This is the accessible text file for GAO report number GAO-03-723 
entitled 'Military Base Closures: Better Planning Needed for Future 
Reserve Enclaves' which was released on June 27, 2003.

This text file was formatted by the U.S. General Accounting Office 
(GAO) to be accessible to users with visual impairments, as part of a 
longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov.

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately.

Report to the Secretary of Defense:

United States General Accounting Office:

GAO:

June 2003:

Military Base Closures:

Better Planning Needed for Future Reserve Enclaves:

GAO-03-723:

GAO Highlights:

Highlights of GAO-03-723, a report to the Secretary of Defense 

Why GAO Did This Study:

While four previous base closure rounds have afforded the Department 
of Defense (DOD) the opportunity to divest itself of unneeded 
property, it has, at the same time, retained more than 350,000 acres 
and nearly 20 million square feet of facilities on enclaves at closed 
or realigned bases for use by the reserve components. In view of the 
upcoming 2005 base closure round, GAO undertook this review to 
ascertain if opportunities exist to improve the decision-making 
processes used to establish reserve enclaves. Specifically, GAO 
determined to what extent (1) specific infrastructure needs for 
reserve enclaves were identified as part of base realignment and 
closure decision making and (2) estimated costs to operate and 
maintain enclaves were considered in deriving net estimated savings 
for realigning or closing bases.

What GAO Found:

The specific infrastructure needed for many DOD reserve enclaves 
created under the previous base realignment and closure process was 
generally not identified until after a defense base closure commission 
had rendered its recommendations. While the Army generally decided it 
wanted much of the available training land for its enclaves before the 
time of the commission’s decision making during the 1995 closure 
round, time constraints precluded the Army from fully identifying 
specific training acreages and facilities until later. Subsequently, 
in some instances the Army created enclaves that were nearly as large 
as the bases that were being closed. In contrast, the infrastructure 
needed for Air Force reserve enclaves was more defined during the 
decision-making process. Moreover, DOD’s enclave-planning processes 
generally did not include a cross-service analysis of military 
activities that may have benefited by their inclusion in a nearby 
enclave.

The Army did not include estimated costs to operate and maintain its 
reserve enclaves in deriving net estimated base realignment or closure 
savings during the decision-making process, but the Air Force 
apparently did so in forming its enclaves. GAO’s analysis showed that 
the Army overestimated savings and underestimated the time required to 
recoup initial investment costs to either realign or close those bases 
with proposed enclaves. However, these original cost omissions have 
not materially affected DOD’s recent estimate of $6.6 billion in 
annual recurring savings from the previous closure rounds because the 
Army subsequently updated its estimates in its budget submissions to 
reflect expected enclave costs.

What GAO Recommends:

As part of the new base realignment and closure round scheduled for 
2005, GAO is recommending that the Secretary of Defense provide the 
Defense Base Closure and Realignment Commission with data that clearly 
specify the (1) infrastructure needed for any proposed reserve 
enclaves and (2) estimated costs to operate and maintain such 
enclaves.

In commenting on a draft of this report, DOD agreed with the 
recommendations. 

www.gao.gov/cgi-bin/getrpt?GAO-03-723.

To view the full product, including the scope and methodology, click 
on the link above. For more information, contact Barry Holman at (202) 
512-8412 or holmanb@gao.gov.

[End of section]

Contents:

Letter:

Results in Brief:

Background:

Infrastructure Needs of Many Enclaves Not Identified Until after BRAC 
Decision Making:

Many Initial Base Savings Estimates Did Not Account for Projected 
Enclave Costs:

Conclusions:

Recommendations for Executive Action:

Agency Comments:

Scope and Methodology:

Appendix I: General Description of Major Reserve Component Enclaves 
(Pre-BRAC and Post-BRAC):

Appendix II: Reserve Enclaves Created under Previous BRAC Rounds:

Appendix III: Comments from the Department of Defense:

Appendix IV: GAO Contact and Staff Acknowledgments:

Tables:

Table 1: DOD Pre-BRAC and Post BRAC Base Acreage and Facilities for 
Bases Where Major Reserve Enclaves Were Created:

Table 2: Estimated Annual Costs to Operate and Maintain Selected Army 
Reserve Enclaves:

Table 3: Comparison of Estimated Annual Recurring Savings and Payback 
Periods for Selected Bases with Reserve Enclaves:

Figures:

Figure 1: Major Reserve Component Enclaves Created under Previous 
BRAC Rounds:

Figure 2: Property Layout of the Former March Air Force Base:

Figure 3: Navy Compound at March Air Reserve Base:

Abbreviations:

BRAC: base realignment and closure:

COBRA: Cost of Base Realignment Actions:

United States General Accounting Office:

Washington, DC 20548:

June 27, 2003:

The Honorable Donald H. Rumsfeld 
Secretary of Defense:

Dear Mr. Secretary:

Since 1988, the Department of Defense (DOD) has undergone four rounds 
of base realignments and closures and has reportedly reduced its base 
infrastructure by about 20 percent, saving billions of dollars in the 
process. While the closure process has afforded DOD the opportunity to 
divest itself of property it no longer needed[Footnote 1] to meet its 
national security requirements, it has, at the same time, retained more 
than 350,000 acres of land and nearly 20 million square feet of 
facilities, typically referred to as enclaves,[Footnote 2] on closed or 
realigned bases for use by the reserve components. Most of the larger 
enclaves were established during the 1995 round of base closures and 
are now managed by either the Army National Guard or Army Reserve 
rather than the active component.

We prepared this report under our basic legislative responsibilities as 
authorized by 31 U.S.C. § 717 and are providing it to you because of 
your responsibilities in the upcoming base closure round authorized for 
2005.[Footnote 3] In view of this round, we undertook this review to 
ascertain if opportunities exist to improve the planning and decision-
making processes that were used to establish reserve enclaves in the 
previous closure rounds. Specifically, our objectives were to determine 
to what extent (1) specific infrastructure needs (e.g., needs for 
acreage and facilities) for reserve enclaves were identified as part of 
base realignment and closure decision making in previous closure rounds 
and (2) estimated costs to operate and maintain enclaves were 
considered in deriving the net estimated savings for realigning or 
closing bases.

In performing our work, we focused our attention on the processes used 
by the department to define infrastructure needs for major[Footnote 4] 
reserve enclaves for the Army in the 1995 round and for the Air Force 
in the earlier rounds. We did not validate the need for any of the 
department's enclaves nor the specific infrastructure needs for those 
enclaves. Of the 10 major reserve enclaves created during the previous 
closure rounds, 7 are within the Army and 3 are within the Air Force. 
Neither the Navy nor the Marines have formed a major enclave (see 
app. I for a brief description of DOD's major reserve component 
enclaves). We visited five major Army enclaves--Fort Hunter Liggett, 
California; Fort Chaffee, Arkansas; Fort Pickett, Virginia; Fort 
McClellan, Alabama; and Fort Indiantown Gap, Pennsylvania--that were 
created during the 1995 closure round and account for nearly 
90 percent, or more than 310,000 acres, of DOD's total major reserve 
component enclave acreage. We also visited two of three major Air Force 
enclaves at Grissom Air Reserve Base in Indiana (a 1991 round action) 
and March Air Reserve Base in California (a 1993 round action). We also 
visited a smaller Air Force enclave at Rickenbacker Air National Guard 
Base in Ohio (a 1991 round action) to gain a perspective on Air Guard 
enclave formation processes. Our review efforts were constrained by the 
limited availability of officials (owing to the passage of time) who 
had participated in previous rounds of base closure decision making and 
the general lack of planning documentation regarding enclave 
infrastructure needs and estimated costs.

Results in Brief:

The specific infrastructure needed for many reserve enclaves was 
generally not identified until after the base closure and realignment 
commission for a closure round had rendered its recommendations. 
According to Army officials, while the Army had generally decided it 
wanted much of the available training land for its enclaves prior to 
completion of commission decision making during the 1995 round, time 
constraints precluded the Army from fully identifying specific training 
acreages and facility needs until after the commission made its 
recommendations. Consequently, while some of the commission's 
recommendation language[Footnote 5] for the 1995 closure round 
suggested that many Army reserve enclaves would be small, it was 
nevertheless sufficiently general to allow, in practice, the Army wide 
flexibility in creating such enclaves. Subsequently, the Army created 
several enclaves that were nearly as large as the closing bases on 
which they were located. In contrast, the infrastructure needed for Air 
Force enclaves was more defined during the decision-making process and 
subsequent commission recommendations were more specific than those 
provided for the Army. Moreover, the department's enclave-planning 
processes generally did not include a cross-service analysis of the 
needs of military activities or organizations near the enclaves that 
may have benefited by inclusion in them. Without more complete data 
regarding the extent of needed enclave infrastructure and cross-service 
needs--important considerations in the decision-making process, the 
risk continues that a future base closure commission will not have 
sufficient information to make informed judgments on the establishment 
of proposed enclaves, including informed decisions on the facility 
needs of these enclaves, decisions that can affect expected closure 
costs and savings. Nor can the department be assured that it is taking 
advantage of opportunities to achieve operational, economic, and 
security benefits--such as enhanced readiness, savings, and enhanced 
force protection--that cross-servicing can provide. However, the 
department recently issued guidance for the upcoming base closure round 
that addresses the potential benefits of considering cross-service 
needs in its infrastructure analyses.

Although the Army did not include estimated costs to operate and 
maintain most of its major reserve enclaves in deriving net estimated 
base savings during the decision-making process, the Air Force 
apparently did so in forming its enclaves. The Army Audit Agency 
reported in 1997[Footnote 6] that about $28 million in estimated annual 
costs to operate and maintain four of the Army's major enclaves were 
not considered in the bases' savings calculations as part of the 1995 
closure round. Our analysis showed that the omission of these costs had 
a significant impact on the estimated savings and payback 
periods[Footnote 7]--important considerations in the realignment and 
closure decision-making process--for several of these bases. In 
particular, the estimated savings were overstated and the estimated 
payback periods were understated for those specific bases. For example, 
if expected enclave costs would have been considered at one Army 
location, the annual recurring savings estimate for the base would have 
been reduced by over 50 percent. However, these original cost omissions 
have not materially affected the department's recent estimate of 
$6.6 billion in annual recurring savings from the previous closure 
rounds because the Army has subsequently updated its savings estimates 
to reflect expected enclave costs. On the other hand, Air Force 
officials told us that it had considered expected costs to operate and 
maintain its proposed reserve enclaves in deriving its base closure 
savings estimates.[Footnote 8] We were unable to verify this point, 
however, because of the passage of time and lack of available 
supporting documentation. In the absence of more complete data 
regarding cost and net savings estimates, a base closure commission may 
be placed in the position of recommending realignment or closure 
actions without sufficient information on the financial implications of 
those proposed actions.

We are making recommendations that are intended to ensure that data 
provided to the Defense Base Closure and Realignment Commission for 
2005 round actions clearly specify enclave needs and costs to operate 
and maintain any proposed enclaves. In commenting on a draft of this 
report, DOD concurred with our recommendations.

Background:

To enable DOD to more readily close unneeded bases and realign others 
to meet its national security requirements, the Congress enacted base 
realignment and closure (BRAC) legislation that instituted base closure 
rounds in 1988, 1991, 1993, and 1995. A special commission established 
for the 1988 round made recommendations to the Committees on Armed 
Services of the Senate and House of Representatives. For the remaining 
rounds, special BRAC commissions were set up to recommend specific base 
realignments and closures to the President, who in turn sent the 
commissions' recommendations with his approval to the Congress. The 
four commissions generated nearly 500 recommendations--on 97 major base 
closures and hundreds of realignments and smaller closures.

As a result of the BRAC process, DOD has reported that it reduced its 
infrastructure[Footnote 9] by about 20 percent; has transferred over 
half of the approximately 511,000 acres of unneeded property to other 
federal and nonfederal users and continues work on transferring the 
remainder; and generated about $16.7 billion in estimated savings 
through fiscal year 2001, with an estimated $6.6 billion in annual 
recurring savings expected thereafter.[Footnote 10] We and others who 
have conducted reviews of BRAC savings have found that the DOD's 
savings are substantial, although imprecise, and should be viewed as 
rough approximations of the likely savings.[Footnote 11] Under the 
property disposal process, unneeded DOD BRAC property is initially made 
available to other federal agencies for their use. After the federal 
screening process has taken place, remaining property is generally 
provided to state and local governments for public benefit and economic 
development purposes. In other cases, DOD has publicly sold its 
unneeded property.

Under the decision-making processes during the last 3 BRAC rounds, 
DOD assessed its bases or activities for closure or realignment using 
an established set of eight criteria covering a broad range of 
military, fiscal, environmental, and other considerations. DOD 
subsequently forwarded its recommended list of proposed realignments 
and closures to the BRAC Commission for its consideration in 
recommending specific realignments and closure actions. Although 
military value considerations such as mission requirements and impact 
on operational readiness were critical evaluation factors, potential 
costs and savings, along with estimated payback periods associated with 
proposed closure or realignment actions were also important factors in 
the assessment process. To assist with the financial aspects of 
proposed actions, DOD and the BRAC Commissions used a quantitative 
analytical model, frequently referred to as the Cost of Base 
Realignment Actions (COBRA), to provide decision makers with a relative 
assessment of the potential costs, estimated savings, and payback 
periods of proposed alternative realignment or closure actions. 
Although the COBRA model was not designed to produce budget-quality 
financial data, it was useful in providing a relative financial 
comparison among potential alternative proposed base actions. DOD 
generally provided improved financial data for each of the services in 
its annual BRAC budget submission to the Congress following a BRAC 
Commission's recommendations.[Footnote 12]

The four previous BRAC Commissions recommended 27 actions in 
which either a reserve enclave or similar reserve presence was to be 
formed at a base that was to be realigned or closed (see app. II). In 
many instances, these actions were relatively minor in that they 
involved only several acres, but in other cases the actions involved 
creating enclaves with large acreages and millions of square feet of 
facilities under reserve component management to conduct training for 
not only the reserve component but also the active component as well. 
Figure 1 shows the locations of DOD's 10 major (i.e., sites exceeding 
500 acres) reserve component enclaves established under the previous 
BRAC rounds.

Figure 1: Major Reserve Component Enclaves Created under Previous 
BRAC Rounds:

[See PDF for image]

[End of figure]

As shown in figure 1, the Army has 7 enclave locations; all of these 
enclaves, with the exception of Fort Devens (a 1991 round action), 
were created during the 1995 round. The Air Force has the remaining 
3 enclaves: Air Reserve--Grissom Air Reserve Base (a 1991 round 
action); Homestead Air Reserve Base (a 1993 round action); and March 
Air Reserve Base (a 1993 round action). Neither the Navy nor the 
Marines created any major enclaves.[Footnote 13]

Infrastructure Needs of Many Enclaves Not Identified Until after BRAC 
Decision Making:

Many of DOD's specific enclave infrastructure needs were not identified 
until after the commission for a BRAC round held its deliberations and 
had rendered its recommendations. Although the Army's enclave planning 
process--particularly for the 1995 BRAC round--began before the 
issuance of commission recommendations,[Footnote 14] specificity of 
needed infrastructure was not defined until after the recommendations 
were finalized. The subsequent size of several of these enclaves was 
much greater than seemingly reflected in commission recommendations 
that called for minimum essential facilities and land for reserve use. 
On the other hand, the Air Force's planning process was reportedly 
further along and enclave needs were better defined at the time the 
commission made its recommendations. In addition, DOD's enclave-
planning processes generally did not include a cross-service[Footnote 
15] analysis of the needs of military activities or activities in the 
vicinity of a realigning or closing base with a proposed enclave. As a 
result, the commission often held deliberations without the benefit of 
some critical information, such as the extent of the enclave 
infrastructure needed to support training and potential opportunities 
to achieve benefits by collocating nearby reserve components on enclave 
property.

Army Enclave Infrastructure Needs Not As Well Defined As Those of the 
Air Force during BRAC Decision Making:

While the Army's enclave planning process for the 1995 round began 
previous to completion of the BRAC Commission's deliberations, specific 
enclave infrastructure needs were not identified until after commission 
recommendations had been issued on July 1, 1995. Army officials told us 
that it was recognized early in the process that the Army wanted to 
retain the majority of existing training land at some of its bases 
slated for closure or realignment that also served as reserve component 
maneuver training locations, but time constraints precluded the Army 
from fully identifying specific enclave needs before the commission 
completed decision-making. According to a 1999 DOD report on the effect 
of base closures on future mobilization options, the retention of much 
of the Army maneuver training acreage at the enclave locations served 
not only to meet current training needs but also could serve, if 
necessary, as future maneuver bases with new construction or renovation 
of existing facilities for an increased force structure.[Footnote 16] 
In testimony before the commission, the Army had indicated that much of 
the training land should be retained, but the Army was less specific on 
the size and facility needs (i.e., in total square footage) for 
the enclaves. Most facility needs fall within the enclaves' primary 
infrastructure (or cantonment area)[Footnote 17] necessary to operate 
and maintain the enclaves.

The Army formed an officer-level committee--a "Council of Colonels"--
that reviewed reserve component enclave proposals but did not approve 
them for higher-level reviews until July 7, 1995--about 1 week after 
the BRAC Commission had issued its recommendations. Following the 
Council of Colonels' approval, a General Officer Steering Committee 
worked with the Army reserve components to refine the infrastructure 
needs for the enclaves, needs that the steering committee approved 
(except for Fort Hunter Liggett[Footnote 18]) in October 1995--more 
than 3 months following the 1995 BRAC Commission's recommendations.

Although Army approval for most of its enclaves' infrastructure needs 
occurred in late 1995, the number of acres and facilities for some 
installations changed as various implementation plans took effect to 
establish the enclaves. Changes occurred as a result of Army decisions 
and community reuse plans for property disposed of by the department, 
as illustrated in the following examples.

* At Fort Hunter Liggett, the number of facilities to be retained in 
the enclave increased over time based on an Army decision to retain 
some of the family housing (40 units); morale, welfare, and recreation 
facilities (9 facilities) and other training-related facilities 
(3 barracks and 2 classrooms) that had originally been excluded from 
the enclave.

* At Fort McClellan, the expected cantonment area decreased 
considerably from an initial proposal of about 10,000 acres (excluding 
about 22,200 training-range acres) to about 286 acres in response to 
concerns raised by the local community.

The Air Force's enclave infrastructure needs were reportedly more 
defined than those of the Army at the time of commission deliberation 
and decision making. Air Force officials told us that the base 
evaluation process for the 1991 and 1993 rounds--the rounds when the 
Air Force's major reserve enclaves were created--included a detailed 
analysis of the infrastructure needed for the enclaves, including 
enclave size, identification of required facilities, and expected costs 
to operate and maintain its proposed enclaves prior to commission 
consideration of its proposals. These officials did note that some 
revisions in the sizing of the enclaves and associated enclave 
boundaries were minor and have occurred over time as plans were further 
defined, but stated that these changes did not materially affect 
enclave costs. Although documentation on the initial plans was not 
available (due to the passage of time), we were able to document some 
enclave revisions made after the issuance of the BRAC Commissions' 
recommendations as follows:

* At March Air Reserve Base, the Air Force made at least 3 sets of 
revisions to its enclave size which now encompasses 2,359 acres. These 
revisions were relatively minor in scope, such as one revision that 
expanded the boundaries by about 38 acres to provide a clear zone for 
flight operations.

* At Grissom Air Reserve Base, the Air Force has made one revision--an 
exchange of about 70 acres with the local redevelopment 
authority[Footnote 19]--to its enclave configuration, which now 
encompasses 1,380 acres. In addition, base officials are negotiating 
with the redevelopment authority for acquisition of a small parcel to 
improve force protection at the enclave's main gate.

* At Rickenbacker Air National Guard Base, the Guard made several 
revisions prior to reaching its current 168-acre enclave, including 
the transfer of 3.5 acres of unneeded property to the local 
redevelopment authority after the Guard relocated its fuel tanks for 
force protection reasons.

The degree of specificity in a commission's recommendation language for 
proposed enclaves varied between the Army and the Air Force. In 
general, the recommendation language for the Army's 1995 round enclaves 
was based largely on the Army's proposed language, specifying that the 
bases were to be closed, except that minimum essential ranges, 
facilities, and training areas be retained for reserve component use. 
In contrast, for Army and Air Force enclaves created in earlier rounds, 
the recommendation language was more precise--even specifying specific 
acreages to be retained in some cases.

Acting on the authority contained in the commissions' recommendations, 
the Army and Air Force created enclaves that varied widely in size 
(i.e., from several acres to more than 164,000 acres). Table 1 provides 
a comparison of the reported size and number of facilities of pre-BRAC 
bases with those of post-BRAC enclaves for DOD's 10 major enclaves.

Table 1: DOD Pre-BRAC and Post BRAC Base Acreage and Facilities for 
Bases Where Major Reserve Enclaves Were Created:

Service: Army:

Base: Fort Hunter Liggett; Number of acres: Pre-BRAC: 
164,762; Number of acres: Post-BRAC: 164,272; Number of acres: Percent 
Retained: 100; Square footage of facilities: Pre-BRAC: 
836,420; Square footage of facilities: Post-BRAC: 832,906; Square 
footage of facilities: Percent Retained: 100.

Base: Fort Chaffee; Number of acres: Pre-BRAC: 71,381; Number of 
acres: Post-BRAC: 64,272; Number of acres: Percent Retained: 90; : 
Square footage of facilities: Pre-BRAC: 4,839,241; Square 
footage of facilities: Post-BRAC: 1,695,132; Square footage of 
facilities: Percent Retained: 35.

Base: Fort Pickett; Number of acres: Pre-BRAC: 45,145; Number of 
acres: Post-BRAC: 42,273; Number of acres: Percent Retained: 94; : 
Square footage of facilities: Pre-BRAC: 3,103,000; Square 
footage of facilities: Post-BRAC: 1,642,066; Square footage of 
facilities: Percent Retained: 53.

Base: Fort Dix; Number of acres: Pre-BRAC: 30,997; Number of acres: 
Post-BRAC: 30,944; Number of acres: Percent Retained: 100; : 
Square footage of facilities: Pre-BRAC: 8,645,293; Square 
footage of facilities: Post-BRAC: 7,246,964; Square footage of 
facilities: Percent Retained: 84.

Base: Fort Indiantown Gap; Number of acres: Pre-BRAC: 17,797; 
Number of acres: Post-BRAC: 17,227; Number of acres: Percent 
Retained: 97; : Square footage of facilities: Pre-BRAC: 
4,388,000; Square footage of facilities: Post-BRAC: 1,565,726; Square 
footage of facilities: Percent Retained: 36.

Base: Fort McClellan; Number of acres: Pre-BRAC: 41,174; Number of 
acres: Post-BRAC: 22,531; Number of acres: Percent Retained: 55; : 
Square footage of facilities: Pre-BRAC: 6,560,687; Square 
footage of facilities: Post-BRAC: 873,852; Square footage of 
facilities: Percent Retained: 13.

Base: Fort Devens; Number of acres: Pre-BRAC: Air Force: 
9,930; Number of acres: Post-BRAC: Air Force: 5,226; Number of acres: 
Percent Retained: Air Force: 53; Air Force: Square footage of 
facilities: Pre-BRAC: Air Force: 5,610,530; Square footage of 
facilities: Post-BRAC: Air Force: 1,537,174; Square footage of 
facilities: Percent Retained: Air Force: 27.

Service: Air Force; 

Base: March Air Force Base; Number of acres: Pre-
BRAC: 6,606; Number of acres: Post-BRAC: 2,359; Number of acres: 
Percent Retained: 36; Square footage of facilities: Pre-BRAC: 
3,184,321; Square footage of facilities: Post-BRAC: 2,538,742; Square 
footage of facilities: Percent Retained: 80.

Base: Grissom Air Force Base; Number of acres: Pre-BRAC: 2,722; 
Number of acres: Post-BRAC: 1,380; Number of acres: Percent Retained: 
51; Square footage of facilities: Pre-BRAC: 3,910,171; 
Square footage of facilities: Post-BRAC: 1.023,176; Square footage of 
facilities: Percent Retained: 26.

Base: Total: Homestead Air Force Base; Number of acres: Pre-BRAC: 
Total: 2,916; Number of acres: Post-BRAC: Total: 852; Number of acres: 
Percent Retained: Total: 29; Total: Square footage of 
facilities: Pre-BRAC: Total: 5,373,132; Square footage of facilities: 
Post-BRAC: Total: 867,341; Square footage of facilities: Percent 
Retained: Total: 16.

Service: Total; Base: Number of acres: Pre-BRAC: 394,430; 
Number of acres: Post-BRAC: 351,386; Number of acres: Percent Retained: 
89; Square footage of facilities: Pre-BRAC: 46,450,795; Square 
footage of facilities: Post-BRAC: 19,823,079; Square footage of 
facilities: Percent Retained: 43.

Source: DOD.

Note: "Major" reserve enclaves refer to those enclaves with more than 
500 acres. "Pre-BRAC" refers to base data at the time of the BRAC 
Commission recommendation while "Post-BRAC" refers to enclave data as 
of the end of fiscal year 2002. Percentages are rounded to nearest 
whole number.

[End of table]

As shown in table 1, the vast majority--nearly 90 percent--of the 
pre-BRAC land has been retained for the major reserve enclaves with 
most enclaves residing in Army maneuver training sites (e.g., Forts 
Hunter Liggett, Chaffee, Pickett, and Indiantown Gap). While the 
management of these Army enclaves has generally shifted from the active 
to the reserve component, the training missions at these Army bases 
have remained, although the extent of use[Footnote 20] has decreased 
slightly in some instances and increased in others (see app. I). On the 
other hand, the Air Force enclaves are generally much smaller in 
acreage than those of the Army due in large part to the departure of 
active Air Force organizations and associated missions from the former 
bases. While the Army retained much of the pre-BRAC acreage, it 
generally made greater reductions in the amount of square footage for 
its enclave facilities. Many of these reductions were due in part to 
the demolition of older unusable facilities built during World War II, 
and the transfer of other facilities (such as family housing activities 
once required for the departing active personnel) to local 
redevelopment authorities. At Fort Indiantown Gap, for example, the 
Army has reportedly demolished 349 facilities since the Army National 
Guard assumed control of the base in 1998. As shown in table 1, the Air 
Force significantly reduced the amount of its facilities' square 
footage for 2 of its 3 major enclaves.

While the language of the 1995 BRAC Commission recommendations 
regarding enclaves allowed the Army to form several enclaves of 
considerable size, these enclaves are considerably larger than one 
might expect from the language, which provided for minimum essential 
land and facilities for reserve component use. In this regard, the 
Army's Office of the Judge Advocate General questioned proposed enclave 
plans during the planning process. For example, the Judge Advocate 
General questioned Fort Indiantown Gap and Fort Hunter Liggett enclave 
plans,[Footnote 21] calling for retention of essentially the entire 
former base while the commission's recommendation would suggest smaller 
enclaves comprising a section of the base. Nonetheless, the Army 
approved the implementation plans based on mission needs. Having more 
complete information regarding expected enclave infrastructure would 
have provided previous commissions with an opportunity to draft more 
precise recommendation language, if they chose to do so, and produce 
decisions having greater clarity on enclave infrastructure and expected 
costs and savings from the closure and realignment actions.

Enclave Planning Analyses Generally Did Not Consider 
Cross-Service Needs:

DOD generally did not consider cross-service needs of nearby military 
activities in planning for many of its reserve enclaves, although their 
inclusion may have been beneficial in terms of potential for increased 
cost savings, force protection, or training reasons. While some other 
reserve activities have subsequently relocated on either enclaves 
created as part of the closure decision or later on former base 
property after it was acquired by local redevelopment authorities, 
those relocations outside enclave boundaries have not necessarily been 
ideal for either DOD or the communities surrounding the enclaves. 
Ideally, enclave planning analyses would involve an integrated cross-
service approach to forming enclaves and enable DOD to maximize its 
opportunities for achieving operational, economic, and security 
benefits while, at the same time, providing for the interests of 
affected communities surrounding realigning or closing bases.

Officials at several Air Force bases we visited told us that while 
other service and federal government organizations that had already 
resided on the former bases may have been included in the enclaves, 
military activities of other services in the local area were not 
generally considered for possible inclusion in the proposed enclaves. 
These officials told us that these activities were either not 
approached for consideration or were not considered due to service 
interests to minimize the size and relative costs to operate and 
maintain the enclaves.

Following the formation of the enclaves, some additional reserve 
activities have since relocated on either enclave or former base 
property. Some have occupied available facilities on enclaves as 
tenants and are afforded various benefits such as reduced operating 
costs, training enhancements, or increased force protection. For 
example, a Navy Reserve training center, originally based in South 
Bend, Indiana, moved its operations to an available facility at Grissom 
Air Reserve Base in August 2002 because the activity could not meet 
force protection requirements at its previous facilities in South Bend. 
After the move, the commander of the activity told us that his 
personnel have experienced enhanced training opportunities since they 
can now work closely with other military activities on "hands-on" 
duties during weekend reserve drills. This opportunity has led, in 
turn, to his assessment that both his recruiting efforts and readiness 
have improved.

On the other hand, the relocation of some activities to the former 
base, or those remaining on the former property outside the confines of 
the enclave, has resulted in a less-than-ideal situation for both the 
department and the communities surrounding the former base. For 
example, at the former March Air Force Base in California, other 
service activities from the Army Reserve, Army National Guard, Navy 
Reserve and Marine Corps Reserve reside outside the enclave boundaries 
in a non-contiguous arrangement. This situation, combined with the 
enclave itself and other enclave "islands" established on the former 
base, has resulted in a "checkerboard" effect, as shown in figure 2, of 
various military-occupied property interspersed with community 
property on the former base.

Figure 2: Property Layout of the Former March Air Force Base:

[See PDF for image]

Note: Army, Navy, and Marine Corps Reserve properties are owned by DOD 
but are not a part of the enclave.

[End of figure]

Further, some of the activities located outside the enclave boundaries 
have incurred expenses to erect security fences, as shown in figure 3, 
for force protection purposes. These fences are in addition to the 
fence that surrounds the main enclave area.

Figure 3: Navy Compound at March Air Reserve Base:

[See PDF for image]

[End of figure]

Local redevelopment authority officials told us that a combination of 
factors (including the dispersion of military property on the former 
base along with the separate unsightly security fences) has made it 
very difficult to market the remaining property.

In its April 16, 2003, policy guidance memorandum for the 2005 
BRAC round, DOD recognizes the benefits of the joint use of facilities. 
The memorandum instructs the services to evaluate opportunities to 
consolidate or relocate active and reserve components on any enclave of 
realigning and closing bases where such relocations make operational 
and economic sense. If the services adhere to this guidance in the 
upcoming round, we believe it will not only benefit DOD but also will 
mitigate any potential adverse effects, such as the checkerboard base 
layout at the former March Air Force Base, on community redevelopment 
efforts.

Many Initial Base Savings Estimates Did Not Account for Projected 
Enclave Costs:

The estimated costs to operate and maintain the infrastructure for many 
of the Army enclaves were not considered in calculating savings 
estimates for bases with proposed enclaves during the decision-making 
process. As a result, estimated realignment or closure costs and 
payback periods were understated and estimated savings were overstated 
for those specific bases. The Army subsequently updated its savings 
estimates in its succeeding annual budget submissions to reflect 
estimated costs to operate and maintain many of its enclaves. On the 
other hand, Air Force officials told us that its estimated base closure 
savings were partially offset by expected enclave costs, but 
documentation was insufficient to demonstrate this statement. Because 
estimated costs and savings are an important consideration in the 
closure and realignment decision-making process and may impact specific 
commission recommendations, it is important that estimates provided to 
the commission be as complete and accurate as possible for its 
deliberations.

Army Enclave Costs Were Not Generally Considered in BRAC 
Decision-Making Process:

During the 1995 BRAC decision-making process, estimated savings for 
most 1995-round bases where Army enclaves were established did not 
reflect estimated costs to operate and maintain the enclaves. The Army 
Audit Agency reported in 1997[Footnote 22] that about $28 million in 
estimated annual costs to operate and maintain four major Army 
enclaves,[Footnote 23] as shown in table 2, were not considered in the 
bases' estimated savings calculations.

Table 2: Estimated Annual Costs to Operate and Maintain Selected Army 
Reserve Enclaves:

Dollars in millions.

Installation.

Fort Chaffee; Cost[S]: Maintenance: $3.6; Cost[S]: Other support: $3.2; 
Cost[S]: Total: $6.9.

Fort Indiantown Gap; Cost[S]: Maintenance: 4.9; Cost[S]: Other support: 
3.4; Cost[S]: Total: 8.3.

Fort McClellan; Cost[S]: Maintenance: 3.3; Cost[S]: Other support: 2.6; 
Cost[S]: Total: 5.9.

Fort Pickett; Cost[S]: Maintenance: 3.4; Cost[S]: Other support: 3.2; 
Cost[S]: Total: 6.6.

Total; Cost[S]: Maintenance: $15.2; Cost[S]: Other support: $12.4; 
Cost[S]: Total: $27.7.

Source: U.S. Army Audit Agency.

Note: Estimated costs as reported by the Army Audit Agency in fiscal 
year 1995 dollars. Totals may not add due to rounding.

[A] Other support costs include expenses for automated target systems, 
environmental, personnel, integrated training-area management, and 
security.

[End of table]

Enclave costs are only one of many costs that may be incurred by DOD in 
closing or realigning an entire base. For example, other costs include 
expenditures for movement of personnel and supplies to other locations 
and military construction for facilities receiving missions from a 
realigning base. The extent of all costs incurred have a direct bearing 
on the estimated savings and payback periods associated with a 
particular closure or realignment. Table 3 provides the results of the 
Army Audit Agency's review (which factored in all costs) of the 
estimated savings and payback periods for the realignment or closure of 
the same Army bases shown in table 2 where enclaves were created. As 
shown in table 3, the commission's annual savings' estimates were 
overstated and the payback periods were underestimated for these 
particular bases.

Table 3: Comparison of Estimated Annual Recurring Savings and Payback 
Periods for Selected Bases with Reserve Enclaves:

Dollars in millions.

Base: 

Fort Chaffee; Estimated annual recurring savings: 1995 BRAC Commission: 
$13.4; Estimated annual recurring savings: Army Audit Agency: $1.4; 
Estimated payback period: 1995 BRAC Commission: 1 year; 
Estimated payback period: Army Audit Agency: 18 years.

Fort Indiantown Gap; Estimated annual recurring savings: 1995 BRAC 
Commission: 18.4; Estimated annual recurring savings: Army Audit 
Agency: 11.8; Estimated payback period: 1995 BRAC Commission: 
Immediate; Estimated payback period: Army Audit Agency: 1 year.

Fort McClellan; Estimated annual recurring savings: 1995 BRAC 
Commission: 40.6; Estimated annual recurring savings: Army Audit 
Agency: 27.4; Estimated payback period: 1995 BRAC Commission: 
6 years; Estimated payback period: Army Audit Agency: 14 years.

Fort Pickett; Estimated annual recurring savings: 1995 BRAC Commission: 
21.8; Estimated annual recurring savings: Army Audit Agency: 5.9; 
Estimated payback period: 1995 BRAC Commission: Immediate; 
Estimated payback period: Army Audit Agency: 2 years.

Total; Estimated annual recurring savings: 1995 BRAC Commission: $94.2; 
Estimated annual recurring savings: Army Audit Agency: $46.5; 
Estimated payback period: 1995 BRAC Commission: Estimated 
payback period: Army Audit Agency: [Empty].

Sources: U.S. Army Audit Agency and 1995 BRAC Commission.

Note: GAO analysis of U.S. Army Audit Agency and 1995 BRAC Commission 
data.

[End of table]

Our analysis showed that the omission of enclave costs significantly 
affected the initial estimates of savings and payback periods at all 
locations except Fort McClellan as shown in table 3. For example, the 
omission of $6.8 million in enclave costs at Fort Chaffee (see table 2) 
accounted for more than 50 percent of the $12 million in estimated 
reduced annual recurring savings at that location. Further, the enclave 
cost omissions were instrumental in increasing Fort Chaffee's estimated 
payback period from 1 year to 18 years. On the other hand, at 
Fort McClellan, estimates on costs[Footnote 24] other than those 
associated with the enclave had a greater impact on the resulting 
estimated annual recurring savings and payback periods.

Although it is unknown whether the enclave cost omissions or any other 
similar omissions would have caused the 1995 BRAC Commission to revise 
its recommendations for these installations, it is important to have 
cost and savings estimates that are as complete and accurate as 
possible in order to provide a commission with a better basis to make 
informed judgments during its deliberative process.

Although the Army omitted enclave operation and maintenance costs 
from its savings calculations for most of its 1995 actions during the 
initial phases of the BRAC process, it subsequently updated many of 
these savings estimates in its annual budget submissions to the 
Congress. In our April 2002 report on previous-round BRAC actions, we 
noted that even though DOD had not routinely updated its BRAC base 
savings estimates over time because it does not maintain an accounting 
system that tracks savings, the Army had made the most savings updates 
of all the services in recent years.[Footnote 25] According to Army 
officials, the Army Audit Agency report provided a basis for the Army 
to update the annual BRAC budget submissions and adjust the savings 
estimates at the installations reviewed. As a result, the previous 
estimated cost omissions have not materially affected the department's 
estimate of $6.6 billion in annual recurring savings across all 
previous round BRAC actions due to the fact that the savings estimates 
for these locations have been updated to reflect many enclave costs in 
subsequent annual budget submissions.

Because of the passage of time and the lack of supporting 
documentation, we were unable to document whether the Air Force had 
considered enclave costs in deriving its savings estimates for the 
former air bases we visited at Grissom in Indiana (a 1991 round 
action), March in California (a 1993 round action), and Rickenbacker in 
Ohio (a 1991 round action). Air Force Reserve Command officials, 
however, told us that estimated costs to operate and maintain their 
enclaves were considered in calculating savings estimates for these 
base actions. Officials at the bases we visited were unaware of the 
cost and savings estimates that were established for their bases during 
the BRAC decision-making process.

Conclusions:

With an upcoming round of base realignments and closures approaching 
in 2005, it is important that the new Defense Base Closure and 
Realignment Commission have information that is as complete and 
accurate as possible on DOD-proposed realignment and closure actions in 
order to make informed judgments during its deliberations. Previous 
round actions indicate that, in several cases, a commission lacked key 
information (e.g., about the projected needs of an enclave 
infrastructure and estimated costs to operate and maintain an enclave) 
because DOD had not fully identified specific infrastructure needs 
until after the commission had issued its recommendations. Without the 
benefit of more complete data during the deliberative process, the 
commission subsequently issued recommendation language that permitted 
the Army to form reserve enclaves that are considerably larger than one 
might expect based on the commission's language concerning minimum 
essential land and facilities for reserve component use. In addition, 
because DOD did not adequately consider cross-service requirements of 
various military activities located in the vicinity of its proposed 
enclaves and did not include them in the enclaves, it may have lost the 
opportunity to achieve several benefits to obtain savings, enhance 
training and readiness, and increase force protection for these 
activities. DOD has recently issued policy guidance as part of the 2005 
closure round that, if implemented, should address cross-service 
requirements and the potential to relocate activities on future 
enclaves where relocation makes operational and economic sense.

Recommendations for Executive Action:

As part of the new base realignment and closure round scheduled for 
2005, we recommend that you establish provisions to ensure that data 
provided to the Defense Base Closure and Realignment Commission clearly 
specify the (1) infrastructure (e.g., acreage and total square footage 
of facilities) needed for any proposed reserve enclaves and 
(2) estimated costs to operate and maintain such enclaves.

As you know, 31 U.S.C. 720 requires the head of a federal agency to 
submit a written statement of the actions taken on our recommendations 
to the Senate Committee on Government Affairs and the House Committee 
on Government Reform not later than 60 days after the date of this 
report. A written statement must also be sent to the House and Senate 
Committees on Appropriations with the agency's first request for 
appropriations made more than 60 days after the date of this report.

Agency Comments:

In commenting on a draft of this report, the Assistant Secretary of 
Defense for Reserve Affairs concurred with our recommendations. The 
department's response indicated that it would work to resolve the 
issues addressed in our report, recognizing the need for improved 
planning for reserve enclaves as part of BRAC decision making and 
include improvements in selecting facilities to be retained, 
identifying costs of operation, and assessing impacts on BRAC costs and 
savings. DOD's comments are included in appendix III of this report.

Scope and Methodology:

We prepared this report under our basic legislative responsibilities as 
authorized by 31 U.S.C. § 717. We performed our work at, and met with 
officials from, the Office of the Assistant Secretary of Defense for 
Reserve Affairs, the Army National Guard, the Air National Guard, the 
headquarters of the Army Reserve Command and Air Force Reserve Command, 
and Army and Air Force BRAC offices. We also visited and met with 
officials from several reserve component enclave locations, including 
the Army's Fort Pickett, Virginia; Fort Indiantown Gap, Pennsylvania; 
Fort Chaffee, Arkansas; Fort McClellan, Alabama; and Fort Hunter 
Liggett, California; as well as the Air Force's March Air Reserve Base, 
California; Grissom Air Reserve Base, Indiana; and Rickenbacker Air 
National Guard Base, Ohio. We also contacted select officials who had 
participated in the 1995 BRAC round decision-making process to discuss 
their views on establishing enclaves on closed or realigned bases. Our 
efforts regarding previous-round enclave planning were hindered by the 
passage of time, the lack of selected critical planning documentation, 
and the general unavailability of key officials who had participated in 
the process.

To determine whether enclave infrastructure needs had been identified 
prior to BRAC Commission decision making, we first identified the scope 
of reserve enclaves by examining BRAC Commission reports from the four 
previous rounds and DOD data regarding those enclave locations. To the 
extent possible, we reviewed available documentation and compared 
process development timelines with the various commission reporting 
dates to determine the extent of enclave planning completed before a 
commission's issuance of specific BRAC recommendations. We examined 
available commission hearings from the 1995 round to ascertain the 
extent of commission discussion regarding proposed enclaves. We also 
interviewed officials at most of the major enclave locations as well as 
at the major command level to discuss their understanding of the 
enclave planning process and associated timelines employed in the 
previous rounds. We also discussed with these officials any previous 
planning actions or actions currently underway to relocate various 
reserve activities or organizations to enclave locations.

To determine whether projected costs to operate and maintain reserve 
enclaves were considered in deriving estimated savings during the 
BRAC decision-making process, we reviewed available cost and savings 
estimation documentation derived from DOD's COBRA model to ascertain if 
estimated savings were offset by projected enclave costs. We reviewed 
Army Audit Agency BRAC reports issued in 1997 on costs and savings 
estimates at various BRAC locations, including some enclave sites. 
Further, we analyzed how omitted enclave costs affected estimated 
annual recurring savings and payback periods at selected Army bases. We 
also discussed cost and savings estimates with Army and Air Force BRAC 
office officials as well as officials at bases we visited. However, as 
in our other efforts, we were generally constrained in our efforts by 
the general unavailability of knowledgeable officials on specific 
enclave data and adequate supporting documentation. We also examined 
recent annual BRAC budget submissions to the Congress to ascertain if 
savings estimates at the major enclave locations had been updated over 
time.

In performing this review, we used the same accounting records and 
financial reports DOD and reserve components use to manage their 
facilities. We did not independently determine the reliability of the 
reported financial and real property information. However, in our 
recent audit of the federal government's financial statements, 
including DOD's and the reserve components' statements, we questioned 
the reliability of reported financial information because not all 
obligations and expenditures are recorded to specific financial 
accounts.[Footnote 26] In addition, we did not validate infrastructure 
needs for DOD enclaves.

We conducted our work from July 2002 through April 2003 in accordance 
with generally accepted government auditing standards.

We are sending copies of this report to the Secretaries of the Army, 
Navy, and Air Force; the Commandant of the Marine Corps; the Director, 
Office of Management and Budget; and interested congressional 
committees and members. In addition, the report is available to others 
upon request and can be accessed at no charge on GAO's Web site at 
www.gao.gov.

Please contact me on (202) 512-8412 if you or your staff have any 
questions regarding this report. Key contributors to this report are 
listed in appendix IV.

Sincerely yours,

Barry W. Holman, 
Director 
Defense Capabilities and Management:

Signed by Barry W. Holman: 

[End of section]

Appendix I: General Description of Major Reserve Component Enclaves 
(Pre-BRAC and Post-BRAC):

Installation: Fort Hunter Liggett; BRAC recommendation: Realign Fort 
Hunter Liggett by relocating the Army Test and Experimentation Center 
missions and functions to Fort Bliss, Texas. Retain minimum essential 
facilities and training area as an enclave to support the reserve 
component; Utilization: * Prior to BRAC 1995, the Army Reserve managed 
the base, assuming control of the property in December 1994 from the 
active Army; * In September 1997, the base became a sub-installation 
of the Army Reserve's Fort McCoy. The training man days have increased 
by about 55 percent since 1998.

Installation: Fort Chaffee; BRAC recommendation: Close Fort Chaffee 
except for minimum essential ranges, facilities, and training areas 
required for a reserve component training enclave for individual and 
annual training; Utilization: * Prior to BRAC 1995, the active Army 
managed the base. The reserve components had the majority of training 
man days (75 percent) while the active component had 24 percent; the 
remaining training was devoted to non-DOD personnel; * In October 
1997, base management transferred to the Arkansas National Guard. 
Overall training has decreased 51 percent with reserve component 
training being down 59 percent.

Installation: Fort Pickett; BRAC recommendation: Close Fort Pickett 
except minimum essential ranges, facilities, and training areas as a 
reserve component training enclave to permit the conduct of individual 
and annual training; Utilization: * Prior to BRAC 1995, the Army 
Reserve managed the base. The reserve components had the majority of 
the training man days (62 percent) while the active component had 37 
percent; the remaining training was devoted to non-DOD personnel; the 
remaining training was devoted to non-DOD personnel; * In 
October 1997, base management transferred to the Virginia National 
Guard. Overall training has increased by 6 percent.

Installation: Fort Dix; BRAC recommendation: Realign Fort Dix by 
replacing the active component garrison with an Army Reserve garrison. 
In addition, it provided for retention of minimum essential ranges, 
facilities, and training areas as an enclave required for reserve 
component training; Utilization: * Prior to BRAC 1995, the active Army 
managed the base. The reserve components had the majority of training 
man days (72 percent) while the active component had 8 percent; the 
remaining training was devoted to non-DOD personnel; * In October 
1997, base management transferred to the Army Reserve. Overall training 
has increased 8 percent.

Installation: Fort Indiantown Gap; BRAC recommendation: Close Fort 
Indiantown Gap, except minimum essential ranges, facilities and 
training areas as a reserve component training enclave to permit the 
conduct of individual and annual training; Utilization: * Prior to 
BRAC 1995, the active Army managed the base. The reserve components had 
the majority of training man days (85 percent) while the active 
component had 3 percent; the remaining training was devoted to non-DOD 
personnel; * In October 1998, base management transferred to the 
Pennsylvania National Guard. Overall training has increased by about 
7 percent.

Installation: Fort McClellan; BRAC recommendation: Close Fort 
McClellan, except minimum essential land and facilities for a reserve 
component enclave and minimum essential facilities, as necessary, to 
provide auxiliary support to the chemical demilitarization operation at 
Anniston Army Depot, Alabama; Utilization: * Prior to BRAC 1995, the 
active Army managed the base; * In May 1999, base management 
transferred to the Alabama National Guard. Overall training has 
increased 75 percent.

Installation: Fort Devens; BRAC recommendation: Close Fort Devens. 
Retain 4600 acres and those facilities necessary for reserve component 
training requirements; Utilization: * Prior to BRAC 1991, the active 
Army managed the base; * In March 1996, base management transferred to 
the Army Reserve as a sub-installation of Fort Dix.

Installation: March Air Reserve Base; BRAC recommendation: Realign 
March Air Force Base. The 445[TH] Airlift Wing Air Force Reserve, 452nd 
Air Refueling Wing, 163th RECONNAISSANCE GROUP, THE AIR FORCE Audit 
Agency and the Media Center will remain and the base will convert to a 
reserve base; Utilization: * Prior to BRAC 1993, the active Air Force 
managed the base, with major activities being the 452[ND] Air Refueling 
Wing, 445th Airlift Wing and the 452nd Air Mobility Wing, 163rd Air 
Refueling Wing; * In April 1996, base management transferred to the 
Air Force Reserve with major activities being the 63rd Air Refueling 
Wing and the 144[TH] Fighter Wing as well as tenants such as U.S. 
Customs.

Installation: Grissom Air Reserve Base; BRAC recommendation: Close 
Grissom Air Force Base and transfer assigned KC-135 aircraft to the Air 
reserve components; Utilization: * Prior to BRAC 1991, the active Air 
Force managed the base with major activities being the 434th Air 
Refueling Wing and several Air Force Reserve units; * In 1994, base 
management transferred to the Air Force Reserve. Grissom Air Reserve 
Base houses the 434[TH] Air Refueling Wing as well as other tenants 
such as the Navy Reserve.

Installation: Homestead Air Reserve Base; BRAC recommendation: Realign 
Homestead Air Force Base. The 482d F-16 Fighter Wing and the 301[ST] 
Rescue Squadron and the North American Air Defense Alert activity will 
remain in a cantonment area; Utilization: * Prior to BRAC 1991, the 
active Air Force managed the base, with major activities being the 
482[ND] Fighter Wing and the 301st Rescue Squadron; * In August 1992, 
Hurricane Andrew destroyed most of the base. After the base was rebuilt 
and management transferred to the Air Force Reserve, operations were 
reinstated with major activities being the 482[ND] Fighter Wing and the 
NORAD Air Defense Alert activity.

[End of table]

Sources: 1991, 1993, and 1995 BRAC Commission reports and DOD.

[End of section]

Appendix II: Reserve Enclaves Created under Previous BRAC Rounds:

BRAC Round: 1988; Bases With Enclaves: Fort Douglas, Utah; Acreage: 50.

Bases With Enclaves: BRAC Round: Fort Sheridan, Ill; Acreage: BRAC 
Round: 100.

Bases With Enclaves: BRAC Round: Hamilton Army Airfield, Calif; 
Acreage: BRAC Round: 150.

Bases With Enclaves: BRAC Round: Mather Air Force Base, Calif; 
Acreage: BRAC Round: 91.

Bases With Enclaves: BRAC Round1991: Pease Air Force Base, N.H; 
Acreage: BRAC Round1991: 218.

BRAC Round: 1991; Bases With Enclaves: Fort Benjamin Harrison, Ind; 
Acreage: 138.

Bases With Enclaves: BRAC Round: Fort Devens, Mass; Acreage: BRAC 
Round: 5,226.

Bases With Enclaves: BRAC Round: Grissom Air Force Base, Ind; Acreage: 
BRAC Round: 1,380.

Bases With Enclaves: BRAC Round1993: Sacramento Army Depot, Calif; 
Acreage: BRAC Round1993: 38.

BRAC Round: 1993; Bases With Enclaves: Griffiss Air Force Base, N.Y; 
Acreage: 39.

Bases With Enclaves: BRAC Round: Homestead Air Force Base, Fla; 
Acreage: BRAC Round: 852.

Bases With Enclaves: BRAC Round: March Air Force Base, Calif; Acreage: 
BRAC Round: 2,359.

Bases With Enclaves: BRAC Round1995: Rickenbacker Air National Guard 
Base, Ohio; Acreage: BRAC Round1995: 168.

BRAC Round: 1995; Bases With Enclaves: Camp Kilmer, N.J; Acreage: 24.

Bases With Enclaves: BRAC Round: Camp Pedricktown, N.J; Acreage: BRAC 
Round: 86.

Bases With Enclaves: BRAC Round: Fitzsimmons Medical Center, Colo; 
Acreage: BRAC Round: 21.

Bases With Enclaves: BRAC Round: Fort Chaffee, Ark; Acreage: BRAC 
Round: 64,272.

Bases With Enclaves: BRAC Round: Fort Dix, N.J; Acreage: BRAC Round: 
30,944.

Bases With Enclaves: BRAC Round: Fort Hamilton, N.Y; Acreage: BRAC 
Round: 168.

Bases With Enclaves: BRAC Round: Fort Hunter Liggett, Calif; Acreage: 
BRAC Round: 164,272.

Bases With Enclaves: BRAC Round: Fort Indiantown Gap, Pa; Acreage: 
BRAC Round: 17,227.

Bases With Enclaves: BRAC Round: Fort McClellan, Ala; Acreage: BRAC 
Round: 22,531.

Bases With Enclaves: BRAC Round: Fort Missoula, Mont; Acreage: BRAC 
Round: 16.

Bases With Enclaves: BRAC Round: Fort Pickett, Va; Acreage: BRAC 
Round: 42,273.

Bases With Enclaves: BRAC Round: Fort Ritchie, Md; Acreage: BRAC 
Round: 19.

Bases With Enclaves: BRAC Round: Fort Totten, N.Y; Acreage: BRAC 
Round: 36.

Bases With Enclaves: BRAC RoundBases With Enclaves: Oakland Army Base, 
Calif; Acreage: BRAC RoundAcreage: 27.

Sources: 1988, 1991, 1993, and 1995 BRAC Commission reports and DOD.

[End of table]

[End of section]

Appendix III: Comments from the Department of Defense:

RESERVE AFFAIRS:

ASSISTANT SECRETARY OF DEFENSE 1500 DEFENSE PENTAGON WASHINGTON, DC 
20301-1500:

19 JUN 2003:

Mr. Barry W. Holman:

Director, Defense Capabilities and Management U.S. General Accounting 
Office:

441 G Street, N.W. Washington, D.C. 20548:

Dear Mr. Holman:

This is the Department of Defense (DoD) response to the GAO draft 
report, GAO-03-723, "MILITARY BASE CLOSURES: Better Planning Needed for 
Future Reserve Enclaves," dated May 15, 2003 (GAO Code 350231).

An important element of the Base Realignment and Closure (BRAG) process 
is the timely collection of complete and accurate data used by the 
Department and the BRAG Commission in the evaluation process. The GAO 
report provides two recommendations that would require DoD to provide 
the Commission with specific infrastructure requirements (e.g. acreage 
and total square footage of facilities), and estimated operation and 
maintenance costs for any Reserve component enclave proposed in BRAG 
2005.

I recognize that in the past, Reserve components may have been required 
to obtain real property in "all or none/as-is" condition that resulted 
in higher than projected operation and maintenance costs. However, the 
Secretary of Defense in his November 2002 memorandum reemphasized 
efficient and effective basing strategies for BRAG 2005. It is 
certainly more efficient to capture real property requirements for 
Reserve components early in the BRAG process to the maximum extent 
practicable, and present that data to the Commission in the same level 
of detail as presented for the Active components.

It is imperative that the Reserve components receive early notification 
of potential realignments or closures to effect efficient planning of 
future Reserve enclaves. I agree that when establishing a Reserve 
enclave, it is important to recognize the "move-in" costs associated 
with assuming the responsibilities of becoming an installation host. In 
past BRAC rounds, the Reserve components' requirements were considered 
later in the process, which led to less effective use of Department 
resources.

I concur with the recommendations as stated, and will work to resolve 
the issues addressed within this report and ensure that the need for 
appropriate planning is recognized early in the BRAC process.

Sincerely,

T.F. Hall:

Signed by T.F. Hall:

Enclosure:

GAO DRAFT REPORT, GAO-03-723:

"MILITARY BASE CLOSURES: Better Planning Needed for Future Reserve 
Enclaves," (GAO Code 350231).

DEPARTMENT OF DEFENSE COMMENTS TO THE RECOMMENDATIONS:

RECOMMENDATION 1: As part of the new base realignment and closure round 
scheduled for 2005, the GAO recommended that the Secretary of Defense 
establish provisions to ensure that the data provided to the base 
realignment and closure commission clearly specify the infrastructure 
(e.g., acreage and total square footage of facilities) needed for any 
proposed reserve enclaves. (Page 20/Draft Report).

DoD RESPONSE: Concur with comment.

As the GAO stated in the report, "information provided to the 
commission should be as complete and accurate as possible". The 
Assistant Secretary of Defense for Reserve Affairs recommends that 
Reserve component facilities information presented to the BRAG 
commission should be at the same level of detail as presented for the 
Active components.

RECOMMENDATION 2: As part of the new base realignment and closure round 
scheduled for 2005, the GAO recommended that the Secretary of Defense 
establish provisions to ensure that the data provided to the base 
realignment and closure commission clearly specify the estimated costs 
to operate and maintain such enclaves. (Page 21/Draft Report).

DoD RESPONSE: Concur with comment.

In some cases, the Reserve components may have been required to pick up 
real property in "as-is" condition resulting in higher than projected 
operation and maintenance (O&M) costs. The Assistant Secretary of 
Defense for Reserve Affairs recommends that Reserve component cost data 
presented to the BRAG commission capture as complete and accurately as 
possible projected O&M costs for future Reserve enclaves.

[End of section]

Appendix IV: GAO Contact and Staff Acknowledgments:

GAO Contact:

Michael Kennedy (202) 512-8333:

Acknowledgments:

In addition to the individual named above, Julie Chamberlain, Shawn 
Flowers, Richard Meeks, Maria-Alaina Rambus, James Reifsnyder, 
Donna Weiss, and Susan Woodward made key contributions to this report.

FOOTNOTES

[1] DOD reported that, as of December 2002, it had disposed of about 
272,000 acres (53 percent) of an approximately 511,000 acres that it 
had identified during the previous base closure rounds as unneeded and 
being made available to others for reuse.

[2] See Defense Base Closure and Realignment Commission, 1995 Report to 
the President (Washington D.C.: July 1, 1995), B-2. An enclave is "a 
section of a military installation that remains intact from that part 
which is closed or realigned and which will continue with its current 
role and functions subject to specific modifications."

[3] A single round of base realignments and closures in 2005 was 
authorized with the passage of the National Defense Authorization Act 
for Fiscal Year 2002.

[4] For the purpose of this report, we defined "major" as exceeding 
500 acres. The amount of acreage has no bearing on the relative 
importance of the missions being performed at these or other enclave 
locations.

[5] See Defense Base Closure and Realignment Commission, 1995 Report. 
The report recommendation language generally provided that the Army 
bases be "closed, except that minimum essential ranges, facilities, and 
training areas" be retained for reserve component use.

[6] U.S. Army Audit Agency, Base Realignment and Closure: 1995 Savings 
Estimates, Audit Report AA97-225 (Washington, D.C.: July 31, 1997).

[7] A payback period is the time required for cumulative estimated 
savings to exceed the cumulative estimated costs incurred as a result 
of implementing BRAC actions.

[8] An exception is the commission-recommended enclave on the former 
Homestead Air Force Base; DOD did not submit this as a recommendation 
to the commission and therefore had not considered any costs related to 
this action in its submission.

[9] The BRAC legislation--the Defense Authorization Amendments and Base 
Realignment Act (P.L.100-526, as amended) for the 1988 round and the 
Defense Base Closure and Realignment Act of 1990 (P.L. 101-510, as 
amended) for the 1991, 1993, and 1995 rounds--was applicable to 
military installations in the 50 states, the District of Columbia, the 
Commonwealth of Puerto Rico, Guam, the U.S. Virgin Islands, American 
Samoa, and any other commonwealth, territory, or possession of the 
United States.

[10] See U.S. General Accounting Office, Military Base Closures: 
Progress in Completing Actions from Previous Realignments and Closures, 
GAO-02-433 (Washington, D.C.: Apr. 5, 2002).

[11] See GAO-02-433 and U.S. General Accounting Office, Military Base 
Closures: DOD's Updated Net Savings Estimate Remains Substantial, GAO-
01-971 (Washington D.C.: July 31, 2001); Congressional Budget Office, 
Review of the Report of the Department of Defense on Base Realignment 
and Closure (Washington D.C.: July 1, 1998); Department of Defense, 
Office of the Inspector General, Audit Report: Cost and Savings for 
1993 Defense Realignments and Closures, Report No. 98-130 (Washington 
D.C. May 6, 1998); and U.S. Army Audit Agency, Base Realignment and 
Closure: 1995.

[12] An exception to this involves the Air Force, which did not 
routinely update its savings estimates from the COBRA model as part of 
BRAC decision making.

[13] We have excluded any joint reserve bases established by a BRAC 
Commission, such as the Navy-managed Joint Reserve Base-Ft. Worth in 
Texas, because they do not conform to the definition of an enclave as 
previously defined.

[14] This advance planning was based on the recommendations for an 
enclave having already been included in the recommendations of the 
Secretary of Defense, which were forwarded to the BRAC Commission for 
its review.

[15] Various service component (both active and reserve) units travel 
to and conduct training at many reserve enclaves.

[16] Office of the Deputy Under Secretary of Defense (Installations), 
Report on the Effect of Base Closures on Future Mobilization Options 
(Washington D.C.: Nov. 10, 1999).

[17] A cantonment area is that part of a base containing the majority 
of the facilities and most areas that are not part of the training 
areas.

[18] The infrastructure needs for the Fort Hunter Liggett enclave were 
not approved until November 1997.

[19] A local redevelopment authority is the DOD-recognized local 
organization whose role is to coordinate efforts of the community to 
reuse assets of a former military base.

[20] Comparative data on training day usage were not readily available 
at the Ft. Devens location.

[21] See U.S. Army Judge Advocate General memorandum, Review of 
Implementation Plan for Fort Indiantown Gap (Washington D.C.: Aug. 22, 
1995) and U.S. Army Judge Advocate General memorandum, Legal Review of 
Fort Hunter Liggett Facilities Utilization Plan (Washington D.C.: Jan. 
25, 1996). These memorandums were prepared for the Army Assistant Chief 
of Staff for Installation Management in response to his request for a 
review of plans to implement BRAC actions at these specified locations.

[22] See U.S. Army Audit Agency, Base Realignment and Closure: 1995.

[23] The remaining two 1995 major enclaves--Fort Dix and Fort Hunter 
Liggett--were not reviewed by the Army Audit Agency. An Army BRAC 
official told us that enclave costs were considered in deriving net 
savings estimates for Fort Dix but not for Fort Hunter Liggett. 
Supporting documentation was unavailable to verify this statement.

[24] The cost estimates included about $19 million in annual 
recurring costs, about $40 million in one-time construction costs and 
about $26 million in one-time operations and maintenance costs related 
to the Fort McClellan closure.

[25] See GAO-02-433.

[26] U.S. General Accounting Office, Major Management Challenges and 
Program Risks: Department of Defense, GAO-03-98 (Washington, D.C.: 
January 2003).

GAO's Mission:

The General Accounting Office, the investigative arm of Congress, 
exists to support Congress in meeting its constitutional 
responsibilities and to help improve the performance and accountability 
of the federal government for the American people. GAO examines the use 
of public funds; evaluates federal programs and policies; and provides 
analyses, recommendations, and other assistance to help Congress make 
informed oversight, policy, and funding decisions. GAO's commitment to 
good government is reflected in its core values of accountability, 
integrity, and reliability.

Obtaining Copies of GAO Reports and Testimony:

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through the Internet. GAO's Web site ( www.gao.gov ) contains 
abstracts and full-text files of current reports and testimony and an 
expanding archive of older products. The Web site features a search 
engine to help you locate documents using key words and phrases. You 
can print these documents in their entirety, including charts and other 
graphics.

Each day, GAO issues a list of newly released reports, testimony, and 
correspondence. GAO posts this list, known as "Today's Reports," on its 
Web site daily. The list contains links to the full-text document 
files. To have GAO e-mail this list to you every afternoon, go to 
www.gao.gov and select "Subscribe to e-mail alerts" under the "Order 
GAO Products" heading.

Order by Mail or Phone:

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to:

U.S. General Accounting Office

441 G Street NW,

Room LM Washington,

D.C. 20548:

To order by Phone: 	

	Voice: (202) 512-6000:

	TDD: (202) 512-2537:

	Fax: (202) 512-6061:

To Report Fraud, Waste, and Abuse in Federal Programs:

Contact:

Web site: www.gao.gov/fraudnet/fraudnet.htm E-mail: fraudnet@gao.gov

Automated answering system: (800) 424-5454 or (202) 512-7470:

Public Affairs:

Jeff Nelligan, managing director, NelliganJ@gao.gov (202) 512-4800 U.S.

General Accounting Office, 441 G Street NW, Room 7149 Washington, D.C.

20548: