This is the accessible text file for GAO report number GAO-02-433 
entitled 'Military Base Closures: Progress in Completing Actions from 
Prior Realignments and Closures' which was released on April 05, 2002.



This text file was formatted by the U.S. General Accounting Office 

(GAO) to be accessible to users with visual impairments, as part of a 

longer term project to improve GAO products’ accessibility. Every 

attempt has been made to maintain the structural and data integrity of 

the original printed product. Accessibility features, such as text 

descriptions of tables, consecutively numbered footnotes placed at the 

end of the file, and the text of agency comment letters, are provided 

but may not exactly duplicate the presentation or format of the printed 

version. The portable document format (PDF) file is an exact electronic 

replica of the printed version. We welcome your feedback. Please E-mail 

your comments regarding the contents or accessibility features of this 

document to Webmaster@gao.gov.



Report to the Honorable Vic Snyder,



House of Representatives:



United States General Accounting Office:



GAO:



April 2002:



MILITARY BASE CLOSURES:



Progress in Completing Actions from Prior Realignments and Closures:



Military Base Closures:



GAO-02-433:



Contents:



Letter:



Results in Brief:



Background:



BRAC Net Savings Are Substantial but Imprecise:



Transfer of Unneeded BRAC Property Is Only Partially Completed:



Most Communities Are Continuing to Recover from the Economic Impact of 

BRAC:



Conclusions:



Recommendations for Executive Action:



Agency Comments:



Appendix I: Scope and Methodology:



Appendix II: Revisions to BRAC Cost and Savings Estimates:



Appendix III: DOD’s Use of Economic Development Conveyances:



Appendix IV: Civilian Jobs Lost and Created at Major BRAC 

Locations during the Prior Four BRAC Rounds:



Appendix V: Average Unemployment Rates of BRAC-Affected Areas Compared 

with the U.S. Average Rate:



Appendix VI: Average Annual Real per Capita Income Growth 

Rates of BRAC-Affected Areas Compared with the 

U.S. Average Rate:



Appendix VII: Case Examples of Community Impacts and Recovery from 
BRAC:



Appendix VIII: Key Reports Related to Base Closure Implementation 
Issues:



Appendix IX: Comments from the Department of Defense:



Appendix X: GAO Contacts and Staff Acknowledgments:



Tables:



Table 1: DOD’s Cost and Savings Estimates through Fiscal Year 2001 for 

the Four BRAC Rounds:



Table 2: Actual Transfers of Unneeded BRAC Property, as of September 

30, 2001:



Table 3: Leased BRAC Acreage, as of September 30, 2001:



Table 4: Use and Status of Early Transfer Authority at BRAC Bases 

through Fiscal Year 2001:



Table 5: Cumulative Cost and Savings Estimates through Fiscal Year 2001 

for the Prior Four BRAC Rounds as Reflected in DOD’s Budget Requests 

and Documentation for Fiscal Years 1999 and 2002:



Table 6: DOD’s Use of Economic Development Conveyances:



Table 7: Civilian Jobs Lost and Created at Major Base Realignments and 

Closures during the Prior Four BRAC Rounds, as of October 31, 2001:



Table 8: Community Impacts Resulting from the Closure of Chase Naval 

Air Station, Texas, as Reported in 1998 and 2001:



Table 9: Community Impacts Resulting from the Closure of Castle Air 

Force Base, California, as Reported in 1998 and 2001:



Table 10: Reported Community Impacts Resulting from Base Closures for 

Communities Not Visited in 1998:



Figures:



Figure 1: DOD’s Usual Procedures for Transferring Property:



Figure 2: Cumulative BRAC Cost and Savings Estimates through Fiscal 

Year 2001:



Figure 3: Planned Disposition of Unneeded Property:



Figure 4: Planned Transfers to Federal Agencies:



Figure 5: Planned Transfers to Nonfederal Entities:



Figure 6: DOD’s Estimated Environmental Cleanup Cost at Base Closure 

Sites After Fiscal Year 2001, as of September 30, 2001:



Figure 7: Factors Affecting Economic Recovery from Base Closures:



Figure 8: Average Unemployment Rates of 62 BRAC-Affected Communities 

Compared with Average U.S. Rate for January-September 2001:



Figure 9: Calendar Years 1996-99 Average Annual per Capita Income 

Growth Rates of BRAC-Affected Areas Compared with U.S. Average:



Figure 10: Comparison of Unemployment Rates of 24 BRAC-Affected 

Locations West of the Mississippi River:



Figure 11: Comparison of Unemployment Rates of 38 BRAC-Affected 

Locations East of the Mississippi River:



Figure 12: Comparison of Average Annual Real per Capita Income Growth 

Rates of 24 BRAC-Affected Locations West of the Mississippi River:



Figure 13: Comparison of Average Annual Real per Capita Income Growth 

Rates of 38 BRAC-Affected Locations East of the Mississippi River:



Abbreviations:



BRAC: base realignment and closure

CBO: Congressional Budget Office

DOD: Department of Defense:



United States General Accounting Office:



Washington, DC 20548:



April 5, 2002:



The Honorable Vic Snyder

House of Representatives:



Dear Mr. Snyder:



Through base realignment and closure rounds in 1988, 1991, 1993, and 

1995, the Department of Defense expected to significantly reduce its 

domestic infrastructure and provide needed dollars for high-priority 

programs such as modernization. With the conclusion of the 6-year 

implementation period of the last round in fiscal year 2001, the 

department has closed or realigned hundreds of bases, has generated 

savings from these actions, and is in the process of transferring 

unneeded base property to other users. At the same time, the 

communities surrounding the former defense bases continue the lengthy 

process of recovery from the economic impact of the closure process. 

Our last comprehensive report on the implementation of base closure 

decisions was issued in December 1998.[Footnote 1] In that report, we 

concluded that the closure process was generating substantial savings 

(although the savings estimates were imprecise), most former base 

property had not yet been transferred to other users, and most 

communities surrounding closed bases were faring well economically in 

relation to key national economic indicators. In a July 2001 report and 

August 2001 testimony, we updated our closure implementation data and 

reaffirmed the primary results of our prior work.[Footnote 2]



While the Congress recently authorized another round of defense base 

realignments and closures beginning in 2005, many in the Congress 

continue to have questions about the implementation of the prior 

rounds. Some in Congress have raised concerns about the adequacy of the 

department’s accounting for the costs and savings associated with 

closure decisions and the economic impact on communities affected by 

the closures and their ability to recover. Others have expressed the 

view that all prior round actions should be completed before the 

introduction of any new rounds.



As requested, this report further updates the status of the four prior 

rounds of defense base realignments and closures at the conclusion of 

the 6-year implementation period associated with the 1995 round. It 

addresses (1) the magnitude of the net savings accruing from the prior 

four closure rounds and the impact of remaining closure-related costs 

on future savings, (2) the department’s progress in transferring 

unneeded base property to other users, and (3) the economic recovery of 

communities affected by base closures.



In performing our work, we used our December 1998 status report on 

prior realignments and closures as a baseline for assessing the 

department’s progress in completing prior round actions. First, we 

examined the department’s recently reported net savings estimates and 

the rationale for estimate revisions over time. Second, we compared 

data on actual unneeded property transfers with earlier data and sought 

out the reasons for transfer delays. Finally, we reviewed key economic 

indicators (e.g., unemployment rates and real per capita income growth) 

for communities affected by the closure process and visited select 

communities to assess the overall recovery process. Further details on 

the scope and methodology for our work are described in appendix I.



Results in Brief:



The Department of Defense has generated substantial net savings from 

the prior four closure rounds and expects those savings to grow on an 

annual basis. Our analyses have consistently affirmed that the net 

savings for the four closure rounds are substantial and can best be 

depicted as cost avoidances in specific operational areas. On the basis 

of our analysis of defense budget documentation for fiscal year 2002, 

the Department has accrued an estimated $16.7 billion in savings 

through fiscal year 2001, an increase over prior estimates. The 

department also expects to gain an estimated $6.6 billion in annual 

recurring savings thereafter--up $1 billion over estimates made in 

fiscal year 1999. The increase is attributed to adjustments in the 

inflation rate, changes in the planned implementation of base 

realignment and closure actions at specific locations, and the 

department’s underreporting of estimated savings. At the same time, our 

reviews have found that the department’s savings estimates are 

imprecise and should be viewed as rough approximations of the likely 

savings. Our analysis indicates that the imprecision stems primarily 

from the military services’ failure to periodically update overall 

savings estimates, despite departmental guidance to do so. Because 

closure or realignment implementation actions may vary from the 

original plans, it is important for the services to review and update 

these estimates periodically to increase their accuracy. Also, the 

estimates do not include a cumulative $1.5 billion cost incurred by the 

federal government to assist communities affected by the closure 

process or $3.5 billion in environmental costs expected beyond fiscal 

year 2001. The inclusion of these costs would have only a limited 

impact on cumulative long-term savings. Furthermore, although estimated 

environmental costs have fluctuated over time and remain subject to 

change, the total expected costs of about $10.5 billion are still 

within the range of the projected costs estimated in 1996.[Footnote 3]



Although the department has plans in place to transfer nearly all of 

the 518,500 acres of unneeded base property to federal and nonfederal 

users, it has only partially completed the property transfers. As of 

September 30, 2001, it had transferred about 42 percent of the total 

518,500 acres--an increase from the 14-percent transfer rate reported 

in 1998. The primary impediment to transferring the remaining property 

involves environmental cleanup, which could take many more years to 

complete as a condition for conveying property titles. The military 

services are using several mechanisms, such as the early transfer 

authority[Footnote 4] and leasing, to make property available sooner to 

communities and others for reuse. While the early transfer authority 

can be beneficial to all parties, it has not yet been widely used. It 

appears that its use is an evolving process. Service officials told us 

that they expect greater use of this authority as users become more 

familiar with its potential advantages.



While some communities surrounding closed bases are faring better than 

others, most are continuing to recover from the initial economic impact 

of base closures. The economic impact on and recovery of specific 

communities within the region of a closed base can vary because of such 

factors as their proximity to the base and the business diversity 

within the community. While the short-term impact can be very 

traumatic, several factors, such as the strength of the national and 

regional economies, play a role in determining the long-term impact of 

the closure process. While the successful redevelopment of base 

property can also play a role in the process, broader regional economic 

growth may also be key to economic recovery. Two economic indicators--

the unemployment rate and average annual real per capita income growth 

rate--show that the majority of communities are doing well compared 

with average U.S. rates, despite delays in the transfer or reuse of 

former base property. As of September 30, 2001, of the 62 communities 

surrounding major base closures, 44 (71 percent) had average 

unemployment rates lower than the U.S. rate, as reported by the 

Department of Labor’s Bureau of Labor Statistics. In addition, the 

average unemployment rate decreased for 41 of the 62 communities (66 

percent) since 1998. In terms of average annual real (adjusted for 

inflation) per capita income growth rates, 33 (53 percent) of the 

affected communities had rates equal to or higher than U.S. rates for 

1996 through 1999, and another 7 (11 percent) were close to the 

average. Of the rest, the rates of only three (5 percent) were 

significantly lower than the U.S. rate and none had negative rates. In 

addition, the per capita income growth rates increased for 42 of the 49 

communities (86 percent) since we last reported them in 1998. Our 

visits to communities surrounding six major base closures showed that 

they were recovering, although not without difficulty and challenges. 

Overall, while our analysis showed that the general economic trend for 

most communities was favorable, questions remain about some 

communities’ ability to sustain their economic recovery over time, 

particularly in light of the recent downturn in the national economy.



This report contains recommendations for executive action designed to 

(1) improve the Defense Department’s accuracy in reporting estimated 

savings generated from the next congressionally authorized round of 

base closure and realignment rounds beginning in 2005 and (2) 

accelerate property transfers and/or save the department money through 

the expanded use of the early transfer authority. In commenting on a 

draft of this report, the department concurred with our 

recommendations.



Background:



To enable the Department of Defense (DOD) to close unneeded bases and 

realign others, the Congress enacted base realignment and closure 

(BRAC) legislation that instituted base closure rounds in 1988, 1991, 

1993, and 1995.[Footnote 5] A special commission established for the 

1988 round made recommendations to the Committees on Armed Services of 

the Senate and House of Representatives. For the 1991, 1993, and 1995 

rounds, special BRAC Commissions were set up to recommend specific base 

realignments and closures to the president, who in turn sent the 

commissions’ recommendations and his approval to the Congress. The four 

commissions generated 499 recommendations--97 major closures and 

hundreds of smaller base realignments, closures, and other 

actions.[Footnote 6] Of the 499 recommendations, 451 required action; 

the other 48 were modified in some way by a later commission. DOD was 

required to complete its realignment and closure actions for the 1988 

round by September 30, 1995, and for the 1991, 1993, and 1995 rounds 

within 6 years from the date the president forwarded the recommended 

actions to the Congress. Property disposal and environmental cleanup 

actions, however, were allowed to continue beyond the 6-year period.



DOD reported that, as of September 30, 2001, it had taken all necessary 

actions to implement the recommendations of the BRAC Commissions for 

the four rounds.[Footnote 7] As a result of these actions, DOD 

estimates that it has reduced its domestic infrastructure by about 20 

percent and saved billions of dollars in the process. DOD calculates 

its net savings by deducting the costs necessary to implement BRAC 

actions from the savings accrued by realigning or closing bases. These 

accrued savings include savings that occur during the budget year that 

a BRAC decision is implemented as well as the estimated cost avoidances 

during future years--costs that DOD would have incurred if BRAC actions 

had not taken place. Some of the savings are one-time (e.g., canceled 

military construction projects), but most represent an avoidance of 

recurring spending (e.g., personnel reductions). Eliminating or 

reducing recurring base support costs at closing and realigned bases is 

a major component of BRAC savings. Savings are realized through a 

number of actions, such as terminating physical security, fire 

protection, utilities, property maintenance, accounting, payroll, and a 

variety of other services that have associated costs linked 

specifically to base operations. Over time, the value of the recurring 

savings has become the largest and most important portion of BRAC’s 

overall savings. DOD reports these savings estimates to the Congress as 

part of its annual budget requests. The avoidance of other one-time, 

but not-yet-programmed, costs also may be significant over time, but 

they are not easily captured or reported.



Once DOD no longer needs BRAC property, it is considered excess and is 

offered to other federal agencies. As shown in figure 1, any property 

that remains is then considered surplus and is disposed of through a 

variety of means--initially by transfers to states and local 

governments for public benefit purposes and, thereafter, for economic 

development purposes (commonly referred to as “economic development 

conveyances”) and negotiated or public sales. Under public benefit 

transfers, local redevelopment agencies can acquire property for such 

purposes as schools, parks, and airports for little or no cost. In 

1993, BRAC legislation was amended to provide local redevelopment 

authorities with BRAC property at or below fair market value or without 

cost to promote economic recovery in areas affected by closures. DOD 

was required to transfer property for economic development to 

communities in rural areas at no cost. Later, these provisions were 

replaced with others that allowed no-cost property transfers to local 

redevelopment authorities for job generation or lease back to the 

federal government.[Footnote 8] Consequently, local redevelopment 

authorities have usually sought to obtain property at no cost and, 

failing that, pursue it through negotiated sales.



Figure 1: DOD’s Usual Procedures for Transferring Property:



[See PDF for image]



[End of figure]



The economic impact on communities near base realignments and closures 

has been a long-standing source of public anxiety. Because of this 

concern, DOD included “economic impact” as one of eight criteria that 

it used for making BRAC recommendations in the last three rounds. 

Although it did not play as large a role in initial BRAC deliberations 

as did other criteria and was not a key decision factor, “economic 

impact” was of such sufficient importance that DOD components were 

required to estimate the impact of their recommendations.



We have reported on base closure implementation issues on several 

occasions. Although many of our reports have been limited in scope, 

focusing on concerns raised by individual members of Congress on 

closure-related actions at a specific location, our first comprehensive 

report addressing DOD-wide closure issues (e.g., the magnitude and 

precision of cost and savings estimates, the progress of environmental 

cleanup and property transfer, and the latter’s impact on communities 

and their recovery) was issued in December 1998.[Footnote 9] In that 

report, we concluded that the closure process was generating 

substantial savings, although the savings estimates were imprecise; 

most former base property was still awaiting transfer to other users; 

and most communities surrounding closed bases were faring well 

economically in relation to national economic indicators. Subsequent 

reports issued in July and August 2001 updated closure-related 

implementation data and reaffirmed the primary results of our prior 

work.[Footnote 10] In our July 2001 report, for example, we noted that 

DOD’s net BRAC savings estimates, while imprecise, had not only 

remained substantial but also were higher than projected earlier. In 

August 2001, we reported that most BRAC-affected communities were 

continuing to recover from the impact of base closures and were doing 

well economically in terms of key U.S. economic indicators. 

Furthermore, we noted that while progress was being made, over one-half 

of unneeded former base property had not yet been transferred.



BRAC Net Savings Are Substantial but Imprecise:



Through fiscal year 2001, financial data show that DOD generated an 

estimated $16.7 billion in net BRAC savings from the four rounds, an 

increase of $2.5 billion from its fiscal year 1999 estimate, and 

expects additional annual recurring savings of $6.6 billion beginning 

in fiscal year 2002, an increase of $1 billion.[Footnote 11] Although 

they have fluctuated over time, as projected costs and savings arising 

from the BRAC actions have changed, the net savings estimates have 

remained substantial. In addition to our analyses, studies by other 

federal agencies, such as the Congressional Budget Office (CBO), the 

DOD Inspector General, and the Army Audit Agency, have shown that BRAC 

savings are real and substantial. However, because they are based on 

cost and savings projections that are not precise, net savings should 

be viewed as a rough approximation of the likely savings. The estimates 

are imprecise because the military services have not regularly updated 

their savings projections. Furthermore, DOD has not incorporated into 

its estimates all costs, including reported cumulative federal 

government expenditures of about $1.5 billion incurred by agencies to 

assist communities affected by the BRAC process. On the other hand, 

estimated net savings could be viewed as greater than reported by DOD 

if one considers, for example, that many environmental-related costs 

attributed to the closures would have likely occurred, but probably at 

a slower pace, even if the bases had remained open. Also, closures 

avoid future, but not yet programmed, recapitalization costs on 

unneeded facilities.



BRAC Net Savings Estimates through Fiscal Year 2001 Have Increased $2.5 

Billion:



DOD’s fiscal year 2002 budget request and supporting data show that 

BRAC net savings estimates have increased in recent years. DOD data 

show savings estimates of about $16.7 billion through fiscal year 2001-

-an increase of about $2.5 billion from that reported in the fiscal 

year 1999 budget request. As figure 2 shows, DOD’s data indicate that, 

in 1998, the cumulative net savings estimates surpassed the costs 

incurred to implement BRAC actions, and the net savings have grown from 

that point.



Figure 2: Cumulative BRAC Cost and Savings Estimates through Fiscal 

Year 2001:



[See PDF for image]



[End of figure]



Source: Our analysis of DOD’s data.



In preparing net savings estimates, DOD deducts the costs of 

implementing BRAC actions for the four closure rounds (e.g., personnel 

and equipment relocation and environmental cleanup) from the estimated 

savings (e.g., cost avoidances such as base operational costs that 

would have occurred without BRAC action) to project net 

savings.[Footnote 12] Table 1 summarizes the cost and savings estimates 

through fiscal year 2001 for the four BRAC rounds as presented in the 

budget-related documentation for fiscal years 1999 and 2002.



Table 1: DOD’s Cost and Savings Estimates through Fiscal Year 2001 for 

the Four BRAC Rounds:



Dollars in millions.



Costs through fiscal year 2001; Fiscal year 1999 

budget request and supporting documentation: $22,881; 

Fiscal year 2002 budget request and supporting documentation: 

$21,972; Total change: $(909).



Savings through fiscal year 2001; Fiscal year 1999 

budget request and supporting documentation: 37,066; 

Fiscal year 2002 budget request and supporting documentation: 

38,679; Total change: 1,613.



Net savings through 

fiscal year 2001; Fiscal year 1999 budget request 

and supporting documentation: 14,185; Fiscal year 

2002 budget request and supporting documentation: 16,707; Total change: 
2,522.



Note: Figures are adjusted for inflation.



Source: Our analysis of DOD’s budget requests for fiscal years 1999 and 

2002 and supporting documentation.



[End of table]



As table 1 illustrates, our comparative analysis of BRAC budget 

submissions and supporting data for fiscal years 1999 and 2002 shows 

that the estimated net savings increase of $2.5 billion through 2001 

was due to a combination of decreased costs ($909 million) and 

increased savings ($1,613 million) estimates.



A significant portion of the estimated cost reduction resulted from 

delays in planned environmental cleanup through 2001, leading to a 

decrease of $379 million in reported environmental costs during that 

time period. However, expected environmental costs beyond 2001 are now 

$3.5 billion rather than the $2.4 billion estimate reported in fiscal 

year 1999. At the same time, our analysis shows that overall 

environmental costs remain within the range of prior program estimates 

that we reported on in 1996.[Footnote 13] A significant portion of the 

increased savings estimate is attributable to (1) an underreporting of 

$925 million in savings accrued from the 1991 closure round and (2) the 

inclusion of a $381 million savings estimate for two Air Force bases--

McClellan Air Force Base, California, and Kelly Air Force Base, Texas-

-which was not included in the fiscal year 1999 submission. Additional 

details regarding the increase in projected net savings through fiscal 

year 2001 and the rationale for revisions are included in appendix II.



Estimated Annual Recurring Savings Have Increased $1 Billion:



In addition to the revisions made to cost and savings estimates through 

fiscal year 2001, DOD revised its annual recurring savings estimate for 

fiscal years 2002 and beyond. DOD’s data now show that DOD will accrue 

an expected $6.6 billion in annual recurring savings for the four BRAC 

rounds--an increase of approximately $1 billion from its fiscal year 

1999 estimate. This increase is attributed to adjustments in the 

inflation rate, changes in the implementation of BRAC actions at 

specific locations, and underreported savings by the Navy, as explained 

below:



* About $470 million of the $1 billion increase in expected annual 

recurring savings is primarily a result of changes in the reporting 

base year (from fiscal year 1999 to fiscal year 2002), which resulted 

in 3 additional years of inflation.



* About $366 million of the increase is due to overall estimated 

savings updates for specific BRAC actions made by the military services 

since fiscal year 1999. The Army updated its savings estimates for 24 

BRAC actions on the basis of revisions submitted by Army major commands 

and in response to a 1997 Army Audit Agency report that recommended 

specific adjustments for audited BRAC actions.[Footnote 14] The Navy 

revised its savings estimate for the Navy Medical Research Institute, 

Bethesda, Maryland, because of changes to planned implementation 

actions at the facility. Finally, the Air Force’s reported savings 

estimates rose as a result of updates for BRAC actions at McClellan Air 

Force Base, California, and Kelly Air Force Base, Texas, in its fiscal 

year 2000 and 2001 requests.



* Another $208 million of the increase is the result of underreported 

estimated savings in the Navy’s 1991 BRAC round. Because the Navy 

received an appropriation for the 1991 BRAC round in fiscal year 1998, 

1 year after the last year of implementation, it reported some, but not 

all, of the recurring savings in that additional year. Consequently, 

about $208 million ($183 million plus an adjustment for inflation) was 

not included in DOD’s reported annual recurring savings.



Other Government Studies Also Show Substantial BRAC Savings:



In addition to our analyses, studies by other federal agencies, such as 

CBO, the DOD Inspector General, and the Army Audit Agency, have shown 

that BRAC savings are real and substantial and are related to cost 

reductions in key operational areas as a result of BRAC actions. The 

following are examples:



* In a July 1998 report, CBO reported substantial BRAC savings, even 

though it found some imprecision in DOD’s costs and savings 

estimates.[Footnote 15] CBO stated its belief that DOD’s estimate of 

$5.6 billion in annual recurring savings at that time was reasonable, 

given that the Budget Office’s estimate was about $5 billion annually.



* In a May 1998 report on more than 70 closed or realigned bases during 

the 1993 BRAC round, the DOD Inspector General found that BRAC savings 

could potentially reach $9.2 billion.[Footnote 16]



* In a July 1997 report on BRAC costs and savings, the Army Audit 

Agency concluded that savings after full implementation would be 

substantial for ten 1995 BRAC round sites that it had 

examined.[Footnote 17]



Precision of Cost and Savings Estimates Is Limited:



While the net savings from BRAC activities are clearly substantial, 

savings and cost estimates used by DOD to calculate the net savings at 

its BRAC-affected bases are imprecise. Despite DOD guidance directing 

the military services to periodically update their savings estimates, 

the services have not done this. Furthermore, DOD has not included all 

costs associated with BRAC closures in its estimates. For example, the 

estimated costs exclude some federal government costs related to BRAC 

implementation and expected environmental costs beyond 2001. The 

omission of these costs has the effect of overstating net savings 

estimates. On the other hand, net savings could be viewed as 

understated if one considers the broader implications of BRAC on the 

DOD budget. For example, while the costs incurred for the environmental 

cleanup of BRAC bases is recorded as a BRAC cost, DOD asserts that many 

of these costs would have been incurred anyway had the closing bases 

remained open. In this regard, it could be argued that the net costs 

incurred by DOD are overstated and that net savings would thus be 

increased.



BRAC Savings Estimates Are Not Updated Periodically:



The results of our prior and current work show that the military 

services have not updated their savings estimates periodically, thereby 

contributing to imprecision in overall BRAC estimated net savings 

figures. Because closure or realignment actions may vary from the 

original plans, it is important for the services to review and update 

these estimates periodically to increase their accuracy. Moreover, DOD 

guidance to the services emphasizes the importance of frequent updates 

and directs them to update estimates in their annual budget 

submissions.



Since our last review in 1998 of the services’ efforts to update their 

estimates, the Army has increased the frequency and scope of its 

updates. As discussed previously, it updated savings estimates for 24 

BRAC actions in its fiscal year 2000 budget request and an additional 6 

in its fiscal year 2001 budget request. The Navy, on the other hand, 

has revised the savings estimate for only one of its BRAC actions since 

1998. Consistent with our previous reporting in 1998, Army and Navy 

officials told us they revise estimates only when there are substantive 

changes to BRAC decisions that warrant such revisions. While the Air 

Force does not routinely revise its savings estimates from the initial 

estimates established by the various BRAC commissions in rendering 

their decisions, it did, however, update its estimates for McClellan 

Air Force Base, California, and Kelly Air Force Base, Texas, in its 

fiscal year 2000 and 2001 budget requests.[Footnote 18]



Service officials have cited a number of reasons for not routinely 

updating savings estimates from BRAC closures and realignment. They 

acknowledged that updating savings has not been a high priority and 

that, instead, the emphasis in preparing the annual budget lies in 

estimating costs--not savings. They told us that updating savings 

estimates is a labor-intensive process and could be costly because no 

systematic approach exists for the process. A fundamental limitation in 

DOD’s ability to identify and track savings from BRAC closures and 

realignments is DOD’s accounting systems, which like other accounting 

systems, are not oriented toward identifying and tracking 

savings.[Footnote 19] The services develop savings estimates when they 

create their initial BRAC implementation budgets and report them in 

DOD’s BRAC budget justifications. Because the accounting systems do not 

track savings, however, updating these estimates would require a 

separate tracking method or system.



In those instances in which the services did update savings estimates, 

the process for updating estimates varied among them, and they were 

unable to provide us with adequate documentation to permit us to 

independently validate the basis for the revised estimates. Army 

officials told us that their major commands provided estimate revisions 

during their funding request briefings with the Army Budget Office. 

Similarly, Navy commands submitted revised estimates to the Naval 

Engineering Facilities Command when a significant change was warranted. 

The Air Force, on the other hand, did not require its commands to 

submit updated estimates--instead, it formed a special team to arrive 

at savings estimates for the McClellan Air Force Base and Kelly Air 

Force Base submissions.



BRAC Costs Are Not Comprehensive:



BRAC costs are not comprehensive because they do not include certain 

costs related to BRAC activities that are incurred either by DOD or by 

other governmental agencies. However, while their inclusion would 

reduce BRAC overall net savings, their impact would be marginal.



First, DOD’s calculation of one-time estimated net savings do not 

include BRAC-related economic assistance costs, most of which are 

incurred by federal agencies other than DOD. As of September 30, 2001, 

federal agencies had reported expenditures of about $1.5 billion (an 

increase from the $1.1 billion in our 1998 report) to assist BRAC-

affected communities and individuals for such purposes as base reuse 

planning, airport planning, job training, infrastructure improvements, 

and community economic development.



* About $568 million was provided by the Department of Commerce’s 

Economic Development Administration to assist communities with 

infrastructure improvements, building demolition, and revolving fund 

loans.



* About $405 million was provided by the Federal Aviation 

Administration to assist with converting former military airfields to 

civilian use.



* About $218 million was provided by the Department of Labor to help 

communities retrain workers who have lost their jobs because of 

closures.



* About $270 million was provided by DOD’s Office of Economic 

Adjustment to help communities plan and implement the reuse of BRAC 

bases.



Second, DOD’s calculation of estimated annual net recurring savings 

beyond 2001 does not include expected environmental costs of about $3.5 

billion. Because these costs would be spread over many years, however, 

they would provide only a marginal reduction in the annual recurring 

savings estimates.



Savings May Be Greater Than Estimated:



DOD’s difficulty in providing precise estimates is further complicated 

by the fact that certain actions it undertakes in the BRAC process 

could produce other savings that are not captured in its net savings 

estimates. For example, the inclusion of BRAC environmental cleanup 

costs in calculating net savings has the effect of overstating costs 

(and understating net savings for DOD) if one considers that DOD has 

reported previously that it would have incurred many of these costs 

even if the BRAC bases had remained active facilities.[Footnote 20] DOD 

acknowledges, however, that environmental costs under the BRAC process 

may have been accelerated in the short term, and may have been more 

costly because of more stringent regulatory requirements. However, the 

marginal difference is not easily quantified. A similar case can be 

made for military construction activities. DOD has expended significant 

funds (an estimated $6.6 billion through fiscal year 2001) on military 

construction at receiving bases under the BRAC process. Although they 

are difficult to quantify, over time DOD would have likely incurred 

these and other costs under its facilities capital improvement 

initiatives if the closing bases would have remained open.



Transfer of Unneeded BRAC Property Is Only Partially Completed:



As a result of the BRAC process, DOD designated about 518,500 acres of 

property at BRAC-affected installations as unneeded.[Footnote 21] 

Forty-six percent of the acreage has been scheduled to go to federal 

entities, and most of the remainder will go to nonfederal entities; the 

disposition of less than 1 percent of the property has not yet been 

decided. However, as of September 30, 2001, less than half of the 

unneeded property--42 percent--had been transferred to these entities, 

and according to plans, it will take many years for DOD to transfer all 

of its unneeded property.[Footnote 22] Nearly half of the 236,400 acres 

designated for federal use has been transferred while about one-third 

of the 279,900 acres intended for nonfederal use, such as local 

authorities or private entities, has been conveyed; and the disposition 

of less than 1 percent (2,200 acres) has not yet been decided. While 

delays in property transfer are due to many factors, the primary one in 

most instances has been related to environmental cleanup. In the 

interim, DOD is using several techniques, such as leasing, to get 

property into the hands of users more quickly for further reuse while 

awaiting the transfer of property titles.



Designation of Unneeded BRAC Property Is Nearly Finished:



DOD has made considerable progress in completing the designation of 

unneeded BRAC property for federal or nonfederal use. As of September 

30, 2001, DOD had about 2,200 acres, or less than 1 percent of the 

total unneeded BRAC property, left to designate. This was a reduction 

from the 98,000 acres (21 percent of the total unneeded property) that 

we reported in 1998.



According to DOD documentation, about 46 percent, or 236,400 acres, of 

the total unneeded BRAC property is slated to go to federal entities, 

including other services within DOD. (See fig. 3.) About 54 percent, or 

279,900 acres, is designated to go to nonfederal entities.



Figure 3: Planned Disposition of Unneeded Property:



[See PDF for image]



[End of figure]



Source: Our analysis of DOD’s data.



As shown in figure 4, most of the property (81 percent, or 191,700 

acres) remaining within the federal government is to be transferred to 

the Department of the Interior’s U.S. Fish and Wildlife Service and 

Interior’s Bureau of Land Management. About 16 percent (37,300 acres) 

will go to other federal recipients, including the Bureau of Indian 

Affairs, and the Bureau of Prisons. DOD is also retaining some of the 

property (7,500 acres) for use by other services and DOD 

agencies.[Footnote 23]



Figure 4: Planned Transfers to Federal Agencies:



[See PDF for image]



[End of figure]



Source: Our analysis of DOD’s data.



DOD can dispose of BRAC property to nonfederal entities through public 

benefit transfers (for such purposes as airports, education, parks and 

recreation, and homeless assistance), economic development 

conveyances, and market (advertized) or negotiated sales. Depending on 

the transfer method used, DOD may or may not receive consideration for 

the property. For example, property transferred for a public benefit 

can typically be at no cost or a discounted cost. With the enactment of 

the National Defense Authorization Act for Fiscal Year 2000, all BRAC-

affected communities became eligible to receive property at no cost for 

economic development. However, with the enactment of the National 

Defense Authorization Act for Fiscal Year 2002, DOD is to seek fair 

market value for property transferred from bases recommended for 

closure or realignment in the BRAC 2005 round. The act also authorizes 

property transfers without consideration if circumstances warrant.



As of September 30, 2001, economic development conveyances were the 

most common method used to transfer property to nonfederal entities. 

(See fig. 5.) They accounted for about 114,900 acres (41 percent) of 

the acres slated for nonfederal use. Public benefit transfers accounted 

for 73,100 acres (26 percent), and market/negotiated sales accounted 

for 9,700 acres (3 percent).



Figure 5: Planned Transfers to Nonfederal Entities:



[See PDF for image]



[End of figure]



Note: Numbers may not add because of rounding. Other conveyances 

include reversions to state or local government entities and 

legislation mandating specific unneeded property disposition.



Source: Our analysis of DOD’s data.



Transfer of Unneeded BRAC Property Is Less Than Half Completed:



Although DOD has plans to transfer nearly all of its unneeded BRAC 

property, as of September 30, 2001, it had actually transferred less 

than half of the 518,500 acres designated for federal or nonfederal 

reuse. As shown in table 2, about 42 percent, or 219,600 acres, of the 

planned property transfers have been completed.[Footnote 24]



Table 2: Actual Transfers of Unneeded BRAC Property, as of September 

30, 2001:



Planned; Acres to 

federal entities: 236,400; Acres to 

nonfederal entities: 279,900; Undetermined: 2,200; Total: 518,500.



Transferred; Acres to 

federal entities: 114,300; Acres to 

nonfederal entities: 105,300; Undetermined: [Empty]; Total: 219,600.



Percent of planned; Acres to 

federal entities: 48; Acres to 

nonfederal entities: 38; Undetermined: [Empty]; Total: 42.



Not transferred; Acres to 

federal entities: 122,100; Acres to 

nonfederal entities: 174,600; Undetermined: 2,200; Total: 298,900.



Source: Our analysis of DOD’s data.



[End of table]



While the amount transferred is a significant improvement over the 14-

percent transfer figure that we reported in our December 1998 report, 

DOD still has 298,900 acres of unneeded property left to transfer. Of 

this amount, nearly 60 percent, or 174,600 acres, is slated to go to 

nonfederal entities. Most of the untransferred property comes from the 

last closure round in 1995, although about 33 percent, or 98,700 acres, 

stems from the earlier BRAC rounds.



The military services expect to complete the transfer of most of the 

remaining unneeded acreage by 2007. The Air Force’s property transfer 

schedule showed that transfers to federal entities and most nonfederal 

entities would be completed by 2005 and 2006, respectively. However, 

one parcel at McClellan Air Force Base, California, is not slated for 

transfer until 2016 because of significant unanticipated environmental 

cleanup issues. The Navy’s property transfer schedule indicated that 

transfers to federal entities and nonfederal entities would be finished 

by 2007. The Army’s property transfer schedule showed that many 

property transfers would be completed by 2006; however, transfers 

beyond 2007 were anticipated at Fort McClellan, Alabama; Fort Meade, 

Maryland; Fort Wingate, New Mexico; and the Sierra Army Depot, 

California. Furthermore, the Army has not established expected transfer 

dates for property on a few bases where unexploded ordnance is a 

cleanup issue. These properties include Camp Bonneville, Washington; 

Fort McClellan, Alabama; Fort Ord, California; and the Savanna Army 

Depot, Illinois.



Most Property Transfer Delays Are Due to Environmental Cleanup Issues:



Our analysis of former bases with untransferred acreage and our 

discussions with military service officials show that, while there are 

several reasons for delays in transferring property to other users, 

including other federal entities, environmental cleanup-related issues 

are predominant. Environmental cleanup has been a long-standing concern 

in the BRAC program--one that has been not only costly and challenging 

for DOD but also frustrating for intended users of the property. While 

DOD has already spent an estimated $7 billion through fiscal year 2001 

on BRAC environmental-related actions, DOD expects to spend an 

additional $3.5 billion beyond 2001 to complete its cleanup work.



Environmental Cleanup Is Impeding Property Transfer:



In analyzing impediments to property transfers, we looked at all 51 

BRAC bases with 500 or more acres of property that as of September 30, 

2001, had yet to be transferred to another military service, a federal 

agency, or a nonfederal entity. These bases had a total of 291,447 

untransferred acres, representing almost 98 percent of the 

untransferred BRAC acreage. Service officials cited environmental 

cleanup concerns--an issue at 40 of the 51 bases--as the primary reason 

for property transfer delays. Because base property is normally 

subdivided into various parcels for transfer and reuse purposes, a base 

may have several reasons for property delays. At 27 of the 51 bases, 

environmental cleanup was ongoing on some parcels while 9 bases were 

awaiting regulatory approval for transfer on other parcels. Officials 

at 10 bases cited difficulties in either establishing the extent of 

cleanup required for transfer or deciding on the ultimate reuse of the 

property. On a more limited scale, at six Army bases, delays stemmed 

from the difficult challenge, in terms of both time and money, of 

cleaning up unexploded ordnance. Service officials also cited that 

reaching agreement with other federal agencies in the transfer of 

property has been a difficult and tedious process.



Environmental Cleanup Costs Continue beyond 2001:



As of September 30, 2001, DOD had spent an estimated $7 billion on 

actions related to BRAC environmental cleanup, and it estimates it will 

spend about $3.5 billion beyond 2001 to complete the cleanups. As shown 

in figure 6, the Air Force is expected to bear the largest burden of 

future costs.



Figure 6: DOD’s Estimated Environmental Cleanup Cost at Base Closure 

Sites After Fiscal Year 2001, as of September 30, 2001:



[See PDF for image]



[End of figure]



Dollars in millions:



Source: Our analysis of DOD’s data.



DOD’s current cost estimate of $3.5 billion to complete the cleanup 

after 2001 is $1.1 billion higher than reported in fiscal year 1999. 

Service officials attribute the growth to several factors, including 

delays in planned environmental cleanup schedules, increased costs as 

requirements have become more refined, and more stringent cleanup 

standards at bases where reuse plans have changed. While post-2001 

costs are expected to rise, the total estimated BRAC environmental 

cleanup cost, which is now set at about $10.5 billion, has remained 

relatively stable over time. In 1996, for example, the total 

environmental costs were projected at about $11.3 billion and about 

$9.6 billion in 1998.



The out-year estimates, however, are still subject to change because 

the extent of the remaining cleanup required at some bases is 

uncertain. In particular, the cost of cleaning up unexploded ordnance 

at several former bases has been and continues to be difficult to 

estimate.[Footnote 25] For example, at former Fort Ord, California, the 

estimated $306 million needed to complete unexploded ordnance cleanup 

is likely to change because the location and concentration of all 

unexploded ordnance is still being investigated. A similar situation 

exists at Camp Bonneville, Washington, where, according to Army 

officials, the current $73 million cost estimate is likely too high, 

depending on the extent of cleanup agreed upon by environmental 

regulators and the Army. Aside from unexploded ordnance, the discovery 

of other hazardous materials can dramatically change cleanup cost 

estimates. For example, at McClellan Air Force Base, California, the 

more than $600 million estimate is likely to rise because recent 

cleanup actions have uncovered about 100 buried and forgotten drums of 

materials, some of which contained plutonium waste. According to Air 

Force officials, it is too early to tell how many more drums will be 

unearthed and what cleanup actions will be required in those areas 

where they are found. However, one estimate states that another 1,000 

barrels may be buried. Under the Air Force’s worst-case scenario, the 

remaining environmental cleanup cost estimate at the base would 

increase to about $1.5 billion.



Considering the magnitude of the expected out-year environmental costs, 

the Congress has recently expressed concern over the cost accuracy and 

amount of funding devoted to DOD’s BRAC environmental cleanup efforts. 

The Military Construction Appropriations Act of 2002, contained a 

general provision that directed DOD to accurately reflect the cost of 

environmental cleanup activities in its future BRAC budget submissions. 

According to the conference report, this was based on the fact that 

Navy and Air Force budget requests for fiscal year 2002 were far below 

the level needed to meet urgent obligations. As a result of what it 

termed inadequate programming and budgeting decisions by these two 

services, the Congress found it necessary to provide both services with 

additional funding (about $80.5 million for the Navy and $20 million 

for the Air Force) in fiscal year 2002 to complete mandated cleanups. 

Furthermore, the conferees directed the Navy and Air Force to allocate 

all unobligated balances from previous BRAC appropriations to address 

additional cleanup funding shortfalls.



DOD Is Using Several Methods to Expedite Property Reuse or Transfer:



Recognizing delays in the transfer process, DOD has resorted to several 

methods to make unneeded property more readily available to future 

users for reuse purposes. They include leasing; the so-called “early 

transfer authority” which facilitates the deeding of property under a 

transfer authority; and no-cost economic development conveyances. These 

methods have created benefits for both DOD as well as affected users. 

By getting property into the hands of users sooner, DOD is able to 

reduce its expenses (e.g., caretaker costs). At the same time, users 

have the opportunity to put the property to quicker productive reuse 

(e.g., creating jobs and stimulating economic growth).



Long-Term and Interim Leasing Can Expedite Property Reuse:



The military services are using long-term and interim leasing to get 

property into the hands of communities while awaiting final transfer. 

Long-term leases are issued when deeds cannot be obtained immediately-

-usually because of environmental cleanup issues. These leases, 

commonly referred to as “leases in furtherance of conveyance,” are 

usually provided to the expected ultimate transferee after the service 

has issued a final disposal decision for the BRAC property, and they 

can extend for many years. The Air Force, for example, has entered into 

55-year leases at several of its former bases. Interim leases are 

short-term leases that make no commitment to the lessee for future use 

or transfer, and they are usually used in cases where the service has 

not yet made a final disposal decision.



Leasing can provide advantages for both the services and lessees. It 

may allow the military services to reduce their operation and 

maintenance costs for BRAC property before final transfer by allowing 

the lessee to assume more of these responsibilities. It also allows the 

services to keep base utilities and infrastructure operational, thereby 

saving them and the lessee the expense of having to restart these 

services. Community officials stated that lease terms of 25 years or 

greater are advantageous because financial institutions are more 

willing to lend funds to lessees to finance their reuse and 

redevelopment efforts. Leasing also allows lessees to redevelop closed 

bases without assuming the risks of property ownership. As shown in 

table 3, the Air Force has leased more property (in terms of acreage) 

than the Army or the Navy.



Table 3: Leased BRAC Acreage, as of September 30, 2001:



Service: Army; Interim leases: 923; Long-term leases: 5,982; Total: 

6,905.



Service: Navy; Interim leases: 7,727; Long-term leases: 2,883; Total: 

10,610.



Service: Air Force; Interim leases: 1,899; Long-term leases: 29,877; 

Total: 31,776.



Service: Total; Interim leases: 10,549; Long-term leases: 38,742; 

Total: 49,291.



Source: Our analysis of DOD’s data.



[End of table]



Two of the BRAC-affected sites we visited had leases in place while 

awaiting property transfer. At the former Loring Air Force Base, Maine, 

the Air Force in April 1997 negotiated a 55-year lease with the local 

reuse authority for 3,600 acres on the base. Reuse authority officials 

told us that the lease has allowed them to take on several expected 

long-term tenants and generate revenue for further redevelopment and 

reuse. At the same time, the lease also helped the Air Force reduce its 

base operation and maintenance costs. In April 2001, 2,800 of the 3,600 

acres were transferred to the reuse authority, and the Air Force is 

retaining the remaining acreage as environmental cleanup proceeds. At 

the former Charleston Naval Shipyard, South Carolina, the Navy leased 

several properties to the local reuse authority while cleaning up the 

land to meet environmental standards. The reuse authority initially 

offered tenants short-term, 5-year interim leases, but these were 

modified to 30-year terms when it was assured that these tenants would 

become the eventual property owners.



Early Transfer Authority Can Accelerate Property Transfer and Reuse:



Recognizing that environmental cleanup has often delayed the transfer 

of BRAC property, the Congress in 1996 enacted the so-called “early 

transfer authority” provision,[Footnote 26] which allowed property to 

be transferred before all necessary cleanup actions had been completed. 

For DOD to exercise this authority, however, certain conditions must 

exist, including the following:



* The property must be suitable for transfer for the intended use.



* The agency must submit the terms of the transfer for a 30-day public 

written comment period.



* The transfer of the property must not substantially delay any cleanup 

actions.



* The deed must contain necessary restrictions on the use of the 

property to protect human health and the environment, ensure no 

disruption of remedial actions, and provide that all cleanup actions 

will be taken as approved by the appropriate regulatory agency.



* The agreements must have the concurrence of the governor of the state 

where the property is located.



In terms of cost, DOD retains the responsibility for funding the 

environmental cleanup, regardless of whether it is performed by DOD or 

the user.



A primary advantage of using the early transfer authority is that it 

makes property available to the future user as soon as possible, thus 

allowing environmental cleanup and redevelopment activities to proceed 

concurrently. This can save time and cost and provide users with 

greater control over both activities. Furthermore, it provides 

communities with the means to quickly put property into productive use, 

create jobs, and generate tax revenue. The Navy estimates that use of 

the early transfer authority has shortened the time required to 

transfer property by at least 4 months and, in one case, up to 54 

months. According to an Air Force official, early transfers helped to 

transfer property sooner than conventional methods, and in one case 

saved the property recipient over $100,000 in loan interest costs.



While early transfer authority can benefit all parties, it has not yet 

been exercised widely within the BRAC process. According to service 

officials, several factors have worked against its application, such as 

community adversity to taking risks, the absence of ready-to-implement 

reuse plans, the lack of support from state and local regulators, 

changes in intended property reuse, and distrust of DOD. Furthermore, 

exercising the authority may require DOD to commit more funds, in the 

short term, than what is available to meet environmental cleanup 

requirements. It appears that early transfer authority’s use is an 

evolving process; service officials told us that they expect greater 

application as users and other parties become more familiar with its 

potential advantages. Table 4 provides a list of locations where early 

transfer authority has been exercised through fiscal year 2001, 

including those locations where a deeded transfer has been completed.



Table 4: Use and Status of Early Transfer Authority at BRAC Bases 

through Fiscal Year 2001:



Installation: Naval Shipyard,Mare Island, Calif.; Acres: 3,568; Status 

of transfer[A]: Pending.



Installation: Naval Air Station, Memphis, Tenn.; Acres: 1,862; Status 

of transfer[A]: Complete.



Installation: Naval Air Station, Agana, Guam; Acres: 1,799; Status of 

transfer[A]: Complete.



Installation: Tooele Army Depot, Utah; Acres: 1,621; Status of 

transfer[A]: Complete.



Installation: Guam Naval Activities/Public Works Center, Guam; Acres: 

1,507; Status of transfer[A]: Complete.



Installation: Naval Air Station, South Weymouth, Mass.; Acres: 1,452; 

Status of transfer[A]: Pending.



Installation: Fleet Industrial Supply Center, Oakland, Calif.; Acres: 

529; Status of transfer[A]: Complete.



Installation: Grissom Air Force Base, Ind.; Acres: 201; Status of 

transfer[A]: Complete.



Installation: Griffiss Air Force Base, N.Y.; Acres: 179; Status of 

transfer[A]: Complete.



Installation: Mather Air Force Base, Calif.; Acres: 163; Status of 

transfer[A]: Complete.



Installation: Wurtsmith Air Force Base, Mich.; Acres: 149; Status of 

transfer[A]: Complete.



Installation: Fleet Industrial Supply Center Annex, Alameda, Calif.; 

Acres: 147; Status of transfer[A]: Complete.



Installation: Naval Air Station, Louisville, Ky.; Acres: 142; Status of 

transfer[A]: Pending.



Installation: Griffiss Air Force Base, N.Y.; Acres: 132; Status of 

transfer[A]: Pending.



Installation: Naval Training Center, San Diego, Calif.; Acres: 51; 

Status of transfer[A]: Complete.



Installation: Lowry Air Force Base, Colo.; Acres: 27; Status of 

transfer[A]: Future.



Installation: Fitzsimons Army Medical Center, Colo.; Acres: 17; Status 

of transfer[A]: Pending.



Installation: Lowry Air Force Base, Colo.; Acres: 17; Status of 

transfer[A]: Complete.



[A] “Complete” refers to property that has been transferred to the new 

user; “Pending” refers to property that is in the process of being 

transferred; and “Future” refers to property that is planned for early 

transfer authority.



Source: Our analysis of DOD’s data.



[End of table]



Economic Development Conveyances Can Accelerate Property Transfer and 

Reuse:



DOD also uses economic development conveyances, which are designed to 

create jobs and promote economic activity, to transfer unneeded BRAC 

property to users. In 1993, BRAC legislation was amended to provide 

local redevelopment authorities with BRAC property at or below fair 

market value or without cost to promote the economic recovery of areas 

affected by closures. DOD was required to transfer property for 

economic development to communities in rural areas at no cost. 

Subsequently, the National Defense Authorization Act for Fiscal Year 

2000 included a provision that required all economic development 

conveyances to be no-cost. It also permitted existing economic 

development conveyances to be modified to no-cost agreements if certain 

conditions were met. According to the conference report accompanying 

the act, the purpose of the provision was to support permanent job 

creation. Service and community officials told us that the effect of 

the provision has been to eliminate delays resulting from prolonged 

negotiation over the fair market value of BRAC property and to 

accelerate economic development and job creation. More recently, the 

National Defense Authorization Act for Fiscal Year 2002 stipulates that 

DOD “shall seek to obtain” fair market value for property transferred 

from bases recommended for closure or realignment in the BRAC 2005 

round. It also authorizes property transfers without consideration if 

circumstances warrant. DOD has not yet developed policy guidance for 

implementing these provisions.



As of September 30, 2001, DOD had 61 economic development conveyances 

in place. Of these, 28 were implemented as no-cost agreements following 

enactment of the National Defense Authorization Act for Fiscal Year 

2000, and 9 previously negotiated conveyances were modified to no-cost 

conveyances as allowed in the act. Appendix III provides a listing by 

location of the 61 economic development conveyances in effect.



Although DOD has not quantified the overall impact of no-cost economic 

development conveyances in terms of facilitating faster transfers and 

improving economic activity, the reuse authorities and DOD officials we 

interviewed agreed that their use generally has benefited both parties. 

Negotiations between DOD and reuse authorities over fair market 

property values, which were often highly contentious, have essentially 

been eliminated, thereby accelerating the transfer process in many 

cases. According to officials from several communities we visited, 

funds raised to pay DOD for BRAC properties could now be used to invest 

in reuse and redevelopment efforts. And, as DOD officials pointed out, 

DOD has been able, in some cases, to reduce its maintenance costs at 

BRAC bases because of faster transfers.



Most Communities Are Continuing to Recover from the Economic Impact of 

BRAC:



While some communities surrounding closed bases are faring better than 

others, our analyses of key economic indicators and visits to select 

communities show that most are continuing to recover over time from the 

initial economic impact of base closures. Overcoming the negative 

economic impact of base closures or realignments on local communities, 

including the loss of perhaps thousands of jobs, has long been a 

concern for their citizens, as well as members of Congress. Despite the 

difficulties of transition, local community officials attributed their 

recovery to a number of factors, including a strong national economy, 

diversified local economies, and the redevelopment of former base 

property, all of which play key roles in unemployment rates and income 

levels. According to recent economic data, a majority had unemployment 

rates for the 9-month period ending September 30, 2001, that were lower 

than the national average and had annual per capita income growth rates 

that exceeded the national average during 1996 through 1999. 

Furthermore, a majority of the communities had lower unemployment and 

higher per capita growth rates than when we last reported these figures 

in December 1998. Our work at six selected base closure sites showed 

that the surrounding communities were recovering from BRAC, although 

the transition had not necessarily been easy.[Footnote 27] Many 

community officials credited the strong economy at the time and 

diversified economic activity in their region as key to their economic 

recovery.



Several Factors Play Key Roles in Community Recovery from BRAC:



Various officials in surrounding communities affected by BRAC cited the 

strong national and local economies as key reasons why their 

communities were able to avoid economic devastation and find new areas 

of economic growth after a closure or realignment of a nearby military 

base. Officials also pointed to government assistance and base 

development, among other factors. (See fig. 7.) Although optimistic 

about the continued economic recovery of their communities, some local 

officials were concerned that the recent downturn in the national 

economy could hinder continued economic recovery.



Figure 7: Factors Affecting Economic Recovery from Base Closures:



[See PDF for image]



[End of figure]



Officials from BRAC communities have stressed the importance of having 

a strong national economy and local industries that could soften the 

impact of job losses from base closures. Since the 1991 recession, and 

until the recent slowdown, the economic performance of the United 

States has been robust. Officials from rural communities surrounding 

Fort McClellan, Alabama, for example, told us that the strong national 

economy during the 1990s helped to mask the worst effects of the base 

closing, but as the economy has slowed in recent months, the area is 

beginning to feel the full effects of the Fort McClellan closure.



Officials also point to diversification of the local and regional 

economy as key factors in easing economic recovery. For example, 

officials from urban communities surrounding the former Charleston 

Naval Shipyard Complex, South Carolina, believe they are better able to 

absorb the job losses from the base closure because their diversified 

economies provide a wider range of job and business opportunities. In a 

January 1998 report, we examined defense-related spending trends in New 

Mexico and the relationship between those trends and New Mexico’s 

economy. [Footnote 28] We reported that, although defense-related 

spending had declined in the state, the state’s gross product and total 

per capita income had increased and that this economic growth might be 

due to efforts to diversify the economy to counter the loss of defense 

jobs.



Officials also pointed to other economic forces at work in their region 

during the closure period that affected recovery efforts. For example, 

according to officials from communities surrounding Loring Air Force 

Base, Maine, a potato blight in the early 1990s adversely affected the 

potato-related industry--a significant revenue producer for the county 

and the state--and, in turn, slowed down the regional economy. Another 

event that adversely affected the regional economy was the enactment in 

the early 1990s of a Canadian law that allowed the Province of New 

Brunswick to apply a provincial sales tax on goods entering Canada from 

Maine. These fees forced many Canadian shoppers to remain at home 

rather than cross the border into Maine to shop, thereby ending most 

Canadian commerce in Aroostook County, where the former Loring Air 

Force Base was located.



An area’s natural and labor resources also can help economic recovery. 

The rural areas we visited, where agriculture has historically 

dominated the economy, have benefited from their efforts to diversify. 

For example, Beeville, Texas (Chase Naval Air Station), and Merced 

County, California (Castle Air Force Base), where farming or ranching 

have long prevailed, have been recently aided by an expanding prison 

industry. In Blytheville, Arkansas, where Eaker Air Force Base closed, 

the growing steel industry, which was attracted to the area in late 

1980s, in part because of its access to the Mississippi River, has 

benefited the community. While the extent of economic recovery varies 

in each of these communities, economic diversity has provided a broader 

basis for long-term growth.



Leadership and teamwork among participants at the federal, state, and 

local levels are essential to reaching agreement on key issues, such as 

property transfer, base reuse, and environmental cleanup, all of which 

can promote economic recovery. The lack of agreement can prolong the 

cleanup and transfer of property. In Charleston, South Carolina, reuse 

authority officials told us that state officials have been very 

supportive of their redevelopment efforts, both in terms of financial 

assistance and other efforts.



Publicizing base redevelopment efforts and goals within the community 

and outside the community is a key strategy for attracting industry and 

helping communities gain confidence in recovering from the closure. For 

example, Charleston Naval Complex Redevelopment Authority’s recent 

marketing efforts helped it to enter into an agreement with a British 

firm specializing in the packaging and shipping of machine and 

engineering products to move its world headquarters to the former base. 

Charleston officials also said that the positive efforts of the 

surrounding community governments to work together to recover from the 

shipyard closure helped the community to regain confidence quickly.



To help communities successfully transform closed bases into 

opportunities, federal agencies have provided areas affected by closed 

or realigned bases with about $1.5 billion since 1988 in direct 

financial assistance. This assistance has come in several forms, 

including planning grants to help develop the property, training grants 

to provide new skills for the workforce, and grants for base 

infrastructure improvements. A 1997 study requested by the Department 

of Commerce’s Economic Development Administration and prepared by a 

Rutgers University research team concluded that federal financial 

assistance succeeded in aiding job creation and economic recovery from 

base closures and defense downsizing.[Footnote 29]



The redevelopment of base property is widely viewed as an important 

component of economic recovery for BRAC-affected communities. While not 

the only determinant of economic recovery for surrounding communities, 

it can, nevertheless, be an important catalyst for recovery efforts. 

Base closures make buildings and land available for new uses, which can 

generate new economic activity and new jobs. DOD data show that, as of 

October 2001, over 79,000 jobs, or about 62 percent of the nearly 

130,000 jobs lost at major base closures from the prior rounds, had 

been replaced--an increase from the 36 percent recovery rate reported 

in 1998. (See app. IV for further details on jobs lost and created at 

major BRAC bases.) Closed bases can have various impacts on the 

recovery process. For example, DOD data show that when the Charleston 

Naval Shipyard Complex closed in 1996, more than 6,000 civilian 

positions were lost. Charleston redevelopment officials told us that 

since 1996 they have attracted some 80 tenants and more than 4,200 new 

jobs to the former base. Further, for the 1996-2000 period, overall 

employment in the Charleston metro area has risen by about 20 percent, 

or over 45,000 jobs. However, a closed base can also hinder economic 

recovery. At Fort Ord, California, for example, officials stated that 

the poor condition of the base’s infrastructure has slowed the economic 

redevelopment of the base. They estimate that area communities will 

have to spend $500 million to demolish unusable buildings and replace 

the base infrastructure to support tenants.



Most BRAC-Affected Communities’ Economic Indicators Compare Favorably 

with National Averages:



Selected economic indicators for BRAC-affected communities in the 

United States compared favorably with national averages. We used 

unemployment rates and real per capita income growth rates as broad 

indicators of the economic health of those communities where base 

closures occurred.[Footnote 30] We identified 62 communities involving 

88 base closures in which government and contractor civilian job loss 

was estimated to be 300 or more.[Footnote 31]



Unemployment Rates Compare Favorably with National Average:



Our analysis of annual unemployment rates for the 9-month period ending 

September 30, 2001, indicates that the rates for most of the 62 BRAC-

affected communities compare favorably with the national average. (See 

fig. 8.) During this period, 44 (71 percent) of the 62 communities 

affected by base closures had unemployment rates below the average 9-

month national rate of 4.58 percent. For all BRAC-affected communities 

with a higher-than-average calendar year 2001 unemployment rates 

through September 2001, only three--Merced County, California (Castle 

Air Force Base); Mississippi County, Arkansas (Eaker Air Force Base); 

and Iosco County, Michigan (Wurtsmith Air Force Base)--had double-digit 

rates of 13.7 percent, 13 percent, and 10.2 percent, respectively. 

Appendix V provides additional detail on the average unemployment rates 

for the 62 communities.



Figure 8: Average Unemployment Rates of 62 BRAC-Affected Communities 

Compared with Average U.S. Rate for January-September 2001:



[See PDF for image]



[End of figure]



Note: Each of these 62 communities, from all four BRAC rounds, lost an 

estimated 300 or more government and contractor civilian jobs.



Source: Our analysis of the Department of Labor’s data.



The unemployment situation for most of the 62 communities affected by 

BRAC closures has improved since we last reported on them in 1998. We 

found that 41 of the 62 communities (66 percent) had lower unemployment 

rates for the first 9 months of 2001 than they had for the same 9-month 

period in calendar year 1997. About 26 percent (16 communities) had 

higher unemployment rates, and for the remaining communities (5 

communities, or about 8 percent), the rates were the same.



Growth Rates of Average Annual Real per Capita Income Compare Favorably 

with National Average:



As with unemployment rates, annual real per capita income growth rates 

for BRAC-affected communities compared favorably with national 

averages. From 1996 through 1999, 53 percent, or 33, of the 62 areas 

had an estimated average real per capita income growth rate that was at 

or above the average of 3.03 percent for the nation.[Footnote 32] Seven 

communities (11 percent) had average annual per capita growth rates 

that were in close proximity to the national average, while the 

remaining 22 communities (35 percent) were below the national average 

growth rate. (See fig. 9.) Appendix VI provides additional detail on 

the average annual real per capita income growth rates for the 62 

communities.



Figure 9: Calendar Years 1996-99 Average Annual per Capita Income 

Growth Rates of BRAC-Affected Areas Compared with U.S. Average:



[See PDF for image]



[End of figure]



Note: Each of these 62 communities, from all four BRAC rounds, lost an 

estimated 300 or more government and contractor civilian jobs.



Source: Our analysis of the Department of Labor’s data.



Most of the communities affected by BRAC closures had higher per capita 

income growth rates than they were when we last reported on them in 

1998. In 1998, we reported on the growth rates from 1991 through 1995 

of average annual real per capita income for 49 communities affected by 

the 1988, 1991, and 1993 BRAC rounds.[Footnote 33] Our 2001 analysis of 

the growth rates for these same communities shows that for 42 of the 49 

communities (86 percent), the rate increased; for 6 communities (12 

percent), it decreased; and for 1 community (2 percent), it remained 

the same.



In general, the six communities we visited had experienced an initial 

economic disruption, followed by recovery after base closure. During 

revisits to communities surrounding two closed bases that we had 

studied in 1998, we found that these communities were recovering but 

were still having some problems. Less tangible, but harder to correct, 

were the social losses--such as the cultural diversity of military 

personnel and their families--that resulted from the departure of base 

personnel. Through our visits to all six communities, we learned about 

each community’s unique process of drawing on local and regional 

strengths to adjust to job losses associated with base closures. 

Additional details about the sites we visited during this review are 

found in appendix VII.



Conclusions:



With the closure and realignment actions from the prior closure rounds 

now complete, questions remain about the extent of savings generated by 

the BRAC process. Although we believe that net savings from the four 

closure rounds are substantial, we recognize that they are based on 

cost and savings estimates that are imprecise and that the military 

services have not updated these projections on a regular basis. The 

periodic updating of cost and savings estimates is not only a good 

financial management practice but also one that strengthens DOD’s 

budgeting process by helping to ensure that correct assumptions are 

made about expected reductions in base operating costs. We recognize 

that accounting systems are more oriented to tracking expenditures than 

savings and that practical limitations may exist in fully accounting 

for all changes in savings estimates over time. At the same time, it is 

important for the services to have some means for periodically, 

systematically, and consistently updating their savings estimates where 

closure and realignment actions vary over time from original plans. 

Without a sound process in place to improve the accuracy of the 

estimates, the process becomes subject to criticism and the subsequent 

erosion of credibility.



While DOD continues the lengthy process of transferring unneeded 

property from former military bases to other users and as communities 

continue recovering, DOD still has more than half of its unneeded 

property left to transfer. As property remains in its inventory, DOD 

continues to incur property-maintenance-related costs, and future users 

are not afforded the full opportunity to redevelop and reuse former 

base properties. By using early transfer authority, the department has 

the potential not only to accelerate the transfer process and benefit 

future users, but also to save money in many cases. Yet, the authority 

has not been widely used since it became available in 1996.



Recommendations for Executive Action:



As part of the new base realignment and closure round scheduled for 

2005, we recommend that the under secretary of defense for acquisition, 

technology, and logistics, in consultation with the under secretary of 

defense (comptroller and chief financial officer), develop (1) a 

Defense-wide systematic approach for the periodic updating of initial 

closure savings estimates and (2) an oversight mechanism to ensure that 

the military services and components update such estimates in 

accordance with the prescribed approach.



We also recommend that the secretary of defense encourage the 

secretaries of the military services to work with communities impacted 

by the base closure process to expand the use of the early transfer 

authority in those cases where the department can accelerate the 

transfer of unneeded former base property and/or save money.



Agency Comments:



In commenting on a draft of this report, the deputy under secretary of 

defense (installations & environment) concurred with the 

recommendations. His comments are included in this report as appendix 

IX.



We are sending copies of this report to the appropriate congressional 

committees; the secretaries of defense, the army, the navy, and the air 

force; the directors of the Defense Logistics Agency and the Defense 

Information Systems Agency; and the director, Office of Management and 

Budget. We will also make it available at www.gao.gov and to others 

upon request.



Please contact me on (202) 512-8412 if you or your staff have any 

questions concerning this report. Key reports related to base closure 

implementation issues are listed in appendix VIII. Additional contacts 

and staff acknowledgments are provided in appendix X.



Sincerely yours,



Barry W. Holman, Director

Defense Capabilities and Management



[Signed by Barry W. Holman



[End of section]



Appendix I: Scope and Methodology:



To determine the magnitude of the savings from the four base 

realignment and closure (BRAC) rounds, we reviewed the Department of 

Defense’s (DOD) annual BRAC budget submissions for the four closure 

rounds and interviewed BRAC and financial officials from the military 

services and the Office of the Secretary of Defense. To ascertain the 

extent to which cost and savings estimates have changed over time, we 

compared the data contained in DOD’s fiscal year 2002 BRAC budget 

submission and related documentation with similar data in DOD’s fiscal 

year 1999 submission, which was the latest budget document available 

when we produced our last comprehensive report on BRAC issues in 

December 1998. Through this comparison, we identified where major 

changes had occurred in the various costs and savings categories within 

the BRAC account and sought a rationale for the changes.



To gain a sense of the accuracy of the cost and savings estimates, we 

relied primarily on our prior BRAC reports and reviewed Congressional 

Budget Office, DOD, DOD’s Office of Inspector General, and the service 

agencies’ audit reports. We also reviewed the annual military service 

budget submissions for fiscal years 2000 through 2002 to determine how 

frequently changes were made to the cost and savings estimates. Where 

revisions were made, we sought out the rationale the services used in 

making the revisions. We examined available documentation in an effort 

to independently verify the adequacy of the basis for the revisions. 

Where documentation was unavailable, we interviewed service officials 

to obtain their justifications for the changes. In assessing the 

completeness of the cost and savings data, we reviewed the component 

elements considered by DOD in formulating overall BRAC costs and 

savings estimates. Because DOD did not include in its estimates federal 

expenditures to provide economic assistance for communities and 

individuals affected by BRAC, we collected these data from the 

Department of Labor; Federal Aviation Administration; Economic 

Development Administration, Department of Commerce; and DOD’s Office of 

Economic Adjustment. We further reviewed the cost estimates for 

environmental cleanup activities beyond fiscal year 2001 because they 

have the effect of reducing the expected annual recurring savings for 

the four rounds.



To determine the progress made by DOD in transferring unneeded base 

property to other users, we reviewed BRAC property disposition plans 

and actual property transfers as of September 30, 2001, and compared 

them with similar data presented in our December 1998 report. To assure 

that we were using the most reliable data available, we validated, on a 

limited basis, the data contained in various databases and reconciled 

discrepancies when they arose. We also categorized the property 

disposition data into the various transfer methods (e.g., economic 

development conveyances) used for property transfers to gain a sense of 

the predominant method being used. With regard to the untransferred 

acreage, we sought to determine the primary impediments to property 

transfer by examining 51 former bases with a combined untransferred 

acreage of about 291,447 acres as of September 30, 2001, or about 98 

percent of the total untransferred BRAC property. We also collected 

data and obtained the military services’ views on the use of the so-

called “early transfer authority” in which property can be transferred 

under certain conditions before an environmental cleanup remedy is in 

place. Furthermore, we collected data on the use of no-cost economic 

development conveyances to transfer property and stimulate its reuse. 

Finally, because leasing is used as an interim measure to make property 

available to users while awaiting property transfer, we also collected 

data related to leased property.



To assess the economic recovery of communities affected by the BRAC 

process, we first performed a broad-based economic assessment of 

communities where more than 300 civilian jobs were eliminated during 

the prior closure rounds.[Footnote 34] In performing our assessment, we 

used unemployment and real per capita income growth rates as measures 

to analyze changes in the economic condition of communities over time 

and in relation to national averages. We chose to use unemployment and 

real per capita income as key performance indicators because (1) DOD 

used these measures in its community economic impact analysis during 

the BRAC location selection process and (2) these measures are commonly 

used by economists in assessing the economic health of an area over 

time. While our assessment does provide an overall picture of how these 

communities compare with the national averages, it does not necessarily 

isolate the condition, or the changes in that condition, that may be 

attributed to a BRAC action. In this regard, we also visited the 

surrounding communities affected by six major closures to (1) enhance 

our understanding of the relationship between base closures and local 

communities and (2) provide a close-up picture of how base closure 

affected these communities. Those visits included the former military 

bases at Castle Air Force Base, California; Fort Ord, California; 

Charleston Naval Shipyard, South Carolina; Chase Naval Air Station, 

Texas; Fort McClellan Army Base, Alabama; and Loring Air Force Base, 

Maine. These visits gave us a mix of Army, Navy, and Air Force sites 

across various BRAC rounds; two of the areas we visited--Castle Air 

Force Base and Chase Naval Air Station--were areas that we visited 

during our 1998 review. These repeat visits were designed to gain a 

sense of the progress being made, since our last visits, by the 

communities surrounding these former bases.



We performed our review from March 2001 through February 2002 in 

accordance with generally accepted government auditing standards.



[End of section]



Appendix II: Revisions to BRAC Cost and Savings Estimates:



As shown in table 5, DOD has increased its net savings estimate through 

2001 for the prior four BRAC rounds from about $14.2 billion in fiscal 

year 1999 to about $16.7 billion in fiscal year 2002--a $2.5 billion 

increase. The increase in net savings is due to a combination of lower-

than-expected BRAC implementation costs through the 2001 time frame and 

an increase in the estimated savings accruing during that same time 

period. Net savings estimates are calculated by deducting expected 

costs from expected savings generated from the BRAC process.



Table 5: Cumulative Cost and Savings Estimates through Fiscal Year 2001 

for the Prior Four BRAC Rounds as Reflected in DOD’s Budget Requests 

and Documentation for Fiscal Years 1999 and 2002:



Dollars in millions.



Costs through fiscal year 2001; Fiscal year 1999 

budget request and 

supporting documentation: [Empty]; Fiscal year 2002 

budget request and 

supporting documentation: [Empty]; Total change: [Empty].



Military construction; Fiscal year 1999 

budget request and 

supporting documentation: $6,566; Fiscal year 2002 

budget request and 

supporting documentation: $6,638; Total change: $72.



Family housing; Fiscal year 1999 

budget request and 

supporting documentation: 93; Fiscal year 2002 

budget request and 

supporting documentation: 92; Total change: (1).



Environmental; Fiscal year 1999 

budget request and 

supporting documentation: 7,337; Fiscal year 2002 

budget request and 

supporting documentation: 6,958; Total change: (379).



Operations and maintenance; Fiscal year 1999 

budget request and 

supporting documentation: 7,984; Fiscal year 2002 

budget request and 

supporting documentation: 7,603; Total change: (381).



Military personnel-permanent change of station; Fiscal year 1999 

budget request and 

supporting documentation: 175; Fiscal year 2002 

budget request and 

supporting documentation: 139; Total change: (35).



Estimated land revenues; Fiscal year 1999 

budget request and 

supporting documentation: (121); Fiscal year 2002 

budget request and 

supporting documentation: (336); Total change: (215).



Other; Fiscal year 1999 

budget request and 

supporting documentation: 847; Fiscal year 2002 

budget request and 

supporting documentation: 877; Total change: 30.



Subtotal costs (through fiscal year 2001); Fiscal year 1999 

budget request and 

supporting documentation: $22,881; Fiscal year 2002 

budget request and 

supporting documentation: $21,972; Total change: (909).



Savings through implementation period; Fiscal year 1999 

budget request and 

supporting documentation: [Empty]; Fiscal year 2002 

budget request and 

supporting documentation: [Empty]; Total change: [Empty].



Military construction; Fiscal year 1999 

budget request and 

supporting documentation: $965; Fiscal year 2002 

budget request and 

supporting documentation: $965; Total change: $0.



Family housing--construction; Fiscal year 1999 

budget request and 

supporting documentation: 177; Fiscal year 2002 

budget request and 

supporting documentation: 177; Total change: 0.



Family housing--operations; Fiscal year 1999 

budget request and 

supporting documentation: 658; Fiscal year 2002 

budget request and 

supporting documentation: 652; Total change: (6).



Operations and maintenance; Fiscal year 1999 

budget request and 

supporting documentation: 10,583; Fiscal year 2002 

budget request and 

supporting documentation: 11,142; Total change: 559.



Military personnel; Fiscal year 1999 

budget request and 

supporting documentation: 5,229; Fiscal year 2002 

budget request and 

supporting documentation: 5,229; Total change: 0.



Other; Fiscal year 1999 

budget request and 

supporting documentation: 4,601; Fiscal year 2002 

budget request and 

supporting documentation: 4,591; Total change: (10).



Subtotal savings (through implementation period); Fiscal year 1999 

budget request and 

supporting documentation: $22,213; Fiscal year 2002 

budget request and 

supporting documentation: $22,756; Total change: $543.



Post-implementation savings (through fiscal year 2001)[A]; Fiscal year 

1999 

budget request and 

supporting documentation: $14,853; Fiscal year 2002 

budget request and 

supporting documentation: $15,924; Total change: $1,071.



Subtotal savings (through fiscal year 2001); Fiscal year 1999 

budget request and 

supporting documentation: $37,066; Fiscal year 2002 

budget request and 

supporting documentation: $38,679; Total change: $1,613.



Net cumulative savings (through fiscal year 2001)[B]; Fiscal year 1999 

budget request and 

supporting documentation: $14,185; Fiscal year 2002 

budget request and 

supporting documentation: $16,707; Total change: $2,522.



Note: Totals may not add because of rounding.



[A] These savings begin the year after the implementation period for 

each BRAC round, are cumulative estimates through fiscal year 2001, and 

are usually based on estimated recurring savings during the last 

implementation year for each round.



[B] Net cumulative savings consist of total savings less total costs 

through fiscal year 2001.



Source: Our analysis of DOD’s budget-related documentation for fiscal 

years 1999 and 2002.



[End of table]



Estimated Costs through Fiscal Year 2001 Have Decreased:



DOD cost estimates through fiscal year 2001 for implementing the four 

BRAC rounds have decreased by about $909 million--from about $22.9 

billion to $22 billion--from fiscal year 1999 to fiscal year 2002. Our 

analysis of the data shows that most of the reported decrease is 

attributed to lower reported operation and maintenance costs (about 

$381 million) and environmental costs--about $379 million--through 

fiscal year 2001. About 50 percent, or $189 million, of the reported 

reduction in costs within the operation and maintenance account is 

attributable to the Air Force, and most of that reduction resulted from 

reported decreased expenses at McClellan Air Force Base, California, 

and Kelly Air Force Base, Texas. Most, or $297 million, of the 

environmental cost reduction is attributable to the Navy. According to 

Navy officials, some of this amount is due to delaying some planned 

environmental cleanup actions to after 2001. It does not imply that 

overall environmental costs have decreased, since DOD has increased its 

post-2001 environmental cost estimate to about $3.5 billion--an 

increase of about $1.1 billion over the $2.4 billion reported in fiscal 

year 1999.



In addition, estimated revenues generated from land sales, property 

leases, and other reimbursements have increased significantly from $121 

million to $336 million from fiscal year 1999 to fiscal year 2002, 

thereby raising the offset to BRAC program cost estimates. According to 

the Air Force, its increased revenues resulted from the reporting of 

nearly $95 million in reimbursements received for fiscal year 1997 from 

the city of Chicago, Illinois, for the cost of moving an Air National 

Guard unit from O’Hare International Airport to Scott Air Force Base, 

Illinois, and from increased proceeds from BRAC land sales and property 

leases. The Army and the Navy reported about $50 million and $25 

million, respectively, in additional BRAC-related revenue from 

reimbursements, land sales, and leases since the fiscal year 1999 

budget request.



Estimated Savings through Fiscal Year 2001 Have Increased:



DOD’s estimate for savings that accrued through fiscal year 2001 for 

the four BRAC rounds have increased by about $1.6 billion to $38.7 

billion from 1999 to 2002. Our analysis shows that $925 million (nearly 

60 percent) of the increase resulted from DOD’s miscalculations in 

recording its savings estimate for the 1991 BRAC round. The $925 

million underreporting of savings was a result of two errors. First, 

the Navy inadvertently omitted some estimated savings (about $183 

million) for fiscal year 1998 from one of its 1991 BRAC round 

subaccounts. Because these savings were recurring, in nature, and were 

also omitted in subsequent years through fiscal year 2001, the error 

was compounded, resulting in an underreporting of $760 million. Second, 

estimated recurring savings for all military services were improperly 

adjusted for inflation for fiscal years 1998 through 2001, resulting in 

an additional $165 million reporting error. When combined, these errors 

constitute the $925 million underreported savings error through fiscal 

year 2001.



In addition, another $381 million (about 24 percent) of the increase 

was attributable to increased savings estimates in the Air Force BRAC 

operation and maintenance subaccount at two of its bases--McClellan Air 

Force Base and Kelly Air Force Base. Prior to fiscal year 2000, Air 

Force officials told us they had not submitted savings estimates for 

these two bases in its budget documentation because of uncertainties in 

the workload status of the depots at these locations. Air Force 

officials told us that they had subsequently prepared this estimate 

after the fiscal year 1999 budget submission. We were unable to 

independently validate the basis for these estimates because the Air 

Force could not provide us with adequate supporting documentation.



[End of section]



Appendix III: DOD’s Use of Economic Development Conveyances:



As of September 30, 2001, DOD had 61 economic development conveyances 

in place. (See table 6.) Prior to April 21, 1999, DOD obtained 

consideration from most communities surrounding a BRAC base for 

property transfers for economic development purposes. As a result, only 

9 of the 33 such transfers issued prior to April 21, 1999, were 

initially no-cost and they were obtained by communities in rural areas. 

The remainder was provided under negotiated terms. Subsequently, the 

National Defense Authorization Act of Fiscal Year 2000 contained a 

provision that allowed for no-cost conveyances for all BRAC communities 

after April 21,1999, and for the modification of previous conveyances 

to no-cost under certain circumstances. As a result, 28 additional 

conveyances have been provided at no cost and an additional 9, 

previously approved prior to April 21, 1999,were later modified to no-

cost in accordance with the terms of the act.



Table 6: DOD’s Use of Economic Development Conveyances:



Period: Before April 21, 1999; Location: [Empty]; Terms of payment: 

[Empty]; Acres: [Empty].



Location: Period: Seneca Army Depot, N.Y.; Terms of payment: Period: 

Negotiated price; Acres: Period: 9,081.



Location: Period: George Air Force Base, Calif.; Terms of payment: 

Period: Negotiated price; Acres: Period: 1,860.



Location: Period: Orlando Naval Training Center, Fla.; Terms of 

payment: Period: Negotiated price; Acres: Period: 1,576.



Location: Period: Mare Island Naval Shipyard, Calif.; Terms of payment: 

Period: Negotiated price; Acres: Period: 1,412.



Location: Period: Glenview Naval Air Station, Ill.; Terms of payment: 

Period: Negotiated price; Acres: Period: 1,029.



Location: Period: Vint Hill Farms, Va.; Terms of payment: Period: 

Negotiated price; Acres: Period: 678.



Location: Period: Fort Benjamin Harrison, Ind.; Terms of payment: 

Period: Negotiated price; Acres: Period: 604.



Location: Period: Lexington-Bluegrass Army Depot, Ky.; Terms of 

payment: Period: Negotiated price; Acres: Period: 570.



Location: Period: Sacramento Army Depot, Calif.; Terms of payment: 

Period: Negotiated price; Acres: Period: 380.



Location: Period: Gentile Air Force Station, Ohio; Terms of payment: 

Period: Negotiated price; Acres: Period: 164.



Location: Period: Detroit Arsenal, Mich.; Terms of payment: Period: 

Negotiated price; Acres: Period: 153.



Location: Period: Newark Air Force Base, Ohio; Terms of payment: 

Period: Negotiated price; Acres: Period: 57.



Location: Period: Long Beach Naval Hospital, Calif.; Terms of payment: 

Period: Negotiated price; Acres: Period: 31.



Location: Period: Army Material Technology Laboratory, Mass.; Terms of 

payment: Period: Negotiated price; Acres: Period: 30.



Location: Period: Long Beach Naval Shipyard, Calif.; Terms of payment: 

Period: Negotiated price; Acres: Period: 30.



Location: Period: Fort Devens, Mass.; Terms of payment: Period: 

Negotiated price[A]; Acres: Period: 3,623.



Location: Period: McClellan Air Force Base, Calif.; Terms of payment: 

Period: Negotiated price[A]; Acres: Period: 3,072.



Location: Period: Kelly Air Force Base, Tex.; Terms of payment: Period: 

Negotiated price[A]; Acres: Period: 2,085.



Location: Period: Philadelphia Naval Shipyard/Station, Pa.; Terms of 

payment: Period: Negotiated price[A]; Acres: Period: 1,181.



Location: Period: Lowry Air Force Base, Colo.; Terms of payment: 

Period: Negotiated price[A]; Acres: Period: 821.



Location: Period: Mather Air Force Base, Calif.; Terms of payment: 

Period: Negotiated price[A]; Acres: Period: 774.



Location: Period: Norton Air Force Base, Colo.; Terms of payment: 

Period: Negotiated price[A]; Acres: Period: 575.



Location: Period: Myrtle Beach Air Force Base, S.C.; Terms of payment: 

Period: Negotiated price[A]; Acres: Period: 429.



Location: Period: Carswell Air Force Base, Tex.; Terms of payment: 

Period: Negotiated price[A]; Acres: Period: 382.



Location: Period: Loring Air Force Base, Maine; Terms of payment: 

Period: Rural no-cost; Acres: Period: 3,861.



Location: Period: Tooele Army Depot, Utah; Terms of payment: Period: 

Rural no-cost; Acres: Period: 1,662.



Location: Period: Eaker Air Force Base, Ark.; Terms of payment: Period: 

Rural no-cost; Acres: Period: 1,447.



Location: Period: Letterkenny Army Depot, Pa.; Terms of payment: 

Period: Rural no-cost; Acres: Period: 1,400.



Location: Period: KI Sawyer Air Force Base II, Mich.; Terms of payment: 

Period: Rural no-cost; Acres: Period: 1,065.



Location: Period: Grissom Air Force Base, Ind.; Terms of payment: 

Period: Rural no-cost; Acres: Period: 828.



Location: Period: Wurtsmith Air Force Base, Mich.; Terms of payment: 

Period: Rural no-cost; Acres: Period: 508.



Location: Period: KI Sawyer Air Force Base I, Mich.; Terms of payment: 

Period: Rural no-cost; Acres: Period: 146.



Location: PeriodAfter April 21, 1999: Presque Isle (Part of Loring), 

Maine; Terms of payment: PeriodAfter April 21, 1999: Rural no-cost; 

Acres: PeriodAfter April 21, 1999: 36.



Period: After April 21, 1999; Location: [Empty]; Terms of payment: 

[Empty]; Acres: [Empty].



Location: Period: Fort McClellan, Ala.; Terms of payment: Period: No-

cost; Acres: Period: 9,378.



Location: Period: Cecil Field Naval Air Station, Fla.; Terms of 

payment: Period: No-cost; Acres: Period: 8,295.



Location: Period: Fort Ord, Calif.; Terms of payment: Period: No-cost; 

Acres: Period: 7,589.



Location: Period: Fort Chaffee, Ark.; Terms of payment: Period: No-

cost; Acres: Period: 5,261.



Location: Period: Reese Air Force Base, Tex.; Terms of payment: Period: 

No-cost; Acres: Period: 2,946.



Location: Period: March Air Force Base, Calif.; Terms of payment: 

Period: No-cost; Acres: Period: 2,849.



Location: Period: Guam Naval Activities/Public Works Center, Guam; 

Terms of payment: Period: No-cost; Acres: Period: 2,725.



Location: Period: Fort Pickett, Va.; Terms of payment: Period: No-cost; 

Acres: Period: 1,675.



Location: Period: Griffiss Air Force Base, N.Y.; Terms of payment: 

Period: No-cost; Acres: Period: 1,649.



Location: Period: Chase Field Naval Air Station, Tex.; Terms of 

payment: Period: No-cost; Acres: Period: 1,570.



Location: Period: Alameda Naval Air Station, Calif.; Terms of payment: 

Period: No-cost; Acres: Period: 1,406.



Location: Period: Charleston Naval Base, S.C.; Terms of payment: 

Period: No-cost; Acres: Period: 1,368.



Location: Period: Memphis Naval Air Station, Tenn.; Terms of payment: 

Period: No-cost; Acres: Period: 1,312.



Location: Period: Ogden Defense Distribution Depot, Utah; Terms of 

payment: Period: No-cost; Acres: Period: 1,003.



Location: Period: Plattsburgh Air Force Base, N.Y.; Terms of payment: 

Period: No-cost; Acres: Period: 929.



Location: Period: Red River Army Depot, Tex.; Terms of payment: Period: 

No-cost; Acres: Period: 765.



Location: Period: Bayonne Military Ocean Terminal, N.J.; Terms of 

payment: Period: No-cost; Acres: Period: 652.



Location: Period: Fitzsimons Army Medical Center, Colo.; Terms of 

payment: Period: No-cost; Acres: Period: 344.



Location: Period: Warminster Naval Air Warfare Center, Pa.; Terms of 

payment: Period: No-cost; Acres: Period: 297.



Location: Period: San Diego Naval Training Center, Calif.; Terms of 

payment: Period: No-cost; Acres: Period: 281.



Location: Period: Agana Naval Air Station, Guam; Terms of payment: 

Period: No-cost; Acres: Period: 248.



Location: Period: Indianapolis Naval Air Warfare Center, Ind.; Terms of 

payment: Period: No-cost; Acres: Period: 163.



Location: Period: Louisville, Naval Ordnance Station, Ky.; Terms of 

payment: Period: No-cost; Acres: Period: 142.



Location: Period: Philadelphia Defense Personnel Support Center, Pa.; 

Terms of payment: Period: No-cost; Acres: Period: 86.



Location: Period: Annapolis Naval Surface Warfare Center, Md.; Terms of 

payment: Period: No-cost; Acres: Period: 44.



Location: Period: New York (Brooklyn) Naval Air Station, N.Y.; Terms of 

payment: Period: No-cost; Acres: Period: 28.



Location: Period: New London Naval Underwater Systems Center, Conn.; 

Terms of payment: Period: No-cost; Acres: Period: 15.



Location: PeriodLocation: Fort Holabird, Md.; Terms of payment: 

PeriodTerms of payment: No-cost; Acres: PeriodAcres: 14.



[A] These nine economic development conveyances were modified to a no-

cost basis as authorized in the provisions of the National Defense 

Authorization Act for Fiscal Year 2000.



Source: Our analysis of DOD’s data.



[End of table]



[End of section]



Appendix IV: Civilian Jobs Lost and Created at Major BRAC Locations 

during the Prior Four BRAC Rounds:



The closure or realignment of military bases creates job losses at 

these facilities, but subsequent redevelopment of the former bases’ 

property provides opportunities for creating new jobs. In 1998, we 

reported that only 36 percent (49,000) of the more than 135,000 jobs 

lost because of BRAC actions had been replaced. The number of jobs lost 

was derived from estimates made during the BRAC decision-making process 

for each round. As of October 31, 2001, DOD reported that 129,649 jobs 

were lost at major BRAC locations, of which about 62 percent (79,740 

jobs), had been replaced at these sites.[Footnote 35] The figures do 

not include jobs lost or created in the areas surrounding the 

realigning or closing bases. Over time, the number of jobs created will 

increase as additional redevelopment occurs. As a result, the recovery 

rate, which provides a rough indicator of how base reuse is 

contributing to the economic recovery of BRAC-affected communities, 

will also rise. The data presented in table 7 do not include the job 

losses that may have occurred elsewhere in a community, nor do they 

capture jobs created from other economic activity in the area.



Table 7: Civilian Jobs Lost and Created at Major Base Realignments and 

Closures during the Prior Four BRAC Rounds, as of October 31, 2001:



Major base: Alameda Naval Air Station and Naval Aviation Depot, Calif.; 

Estimated jobs lost: 3,228; Estimated jobs created: 2,076; Recovery 

(percent): 64.31.



Major base: Army Materials Technology Lab (Watertown), Mass.; Estimated 

jobs lost: 540; Estimated jobs created: 1,061; Recovery (percent): 

196.48.



Major base: Barbers Point Naval Air Station, Hawaii; Estimated jobs 

lost: 618; Estimated jobs created: 28; Recovery (percent): 4.53.



Major base: Bayonne Military Ocean Terminal, N.J.; Estimated jobs lost: 

2,015; Estimated jobs created: 252; Recovery (percent): 12.51.



Major base: Bergstrom Air Force Base, Tex.; Estimated jobs lost: 927; 

Estimated jobs created: 1,984; Recovery (percent): 214.02.



Major base: Carswell Air Force Base, Tex.; Estimated jobs lost: 869; 

Estimated jobs created: 541; Recovery (percent): 62.26.



Major base: Castle Air Force Base, Calif.; Estimated jobs lost: 1,149; 

Estimated jobs created: 2,447; Recovery (percent): 212.97.



Major base: Cecil Field Naval Air Station, Fla.; Estimated jobs lost: 

995; Estimated jobs created: 596; Recovery (percent): 59.90.



Major base: Chanute Air Force Base, Ill.; Estimated jobs lost: 1,035; 

Estimated jobs created: 1,723; Recovery (percent): 166.47.



Major base: Charleston Naval Complex, S.C.; Estimated jobs lost: 6,272; 

Estimated jobs created: 3,339; Recovery (percent): 53.24.



Major base: Chase Field Naval Air Station, Tex.; Estimated jobs lost: 

956; Estimated jobs created: 1,153; Recovery (percent): 120.61.



Major base: Eaker Air Force Base, Ark.; Estimated jobs lost: 777; 

Estimated jobs created: 991; Recovery (percent): 127.54.



Major base: El Toro Marine Corps Air Station, Calif.; Estimated jobs 

lost: 979; Estimated jobs created: 252; Recovery (percent): 25.74.



Major base: England Air Force Base, La.; Estimated jobs lost: 682; 

Estimated jobs created: 1,834; Recovery (percent): 268.91.



Major base: Fitzsimons Army Medical Center, Colo.; Estimated jobs lost: 

1,612; Estimated jobs created: 2,169; Recovery (percent): 134.55.



Major base: Ft. Benjamin Harrison, Ind.; Estimated jobs lost: 1,050; 

Estimated jobs created: 815; Recovery (percent): 77.62.



Major base: Ft. Devens, Mass.; Estimated jobs lost: 2,178; Estimated 

jobs created: 2,288; Recovery (percent): 105.05.



Major base: Ft. McClellan, Ala.; Estimated jobs lost: 2,156; Estimated 

jobs created: 559; Recovery (percent): 25.93.



Major base: Ft. Ord, Calif.; Estimated jobs lost: 2,835; Estimated jobs 

created: 1,135; Recovery (percent): 40.04.



Major base: Ft. Pickett, Va.; Estimated jobs lost: 245; Estimated jobs 

created: 182; Recovery (percent): 74.29.



Major base: Ft. Ritchie, Md.; Estimated jobs lost: 1,373; Estimated 

jobs created: 108; Recovery (percent): 7.87.



Major base: Ft. Sheridan, Ill.; Estimated jobs lost: 1,681; Estimated 

jobs created: 0; Recovery (percent): 0.00.



Major base: Gentile Air Force Station, Ohio; Estimated jobs lost: 

2,804; Estimated jobs created: 1,828; Recovery (percent): 65.19.



Major base: George Air Force Base, Calif.; Estimated jobs lost: 506; 

Estimated jobs created: 1,085; Recovery (percent): 214.43.



Major base: Glenview Naval Air Station, Ill.; Estimated jobs lost: 389; 

Estimated jobs created: 3; Recovery (percent): 0.77.



Major base: Griffiss Air Force Base, N.Y.; Estimated jobs lost: 1,341; 

Estimated jobs created: 1,874; Recovery (percent): 139.75.



Major base: Grissom Air Force Base, Ind.; Estimated jobs lost: 792; 

Estimated jobs created: 735; Recovery (percent): 92.80.



Major base: Guam Naval Complex, Guam; Estimated jobs lost: 2,193; 

Estimated jobs created: 549; Recovery (percent): 25.03.



Major base: Homestead Air Force Base, Fla.; Estimated jobs lost: 136; 

Estimated jobs created: 622; Recovery (percent): 457.35.



Major base: Hunters Point Annex Naval Shipyard, Calif.; Estimated jobs 

lost: 93; Estimated jobs created: 425; Recovery (percent): 456.99.



Major base: Indianapolis Naval Air Warfare Center, Ind.; Estimated jobs 

lost: 2,196; Estimated jobs created: 1,574; Recovery (percent): 71.68.



Major base: Jefferson Proving Ground, Ind.; Estimated jobs lost: 387; 

Estimated jobs created: 122; Recovery (percent): 31.52.



Major base: Kelly Air Force Base, Tex.; Estimated jobs lost: 10,912; 

Estimated jobs created: 4,444; Recovery (percent): 40.73.



Major base: K.I. Sawyer Air Force Base, Mich.; Estimated jobs lost: 

788; Estimated jobs created: 1,045; Recovery (percent): 132.61.



Major base: Letterkenny Army Depot, Pa.; Estimated jobs lost: 2,512; 

Estimated jobs created: 578; Recovery (percent): 23.01.



Major base: Lexington Army Depot, Ky.; Estimated jobs lost: 1,131; 

Estimated jobs created: 838; Recovery (percent): 74.09.



Major base: Long Beach Naval Complex, Calif.; Estimated jobs lost: 

4,487; Estimated jobs created: 200; Recovery (percent): 4.46.



Major base: Loring Air Force Base, Maine; Estimated jobs lost: 1,311; 

Estimated jobs created: 1,010; Recovery (percent): 77.04.



Major base: Louisville Naval Surface Warfare Station, Ky.; Estimated 

jobs lost: 1,435; Estimated jobs created: 1,018; Recovery (percent): 

70.94.



Major base: Lowry Air Force Base, Colo.; Estimated jobs lost: 2,275; 

Estimated jobs created: 1,357; Recovery (percent): 59.95.



Major base: March Air Force Base, Calif.; Estimated jobs lost: 997; 

Estimated jobs created: 572; Recovery (percent): 57.37.



Major base: Mare Island Naval Shipyard, Calif.; Estimated jobs lost: 

7,567; Estimated jobs created: 1,548; Recovery (percent): 20.46.



Major base: Mather Air Force Base, Calif.; Estimated jobs lost: 1,012; 

Estimated jobs created: 3,514; Recovery (percent): 347.23.



Major base: McClellan Air Force Base, Calif.; Estimated jobs lost: 

8,828; Estimated jobs created: 6,124; Recovery (percent): 69.37.



Major base: Memphis Defense Distribution Depot, Tenn.; Estimated jobs 

lost: 1,289; Estimated jobs created: 573; Recovery (percent): 44.45.



Major base: Memphis Naval Air Station, Tenn.; Estimated jobs lost: 250; 

Estimated jobs created: 112; Recovery (percent): 44.80.



Major base: Myrtle Beach Air Force Base, S.C.; Estimated jobs lost: 

784; Estimated jobs created: 917; Recovery (percent): 116.96.



Major base: Newark Air Force Base, Ohio; Estimated jobs lost: 1,760; 

Estimated jobs created: 1,050; Recovery (percent): 59.66.



Major base: Norton Air Force Base, Calif.; Estimated jobs lost: 2,133; 

Estimated jobs created: 1,853; Recovery (percent): 86.87.



Major base: Oakland Naval Complex, Calif.; Estimated jobs lost: 2,834; 

Estimated jobs created: 838; Recovery (percent): 29.57.



Major base: Ogden Defense Distribution Depot, Utah; Estimated jobs 

lost: 1,105; Estimated jobs created: 611; Recovery (percent): 55.29.



Major base: Orlando Naval Training Center, Fla.; Estimated jobs lost: 

1,105; Estimated jobs created: 1,131; Recovery (percent): 102.35.



Major base: Pease Air Force Base, N.H.; Estimated jobs lost: 400; 

Estimated jobs created: 4,367; Recovery (percent): 1,091.75.



Major base: Philadelphia Defense Personnel Supply Center, Pa.; 

Estimated jobs lost: 1,485; Estimated jobs created: 300; Recovery 

(percent): 20.20.



Major base: Philadelphia Naval Complex, Pa.; Estimated jobs lost: 

8,119; Estimated jobs created: 2,268; Recovery (percent): 27.93.



Major base: Plattsburgh Air Force Base, N.Y.; Estimated jobs lost: 352; 

Estimated jobs created: 881; Recovery (percent): 250.28.



Major base: Presidio of San Francisco, Calif.; Estimated jobs lost: 

3,150; Estimated jobs created: 1,980; Recovery (percent): 62.86.



Major base: Reese Air Force Base, Tex.; Estimated jobs lost: 1,238; 

Estimated jobs created: 138; Recovery (percent): 11.15.



Major base: Red River Army Depot, Tex.; Estimated jobs lost: 386; 

Estimated jobs created: 186; Recovery (percent): 48.19.



Major base: Sacramento Army Depot, Calif.; Estimated jobs lost: 3,164; 

Estimated jobs created: 101; Recovery (percent): 3.19.



Major base: San Diego Naval Training Center, Calif.; Estimated jobs 

lost: 402; Estimated jobs created: 48; Recovery (percent): 11.94.



Major base: Savanna Army Depot, Ill.; Estimated jobs lost: 436; 

Estimated jobs created: 62; Recovery (percent): 14.22.



Major base: Seneca Army Depot, N.Y.; Estimated jobs lost: 273; 

Estimated jobs created: 944; Recovery (percent): 345.79.



Major base: Sierra Army Depot, Calif.; Estimated jobs lost: 374; 

Estimated jobs created: 262; Recovery (percent): 70.05.



Major base: Staten Island Naval Station, N.Y.; Estimated jobs lost: 

1,001; Estimated jobs created: 0; Recovery (percent): 0.00.



Major base: Stratford Army Engineering Plant, Conn.; Estimated jobs 

lost: 1,400; Estimated jobs created: 111; Recovery (percent): 7.93.



Major base: Tooele Army Depot, Utah; Estimated jobs lost: 1,942; 

Estimated jobs created: 819; Recovery (percent): 42.17.



Major base: Treasure Island Naval Station, Calif.; Estimated jobs lost: 

454; Estimated jobs created: 59; Recovery (percent): 13.00.



Major base: Tustin Marine Corps Air Station, Calif.; Estimated jobs 

lost: 348; Estimated jobs created: 2; Recovery (percent): 0.57.



Major base: Vint Hill Farms Station, Va.; Estimated jobs lost: 1,472; 

Estimated jobs created: 344; Recovery (percent): 23.37.



Major base: Warminster Naval Air Warfare Center, Pa.; Estimated jobs 

lost: 2,311; Estimated jobs created: 398; Recovery (percent): 17.22.



Major base: Williams Air Force Base, Ariz.; Estimated jobs lost: 728; 

Estimated jobs created: 2,200; Recovery (percent): 302.20.



Major base: Wurtsmith Air Force Base, Mich.; Estimated jobs lost: 690; 

Estimated jobs created: 587; Recovery (percent): 85.07.



Major base: Total; Estimated jobs lost: 129,649; Estimated jobs 

created: 79,740; Recovery (percent): 61.50.



Source: Our analysis of DOD’s Office of Economic Adjustment data as of 

October 31, 2001.



[End of table]



[End of section]



Appendix V: Average Unemployment Rates of BRAC-Affected Areas Compared 

with the U.S. Average Rate:



As figure 10 shows, 16 (67 percent) of the 24 BRAC-affected localities 

situated west of the Mississippi River had unemployment rates less than 

the U.S. average rate of 4.58 percent during January through September 

2001. The other eight locations had unemployment rates greater than the 

U.S. rate.



Figure 10: Comparison of Unemployment Rates of 24 BRAC-Affected 

Locations West of the Mississippi River:



[See PDF for image]



[End of figure]



Source: Our analysis of the Department of Labor ‘s data.



As figure 11 shows, 28 (76 percent) of the 38 BRAC-affected localities 

situated east of the Mississippi River had unemployment rates that were 

less than the U.S. rate of 4.58 percent during January through 

September 2001. The other 10 locations had unemployment rates that were 

greater than the U.S. rate.



Figure 11: Comparison of Unemployment Rates of 38 BRAC-Affected 

Locations East of the Mississippi River:



[See PDF for image]



[End of figure]



Source: Our analysis of the Department of Labor ‘s data.



[End of section]



Appendix VI: Average Annual Real per Capita Income Growth Rates of 
BRAC-

Affected Areas Compared with the U.S. Average Rate:



As figure 12 shows, 12 (50 percent) of the 24 BRAC-affected localities 

situated west of the Mississippi River had average annual real per 

capita income growth rates that were greater than the U.S. average 

growth rate of 3.03 percent during 1996 through 1999. The other 12 

locations had rates that were below the U.S. average rate.



Figure 12: Comparison of Average Annual Real per Capita Income Growth 

Rates of 24 BRAC-Affected Locations West of the Mississippi River:



[See PDF for image]



[End of figure]



Source: Our analysis of the Department of Commerce’s data.



As figure 13 shows, 21 (55 percent) of the 38 BRAC-affected localities 

situated east of the Mississippi River had average annual real per 

capita income growth rates that were equal to or greater than the U.S. 

average growth rate during 1996 through 1999. The other 17 locations 

had rates that were below the U.S. average rate.



Figure 13: Comparison of Average Annual Real per Capita Income Growth 

Rates of 38 BRAC-Affected Locations East of the Mississippi River:



[See PDF for image]



[End of figure]



Source: Our analysis of the Department of Commerce’s data.



[End of section]



Appendix VII: Case Examples of Community Impacts and Recovery from 
BRAC:



During our review, we visited communities near the former military 

bases at Chase Naval Air Station, Texas; Castle Air Force Base, 

California; Fort Ord, California; Loring Air Force Base, Maine; 

Charleston Naval Shipyard, South Carolina; and Fort McClellan Army 

Base, Alabama. Our visits to communities surrounding the Chase Naval 

Air Station and Castle Air Force Base were designed to see what 

progress they had made since our last visits to them in 1998; the 

remaining visits during this review were with our initial contacts. In 

general, local officials told us that their communities were recovering 

from the impacts of base closure and they were optimistic about the 

future. At the same time, they pointed to the considerable 

difficulties, frustrations, and losses that their communities 

experienced as they adjusted to the loss of military jobs, the 

redevelopment of base property, and the recent declining national 

economy. The economic impact on and recovery of specific communities 

within a region encompassing a closed base can vary--widely in some 

cases--because of such factors as proximity to the base and the 

business diversity within the community. For example, officials in 

Seaside, California (which abuts the former Ft. Ord) told us that the 

base closure caused significant economic problems for the community 

(e.g., closing of local businesses) and that these problems continue to 

hinder recovery. In the neighboring city of Monterey, however, 

officials told us that the impact was less severe because the city had 

a more diverse local economy and was less dependent on the base.



Community Impacts Resulting from the Closure of Chase Naval Air 

Station, Texas:



In 1998, we visited the communities surrounding the former Chase Field 

Naval Air Station, Bee County, Texas, and found that they were 

recovering economically from the base closure. We revisited Bee County 

and found that these communities continued their recovery but were 

still having some problems. Table 8 shows how the closure of Chase 

Field Naval Air Station in February 1993 affected the surrounding 

communities and activities, as indicated by local officials during our 

visits in 1998 and 2001.



Table 8: Community Impacts Resulting from the Closure of Chase Naval 

Air Station, Texas, as Reported in 1998 and 2001:



Overview: Bee County, Texas, and the surrounding counties are 

generally rural; agriculture and ranching are local industries. The 

largest sectors in Bee County are now state and local government, 

trade, and services.: As we reported in 1998; Overview: What we found 

in 2001.



Overview: Bee County, Texas, and the surrounding counties are 

generally rural; agriculture and ranching are local industries. The 

largest sectors in Bee County are now state and local government, 

trade, and services: January-September 1997 unemployment rate of 6.1 

percent; Average real per capita income growth (1991-95) of 0.5 

percent; Sales of expensive items, such as automobiles, dropped; 

; Automobile dealerships had to reduce staff and some businesses 

closed, including high-end clothing stores, a discount department 

store, an automobile dealership, a local janitorial service, a tortilla 

factory, and about four convenience stores; Real estate values in 

the residential market declined, and housing in the $75,000+ range was 

stagnant; Many military families that had brought a range of life 

experiences to the community moved; Skilled workers commuted long 

distances to other bases or were retired, unemployed, or underemployed 

or no longer resided in the area.; Overview: January-September 2001 

unemployment rate of 5 percent; Average real per capita income 

growth (1996-99) of 2.59 percent; Sales of expensive items, such 

as new automobiles, remained low while used automobile sales 

increased; New motel, theatre, and water treatment plant built, 

while one of two large grocery stores closed. New hospital wing added 

to accommodate a significant increase in hospital patients treated. 

County sales tax revenues increased slightly; Real estate values 

in the residential market increased; new home building growth for homes 

was in the $100,000+ range; Evening enrollment at community college 

was 75 percent lower without the military presence; Skilled workers 

continued to commute long distances to other bases.





Source: Discussions with DOD, state, local, and business officials and 

our analysis of the Department of Commerce’s data.



[End of table]



According to local officials, the most important factor contributing to 

economic recovery from the base closing was the decision of the Texas 

Department of Criminal Justice to locate a prison complex on the former 

air base. The medium-security prison, completed in 1994, occupies less 

than one-third of the former base and employs about 1,200 people. 

Without this prison and another prison complex built earlier and 

adjacent to the former base, local officials believe Beeville would not 

have survived as a community. According to a DOD Office of Economic 

Adjustment October 2001 report, 1,153 new jobs, or 120 fewer than 

reported in 1998, were created at the former naval air station. At the 

time of our visit in June 2001, the former air station had only one 

tenant, who maintains the facility instead of paying rent under a 

negotiated 10-year lease agreement with the reuse authority.



Community Impacts Resulting from the Closure of Castle Air Force Base, 

California:



We visited the communities surrounding the former Castle Air Force 

Base, Merced County, California, in 1998 and found that they were 

recovering economically from the base closure. We revisited Merced 

County in 2001 and again found that these communities continued their 

recovery, although they still were experiencing some problems. Table 9 

shows how the closure of Castle Air Force Base in September 1995 

affected the surrounding communities and activities, as local officials 

reported during our visits in 1998 and 2001.



Table 9: Community Impacts Resulting from the Closure of Castle Air 

Force Base, California, as Reported in 1998 and 2001:



Overview: Merced County, California, is a rural area largely 

dedicated to agriculture and related industries. Much of its labor 

force’s seasonally employed in farming and canning. Even during seasons 

of “full employment,” the unemployment rate remains high, around 14 

percent; during the off-season, the rate can rise from 19 to 22 

percent. The area is home to a large immigrant population.[A]: As we 

reported in 1998; Overview: What we found in 2001.



Overview: Merced County, California, is a rural area largely 

dedicated to agriculture and related industries. Much of its labor 

force’s seasonally employed in farming and canning. Even during seasons 

of “full employment,” the unemployment rate remains high, around 14 

percent; during the off-season, the rate can rise from 19 to 22 

percent. The area is home to a large immigrant population.[A]: January-

September 1997 unemployment rate of 15 percent; Average real per 

capita income growth (1991-95) of negative 0.8 percent; Real estate 

values in Atwater dropped 25 to 30 percent, partly because the federal 

government purchased houses of departing military personnel and placed 

them on the market. New housing construction stopped; Atwater 

schools lost enrollment, as well as tax base. The Atwater elementary 

school district had to reduce budget and staff, canceling some 

programs; Local businesses had to reduce staff; some closed, and 

some changed ownership. Several small businesses shut down, including 

restaurants, insurance vendors, and dry cleaners; The community lost 

the military families, who contributed to local organizations, such as 

churches and hospitals.; Overview: January-September 2001 unemployment 

rate of 13.7 percent; Average real per capita income growth (1996-

99) of 2.32 percent; Housing starts have increased significantly 

over the last 2 years partly due to the Bay Area families’ taking 

advantage of affordable residential housing, and to real estate 

speculation from an announced new university campus expected to open in 

2004. Average home prices increased from $114,000 to $140,000; 

Atwater population increased 9.6 percent from 1996 to 2000. Merced 

county population increased by 4.5 percent over the same period; 

Many closed businesses, such as restaurants and other services, have 

not been replaced. There are vacant buildings throughout Atwater; 

Former skilled Castle workers continue to commute more than 4 hours a 

day, round trip, to the Bay Area, while others no longer reside in the 

area.



[A] Many Hmong immigrants from Laos, recruited and trained by the 

United States to conduct rescue missions and guerilla activity during 

the Vietnam war, migrated to the United States after the war to escape 

persecution. India’s Punjabi began immigrating to California after 

World War II and settled largely in rural areas.



Source: Discussions with DOD, state, local, and business officials and 

our analysis of the Department of Commerce’s data.



[End of table]



According to local officials, the closure of Castle Air Force Base had 

an immediate adverse effect on the unemployment rate, housing costs, 

and per capita income. However, within several years these negative 

aspects were overcome. Although the strong national economy helped in 

this recovery, Merced County’s continuing growth is primarily a result 

of three factors. First, a new federal prison now occupies a portion of 

the former air base and employs 200 individuals. Second, real estate 

sales have begun to increase because a new University of California 

campus is expected to open in the fall of 2004 and eventually serve 

25,000 students. Finally, many Bay Area residents are purchasing more 

affordable homes in Merced County and commuting a longer distance to 

their jobs.



On October 31, 2001, DOD’s Office of Economic Adjustment reported an 

increase of 566 new jobs (from 1,881 to 2,447) as a result of the 

redevelopment of Castle Air Force Base from 1998 to 2001. At the time 

of our visit in July 2001, Cingular Wireless was the largest tenant on 

the former air base and employed 1,200 people at its call center. In 

addition, the 42 other tenants employed about 310 individuals. However, 

later that month, Cingular announced that it was cutting 400 jobs at 

its Castle site because the number of calls and the size of the 

workforce had outgrown the center’s space.



Other Communities Recovering from Varied Impacts:



Our visits to communities surrounding four other major base closures 

showed that recovery was occurring, although not without difficulty. 

The impacts of the closures that officials conveyed to us are shown in 

table 10 and included initial economic disruption caused by the news of 

impending closure; loss of population; decreasing business revenue 

leading some businesses to shutdown; a drop in real estate markets and 

a rise in rental property vacancies; declining school enrollments; and 

social losses felt in the communities from the departure of active, 

educated military personnel and families. For example, two school 

districts (Limestone and Presque Isle) surrounding the former Loring 

Air Force Base, Maine, lost 300 to 400 students and 150 to 200 

students, respectively, after the base closed. In the city of Weaver, a 

bedroom community hit hard by the closing of Fort McClellan, Alabama, 

the population dropped by 200 people to about 2,700 after the base 

closed in 1999. But there were some positive effects as well at the 

communities we visited. (See table 10.) For example, local grocers in 

communities surrounding the former Loring Air Force base benefited from 

new business from military retirees, who now shop in their stores 

because the base commissary closed. Furthermore, the early prediction 

of a 20 to 25-percent loss in economic activity in this same area never 

materialized, helped partially by the establishment of a Defense 

Finance and Accounting Service facility, which now employs over 300 

people on the former base.



Table 10: Reported Community Impacts Resulting from Base Closures for 

Communities Not Visited in 1998:



Limestone, Caribou, Presque Isle, Caswell, Fort Fairfield, and Van 

Buren, Maine; Overview; The former Loring Air Force Base, which 

closed in 1994, is located in the town of Limestone in Aroostook 

County, Maine. Aroostook County is a rural county located in the 

northeast corner of Maine bordering Canada and covers 6,672 square 

miles. The area is largely dedicated to lumber and paper production and 

the cultivation of such crops as potatoes, broccoli, and peas. 

Unemployment rates for Aroostook County dropped from 8.5 percent for 

January-September 1997 to 3.9 percent in the same 9-month period in 

2001. Average real per capita income growth rose from 1 percent in 

1991-95 to 2.9 percent in 1996-99.



Impact of closure on community; Limestone school district lost 300 to 

400 students, resulting in a loss of federal and state funding. Presque 

Isle schools lost 150 to 200 students.; Many military retirees left the 

area because the base hospital closed.; Retail businesses such as car 

dealerships closed. Other businesses, such as construction and general 

supply companies, were hard hit.; Ethnic and social diversity 

contributed by military personnel and their families disappeared.; Real 

estate markets dropped 20 to 30 percent during the first 3 years after 

the closing announcement.; Loss of economic activity was not as severe 

as initially expected.; Establishment of Defense Finance and Accounting 

Service facility on former base provided additional jobs.



Charleston and North Charleston, South Carolina; Overview; The 

Charleston Naval Shipyard, which closed in 1996, is located in the city 

of North Charleston, South Carolina. Comprising 3 counties, Berkeley, 

Charleston, and Dorchester, the Charleston metropolitan region covers 

3,163 square miles and has a population of 549,000. Major employers 

include the Medical University of South Carolina, the Charleston Air 

Force Base, and the U.S. Navy. The largest business sectors are 

services, retail and wholesale trade, and government. Unemployment 

rates for the metropolitan area dropped from 4.5 percent for January-

September 1997 to 3.2 percent for the same 9-month period in 2001. 

Average real per capita income growth rose from 1.9 percent for 1991-95 

to 3.4 percent for 1996-99.



Impact of closure on community; Economic impact on the area was not 

nearly as severe as expected. While an economic recovery plan expected 

recovery in 5 years, it took only 2.; Car sales dropped initially.; 

Rental property vacancies rose.; Revenues from military personnel were 

lost. For example, the city of Charleston saw a drop in sales taxes 

after the base closed, but it has since recovered.; The closure was an 

impetus for the formation of a regional alliance of affected 

communities--the alliance raised over $8 million from the public and 

private sector for business recruiting purposes.; Establishment of Navy 

space warfare facility on the former base brought in highly paid and 

highly skilled jobs.; New high tech businesses are moving to the 

region.



Anniston, Weaver, and Jacksonville, Alabama; Overview; Fort 

McClellan, which closed in 1999, was located in the city of Anniston in 

Calhoun County, Alabama. Calhoun County covers 609 square miles and has 

a population of 112,000. The top employers include the Anniston Army 

Depot and a regional medical center. The largest business sectors 

include retail trade and service industries. Unemployment rates for 

Anniston remained the same--5.2 percent--for January-September 1997 and 

for the same 9-month period in 2001. Average real per capita income 

growth declined from 2.1 percent for 1991-95 to 1.3 percent for 1996-

99.



Impact of closure on community; Population declined. For example, 

Weaver’s population dropped by 200 people to about 2,700 after the base 

closed in 1999.; Sales tax revenues were lost.; Students left, 

resulting in a reduction of $8,000 to $10,000 in state school funding.; 

Calhoun County lost population from 1999 to 2000, the only county in 

the state to do so.; Rental property vacancies increased significantly 

after closure.; An off-base shopping area lost many small businesses 

and has not been replaced.; Barbershops and clothing stores closed in 

Anniston.; Military personnel and dependents, who brought diversity and 

were involved in the community, left.; Some military retirees moved out 

of the area because of loss of services; but many retirees remained in 

the area, thereby increasing local community business activity that was 

formerly done on the base when it was active.



Monterey, Del Rey Oaks, Seaside, and Marina, California; Overview; 

Fort Ord, which closed in 1994, covers approximately 44 square miles, 

and lies within Monterey County, California, in the cities of Del Rey 

Oaks, Seaside, and Marina. Major employers include Dole Fresh Vegetable 

Company, the County of Monterey/Salinas, the Department of Defense, and 

Tanimura & Ante, Inc., a company that prepares crops for market. 

Monterey County’s economy consists of four primary sectors: tourism, 

agriculture, environmental technologies, and education. Unemployment 

rates for Salinas, a community near the former base, dropped from 10.3 

percent for January-September 1997 to 9.2 percent for the same 9-month 

period in 2001. Average real per capita income growth dropped from 3.4 

percent for 1991-95 to 1.6 percent for 1996-99.



Impact of Closure on Community; 35,000 military personnel and 

civilians left the area when the base closed.; Secondary business in 

nearby communities, such as dry cleaners and grocery markets, reported 

declines in sales.; The loss of military families living off base 

created housing and apartment surpluses, which took time to recover.; 

Employment growth slowed for1990-95, but recovery followed thereafter.; 

From 1990 to 1999, retail sales in the city of Marina grew by 23 

percent. In contrast, the county retail sales grew by 50 percent and 

state retail sales by 41 percent.; Acquisition of the former base’s 

golf course by the city of Seaside has brought in much needed revenue.; 

Acquisition of the former base’s airport for the city of Marina has 

been a success.; Two former base housing areas for the city of Monterey 

have been redeveloped and are fully utilized.; Seven educational 

institutions have or will soon have facilities on the former base; 

California State University (Monterey Bay) has completed $60 million in 

renovations and has a student population of 2,400; enrollment is 

expected to rise to 12,500 over the next 15 years.; Defense Finance and 

Accounting Service facility was established by renovating the former 

base hospital.



Source: Discussions with DOD, state, local, and business officials and 

our analysis of the Department of Commerce’s data.



[End of table]



[End of section]



Appendix VIII: Key Reports Related to Base Closure Implementation 

Issues:



U.S. General Accounting Office. Military Base Closures: Overview of 

Economic Recovery, Property Transfer, and Environmental Cleanup. GAO-

01-1054T. Washington, D.C.: August 28, 2001.



U.S. General Accounting Office. Military Base Closures: DOD’s Updated 

Net Savings Estimate Remains Substantial. GAO-01-971. Washington, D.C.: 

July 31, 2001.



U.S. General Accounting Office. Environmental Liabilities: DOD Training 

Range Cleanup Cost Estimates Are Likely Understated. GAO-01-479. 

Washington, D.C.: April 11, 2001.



U.S. General Accounting Office. Military Base Closures: Unexpended 

Funds Raise Questions About Fiscal Year 2001 Funding Needs. GAO/NSIAD-

00-170. Washington, D.C.: July 7, 2000.



U.S. General Accounting Office. Military Base Closures: Potential to 

Offset Fiscal Year 2000 Budget Request. GAO/NSIAD-99-149. Washington, 

D.C.: July 23, 1999.



U.S. General Accounting Office. Military Bases: Status of Prior Base 

Realignment and Closure Rounds. GAO/NSIAD-99-36. Washington, D.C.: 

December 11, 1998.



U.S. General Accounting Office. Military Bases: Review of DOD’s 1998 

Report on Base Realignment and Closure. GAO/NSIAD-99-17. Washington, 

D.C.: November 13, 1998.



Congressional Budget Office. Review of the Report of the Department of 

Defense on Base Realignment and Closure. Washington, D.C.: July 1, 

1998.



Department of Defense, Office of the Inspector General. Audit Report: 

Cost and Savings for 1993 Defense Base Realignments and Closures. 

Report No. 98-130. Washington, D.C.: May 6, 1998.



Department of Defense. The Report of the Department of Defense on Base 

Realignment and Closure. Washington, D.C.: April 1998.



U.S. General Accounting Office. Defense Infrastructure: Challenges 

Facing DOD in Implementing Reform Initiatives. GAO/T-NSIAD-98-115. 

Washington, D.C.: 

March 18, 1998.



U.S. Army Audit Agency. Base Realignment and Closure 1995 Savings 

Estimates. Audit Report AA97-225. Washington, D.C.: July 31, 1997.



U.S. General Accounting Office. Military Bases: Lessons Learned from 

Prior Base Closure Rounds. GAO/NSIAD-97-151. Washington, D.C.: July 25, 

1997.



Congressional Budget Office. Closing Military Bases: An Interim 

Assessment. Washington, D.C.: December 1996.



U.S. General Accounting Office. Military Base Closures: Reducing High 

Costs of Environmental Cleanup Requires Difficult Choices. GAO/NSIAD-

96-172. Washington, D.C.: September 5, 1996.



U.S. General Accounting Office. Military Bases: Closure and Realignment 

Savings Are Significant, but Not Easily Quantified. GAO/NSIAD-96-67. 

Washington, D.C.: April 8, 1996.



[End of section]



Appendix IX: Comments from the Department of Defense:



OFFICE OF THE UNDER SECRETARY OF DEFENSE:

ACQUISITION, TECHNOLOGY AND LOGISTICS:



3000 DEFENSE PENTAGON WASHINGTON, DC 20301-3000:



MAR 26 2002:



Mr. Barry Holman, Director:



Defense Capabilities and Management U.S. General Accounting Office 

Washington, D.C. 20548:



Dear Mr. Holman:



Attached is the Department of Defense response to the GAO draft report, 

MILITARY BASE CLOSURES: Progress in Completing Actions from Prior 

Realignments and Closures, dated February 26, 2002 (GAO Code 350059).



The Department concurs with GAO’s recommendations. The report found 

most communities continue to recover from the Department’s base closure 

and realignment actions. Most communities have been able to absorb the 

economic loss and show positive economic growth at or above national 

averages in recognition of the initiative and persistence of the 

Military Departments and local redevelopment officials. We will 

continue to work with local and state officials as their redevelopment 

efforts seek a more diversified economy.



The Department appreciates the opportunity to review and comment on the 

draft report.



Sincerely,



for Raymond. DuBois, Jr. Deputy Under Secretary of Defense 

(Installations and Environment):



Attachment: As stated:



GAO DRAFT REPORT DATED FEBRUARY 26, 2002 (GAO CODE 350059):



“MILITARY BASE CLOSURES: PROGRESS IN COMPLETING ACTIONS FROM PRIOR 

REALIGNMENTS NAD CLOSURES “:



DEPARTMENT OF DEFENSE COMMENTS TO THE GAO RECOMMENDATION:



RECOMMENDATION 1: The GAO recommended that, as part of the new base 

realignment and closure round scheduled for 2005, the Under Secretary 

of Defense (Acquisition, Technology and Logistics), in consultation 

with the Under Secretary of Defense (Comptroller), develop a Defense-

wide systematic approach for the periodic updating of initial closure 

savings estimates.



DOD RESPONSE: We concur with the GAO recommendation that the Under 

Secretary of Defense (Acquisition, Technology and Logistics), in 

consultation with the Under Secretary of Defense (Comptroller, develop 

a Defense-wide systematic approach for the periodic updating of initial 

closure savings estimates for the new base realignment and closure 

round scheduled for 2005.



RECOMMENDATION 2: The GAO also recommended that the Under Secretary of 

Defense (Acquisition, Technology and Logistics), in consultation with 

the Under Secretary of Defense (Comptroller), develop an oversight 

mechanism to ensure that the military services and components update 

such estimates in accordance with the prescribed approach.



DOD RESPONSE: We concur with the GAO recommendation that the Under 

Secretary of Defense (Acquisition, Technology and Logistics), in 

consultation with the Under Secretary of Defense (Comptroller), develop 

an oversight mechanism to ensure that the military services and 

components update such estimates in accordance with the prescribed 

approach for the new base realignment and closure round scheduled for 

2005.



RECOMMENDATION 3: The GAO recommended that the Secretary of Defense 

encourage the Secretaries of the Military Services to work with 

communities impacted by the base closure process to expand the use of 

the early transfer authority in those cases where the Department can 

accelerate the transfer of unneeded former base property and/or save 

money.



DOD RESPONSE: We concur with the GAO recommendation that the Secretary 

of Defense encourage the Secretaries of the Military Services to work 

with communities impacted by the base closure process to expand the use 

of the early transfer authority in those cases where the Department can 

accelerate the transfer of unneeded former base property and/or save 

money.



[End of section]



Appendix X: GAO Contacts and Staff Acknowledgments:



GAO Contacts:



Barry W. Holman (202) 512-8412:



Mark A. Little (202) 512-4673:



Acknowledgements:



In addition, Nancy Benco, Jane Hunt, David Keefer, Don Kennedy, Michael 

Kennedy, Tom Mahalek, Charles Perdue, Bob Poetta, James Reifsnyder, 

Thaddeus Rytel, and Arnett Sanders contributed to this report.



FOOTNOTES



[1] See U.S. General Accounting Office, Military Bases: Status of Prior 

Base Realignment and Closure Rounds, GAO/NSIAD-99-36 (Washington, D.C.: 

Dec. 11, 1998).



[2] See U.S. General Accounting Office, Military Base Closures: DOD’s 

Updated Net Savings Estimate Remains Substantial, GAO-01-971 

(Washington D.C.: July 31, 2001) and Military Base Closures: Overview 

of Economic Recovery, Property Transfer, and Environmental Cleanup, 

GAO-01-1054T (Washington D.C.: Aug. 28, 2001).



[3] See U.S. General Accounting Office, Military Base Closures: 

Reducing High Costs of Environmental Cleanup Requires Difficult 

Choices, GAO/NSIAD-96-172 (Washington D.C.: Sept. 5, 1996).



[4] The Congress enacted a so-called “early transfer authority” 

provision in September 1996 legislation to allow property to be 

transferred before all necessary cleanup actions have been taken. 

However, certain conditions must exist for the department to exercise 

this authority. For example, the property must be suitable for transfer 

for the intended use, transfer of the property must not delay any 

cleanup actions, and the governor of the state where the property is 

located must approve the transfer. The advantage of an early transfer 

is that the property is made available under an economic development or 

other disposal authority to the future user as soon as possible to 

allow for concurrent environmental cleanup and redevelopment 

activities.



[5] The 1988 round was completed under the Defense Authorization 

Amendments and Base Closure and Realignment Act (P.L. 100-526, as 

amended). The last three rounds were completed under the Defense Base 

Closure and Realignment Act of 1990 (P.L. 101-510, as amended).



[6] The number of recommendations may vary depending on how they are 

categorized. In this report, the recommendations include closures, 

realignments, disestablishments, relocations, and redirections. In a 

closure, all missions carried out at a base either cease or relocate, 

while in a realignment, a base remains open but loses and sometimes 

gains missions. “Disestablishments” and “relocations” refer to 

missions; those disestablished cease operations, while those relocated 

are moved to another base. “Redirections” refer to cases in which a 

BRAC Commission changes the recommendation of a previous commission. 



[7] The 1995 BRAC round recommendation to close family housing units on 

Fort Buchanan, Puerto Rico, was not implemented because the DOD 

Appropriations Act for Fiscal Year 1999 (P.L. 105-262) authorized the 

secretary of defense to retain all or a portion of the units in support 

of the U.S. Army South’s relocation from Panama to Fort Buchanan.



[8] With the enactment of the National Defense Authorization Act for 

Fiscal Year 2002 (P.L. 107-107, sec. 3006 {a}), DOD “shall seek to 

obtain” fair market value for property transfers at installations 

recommended for closure or realignment after January 1, 2005. The 

section also provides for property transfers without consideration, if 

circumstances warrant. DOD has not yet developed policy guidance for 

implementing this section.



[9] See GAO/NSIAD-99-36.



[10] See GAO-01-971 and GAO-01-1054T.



[11] In terms of constant fiscal year 2001 dollars, the $16.7 billion 

net savings estimate and the $6.6 billion annual recurring savings 

estimate are $16.7 billion and $6.4 billion, respectively.



[12] While cost estimates are routinely updated and tracked in 

financial accounting systems, they are based on obligations and not 

actual outlays, thereby adding a degree of imprecision to the actual 

costs and the basis for savings projections.



[13] See GAO/NSIAD-96-172.



[14] These 24 BRAC actions include the Army Aviation Troop Command, 

Baltimore Publication Center, Bayonne Military Ocean Terminal, Detroit 

Arsenal, Fitzsimons Army Medical Center, Fort Buchanan, Fort Chaffee, 

Fort Dix, Fort Greely, Fort Holabird, Fort Hunter-Liggett, Fort Lee, 

Fort Pickett, Fort Ritchie, Fort Totten, Minor Fort Dix, Minor Army 

Forces Command, Minor Fort Lewis, Oakland Army Base, Red River Army 

Depot, Savanna Army Depot, Seneca Army Depot, Sierra Army Depot, 

Stratford Army Engine Plant, and Tri Service Project Reliance.



[15] See Congressional Budget Office, Review of the Report of the 

Department of Defense on Base Realignment and Closure (Washington D.C.: 

July 1, 1998).



[16] See Department of Defense, Office of the Inspector General, Audit 

Report: Cost and Savings for 1993 Defense Realignments and Closures, 

Report No. 98-130 (Washington D.C.: May 6, 1998).



[17] See U.S. Army Audit Agency, Base Realignment and Closure:1995 

Savings Estimates, Audit Report AA97-225 (Washington D.C.: July 31, 

1997).



[18] The Air Force reported no savings for McClellan Air Force Base and 

Kelly Air Force Base prior to fiscal year 2000 because of uncertainties 

regarding the performance of the bases’ depot workloads.



[19] See GAO/NSIAD-97-11.



[20] See Department of Defense, The Report of the Department of Defense 

on Base Realignment and Closure (Washington, D.C.: Apr. 1998).



[21] The unneeded acreage does not include property at the Pueblo 

Chemical Depot, Colorado, and the Umatilla Chemical Depot, Oregon, 

because it will not be available for further disposition until the 

chemical demilitarization mission at these bases is completed.



[22] In this report, “transferred property” refers to property that has 

been deeded to another user; it does not include leased property. 



[23] In addition, DOD is retaining an additional 343,000 acres at 

closing and realigning bases for reserve component use. Most of this 

acreage is property at several Army bases, including Fort Hunter 

Liggett, California; Fort Chaffee, Arkansas; Fort Pickett, Virginia; 

Fort Dix, New Jersey; and Fort McClellan, Alabama.



[24] As discussed later, an additional 49,291 acres are in use by 

others through interim or long-term leases pending other actions that 

would permit title transfer.



[25] Two former Army bases--Fort Ord, California, and Camp Bonneville, 

Washington--are expected to require most of the funding needed to 

complete unexploded ordnance cleanup.



[26] National Defense Authorization Act for Fiscal Year 1997 (P.L. 104-

201, sec. 334).



[27] During our review, we visited communities near the former military 

bases of Chase Naval Air Station, Texas; Castle Air Force Base, 

California; Fort Ord, California; Loring Air Force Base, Maine; 

Charleston Naval Shipyard, South Carolina; and Fort McClellan Army 

Base, Alabama. We had previously visited two of these areas--Chase 

Naval Air Station and Castle Air Force Base--in completing our 1998 

report.



[28] See U.S. General Accounting Office, Defense Spending and 

Employment: Information Limitations Impede thorough Assessments, GAO/

NSIAD-98-57 (Washington D.C.: Jan. 14, 1998).



[29] See Rutgers University et al., Defense Adjustment Program 

Performance Evaluation (New Brunswick, N.J.: Nov. 1997).



[30] Ideally, to assess how the local communities fared after each BRAC 

round, we would need economic information on how those communities 

would have fared without each BRAC round compared with how they have 

fared since the BRAC program began. Because we did not have these 

baseline data, we compared the national averages for unemployment and 

real per capita income as a benchmark to assess how well the 

communities have fared. This comparison does not isolate the economic 

effects of a base closure from the factors of other economic events 

occurring in a particular region.



[31] One of the limitations of our approach to selecting communities is 

that some areas may have been the receiving location for DOD 

realignments and may have gained jobs. For example, we included St. 

Mary’s County, Maryland, because of the closure of Navy facilities at 

St. Inigoes, Maryland, in the 1993 BRAC round. However, in the 1995 

round, the area gained jobs at the Patuxent River Navy facilities 

because of the relocation of Navy activities from the Washington, D.C., 

metropolitan area. Despite these gains, the communities we selected for 

our analysis lost a significant number of DOD jobs.



[32] Average annual real per capita income rates for 2000 were not 

available for analysis during our review.



[33] The per capita income estimates used at the time were available 

only through 1995. Therefore, we did not analyze per capita income for 

13 communities that were affected only by the 1995 BRAC round.



[34] The impact areas for the communities were defined by using 

accepted standard definitions for metropolitan and nonmetropolitan 

statistical areas and reflected the impact areas used in the 1995 BRAC 

round.



[35] The number of reported civilian positions lost decreased by 5,610 

(from 135,259 to 129,649) from 1998 to 2001 because of adjustments in 

the Griffiss Air Force figures and the omission of Fort Dix, the 

Aviation Troop Command, and Fort Greely from the 2001 report.



GAO’s Mission:



The General Accounting Office, the investigative arm of Congress, 

exists to support Congress in meeting its constitutional 

responsibilities and to help improve the performance and accountability 

of the federal government for the American people. GAO examines the use 

of public funds; evaluates federal programs and policies; and provides 

analyses, recommendations, and other assistance to help Congress make 

informed oversight, policy, and funding decisions. GAO’s commitment to 

good government is reflected in its core values of accountability, 

integrity, and reliability.



Obtaining Copies of GAO Reports and Testimony:



The fastest and easiest way to obtain copies of GAO documents at no 

cost is through the Internet. GAO’s Web site ( www.gao.gov ) contains 

abstracts and full-text files of current reports and testimony and an 

expanding archive of older products. The Web site features a search 

engine to help you locate documents using key words and phrases. You 

can print these documents in their entirety, including charts and other 

graphics.



Each day, GAO issues a list of newly released reports, testimony, and 

correspondence. GAO posts this list, known as “Today’s Reports,” on its 

Web site daily. The list contains links to the full-text document 

files. To have GAO e-mail this list to you every afternoon, go to 

www.gao.gov and select “Subscribe to daily E-mail alert for newly 

released products” under the GAO Reports heading.



Order by Mail or Phone:



The first copy of each printed report is free. Additional copies are $2 

each. A check or money order should be made out to the Superintendent 

of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 

more copies mailed to a single address are discounted 25 percent. 

Orders should be sent to:



U.S. General Accounting Office



441 G Street NW,



Room LM Washington,



D.C. 20548:



To order by Phone: 	



	Voice: (202) 512-6000:



	TDD: (202) 512-2537:



	Fax: (202) 512-6061:



To Report Fraud, Waste, and Abuse in Federal Programs:



Contact:



Web site: www.gao.gov/fraudnet/fraudnet.htm E-mail: fraudnet@gao.gov



Automated answering system: (800) 424-5454 or (202) 512-7470:



Public Affairs:



Jeff Nelligan, managing director, NelliganJ@gao.gov (202) 512-4800 U.S.



General Accounting Office, 441 G Street NW, Room 7149 Washington, D.C.



20548: