAC Commission directed 56 BRAC 2005 recommendations to the Army, 
of which 44 pertained to the reserve components. After the 44 reserve 
component recommendations became effective on November 9, 2005, OSD 
required the Army to submit a detailed business plan for each 
recommendation that includes information such as a listing of all BRAC 
actions, schedules for personnel movements between installations and 
reserve centers, updated cost and savings estimates, and implementation 
completion time frames. In total, the 44 recommendations affecting the 
reserve components direct the construction of 125 new AFRCs. Of the 44 
recommendations, 5 involve the realignment of the Army Reserve's 
command and control structure within five regional areas. An AFRC is a 
joint-use facility that accommodates units from two or more reserve 
components. The primary function of an AFRC is to provide 
administrative, training, and storage areas for the assigned military 
units. As a joint-use facility, the interior of an AFRC consists of 
space shared by all occupying components--such as assembly halls, 
classrooms, conference rooms, physical fitness areas, and restrooms--as 
well as space used exclusively by individual components, such as 
offices, equipment storage, and weapons vaults. In addition, a vehicle 
maintenance shop with work bays and maintenance administrative support 
facilities is generally adjacent to the AFRC to allow units to store 
and maintain their respective military vehicles and related equipment. 
Figure 1 shows an example of an existing AFRC. 

Figure 1: Armed Forces Reserve Center, Greenville, North Carolina: 

[See PDF for image] 

Source: Army Corps of Engineers. 

[End of figure] 

The implementation of these BRAC recommendations involves many key 
stakeholders with differing levels of responsibilities. 

* Army headquarters level has four main offices with BRAC 
responsibilities. 

- Assistant Secretary of the Army for Installations and Environment 
establishes overall Army BRAC policy, direction, and oversight. 

- Assistant Chief of Staff for Installation Management manages the 
overall execution of Army BRAC actions. This office has two primary 
divisions with BRAC responsibilities. First, the BRAC Division serves 
as the program manager for Army base closures, realignments, and 
disposals and manages the financial aspects of the BRAC program. 
Second, the Army Reserve Division serves as the principal advisor for 
the Army Reserve BRAC recommendations. 

- Army Reserve Command oversees the Army Reserve's transformation and 
integrates it with the BRAC program. 

- National Guard Bureau serves as the central coordinator for the 
individual states and for the Army National Guard BRAC recommendations. 

* At the state and regional level, there are two other organizations 
with BRAC responsibilities. 

- Reserve regional readiness commands manage the facilities for the 
Army Reserve units assigned in their respective region. In partnership 
with the Army Reserve Division, these commands develop the requirements 
and budget justification documents needed to construct the 76 Reserve- 
led AFRCs. 

- State National Guard Construction and Facilities Management Offices 
are the principal administrators for the states' military real 
property, facilities, military construction, and environmental 
programs. In partnership with the National Guard Bureau, these state 
offices develop the requirements and budget justification documents 
needed to construct the 49 National Guard-led AFRCs. 

* The Army Corps of Engineers is the Army's primary construction agent 
and provides military construction execution oversight for Reserve-led 
AFRCs. It also assists the Army Reserve Division in the development and 
preparation of the requirements and budget justification documents 
needed to construct the Reserve-led AFRCs. 

Responsibility for managing the actual construction of the AFRCs is 
divided between the two Army Reserve Components--Army National Guard 
and the Army Reserve--with land ownership being a key determinant of 
which component manages which AFRC project. For AFRCs built on federal 
land, whether already owned or to be acquired by the federal 
government, the Army Reserve is the lead component (76 centers out of 
125). In these cases, the Army Reserve in partnership with the Army 
Corps of Engineers identifies and purchases the land, if needed, and 
the Corps manages the construction. In contrast, for AFRCs built on 
state land, whether already owned or to be acquired by the state, each 
state's respective Army National Guard is the lead component (49 
centers out of 125). The National Guard became the lead for these 49 
projects because it indicated to the Army that it either already owned 
suitable land for the AFRC or was able to acquire it at no cost to the 
federal government. For these National Guard-led AFRCs, each state's 
Construction and Facilities Management Office, rather than the Army 
Corps of Engineers, manages the contracting. Regardless of the reserve 
component that manages the construction and where the AFRCs are built, 
DOD provides 100 percent of the funding to construct the 125 AFRCs. 
States are not required to share in AFRC construction cost. The 
expected cost of the 125 AFRCs ranges from $1.5 million to up to $81 
million. The Army started construction on 5 AFRCs in 2006 and expects 
to start construction on 27 more in late fiscal year 2007 if funding 
becomes available. Figure 2 shows the location of the 125 AFRCs 
expected to be constructed because of BRAC recommendations. 

Figure 2: Locations Where the Army Plans to Construct New Armed Forces 
Reserve Centers by September 15, 2011: 

[See PDF for image] 

Source: BRAC Commission (data); MapInfo (map). 

[End of figure] 

Cost Estimates Have Increased from BRAC Commission's Projections While 
Savings Estimates Decreased: 

Data from the fiscal year 2008 President's budget submission show that 
expected costs for implementing the BRAC Army reserve component 
recommendations have increased and expected savings have decreased from 
the BRAC Commission projections. We calculated that DOD's onetime costs 
to implement the BRAC Army reserve component recommendations increased 
$363 million or 13 percent, from $2.9 billion to $3.2 billion, during 
the BRAC 6-year implementation period compared to the BRAC Commission's 
estimates. After the BRAC implementation period, we calculated that DOD 
will achieve a net annual savings of $288 million, 11 percent less than 
the BRAC Commission's estimate of $323 million, as shown in table 1. 

Table 1: Comparison of BRAC Cost and Savings Estimates: 

Dollars in millions (constant fiscal year 2005 dollars). 

Onetime costs during implementation through fiscal year 2011; 
2005 BRAC Commission- reported estimates: $2,857; 
DOD's fiscal year 2008 budget estimates: $3,220; 
Difference: Amount: $363; 
Difference: Percentage: 13. 

Net annual recurring savings after the implementation period; 
2005 BRAC Commission- reported estimates: 323; 
DOD's fiscal year 2008 budget estimates: 288; 
Difference: Amount: (35); 
Difference: Percentage: (11). 

Source: GAO's analysis. 

[End of table] 

Increases in projected military construction costs account for 97 
percent of the increase in onetime costs during implementation. 
Projected military construction costs mainly rose because of increased 
requirements that resulted from the BRAC Commission's estimates either 
underestimating the amount of construction needed or omitting certain 
requirements, such as vehicle maintenance shops, that have now been 
included. For example, the estimated military construction costs for 
the recommendation to build 17 AFRCs in Texas increased from $313 
million to $387 million, or 24 percent, mostly because the original 
square footage estimates for many of the new AFRCs were underestimated 
and lacked vehicle maintenance shops. 

In addition, the savings projected to accrue from the BRAC 2005 reserve 
component recommendations starting in fiscal year 2012 have decreased. 
Although achieving savings is one of the rationales for undertaking a 
BRAC round, DOD also cited other goals such as achieving reserve 
component transformation and increasing recruiting and retention to 
justify the need for the reserve component recommendations. Once 
implementation is completed, DOD believes it will achieve a steady rate 
of annual savings. The BRAC Commission estimated that the BRAC 2005 
Army reserve component recommendations would result in an annual 
recurring savings of $323 million. Based on data in DOD's fiscal year 
2008 President's budget submission, annual recurring savings decreased 
by 11 percent, to $288 million. However, 92 percent or $265 million of 
the annual recurring savings are attributable to eliminating positions 
currently held by military personnel, which both we and the BRAC 
Commission do not consider savings because the Army reserve components 
do not plan to reduce their military personnel end strength. If the 
savings due to military personnel eliminations are removed, then annual 
recurring savings would be reduced from $288 million to $23 million. We 
have previously reported, and the BRAC Commission agreed, that military 
personnel position eliminations are not a true source of savings 
because DOD does not expect to reduce end strength correspondingly but 
rather intends to reassign or shift these personnel to vacant positions 
in other areas. DOD's assumption behind the military personnel savings 
is that transferring military personnel to vacant positions allows DOD 
to obtain new and additional capabilities without having to request 
additional appropriations to hire personnel for these positions. 
Although we agree that transferring personnel to vacant positions may 
enhance capabilities and allows DOD to redirect freed-up resources to 
another area of need, we do not believe that such transfers produce a 
tangible dollar savings that DOD can apply to fund other defense 
priorities outside the military personnel accounts because these 
personnel will remain in the end strength--continuing to receive 
salaries and benefits. In fact, the Army plans to increase its reserve 
component's end-strength authorization by about 9,000 military members 
over the next 6 years. Not recognizing that these dollar savings cannot 
be readily applied elsewhere could create a false sense of the savings 
available for use in other areas outside the military personnel 
account, such as modernization. However, DOD's treatment of military 
personnel savings represents a long-standing difference of opinion 
between DOD and us. 

Potential Challenges Exist to Implement Army's BRAC Recommendations 
Affecting Its Reserve Components: 

The Army identified several challenges that it may face when 
implementing the BRAC 2005 reserve component recommendations to build 
125 AFRCs. Although the Army has started construction on only 5 out of 
125 AFRCs (3 Reserve-led and 2 Guard-led) and none were completed at 
the time we completed the work for this report, reserve component 
officials told us that the more significant challenges that could 
affect BRAC implementation include completing many construction 
projects in a compressed time frame, realizing efficiencies when using 
new military construction processes, potential increasing land and 
supporting infrastructure costs, and changing force structure and 
mission requirements that affect facility capacity. 

Completing Construction of All AFRCs in Compressed Time Frame: 

Other BRAC funding priorities caused the Army recently to shift the 
start of many of its AFRC projects to the later years of the time frame 
ending with the BRAC statutory 2011 deadline. This approach compresses 
the amount of time available to construct the facilities and respond to 
any construction delays that might arise and consequently increases the 
risk that the projects will not be completed in time to meet the BRAC 
statutory completion deadline. As shown in figure 3, the Army 
rescheduled the start of 20 projects that originally were slated to 
begin construction in either fiscal year 2008 or 2009 to fiscal year 
2010--the second to last year of the BRAC statutory completion period. 

Figure 3: Army's Rescheduling of AFRC Project Construction Starts 
(Fiscal Years 2006 through 2011): 

[See PDF for image] 

Source: GAO analysis of OSD and Army data. 

Note: Data are from OSD-approved business plans and the fiscal year 
2008 Army budget justification submission to Congress. 

[End of figure] 

According to Army officials, the Army's reasoning for shifting many 
AFRCs to the later implementation years was to fund the more costly and 
complex BRAC recommendations first, such as those that could affect 
Army combat missions at locations like Fort Bliss, Texas, and Fort 
Riley, Kansas, earlier in the implementation period than originally 
planned. Also according to Army officials, the Army would assume less 
risk as smaller projects theoretically can be completed within shorter 
time frames compared to larger projects, which we believe is reasonable 
given our understanding of the BRAC construction process. 

Realizing Efficiencies from New Military Construction Processes That 
Have Undergone Limited Testing: 

Army officials also stated that the Army could be challenged in 
realizing anticipated cost savings from the Army Corps of Engineers' 
recent military construction transformation efforts. To reduce 
construction costs and complete construction projects faster, the Corps 
is currently transforming and streamlining its process for managing and 
contracting military construction projects by allowing contractors 
flexibility in using a wider variety of less expensive commercial 
construction materials while still meeting all the applicable building 
codes and functional and technical requirements. A major component of 
the transformation initiative is the use of a standard request for 
proposal that is less prescriptive. Based on these and other 
transformation changes, the Corps expects that construction costs of 
the primary facilities will be reduced by 15 percent. As such, the Army 
has already incorporated a 15 percent reduction in its construction 
estimates for all the AFRCs it is expected to build under BRAC. 
Although preliminary results are encouraging for several active Army 
construction projects, results based on a few AFRC projects remain 
inconclusive. Specifically, the Corps initiated three Army Reserve-led 
AFRC construction projects in 2006, which were awarded for amounts less 
than the amount budgeted by the Army. However, it is uncertain whether 
this cost reduction can be totally attributable to military 
construction transformation, as the supporting infrastructure costs to 
develop the sites for these projects were lower than what would 
typically be expected for an AFRC. According to Corps officials, these 
three pilot AFRC projects were located on Army installations with 
access to roads and available utilities, whereas most Army AFRC 
projects are expected to be located at remote or undeveloped sites that 
could be more expensive to develop because they generally require more 
road development and utility access. Moreover, it is uncertain whether 
the National Guard will achieve any of the military construction 
transformation savings because it does not generally use the Corps for 
managing construction projects and the states are not obligated to 
incorporate many of these transformational practices into the 
construction of the 49 Guard-led AFRCs, even though the projects are 
federally funded. 

Further, Army Corps of Engineers officials told us that some of the 
expected military construction transformation savings could decrease if 
the cost of construction materials escalates or there is a shortage of 
construction labor, especially in locations of high construction 
volume. Corps officials told us that in the last several years, the 
actual rate of construction inflation has exceeded the federal 
government's inflation rate as determined by the Office of Management 
and Budget, which DOD is required to use in budgeting for its 
construction projects. While this difference was as high as 6.1 
percentage points in 2004, the difference between the actual rate of 
construction inflation and the government's inflation rate has 
diminished recently. We note, however, that this trend may not 
necessarily continue into the future depending on the economics 
surrounding the construction industry. However, if construction 
inflation continues to exceed the rates used in the construction budget 
process, Corps officials told us they will try to overcome the 
inflation difference by negotiating with the building contractors for a 
lower construction price, redirecting funds from other sources, or 
reducing the scope of some construction projects.[Footnote 7] Given the 
potential for underestimated future inflation rates, combined with the 
fact that DOD is still early in the BRAC implementation process and the 
Corps has only started construction on three reserve-led AFRC projects 
(with the efficiencies gained from military construction transformation 
for those three being inconclusive), the Army lacks assurance it will 
be able to achieve the 15 percent reduction in military construction 
costs for the AFRC projects until it receives bids from more projects. 
Thus, it might have been premature of the Army to have already 
incorporated these anticipated savings into its BRAC budget requests 
before the Corps has more information with which to evaluate the 
results. 

Some Army officials also expressed concern that the Army Corps of 
Engineers' military construction transformation could result in a 
reduction in quality for the centers. Under military construction 
transformation, the Corps is broadening the construction materials 
standards for the AFRC projects it is managing. According to the Corps, 
broadening the standards will allow contractors to pursue a wider 
variety of alternate building systems in lieu of typical reserve 
standards, which is expected to help keep costs down. Previously, the 
Reserves generally required their AFRCs to be built using brick or 
concrete block. Now contractors--while still meeting all applicable 
building codes and technical requirements for the facility--may propose 
less expensive alternatives, such as wood frame, prefabricated and 
modular construction systems. For example, in two 2006 pilot projects 
the typical reserve standard of concrete blocks covered with a brick 
veneer was replaced with a less expensive metal frame covered with a 
brick veneer. However, several state-level Army National Guard 
officials and some Corps officials we met viewed this broadening of 
standards as a reduction in quality and maintain that the savings 
generated from using alternative construction materials may be offset 
later by increased maintenance and repair costs. Corps officials told 
us that they will be monitoring construction quality under these new 
processes but the actual outcome remains uncertain until the Army 
receives and evaluates more AFRC construction proposals and more 
centers are built. 

Potential Increasing Land and Supporting Infrastructure Costs: 

Army Corps of Engineers officials indicated that cost estimates for 
acquiring needed land and building supporting infrastructure could be 
higher than estimated because earlier estimates were too low for many 
Reserve-led projects[Footnote 8] and because supporting infrastructure, 
such as access roads and utilities, is lacking because of the 
remoteness of some AFRC sites. Although the BRAC Commission attempted 
to estimate purchase prices for land while developing the 
recommendations, cost projections for many AFRCs are expected to be 
higher based on some recent site visits. For example, in Connecticut, 
land has not been identified for a Reserve-led AFRC slated to start 
construction in 2007 because according to Corps officials the average 
cost of several proposed locations is $2 million--$1.1 million higher 
than initially projected. This could be even more problematic in the 
later years of BRAC's implementation period because as land 
identification is delayed, inflation and market demands could further 
increase land costs. According to our analysis, the Reserves have 18 
projects slated to begin from 2008 to 2010 where land costs are 
expected to exceed the amount estimated by the BRAC Commission. 
However, the extent these costs could increase will depend on the 
economics of the real estate market at the time of purchase. Moreover, 
Corps officials told us that because some Reserve-led AFRCs are 
expected to be at remote undeveloped sites, actual costs for supporting 
infrastructure, such as access roads and electricity, water, and sewer 
lines, could be higher than currently projected. Other Army officials, 
on the other hand, stated to us that higher than expected land 
acquisition and infrastructure support costs will not be a significant 
issue because the Army can use funds from other BRAC projects if costs 
for those other projects are lower than expected. For example, a 
challenging site location at Fort Lewis caused an increase in the cost 
estimate and as a result the Army recently initiated action to increase 
the programmed amount by $4 million. Although the Army was able to 
reallocate money for the Fort Lewis project, Corps of Engineers 
officials told us that some future projects could incur significantly 
higher supporting costs that the Army may be challenged in funding. 

Changing Force Structure and Mission Requirements for Units Slated to 
Occupy AFRCs: 

Army officials noted that the Army's changing force structure and 
mission requirements may affect the capacity of the AFRCs to meet the 
personnel and equipment requirements of some units relocating into new 
AFRCs. Army modularity is restructuring combat and combat support units 
from a division organization to smaller, more rapidly deployable 
brigade-size units. Reserve and National Guard officials told us that 
they planned for Army modularity changes in determining facilities 
requirements to the extent information was known, but some units were 
reconfigured, disestablished, or newly activated after the BRAC 
recommendations became effective, which complicates how the BRAC 
recommendations will be applied to these units. Furthermore, some Army 
National Guard officials told us that the new centers may not fully 
meet the personnel and equipment requirements of certain types of 
units. For example, Guard officials told us that personnel requirements 
for the newly formed fires brigade were less defined when the BRAC 
recommendations became effective and these requirements have doubled 
since then (e.g., fires brigades have grown from 350 to 750 personnel). 
As more force structure and mission change challenges emerge, Army BRAC 
offices, the National Guard Bureau, the Army Audit Agency, and the 
individual affected states are discussing BRAC implications. Although 
they are uncertain about precise outcomes due to Army modularity, Guard 
officials we interviewed did not see modularity as posing an 
insurmountable implementation challenge at this time because they tried 
to incorporate future modularity changes--to the extent the changes 
were known--into AFRC requirements and because state governors have 
flexibility to balance space requirements of their units with available 
facilities in the states to station their Guard units. However, because 
so few AFRCs have actually begun construction the extent to which 
pending force structure and mission changes could be potential problems 
remains uncertain. 

The Army's Ability to Monitor and Quickly Address Potential Challenges 
Is Unclear: 

It is unclear whether the Army will be able to successfully address 
potential implementation challenges affecting the completion of 125 
AFRC projects because it does not have a plan that routinely brings 
together the various stakeholders, including the state Army National 
Guard when appropriate, to monitor and address these challenges. 
Although the Army has several venues in place to assist with BRAC 
execution and management,[Footnote 9] in discussions with Army BRAC 
headquarters officials they acknowledged to us that they could be more 
proactive in outreaching and communicating with the stakeholders over 
how to deal with and mitigate particular challenges associated with 
constructing 125 AFRCs. Effective development of a plan to address 
challenges associated with the BRAC implementation would enable the 
Army to better communicate with stakeholders, measure progress toward 
its goals, and identify strategies to meet goals that were not met 
because of implementation challenges. Such planning is important to 
ensure that an organization's activities support its goals and are 
guided by good business principles, such as those embodied in the 
Government Performance and Results Act of 1993.[Footnote 10] Although 
the construction of the AFRCs is guided by 44 separate business plans 
that describe required actions, their timing, and resources, Guard and 
Reserve officials said that these plans do not provide the information 
needed to monitor for potential challenges or the steps needed to 
quickly mitigate them. Furthermore, we have previously reported that 
involving stakeholders in planning efforts can help create a clearer 
understanding among the stakeholders of the competing demands that 
confront most agencies, the limited resources available to them, and 
how those demands and resources require careful and continuous 
balancing.[Footnote 11] Because the Army's reserve components 
recommendations involve so many stakeholders, comprehensive and routine 
stakeholder involvement is essential to the success of the Army's 
implementation planning efforts. Additionally, a plan that involves key 
stakeholders would be important because AFRCs will be truly joint 
facilities--the Guard will be co-occupants of centers built by the 
Reserves and the Reserves will be co-occupants of centers built by the 
Guard--and because there are so many stakeholders involved in ensuring 
that construction is completed on time. 

In addition to the various Army headquarters offices that provide 
overall BRAC direction and oversight, key stakeholders involved with 
the Army's BRAC recommendations associated with Army reserve components 
include the Reserves, which is represented by officials from the Army 
Reserve Division of the Assistant Chief of Staff for Installation 
Management; the Office of the Chief Army Reserve; and the various 
regional readiness commands. Similarly, the Guard is represented by 
officials from the National Guard Bureau and officials in each state's 
respective Adjutant General and Construction and Facilities Management 
Office. Moreover, the U.S. Army Corps of Engineers plays a vital role 
in the construction of many AFRCs because it is the Army's primary 
construction agent, responsible for construction management of the 
Reserve-led AFRCs. In our discussions with officials, we found that 
many times component and state-level stakeholders were confused and 
frustrated regarding how to respond to potential challenges and had 
varying viewpoints and perspectives on how these challenges should be 
addressed if they occur. For example, some state National Guard 
officials said that they are concerned about the potential for a 
reduction in quality for many of the Reserve-led AFRCs because the 
Corps' military construction transformation effort is allowing 
alternative building materials to be used in lieu of the traditional 
brick and mortar. Conversely, Reserve officials told us that they were 
concerned about the extent to which the Guard might make what these 
officials deemed unsatisfactory scope reductions in the Guard-led AFRCs 
for such space as classrooms, assembly rooms, maintenance bays, and 
parking lots. Because of varying viewpoints and perspectives on the 
potential challenges and how they might be handled, opportunities for 
these stakeholders to express and address their concerns is of 
importance, particularily the resolution of potential issues before too 
many AFRCs are built. Army officials told us that should some of these 
challenges occur, they might have to adapt by choosing one or more of 
the following alternatives, many with potentially adverse effects: (1) 
request more BRAC funds, which would place additional demands on an 
account with a set limit of funds and potentially undermine DOD's 
ability to complete other BRAC recommendations unless OSD requests and 
receives more funds from Congress; (2) reduce the scope of a 
construction project to stay within the price limit, which could result 
in an overcrowded facility or inadequate space for storing mission- 
needed equipment and supplies; (3) work with the contractors to lower 
the cost by using more alternative, less expensive construction 
materials; (4) request additional funds from the regular military 
construction appropriations; or (5) use funds as allowable from 
operation and maintenance appropriations, which would leave other 
maintenance and repair requirements unfunded. 

Because it is early in the BRAC implementation process, the extent to 
which challenges will occur and alternatives will be used remains 
uncertain until the Army receives and evaluates more AFRC construction 
proposals and more centers are built. However, there are indications 
that some of the challenges identified by the Army are already 
beginning to occur. For example, the Army Corps of Engineers is 
currently debating what to do about two projects expected to start in 
2007--Fort Detrick, Maryland, and Fort Lewis, Washington--where current 
construction estimates exceed the amount budgeted. According to the 
Corps, higher-than-expected supporting infrastructure costs and 
estimate reductions based on anticipated military construction 
transformation efficiencies contributed to the difference between the 
current estimated cost to construct the AFRCs and what was actually 
budgeted, and consequently the projects might run out of money. In 
addition, several Corps officials expressed concern that many of the 
2007 and the 2008 project proposals may exceed the cost estimate set 
for the projects. If this happens, Corps officials told us that they 
could work with the contractors to expand the use of alternative 
construction materials or reduce the scope of a particular project to 
stay within the price limit. However, if the Corps has to reduce the 
scope, this increases the risk that the facility will be too small for 
the number of personnel or their equipment. Likewise, Guard officials 
told us that if they experience similar problems, they would consider 
other alternatives such as using operation and maintenance appropriated 
funds as allowed or requesting funds from the regular military 
construction appropriation. Finally, Guard officials said that they 
could use additional options if project proposals exceed cost 
estimates, such as using state funds, seeking assistance from state 
congressional delegations, allowing temporary overcrowding of the AFRC, 
or leaving open readiness centers expected to close under BRAC. For 
example, some Army Guard officials told us that if a newly built AFRC 
is overcrowded and does not adequately support the unit's personnel and 
equipment, they might retain certain existing armories or readiness 
centers that were expected to close under BRAC, which could further 
reduce BRAC savings and increase operation and maintenance costs should 
the centers continue to support a federal mission.[Footnote 12] 

Conclusions: 

As the Army begins its $3 billion BRAC construction of 125 new AFRCs 
around the nation, it will need to carefully manage many potential 
challenges that could place the successful implementation of the 
program at risk. We recognize that implementing these BRAC 
recommendations while the Army simultaneously implements other BRAC 
recommendations and ongoing, worldwide restationing and transformation 
initiatives is an extremely difficult and daunting task. Although we 
realize the Army has several venues in place to assist with BRAC 
execution and management, the Army has not established a plan that 
routinely brings together the various stakeholders, that includes the 
state Army National Guard when appropriate, to help monitor and address 
potential implementation challenges associated with completing the Army 
reserve component BRAC recommendations. Developing such a plan would 
better ensure clear communication and collaboration between key 
stakeholders, which is especially important given that many 
stakeholders have varying viewpoints and perspectives on these 
potential challenges and the possible adverse effects. Development of 
such a plan for BRAC implementation would also enable the Army to 
better measure progress toward its goals and identify strategies to 
meet goals that were not met because of implementation challenges. 
Without a plan that brings together key stakeholders including the 
state Army National Guard when appropriate, it will be more difficult 
for the Army to monitor for implementation challenges and work through 
alternatives to mitigate them in a timely manner. 

Recommendation for Executive Action: 

To better ensure that BRAC 2005 recommendations affecting the Army's 
reserve components and interests of the states are effectively managed 
and any potential adverse effects are quickly identified, we recommend 
that the Secretary of Defense direct the Secretary of the Army to 
develop a plan for routinely bringing together the various stakeholders 
as a group, to include the state Army National Guard when appropriate, 
to monitor for and develop steps to mitigate implementation challenges 
should they occur. These steps should include ways to monitor and 
mitigate the effects of potential challenges on BRAC completion time 
frames, project cost and scope, construction quality, and capacity of 
the facility to meet changing mission requirements. 

Agency Comments and Our Evaluation: 

In written comments on a draft of this report, DOD partially concurred 
with our recommendation. DOD's comments are reprinted in appendix II 
and addressed as appropriate in the body of the report. DOD further 
provided technical comments, which we also incorporated into this 
report as appropriate. 

DOD partially concurred with our recommendation that the Secretary of 
Defense direct the Secretary of the Army to develop a plan for 
routinely bringing together the various stakeholders as a group to 
monitor for and develop steps to mitigate implementation challenges 
should they occur to better ensure that BRAC recommendations affecting 
the Army's reserve components are effectively managed and any potential 
adverse effects are quickly identified and mitigated. While stating 
that we appropriately highlighted BRAC implementation challenges due to 
transformation, modularity, mission changes, and construction factors 
affecting BRAC military construction projects, to include changes to 
initial BRAC cost savings projections and military construction time 
frames, DOD believes that we overlooked the various groups, forums, or 
plans that the Army has in place to assist with BRAC execution and 
management. Although we were aware of these various venues and we 
changed our report to acknowledge them, we nonetheless found that these 
venues were not adequately meeting the needs of the various state Army 
National Guard and Reserve officials who share in the responsibility 
for the design and construction of the AFRCs. Throughout our work we 
found that many of these officials were still confused and frustrated 
regarding how to respond to potential challenges associated with the 
construction of the 125 new AFRCs despite the existence of the Army's 
various venues. Moreover, because the AFRCs are to be in 38 states and 
because local circumstances may vary, it is unclear how executive-level 
planning groups or other forums that exclude the states will be 
positioned to effectively mitigate the risk that may be unique to a 
given location. Although DOD stated in its comments that the Army 
already has a plan in place to bring the various stakeholders together, 
Army BRAC headquarters officials acknowledged that they could be more 
proactive in outreaching and communicating with the stakeholders on how 
to deal with and mitigate particular challenges associated with 
constructing 125 AFRCs. Moreover, because of varying viewpoints on how 
potential challenges should be addressed, opportunities for these 
stakeholders to meet and express their concerns is of importance, 
especially so that any potential issues can be resolved before too many 
AFRCs are built and the Army can meet the BRAC statutory 2011 deadline. 
Consequently, we continue to believe that the Army would benefit from 
routinely bringing together the reserve component and state-level 
stakeholders who are playing a vital role in the actual design and 
construction of the AFRCs so that challenges and issues can be 
effectively mitigated before they rise to the Army's executive 
headquarters level. Additionally, best practices suggest that involving 
stakeholders in planning can help create a clearer understanding among 
the stakeholders of competing demands, the limited resources available, 
and how those demands and resources require continuous balancing. 

In addition to the existing groups, forums, or plans, DOD also stated 
that the Army BRAC office will begin quarterly BRAC program reviews 
with the Assistant Secretary of the Army for Installations and 
Environment, which will further provide a forum for discussing and 
vetting issues affecting the BRAC program. Although we commend the Army 
for initiating these reviews, it remains unclear the extent to which 
the reserve components and state National Guard offices will be 
routinely involved until these reviews take place and it is this 
involvement that forms the basis of our recommendation. In addition, 
DOD stated that OSD-approved business plans are in place and updated 
biannually as needed. As we stated in the report, although the 
construction of the AFRCs is guided by 44 separate business plans that 
describe required actions, their timing, and resources, Army National 
Guard and Reserve officials said that these plans do not provide 
adequate information needed to monitor for potential challenges or the 
steps needed to quickly mitigate them. 

For the reasons stated above, we continue to believe that our 
recommendation has merit. To clarify the intent, however, we modified 
our recommendation to specifically include state National Guard 
stakeholders when appropriate, because it is unclear how existing 
executive-level planning groups that may not include the states will be 
positioned to effectively mitigate the risk that may be unique to a 
given state. 

DOD also noted in its comments that it continues to disagree with us 
regarding the treatment of military personnel savings. DOD considers 
military personnel reductions attributable to a BRAC recommendation as 
savings that are just as real as savings generated through end-strength 
reductions. As we stated in the report, the issue of military personnel 
savings represents a long-standing difference of opinion between DOD 
and us. Although we agree that transferring personnel to vacant 
positions may enhance capabilities and allows DOD to redirect freed-up 
resources to another area of need, we do not believe that such 
transfers produce a tangible dollar savings that DOD can apply to fund 
other defense priorities outside the military personnel accounts 
because these personnel will remain in the end strength and will 
continue to receive salaries and benefits. Not recognizing that these 
dollar savings cannot be readily applied elsewhere could create a false 
sense of the savings available for use in other areas outside the 
military personnel account, such as modernization. 

We are sending copies of this report to interested congressional 
committees; the Secretary of Defense; the Under Secretary of Defense 
for Acquisition, Technology, and Logistics; the Secretary of the Army; 
the Chief of the National Guard Bureau; and the Director, Office of 
Management and Budget. We will also make copies available to others 
upon request. In addition, the report will be available at no charge on 
GAO's Web site at [hyperlink, http://www.gao.gov]. 

If you or your staff have any questions concerning this report, please 
contact me at (202) 512-4523 or leporeb@gao.gov. Contact points for our 
Offices of Congressional Relations and Public Affairs may be found on 
the last page of this report. GAO staff who made major contributions to 
this report are listed in appendix III. 

Signed by: 

Brian J. Lepore: 
Director: 
Defense Capabilities and Management: 

List of Congressional Addressees: 

The Honorable Carl Levin: 
Chairman: 
The Honorable John McCain: 
Ranking Member: 
Committee on Armed Services: 
United States Senate: 

The Honorable Daniel K. Inouye: 
Chairman: 
The Honorable Ted Stevens: 
Ranking Member: 
Subcommittee on Defense: 
Committee on Appropriations: 
United States Senate: 

The Honorable Tim Johnson: 
Chairman: 
The Honorable Kay Bailey Hutchison: 
Ranking Member: 
Subcommittee on Military Construction, Veterans Affairs, and Related 
Agencies: 
Committee on Appropriations: 
United States Senate: 

The Honorable Ike Skelton: 
Chairman: 
The Honorable Duncan L. Hunter: 
Ranking Member: 
Committee on Armed Services: 
House of Representatives: 

The Honorable John P. Murtha: 
Chairman: 
The Honorable C.W. Bill Young: 
Ranking Member: 
Subcommittee on Defense: 
Committee on Appropriations: 
House of Representatives: 

The Honorable Chet Edwards: 
Chairman: 
The Honorable Roger F. Wicker: 
Ranking Member: 
Subcommittee on Military Construction, Veterans Affairs, and Related 
Agencies: 
Committee on Appropriations: 
House of Representatives: 

The Honorable Tom Davis: 
Ranking Member: 
Committee on Oversight and Government Reform: 
House of Representatives: 

[End of section] 

Appendix I: Scope and Methodology: 

We performed our work at various Office of the Secretary of Defense 
(OSD) and Army base realignment and closure (BRAC) offices involved in 
the implementation of the Army reserve component recommendations and at 
various states affected by the recommendations. 

To determine changes in estimated cost and savings, we used data in the 
Army's BRAC budget justification materials provided to Congress in 
support of the President's fiscal year 2008 budget request and compared 
them to the estimates in the 2005 BRAC Commission report, both publicly 
available data. All cost and savings estimates have been adjusted for 
inflation and are presented in fiscal year 2005 constant dollars 
because the BRAC Commission reported its estimates in 2005 constant 
dollars. BRAC Commission estimates are based on the Department of 
Defense's (DOD) quantitative model, known as the Cost of Base 
Realignment Actions. DOD has used this cost model in each of the 
previous BRAC rounds and, over time, has improved upon its design to 
provide better estimating capability, although the model is not 
intended to produce budget quality estimates. We did not validate the 
Army's military construction requirements because the Army Audit Agency 
was in the process of validating these requirements at the time of our 
review. To assess the reliability of DOD's BRAC cost and savings 
estimates, we talked with officials at the OSD BRAC Office about their 
data quality control procedures and reviewed relevant documentation. We 
determined the Army's budget justification data to be sufficiently 
reliable for the purposes of this report and for making broad cost and 
savings comparisons. We also analyzed data from OSD-approved business 
plans for each recommendation to determine reasons for changes in cost 
and savings estimates. 

To identify what Army officials said were the more significant 
potential challenges that could affect the implementation of the BRAC 
2005 reserve component recommendations, we interviewed numerous 
stakeholders to the process. These stakeholders included officials in 
the OSD BRAC Office, Office of the Assistant Secretary of Defense for 
Reserve Affairs, Office of the Assistant Secretary of the Army for 
Installations and Environment, Army's Office of the Assistant Chief of 
Staff for Installation Management, National Guard Bureau, Army Reserve 
Command, Office of the Chief Army Reserve, and U.S. Army Corps of 
Engineers Headquarters and Louisville District offices. We also 
interviewed National Guard officials in five states and officials in 
two Army Reserve regional readiness commands most affected by the 2005 
BRAC recommendations. Specifically, we visited state National Guard 
officials in Alabama, Arkansas, Kentucky, Oklahoma, and Texas. With the 
exception of Kentucky, we selected these states because they either had 
a large number of Armed Forces Reserve Centers (AFRC) slated for 
construction, had a National Guard headquarters located near a reserve 
regional readiness command, or both. We selected Kentucky because its 
National Guard headquarters is located near the U.S. Army Corps of 
Engineers' Louisville District, which is managing the BRAC construction 
of the Reserve-led AFRCs. In the states we visited, we spoke with the 
chief construction and facilities management officers. In two states, 
we met with the adjutants general. Additionally, we met with officials 
in two reserve regional readiness commands--one in Alabama and one in 
Arkansas. During these meetings, we interviewed key officials involved 
in implementing the recommendations to understand the potential 
challenges the Army faces in completing the recommendations by the end 
of the 6-year statutory BRAC completion period and summarized their 
views. We conducted our work from June 2006 through July 2007 in 
accordance with generally accepted government auditing standards. 

[End of section] 

Appendix II: Comments from the Department of Defense: 

Office Of The Under Secretary Of Defense: 
3000 Defense Pentagon: 
Washington, Dc 20301-3000: 

Acquisition, Technology And Logistics: 

August, 23, 2007

Mr. Brian J. Lepore: 
Director, Defense Capabilities and Management: 
U.S. Government Accountability Office: 
441 G Street, N.W.
Washington, DC 20548-0001 

Dear Mr. Lepore, 

This is the Department of Defense (DOD) response to the GAO draft 
report, GAO-07-1040, "Military Base Closures And Realignments: Plan 
Needed to Monitor Challenges for Completing More than One Hundred Armed 
Forces Reserve Centers," dated July 26, 2007 (GAO Code 350874). 

The Department partially concurs with the GAO's recommendation in the 
draft report concerning development of a plan for routinely bringing 
together the various stakeholders as a group. The Army currently has 
several venues in which it participates in the execution of the Base 
Realignment and Closure (BRAC) program with all of the stakeholders and 
is proactive in monitoring changing mission requirements and adjusting, 
as needed, project cost, scope and construction resources to meet BRAC 
timelines. 

It is also important to note that the Department continues to disagree 
with GAO regarding the treatment of military personnel savings in the 
draft report. The Department considers military personnel reductions 
attributable to a BRAC recommendation as savings that are just as real 
as savings generated through end-strength reductions. While the 
Department may not reduce overall end-strength, the reductions in 
military personnel for each recommendation at a specific location are 
real. As is the case of monetary savings, personnel reductions allow 
the Department to re-apply these military personnel to support new 
capabilities and to improve operational efficiencies.   

The Department's comments regarding the specific recommendations in the 
report are outlined in the enclosure. The Department appreciates the 
work performed by the GAO in this regard and appreciates the 
opportunity to comment on the draft report. 

Sincerely,

Signed by: 

Philip W. Grone: 
Deputy Under Secretary of Defense: 
(Installations and Environment): 

Enclosure: 
As stated: 

GAO Draft Report – Dated July 26, 2007 GAO Code 350874/GAO-07-1040 

"Military Base Closures And Realignments: Plan Needed to Monitor 
Challenges for Completing More than One Hundred Armed Forces Reserve 
Centers" 

Department Of Defense Comments To The Recommendation: 

Recommendation 1: The GAO recommends that the Secretary of Defense 
direct the Secretary of the Army to develop a plan for routinely 
bringing together the various stakeholders as a group to monitor and 
develop steps to mitigate those challenges should they occur. Those 
steps should include ways to monitor and mitigate the effects of 
potential challenges on the base realignment and closure completion 
timeframes, project cost and scope, construction quality, and capacity 
of the facility to meet changing mission requirements. 

DOD Response: DoD partially concurs with comment. Although Army was not 
directed to develop a plan for managing potential adverse effects, the 
following mechanisms and forums exist to mitigate challenges and 
impacts to BRAC program execution. The Army Vice Chief of Staff (VCSA) 
chairs the Stationing Senior Review Group (SSRG) meetings at which 
programmatic issues are raised, discussed, and resolved. The 
Installation Management Board of Directors monitor performance measures 
for programs and operations to ensure compliance with the plan. At the 
installation level the Deputy Garrison Commander for Transformation is 
identified as the BRAC program coordinator and provides project 
feedback to the Senior Mission Commander and the various installation 
stakeholders on a routine basis. The Army BRAC office will begin 
Quarterly BRAC program reviews with the Assistant Secretary of the Army 
for Installations and Environment, inclusive of the stakeholders, which 
further provides a forum for discussing and vetting issues impacting 
the BRAC program. In addition, OSD- approved Business Plans are in 
place and updated biannually, as needed. Army already has a plan in 
place to bring the various stakeholders together and has made 
significant strides in monitoring and mitigating risks that would 
hamper completing mandated BRAC actions by September 15, 2011. 
Additionally, the Army has venues where stakeholders meet for BRAC 
project reviews and conferences. BRAC construction priorities are 
coordinated through the National Guard Bureau Army Installations (ARI) 
Office, Office of the Assistant Chief of Staff for Installation 
Management (OACSIM) Army Reserve Installations Division (ARID) and U.S. 
Army Reserve Command (USARC) Transformation Integration Office (TIO) 
based on mission impact, land acquisition, environmental issues and 
level of funding per fiscal year. BRAC projects are also validated 
through independent U.S. Army Audit Agency (USAAA) audits and Program 
Managers are in place to manage BRAC execution by regions. GAO has 
appropriately highlighted challenges due to transformation, modularity, 
mission changes, and construction factors impacting BRAC military 
construction projects, to include changes to initial BRAC cost savings 
projections and military construction timelines. GAO's draft report 
does not accurately reflect the steps currently in place, nor does it 
address the steps scheduled to further assist with BRAC execution and 
management.

[End of section] 

Appendix III: GAO Contact and Staff Acknowledgments: 

GAO Contact: 

Brian J. Lepore, (202) 512-4523 or leporeb@gao.gov: 

Acknowledgments: 

In addition to the contact named above, Barry Holman, Director 
(retired); Laura Talbott, Assistant Director; Shawn Arbogast; Rachel 
Beers; Grace Coleman; Jennifer Edwards; Julie Matta; and Charles Perdue 
made key contributions to this report. 

[End of section] 

Related GAO Products: 

Defense Infrastructure: Challenges Increase Risks for Providing Timely 
Infrastructure Support for Army Installations Expecting Substantial 
Personnel Growth. GAO-07-1007. Washington, D.C.: September 13, 2007. 

Military Base Realignments and Closures: Observations Related to the 
2005 Round. GAO-07-1203R. Washington, D.C.: September 6, 2007. 

Military Base Closures: Projected Savings from Fleet Readiness Centers 
Likely Overstated and Actions Needed to Track Actual Savings and 
Overcome Certain Challenges. GAO-07-304. Washington, D.C.: June 29, 
2007. 

Military Base Closures: Management Strategy Needed to Mitigate 
Challenges and Improve Communication to Help Ensure Timely 
Implementation of Air National Guard Recommendations. GAO-07-641. 
Washington, D.C.: May 16, 2007. 

Military Base Closures: Opportunities Exist to Improve Environmental 
Cleanup Cost Reporting and to Expedite Transfer of Unneeded Property. 
GAO-07-166. Washington, D.C.: January 30, 2007. 

Military Bases: Observations on DOD's 2005 Base Realignment and Closure 
Selection Process and Recommendations. GAO-05-905. Washington, D.C.: 
July 18, 2005. 

Military Bases: Analysis of DOD's 2005 Selection Process and 
Recommendations for Base Closures and Realignments. GAO-05-785. 
Washington, D.C.: July 1, 2005. 

Military Base Closures: Observations on Prior and Current BRAC Rounds. 
GAO-05-614. Washington, D.C.: May 3, 2005. 

Footnotes: 

[1] BRAC legislation (Pub. L. No. 101-510, Title XXIX, as amended by 
Pub. L. No. 107-107, Title XXX) provided for an independent commission 
to review the Secretary of Defense's realignment and closure 
recommendations and present its findings and conclusions on the 
Secretary's recommendations, along with its own recommendations, to the 
President. 

[2] The Army National Guard, Army Reserve, Air Force Reserve, Air 
National Guard, Navy Reserve, Marine Corps Reserve, and Coast Guard 
Reserve constitute the DOD reserve components. The reserve component 
recommendations addressed in this report only involve the Army. The 
other reserve components are addressed in separate recommendations. 

[3] Pub. L. No. 101-510, § 2904, as amended (1990). 

[4] 31 U.S.C. § 717. 

[5] Per the Commission's recommendations, the Army is not required to 
construct certain AFRCs if the Army is unable to acquire land suitable 
for construction of the facilities. 

[6] Army modularity, which has been referred to as the largest Army 
reorganization in 50 years, encompasses the Army's total force and 
directly affects the Army's combat units and its related support and 
command and control. The foundation of Army modularity is the creation 
of brigade combat teams that will have a common organizational design 
and will increase the pool of available units for deployment. Many 
units of the Army National Guard and the Army Reserve are being 
reorganized because of Army modularity into organizations such as fires 
brigades, which combine the functions of division artillery, general 
support field artillery, and corps artillery into one organization. 

[7] The House Armed Services Committee has directed the Secretary of 
Defense to submit an analysis of the construction cost inflation 
differences by February 1, 2008. H.R. Rep. No. 110-146, at 520 (2007) 
(Conf. Rep.) 

[8] Per the Commission's recommendations, the Army is not required to 
construct certain AFRCs if the Army is unable to acquire land suitable 
for construction of the facilities. 

[9] These include the Stationing Senior Review Group chaired by the 
Army Vice Chief of Staff, the Installation Management Board of 
Directors, and at the installation level, the Deputy Garrison Commander 
for Transformation, who provides project feedback to various 
installation stakeholders on a routine basis. In addition, the Army 
plans to begin quarterly BRAC program reviews with the Assistant 
Secretary of the Army for Installations and Environment to further 
provide a forum for discussing issues associated with the BRAC program. 
Moreover, the Army stated that it has venues where stakeholders meet 
for BRAC project reviews and conferences. 

[10] Pub. L. No. 103-62 (1993). 

[11] GAO, Executive Guide: Effectively Implementing the Government 
Performance and Results Act, GAO/GGD-96-118 (Washington, D.C.: June 
1996). 

[12] In developing its BRAC recommendations for the reserve components 
the Army allowed the states to voluntarily participate in the process. 
The Department of the Army worked very closely with the state adjutants 
general throughout the BRAC 2005 process, and understands that the 
state governors will close 211 Army National Guard facilities with the 
intent of relocating their tenant units into the 125 new AFRCs. 
According to some state guard officials, because many of the Army 
National Guard facilities slated to close under BRAC are owned by the 
states, a state has the option to keep these facilities open if the 
state determines that the new AFRC will not sufficiently meet the 
requirements of the units slated to occupy it. 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "Subscribe to Updates." 

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. Government Accountability Office: 
441 G Street NW, Room LM: 
Washington, D.C. 20548: 

To order by Phone: 
Voice: (202) 512-6000: 
TDD: (202) 512-2537: 
Fax: (202) 512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Gloria Jarmon, Managing Director, JarmonG@gao.gov (202) 512-4400: 

U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Susan Becker, Acting Managing Director, BeckerS@gao.gov (202) 512-4800: 

U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: