This is the accessible text file for GAO report number GAO-08-131T 
entitled 'Secure Border Initiative: Observations on Selected Aspects of 
SBInet Program' which was released on October 24, 2007. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Testimony Before the Subcommittees on Management, Investigations, and 
Oversight, and Border, Maritime and Global Counterterrorism, Committee 
on Homeland Security, 

House of Representatives: 

United States Government Accountability Office: 

GAO: 

For Release on Delivery Expected at 2:00 p.m. EDT: 

Wednesday, October 24, 2007: 

Secure Border Initiative: 

Observations on Selected Aspects of SBInet Program Implementation: 

Statement of Richard M. Stana, Director: 

Homeland Security and Justice Issues: 

For Official Use Only Draft: 

GAO-08-131T: 

GAO Highlights: 

Highlights of GAO-08-131T, a testimony before the subcommittee on 
Management, Investigation, and Oversight, and Border, Maritime and 
Global Counterterrorism, Committee on Homeland Security, House of 
Representatives. 

Why GAO Did This Study: 

In November 2005, the Department of Homeland Security (DHS) established 
the Secure Border Initiative (SBI), a multiyear, multibillion dollar 
program to secure U.S. borders. One element of SBI is SBInet—the U.S. 
Customs and Border Protection (CBP) program responsible for developing 
a comprehensive border protection system through a mix of security 
infrastructure (e.g., fencing), and surveillance and communication 
technologies (e.g., radars, sensors, cameras, and satellite phones). 

The House Committee on Homeland Security asked GAO to monitor DHS 
progress in implementing the SBInet program. This testimony provides 
GAO’s observations on (1) SBInet technology implementation; (2) SBInet 
infrastructure implementation; (3) the extent to which CBP has 
determined the impact of SBInet technology and infrastructure on its 
workforce needs and operating procedures; and (4) how the CBP SBI 
Program Management Office (PMO) has defined its human capital goals and 
the progress it has made to achieve these goals. GAO’s observations are 
based on analysis of DHS documentation, such as program schedules, 
contracts, status, and reports. GAO also conducted interviews with DHS 
officials and contractors, and visits to sites in the southwest border 
where SBInet deployment is underway. GAO performed the work from April 
2007 through October 2007. DHS generally agreed with GAO’s 

What GAO Found: 

DHS has made some progress to implement Project 28—the first segment of 
SBInet technology across the southwest border, but it has fallen behind 
its planned schedule. The SBInet contractor delivered the components 
(i.e., radars, sensors and cameras) to the Project 28 site in Tucson, 
Arizona on schedule. However, Project 28 is incomplete more than 4 
months after it was to become operational—at which point Border Patrol 
agents were to begin using SBInet technology to support their 
activities. According to DHS, the delays are primarily due to software 
integration problems. In September 2007, DHS officials said that the 
Project 28 contractor was making progress in correcting the problems, 
but DHS was unable to specify a date when the system would be 
operational. Due to the slippage in completing Project 28, DHS is 
revising the SBInet implementation schedule for follow-on technology 
projects, but still plans to deploy technology along 387 miles of the 
southwest border by December 31, 2008. DHS is also taking steps to 
strengthen its contract management for Project 28. 

SBInet infrastructure deployment along the southwest border is on 
schedule, but meeting CBP’s goal to have 370 miles of pedestrian fence 
and 200 miles of vehicle barriers in place by December 31, 2008, may be 
challenging and more costly than planned. CBP met its intermediate goal 
to deploy 70 miles of new fencing in fiscal year 2007 and the average 
cost per mile was $2.9 million. The SBInet PMO estimates that 
deployment costs for remaining fencing will be similar to those thus 
far. In the past, DHS has minimized infrastructure construction labor 
costs by using Border Patrol agents and Department of Defense military 
personnel. However, CBP officials report that they plan to use 
commercial labor for future fencing projects. The additional cost of 
commercial labor and potential unforeseen increases in contract costs 
suggest future deployment could be more costly than planned. DHS 
officials also reported other challenging factors they will continue to 
face for infrastructure deployment, including community resistance, 
environmental considerations, and difficulties in acquiring rights to 
land along the border. 

The impact of SBInet on CBP’s workforce needs and operating procedures 
remains unclear because the SBInet technology is not fully identified 
or deployed. CBP officials expect the number of Border Patrol agents 
required to meet mission needs to change from current projections, but 
until the system is fully deployed, the direction and magnitude of the 
change is unknown. For the Tucson sector, where Project 28 is being 
deployed, Border Patrol officials are developing a plan on how to 
integrate SBInet into their operating procedures. 

The SBI PMO tripled in size during fiscal year 2007, but fell short of 
its staffing goal of 270 employees. Agency officials expressed concerns 
that staffing shortfalls could affect the agency’s capacity to provide 
adequate contractor oversight. In addition, the SBInet PMO has not yet 
completed long-term human capital planning. 

To view the full product, including the scope and methodology, click on 
GAO-08-131T. For more information, contact Richard M. Stana at (202) 
512-8777 or stanar@gao.gov 

[End of section] 

Chairman Sanchez, Mr. Souder, Chairman Carney, Mr. Rogers and Members 
of the Subcommittees: 

I am pleased to be here today to discuss observations on selected 
aspects of the Secure Border Initiative's SBInet program 
implementation. 

Securing the nation's borders from illegal entry of aliens and 
contraband, including terrorists and weapons of mass destruction, 
continues to be a major concern. Much of the United States' 6,000 miles 
of international borders with Canada and Mexico remains vulnerable to 
illegal entry. Although the Department of Homeland Security (DHS) 
apprehends hundreds of thousands of people entering the country 
illegally each year, several hundreds of thousands of individuals also 
enter the United States illegally and undetected. In November 2005, DHS 
announced the launch of the Secure Border Initiative (SBI), a 
multiyear, multibillion dollar program aimed at securing U.S. borders 
and reducing illegal immigration. Elements of SBI will be carried out 
by several organizations within DHS. One element of SBI is SBInet. 
Under SBInet, the U.S. Customs and Border Protection (CBP) is 
responsible for developing a comprehensive border protection system. 

You requested that we monitor the SBInet program and provide periodic 
updates on the status of the program. My testimony today is the first 
in a series of interim reports on SBInet implementation and focuses on 
the following issues: 

* SBInet's technology implementation; 

* SBInet's infrastructure implementation; 

* the extent to which CBP has determined the impact of SBInet 
technology and infrastructure on its workforce needs and operating 
procedures; and: 

* how the CBP SBI Program Management Office (PMO)[Footnote 1] has 
defined its human capital goals and the progress it has made to achieve 
these goals. 

To address these issues, we analyzed DHS documents, including program 
schedules and status reports, and workforce data. We interviewed DHS 
and CBP headquarters and field officials, including representatives of 
the SBInet PMO, Border Patrol, CBP Air and Marine, and the DHS Science 
and Technology Directorate. We also visited the Tucson and Yuma, 
Arizona Border Patrol sectors[Footnote 2]--two sites where SBInet 
deployment was underway at the time of our review. We performed our 
work from April 2007 through October 2007 in accordance with generally 
accepted government auditing standards. (App. I provides a detailed 
discussion of our scope and methodology.) 

We also have work underway to review other components of the SBInet 
program. Specifically, we are conducting work for the House Committee 
on Homeland Security to assess the development and deployment of 
SBInet's command, control, and communications systems, and surveillance 
and detection systems and expect to issue a report next year. In 
addition, we are reviewing DHS's use of performance-based services 
acquisition, an acquisition method structured around the results to be 
achieved instead of the manner by which the service should be 
performed. We expect to issue a report on this effort in January 2008. 

Summary: 

DHS has made some progress to implement the first segment of SBInet 
technology, Project 28--a $20 million project to secure 28 miles along 
the southwest border, but it has fallen behind its planned schedule. 
Boeing--the prime contractor that DHS selected to acquire, deploy, and 
sustain systems of new surveillance and communications technology 
across U.S. borders--delivered and deployed the system components 
(i.e., radars, sensors, computers) to the Project 28 site in the Tucson 
sector on schedule. However, Project 28 is incomplete more than 4 
months after it was to become operational--at which point Border Patrol 
agents were to begin using SBInet technology to support their 
activities, and CBP was to begin its operational test and evaluation 
phase. According to CBP and Boeing officials, the delays are primarily 
attributed to software integration problems--such as long delays in 
radar information being displayed in command centers. In September 
2007, CBP officials told us that Boeing was making progress in 
correcting the system integration problems, but CBP was unable to 
provide us with a specific date on when Boeing would complete the 
necessary corrections to make Project 28 operational. CBP reports that 
it is in the early stages of planning for additional SBInet technology 
projects along the southwest border; however, Boeing's delay in 
completing Project 28 has led CBP to extend timelines for deploying 
some technology projects scheduled for calendar years 2007 and 2008. 
CBP reports that it has taken steps to strengthen its contract 
management for this project. 

Deploying SBInet's infrastructure along the southwest border is on 
schedule, but meeting the SBInet program's goal to have 370 miles of 
pedestrian fence and 200 miles of vehicle barriers in place by December 
31, 2008, may prove challenging and more costly than planned. CBP met 
its intermediate goal to deploy 70 miles of new fencing in fiscal year 
2007 and the average cost per mile was $2.9 million. The SBInet PMO 
estimates that deployment costs for remaining fencing will be similar 
to those thus far. In the past, DHS has minimized infrastructure 
construction labor costs by using Border Patrol agents and Department 
of Defense (DOD) military personnel. However, CBP officials report that 
they plan to use commercial labor for future fencing projects. The 
additional cost of commercial labor and potential unforeseen increases 
in contract costs suggest future deployment could be more costly than 
planned. Also, while deployment of tactical infrastructure is on 
schedule, CBP officials reported that meeting deadlines has been 
challenging because of factors the officials will continue to face, 
including conducting outreach necessary to address border-community 
resistance, identifying and completing steps necessary to comply with 
environmental regulations, and addressing difficulties in acquiring 
rights to border lands. 

The impact of SBInet on the Border Patrol's workforce's needs and 
operating procedures remains unclear because the SBInet technology is 
not fully identified or deployed. CBP officials expect the number of 
Border Patrol agents required to meet mission needs to change from the 
current projections, but until the system is fully deployed, the 
direction and magnitude of the change is unknown. In addition, for the 
Tucson sector, where Project 28 is being deployed, the Border Patrol is 
developing a plan on how to integrate SBInet into its operating 
procedures. Moreover, the delays in deploying Project 28 will require 
revising the SBInet's training curriculum, and trainers and operators 
will be retrained. 

The SBI PMO tripled in size in fiscal year 2007 but fell short of its 
staffing goal of 270 employees. Agency officials expressed concerns 
that staffing shortfalls could affect the agency's capacity to provide 
adequate contractor oversight. In addition, the SBI PMO has not yet 
completed its long-term human capital planning. 

In their oral comments on a draft of this statement, DHS generally 
agreed with our findings and provided clarifying information that we 
incorporated as appropriate. 

Background: 

The SBInet program is responsible for identifying and deploying an 
appropriate mix of technology (e.g., sensors, cameras, radars, 
communications systems, and mounted laptop computers for agent 
vehicles), tactical infrastructure (e.g., fencing, vehicle barriers, 
roads,), rapid response capability (e.g., ability to quickly relocate 
operational assets and personnel) and personnel (e.g., program staff 
and Border Patrol agents) that will enable CBP agents and officers to 
gain effective control[Footnote 3] of U.S. borders. SBInet technology 
is also intended to include the development and deployment of a common 
operating picture (COP) that provides uniform data through a command 
center environment to Border Patrol agents in the field and all DHS 
agencies and to be interoperable with stakeholders external to DHS, 
such as local law enforcement. The initial focus of SBInet is on the 
southwest border areas between ports of entry[Footnote 4] that CBP has 
designated as having the highest need for enhanced border security 
because of serious vulnerabilities. Through SBInet, CBP plans to 
complete a minimum of 387 miles of technology deployment across the 
southwest border by December 31, 2008. Figure 1 shows the location of 
select SBInet projects underway on the southwest border. 

Figure 1: Select SBInet Projects Under Way on the Southwest Border: 

This figure is a map of locations where select SBInet projects are 
underway. 

[See PDF for image] 

Source: GAO analysis; Map Resources (map). 

[End of figure] 

In September 2006, CBP awarded a prime contract to the Boeing Company 
for 3 years, with three additional 1-year options. As the prime 
contractor, Boeing is responsible for acquiring, deploying, and 
sustaining selected SBInet technology and tactical infrastructure 
projects. In this way, Boeing has extensive involvement in the SBInet 
program requirements development, design, production, integration, 
testing, and maintenance and support of SBInet projects. Moreover, 
Boeing is responsible for selecting and managing a team of 
subcontractors that provide individual components for Boeing to 
integrate into the SBInet system.[Footnote 5] The SBInet contract is 
largely performance-based--that is, CBP has set requirements for SBInet 
and Boeing and CBP coordinate and collaborate to develop solutions to 
meet these requirements--and designed to maximize the use of commercial 
off-the-shelf technology.[Footnote 6] CBP's SBInet PMO oversees and 
manages the Boeing-led SBInet contractor team. The SBInet PMO workforce 
includes a mix of government and contractor support staff. The SBInet 
PMO reports to the CBP SBI Program Executive Director. 

CBP is executing part of SBInet activities through a series of task 
orders to Boeing for individual projects. As of September 30, 2007, CBP 
had awarded five task orders to Boeing for SBInet projects. These 
include task orders for (1) Project 28, Boeing's pilot project and 
initial implementation of SBInet technology to achieve control of 28 
miles of the border in the Tucson sector; (2) Project 37, for 
construction approximately 32 miles of vehicle barriers and pedestrian 
fencing in the Yuma sector along the Barry M. Goldwater Range 
(BMGR);[Footnote 7] (3) Program Management, for engineering, facilities 
and infrastructure, test and evaluation, and general program management 
services; (4) Fence Lab, a project to evaluate the performance and cost 
of deploying different types of fences and vehicle barriers; and (5) a 
design task order for developing the plans for several technology 
projects to be located in the Tucson, Yuma, and El Paso sectors. 

In addition to deploying technology across the southwest border, the 
SBInet PMO plans to deploy 370 miles of single-layer pedestrian fencing 
and 200 miles of vehicle barriers by December 31, 2008. Whereas 
pedestrian fencing is designed to prevent people on foot from crossing 
the border, vehicle barriers are other physical barriers meant to stop 
the entry of vehicles. The SBInet PMO is utilizing the U.S. Army Corps 
of Engineers (USACE) to contract for fencing and supporting 
infrastructure (such as lights and roads), complete required 
environmental assessments, and acquire necessary real estate.[Footnote 
8] 

DHS has estimated that the total cost for completing the deployment for 
the southwest border--the initial focus of SBInet deployment--will be 
$7.6 billion from fiscal years 2007 through 2011. DHS has not yet 
reported the estimated life cycle cost for this program, which is the 
total cost to the government for a program over its full life, 
consisting of research and development, operations, maintenance, and 
disposal costs.[Footnote 9] For fiscal year 2007, Congress appropriated 
about $1.2 billion for SBInet, about which 40 percent DHS had committed 
or obligated as of September 30, 2007. For fiscal year 2008, DHS has 
requested an additional $1 billion.[Footnote 10] 

SBInet Technology Deployment Delays May Increase Schedule Risks: 

DHS has made some progress to implement Project 28--the first segment 
of technology on the southwest border, but it has fallen behind its 
planned schedule. Project 28 is the first opportunity for Boeing to 
demonstrate that its technology system can meet SBInet performance 
requirements in a real-life environment.[Footnote 11] Boeing's 
inability thus far to resolve system integration issues has left 
Project 28 incomplete more than 4 months after its planned June 13 
milestone to become operational--at which point, Border Patrol agents 
were to begin using SBInet technology to support their activities, and 
CBP was to begin its operational test and evaluation phase. Boeing 
delivered and deployed the individual technology components of Project 
28 on schedule.[Footnote 12] Nevertheless, CBP and Boeing officials 
reported that Boeing has been unable to effectively integrate the 
information collected from several of the newly deployed technology 
components, such as sensor towers, cameras, radars, and unattended 
ground sensors. Among several technical problems reported were that it 
was taking too long for radar information to display in command centers 
and newly deployed radars were being activated by rain, making the 
system unusable. In August 2007, CBP officially notified Boeing that it 
would not accept Project 28 until these and other problems were 
corrected. In September 2007, CBP officials told us that Boeing was 
making progress in correcting the system integration problems; however, 
CBP was unable to provide us with a specific date when Boeing would 
complete the corrections necessary to make Project 28 operational. See 
figures 2 and 3 below for photographs of SBInet technology along the 
southwest border. 

Figure 2: Project 28 Mobile Sensor Tower Deployed in Tucson Sector: 

This figure is two photos of a Project 28 Mobile Sensor Tower. 

[See PDF for image] 

Source: GAO. 

[End of figure] 

Figure 3: At Left, Mounted Laptop Installed in Border Patrol Vehicle; 
at Right, Project 28 Command and Control Center: 

This figure is two photos of a mounted laptop in a border patrol 
vehicle, and a Project 28 command and control center. 

[See PDF for image] 

Source: GAO. 

[End of figure] 

The SBInet PMO reported that is in the early stages of planning for 
additional SBInet technology projects along the southwest border; 
however, Boeing's delay in completing Project 28 has led the PMO to 
change the timeline for deploying some of these projects. In August 
2007, SBInet PMO officials told us they were revising the SBInet 
implementation plan to delay interim project milestones for the first 
phase of SBInet technology projects, scheduled for calendar years 2007 
and 2008.[Footnote 13] For example, SBInet PMO officials said they were 
delaying the start dates for two projects[Footnote 14] that were to be 
modeled on the design used for Project 28 until after Project 28 is 
operational and can provide lessons learned for planning and deploying 
additional SBInet technology along the southwest border. According to 
the SBInet master schedule dated May 31, 2007, these projects were to 
become operational in December 2007 and May 2008. Despite these delays, 
SBInet PMO officials said they still expected to complete all of the 
first phase of technology projects by the end of calendar year 2008. As 
of October 15, 2007, the SBInet PMO had not provided us with a revised 
deployment schedule for this first phase. 

CBP reports that it is taking steps to strengthen its contract 
management for Project 28. For example, citing numerous milestone 
slippages by Boeing during Project 28 implementation, in August 2007, 
CBP sought and reached an agreement with Boeing to give it greater 
influence in milestone setting and planning corrective actions on the 
Project 28 task order. While CBP had selected a firm-fixed-price 
contract to limit cost overruns on Project 28,[Footnote 15] CBP 
officials told us that the firm-fixed-price contract CBP used for 
Project 28 had limited the government's role in directing Boeing in its 
decision making process. For example, CBP and contractor officials told 
us they expressed concern about the timeline for completing Project 28, 
but CBP chose not to modify the contract because doing so would have 
made CBP responsible for costs beyond the $20 million fixed-price 
contract.[Footnote 16] In mid-August 2007, CBP organized a meeting with 
Boeing representatives to discuss ways to improve the collaborative 
process, the submission of milestones, and Boeing's plan to correct 
Project 28 problems. Following this meeting, CBP and Boeing initiated a 
Change Control Board.[Footnote 17] In mid-September representatives 
from Boeing's SBInet team and its subcontractors continued to 
participate on this board and vote on key issues for solving Project 28 
problems. Although CBP participates on this committee as a non-voting 
member, a senior SBInet official said the government's experience on 
the Change Control Board had been positive thus far. For example, the 
official told us that the Change Control Board had helped improve 
coordination and integration with Boeing and for suggesting changes to 
the subcontractor companies working on Project 28. 

SBInet Tactical Infrastructure Deployment on Track but May Be 
Challenging and More Costly than Planned: 

Deploying SBInet's tactical infrastructure along the southwest border 
is on schedule, but meeting the SBInet program's goal to have 370 miles 
of pedestrian fence and 200 miles of vehicle barriers in place by 
December 31, 2008, may be challenging and more costly than planned. CBP 
set an intermediate goal to deploy 70 miles of new pedestrian fencing 
by the close of fiscal year 2007 and, having deployed 73 miles by this 
date, achieved its goal. Table 1 summarizes CBP's progress and plans 
for tactical infrastructure deployment. 

Table 1: Tactical Infrastructure Deployment Progress as of September 
30, 2007: 

Infrastructure type: Pedestrian fencing; 
Miles in place before SBInet: 78; 
Miles deployed through SBInet: 73; 
Total miles in place: 151; 
Target for 12/31/08: 370; 
Miles remaining to meet 12/31/08 target: 219. 

Infrastructure type: Vehicle barriers; 
Miles in place before SBInet: 57; 
Miles deployed through SBInet: 53; 
Total miles in place: 110; 
Target for 12/31/08: 200; 
Miles remaining to meet 12/31/08 target: 90. 

Source: GAO analysis of CBP data. 

[End of table] 

Costs for the 73 miles of fencing constructed in fiscal year 2007 
averaged $2.9 million per mile and ranged from $700,000 in San Luis, 
Arizona, to $4.8 million per mile in Sasabe, Arizona. CBP also deployed 
11 miles of vehicle barriers and, although CBP has not yet been able to 
provide us with the cost of these vehicle barriers, it projects that 
the average per mile cost for the first 75 miles of barriers it deploys 
will be $1.5 million. Figure 4 presents examples of fencing deployed. 

Figure 4: At Left, SBInet Fencing Being Deployed at Sasabe, Arizona; at 
Right, SBInet Fencing Deployed at Yuma, Arizona: 

This figure is two photos of SBInet fencing in Sasabe, Arizona, and 
SBInet fencing at Yuma, Arizona. 

[See PDF for image] 

Source: GAO. 

[End of figure] 

CBP estimates costs for the deployment of fencing in the future will be 
similar to those thus far. However, according to CBP officials, costs 
vary due to the type of terrain, materials used, land acquisition, who 
performs the construction, and the need to meet an expedited schedule. 
Although CBP estimates that the average cost of remaining fencing will 
be $2.8 million per mile, actual future costs may be higher due to 
factors such as the greater cost of commercial labor, higher than 
expected property acquisition costs, and unforeseen costs associated 
with working in remote areas. To minimize one of the many factors that 
add to cost, in the past DHS has used Border Patrol agents and DOD 
military personnel. However, CBP officials reported that they plan to 
use commercial labor for future infrastructure projects to meet their 
deadlines. Of the 73 miles of fencing completed to date, 31 were 
completed by DOD military personnel and 42 were constructed through 
commercial contracts. While the non-commercial projects cost an average 
of $1.2 million per mile,[Footnote 18] the commercial projects averaged 
over three times more--$4 million.[Footnote 19] According to CBP 
officials, CBP plans to utilize exclusively commercial contracts to 
complete the remaining 219 miles of fencing. If contract costs for 
deployment of remaining miles are consistent with those to deploy 
tactical infrastructure to date and average $4 million per mile, the 
total contract cost will be $890 million, considerably more than CBP's 
initial estimate of $650 million. 

Although deployment of tactical infrastructure is on schedule, CBP 
officials reported that meeting deadlines has been challenging because 
factors they will continue to face include conducting outreach 
necessary to address border community resistance, devoting time to 
identify and complete steps necessary to comply with environmental 
regulations,[Footnote 20] and addressing difficulties in acquiring 
rights to border lands. As of July 2007 CBP anticipated community 
resistance to deployment for 130 of its 370 miles of fencing. According 
to community leaders, communities resist fencing deployment for reasons 
including the adverse effect they anticipate it will have on cross- 
border commerce and community unity. In addition to consuming time, 
complying with environmental regulations, and acquiring rights to 
border land can also drive up costs. Although CBP officials state that 
they are proactively addressing these challenges, these factors will 
continue to pose a risk to meeting deployment targets. 

In an effort to identify low cost and easily deployable fencing 
solutions, CBP funded a project called Fence Lab. CBP plans to try to 
contain costs by utilizing the results of Fence Lab in the future. 
Fence Lab tested nine fence/barrier prototypes and evaluated them based 
on performance criteria such as their ability to disable a vehicle 
traveling at 40 miles per hour (see fig. 5), allowing animals to 
migrate through them, and their cost-effectiveness. Based on the 
results from the lab, SBInet has developed three types of vehicle 
barriers and one pedestrian fence that meet CBP operational 
requirements (see fig. 6). The pedestrian fence can be installed onto 
two of these vehicle barriers to create a hybrid pedestrian fence and 
vehicle barrier. CBP plans to include these solutions in a "toolkit" of 
approved fences and barriers,[Footnote 21] and plans to deploy 
solutions from this toolkit for all remaining vehicle barriers and for 
202 of 225 miles of remaining fencing. Further, CBP officials 
anticipate that deploying these solutions will reduce costs because 
cost-effectiveness was a criterion for their inclusion in the toolkit. 
SBInet officials also told us that widely deploying a select set of 
vehicle barriers and fences will lower costs through enabling it to 
make bulk purchases of construction and maintenance materials. 

Figure 5: Fence Lab crash testing conducted in May 2007: 

This is figure is a photo of a fence lab crash testing conducted in May 
2007. 

[See PDF for image] 

Source: CBP. 

[End of figure] 

Figure 6: Vehicle Barriers and Fencing Developed by Fence Lab That Meet 
Performance Requirements and Are Included in SBInet's "Toolbox" of 
Approved Fences and Barriers. 

This figure is a collection of photos. The photos are of the Jersey 
Vehicle Barrier, and Post on Rail Vehicle Barrier, which are Fence Lab 
solutions that can be turned into hybrid vehicle barriers and 
pedestrian fencing when a welded wire mesh fence is mounted on top of 
them. The Normandy vehicle barrier, also pictured, is also a Fence Lab 
solution. It cannot accommodate pedestrian fencing and will be used 
where no other vehicle barriers can be installed because of terrain or 
environmental concerns. 

[See PDF for image] 

Source: GAO analysis of CBP data; photos by CBP. 

[End of figure] 

SBInet Impact on Border Patrol's Workforce Needs and Operating 
Procedures Remains Unclear: 

While SBInet Program officials expect SBInet to greatly reduce the time 
spent by CBP enforcement personnel in performing detection 
activities,[Footnote 22] a full evaluation of SBInet's impact on the 
Border Patrol's workforce needs has not been completed. The Border 
Patrol currently uses a mix of resources including personnel, 
technology, infrastructure, and rapid response capabilities to 
incrementally achieve its strategic goal of establishing and 
maintaining operational control of the border.[Footnote 23] Each year 
through its Operational Requirements Based Budget Program (ORBBP), the 
Border Patrol sectors outline the amount of resources needed to achieve 
a desired level of border control.[Footnote 24] Border Patrol officials 
state this annual planning process allows the organization to measure 
the impact of each type of resource on the required number of Border 
Patrol agents. A full evaluation of SBInet's impact on the Border 
Patrol's workforce needs is not yet included in the ORBBP process; 
however, the Border Patrol plans to incorporate information from 
Project 28 a few months after it is operational. 

According to agency officials, CBP is on track to meet its hiring goal 
of 6,000 new Border Patrol agents by December 2008, but after SBInet is 
deployed, CBP officials expect the number of Border Patrol agents 
required to meet mission needs to change from current projections, 
although the direction and magnitude of the change is unknown. In 
addition, in June 2007, we expressed concern that deploying these new 
agents to the southwest sectors coupled with the planned transfer of 
more experienced agents to the northern border will create a 
disproportionate ratio of new agents to supervisors within those 
sectors--jeopardizing the supervisors' availability to acclimate new 
agents.[Footnote 25] Tucson Sector officials stated CBP is planning to 
hire from 650 to 700 supervisors next year. To accommodate the 
additional agents, the Border Patrol has taken initial steps to provide 
additional work space through constructing temporary and permanent 
facilities, at a projected cost of about $550 million from fiscal year 
2007 to 2011. 

The SBInet PMO expects SBInet to support day-to-day border enforcement 
operations; however, analysis of the impact of SBInet technology on the 
Border Patrol's operational procedures cannot be completed at this time 
because agents have not been able to fully use the system as intended. 
Leveraging technology is part of the National Border Patrol Strategy 
which identifies the objectives, tools, and initiatives the Border 
Patrol uses to maintain operational control of the borders. The Tucson 
sector, where Project 28 is being deployed, is developing a plan on how 
to integrate SBInet into its operating procedures. Border Patrol 
officials stated they intend to re-evaluate this strategy, as SBInet 
technology is identified and deployed, and as control of the border is 
achieved. 

According to agency officials, 22 trainers and 333 operators were 
trained on the current Project 28 system, but because of deployment 
delays and changes to the COP software, the SBInet training curriculum 
is to be revised by Boeing and the government. Training is continuing 
during this revision process with 24 operators being trained each week. 
According to CBP officials, Border Patrol agents are receiving "hands 
on" training during evening and weekend shifts at the COP workstations 
to familiarize themselves with the recent changes made to the Project 
28 system. However, training is to be stopped once a stabilized version 
of the COP can be used and both trainers and operators are to be 
retrained using the revised curriculum. Costs associated with revising 
the training material and retraining the agents are to be covered by 
Boeing as part of the Project 28 task order; however, the government 
may incur indirect costs associated with taking agents offline for 
retraining. 

SBI PMO Did Not Meet All of Its Staffing Goals and Has Not Yet 
Completed Long-Term Human Capital Planning: 

The SBI PMO tripled in size in fiscal year 2007 but fell short of its 
staffing goal of 270 employees.[Footnote 26] As of September 30, 2007, 
the SBI PMO had 247 employees onboard, with 113 government employees 
and 134 contractor support staff. SBI PMO officials also reported that 
as of October 19, 2007, they had 76 additional staff awaiting 
background investigations. In addition, these officials said that a 
Human Capital Management Plan has been drafted, but as of October 22, 
2007, the plan had not been approved. In February 2007, we reported 
that SBInet officials had planned to finalize a human capital strategy 
that was to include details on staffing and expertise needed for the 
program.[Footnote 27] At that time, SBI and SBInet officials expressed 
concern about difficulties in finding an adequate number of staff with 
the required expertise to support planned activities about staffing 
that shortfalls could limit government oversight efforts. Strategic 
human capital planning is a key component used to define the critical 
skills and competencies that will be needed to achieve programmatic 
goals and outlines ways the organization can fill gaps in knowledge, 
skills, and abilities.[Footnote 28] Until SBInet fully implements a 
comprehensive human capital strategy, it will continue to risk not 
having staff with the right skills and abilities to successfully 
execute the program. 

Concluding Observations: 

Project 28 and other early technology and infrastructure projects are 
the first steps on a long journey towards SBInet implementation that 
will ultimately require an investment of billions of taxpayer dollars. 
Some of these early projects have encountered unforeseen problems that 
could affect DHS's ability to meet projected completion dates, expected 
costs, and performance goals. These issues underscore the need for both 
DHS and Boeing, as the prime contractor, to continue to work 
cooperatively to correct the problems remaining with Project 28 and to 
ensure that the SBInet PMO has adequate staff to effectively plan and 
oversee future projects. These issues also underscore Congress's need 
to stay closely attuned to DHS's progress in the SBInet program to make 
sure that performance, schedule, and cost estimates are achieved and 
the nation's border security needs are fully addressed. 

This concludes my prepared testimony. I would be happy to respond to 
any questions that members of the Subcommittees may have. 

Contacts and Acknowledgments: 

For questions regarding this testimony, please call Richard M. Stana at 
(202) 512-8777 or StanaR@gao.gov. Other key contributors to this 
statement were Robert E. White, Assistant Director; Rachel Beers; Jason 
Berman; Katherine Davis; Jeanette Espínola; Taylor Matheson; and Sean 
Seales. 

[End of section] 

Appendix I: Scope and Methodology: 

To determine the progress that the Department of Homeland Security 
(DHS) has made in implementing the Secure Border Initiative (SBI) 
SBInet's technology deployment projects, we analyzed DHS documentation, 
including program schedules, project task orders, status reports, and 
expenditures. We also interviewed DHS and the U.S. Customs and Border 
Protection (CBP) headquarters and field officials, including 
representatives of the SBInet Program Management Office (PMO), Border 
Patrol, CBP Air and Marine, and the DHS Science and Technology 
Directorate, as well as SBInet contractors. We visited the Tucson 
Border Patrol sector--the site where SBInet technology deployment was 
underway at the time of our review. 

To determine the progress that Department of Homeland Security (DHS) 
has made in infrastructure project implementation, we analyzed DHS 
documentation, including schedules, contracts, status reports, and 
expenditures. In addition, we interviewed DHS and CBP headquarters and 
field officials, including representatives of the SBInet PMO, and 
Border Patrol. We also interviewed officials from the U.S. Army Corps 
of Engineers and the Department of the Interior. We visited the Tucson 
and Yuma, Arizona Border Patrol sectors--two sites where tactical 
infrastructure projects were underway at the time of our review. We did 
not review the justification for infrastructure project cost estimates 
or independently verify the source or validity of the cost information. 

To determine the extent to which CBP has determined the impact of 
SBInet technology and infrastructure on its workforce needs and 
operating procedures, we reviewed documentation of the agency's 
decision to hire an additional 6,000 agents and the progress hiring 
these agents. We also interviewed headquarters and field officials to 
track if and how CBP (1) is hiring and training its target number of 
personnel, (2) it is planning to train new agents on SBInet technology, 
and (3) it will incorporate the new system into its operational 
procedures, and any implementation challenges it reports facing in 
conducting this effort. 

To determine how the SBInet PMO defined its human capital goals and 
progress it has made in achieving these goals, we reviewed the office's 
documentation on its hiring efforts related to SBInet, related 
timelines, and compared this information with agency goals. We 
determined that the workforce data were sufficiently reliable for 
purposes of this report. We also interviewed SBI and SBInet officials 
to identify challenges in meeting the goals and steps taken by the 
agency to address those challenges. 

We performed our work from April 2007 through October 2007 in 
accordance with generally accepted government auditing standards. 

[End of section] 

Footnotes: 

[1] The SBInet PMO is part of the CBP SBI PMO. The SBInet PMO is 
responsible for overseeing all SBInet activities; for acquisition and 
implementation, including establishing and meeting program goals, 
objectives, and schedules; for overseeing contractor performance; and 
for coordinating among DHS agencies. 

[2] The U.S. Border Patrol has 20 sectors responsible for detecting, 
interdicting, and apprehending those who attempt illegal entry or 
smuggle people--including terrorists or contraband, including weapons 
of mass destruction--across U.S. borders between official ports of 
entry. 

[3] DHS defines effective control of U.S. borders as the ability to 
consistently: (1) detect illegal entries into the United States; (2) 
identify and classify these entries to determine the level of threat 
involved; (3) respond to these entries; and (4) bring events to a 
satisfactory law enforcement resolution. 

[4] At a port of entry location, CBP officers secure the flow of people 
and cargo into and out of the country, while facilitating legitimate 
travel and trade. 

[5] Boeing employs several companies as subcontractors on the SBInet 
project. These companies provide Boeing with a variety of services. For 
example, Boeing has used a subcontractor to install laptops into CBP 
vehicles, while it has used another to develop and deploy mobile sensor 
towers. 

[6] Commercial off-the-shelf is a term for software or hardware, 
generally technology or computer products, that are available for sale, 
lease, or license to the general public. 

[7] Project 37 consists of three phases, which when complete are to 
provide control over 37 miles of border in the Yuma sector. The first 
two phases focus on deployment of tactical infrastructure. The third 
phase will focus on technology systems. 

[8] The SBInet PMO contracted with Boeing Company to construct 32 miles 
of fencing in the BMGR. Deployment of this fencing has been completed, 
and the SBInet PMO plans to use USACE to contract for all remaining 
pedestrian fencing and vehicle barriers to be deployed through December 
31, 2008. 

[9] GAO, Missile Defense: Actions Needed to Improve Information for 
Supporting Key Decisions for Boost and Ascent Phase Elements, GAO-07- 
430 (Washington, D.C.: April 2007). 

[10] DHS and DOD appropriations bills for fiscal year 2008 that include 
additional funding for border security are awaiting final action in 
Congress. 

[11] CBP has established performance requirements for SBInet 
technology. These include requirements for (1) probability of 
detection; (2) correctly identifying threats; (3) apprehension; (4) 
system availability; and (5) false alarm rate. 

[12] Project 28 components include: 9 mobile radar/sensor towers; 4 
underground sensors, 70 small hand-held satellite phones for agents to 
communicate throughout the Tucson sector; and 50 CBP agent vehicles 
with secure-mounted laptop computers and communications capabilities. 

[13] The SBInet PMO plans to deploy SBInet projects in three phases. 
Phase one projects are scheduled between April 2007 and December 2008; 
phase two projects are scheduled between May 2008 and early 2010; and 
phase three projects are scheduled to begin in May 2009. 

[14] The two projects are Project 37 BMGR phase three technology 
deployment, and the Texas Mobile System, technology deployment for 
about 70 miles of border in the El Paso sector. 

[15] A firm-fixed-price contract provides for a price that is not 
subject to any adjustment on the basis of the contractor's cost 
experience in performing the contract. This contract type places 
maximum risk upon the contractor and full responsibility for all costs 
and resulting profit or loss. 

[16] In April 2007, CBP and Boeing reached an agreement to modify the 
terms of the Project 28 contract, increasing it to about $20.66 
million. CBP modified the contract to add several project design 
requirements that the existing task order did not address. 

[17] The Change Control Board is a voting body that represents the 
interests of program and project management by ensuring that a 
structured process is used to consider proposed changes and incorporate 
them into a specified release of a product. 

[18] CBP's estimates of non-commercial fencing projects do not include 
labor costs associated with using government personnel. 

[19] According to the Congressional Research Service (CRS), DHS 
predicts that the San Diego fence will have a total cost of $127 
million for its 14-mile length when it is completed--roughly $9 million 
a mile. Construction of the first 9.5 miles of fencing cost $31 
million, or roughly $3 million a mile, while construction of the last 
4.5 miles of fencing is projected to cost $96 million, or roughly $21 
million a mile. DHS is proposing to hire private contractors to 
expedite the construction of the remaining 4.5 miles of fencing; 
according to CRS this fact, and the complexity of the construction, may 
account for part of the difference in cost. 

[20] Although the REAL ID Act of 2005 gives DHS the authority to waive 
all legal requirements necessary to ensure expeditious construction of 
certain specified barriers and roads along the southern border (Pub. L. 
No. 109-13, div. B, § 102, 119 Stat. 302, 306), DHS officials told us 
that they only plan to use this authority after they have pursued 
alternatives. 

[21] As the SBInet PMO uses testing and evaluation to identify tactical 
infrastructure and technology components that effectively secure the 
border, the SBInet PMO is approving them for inclusion in a master 
"toolkit" of approved solutions. In addition to vehicle barriers and 
fences, the toolkit will include technology components such as radars 
and satellite phones as well as a list of approved vendors. In the 
future, the SBInet PMO plans to choose among its toolkit components to 
craft border security solutions. 

[22] SBI PMO expects SBInet to provide the capability to predict, 
deter, detect, identify, classify, track, respond to, and resolve 
border incursion; and the operational enhancements of SBInet will 
provide efficiencies by reducing the time agents spend performing 
detection and characterization activities. 

[23] CBP defines operational control as the ability to detect, respond, 
and interdict border penetrations in areas deemed as high priority for 
threat potential or other national security objectives. 

[24] The Border Patrol defines five levels of border security ranging 
from "controlled"--the highest sustainable level of control to "remote/ 
low activity"--the lowest level of control. 

[25] GAO, Border Patrol Costs and Challenges Related to Training New 
Agents, GAO-07-997T (Washington, D.C.: June 2007). 

[26] GAO, SBInet Expenditure Plan Needs to Better Support Oversight and 
Accountability, GAO-07-309 (Washington, D.C.: February 2007). 

[27] GAO-07-309. 

[28] See GAO, Human Capital: Key Principles for Effective Strategic 
Workforce Planning, GAO-04-39 (Washington, D.C.: December 2003) and 
GAO, Framework for Accessing the Acquisition Function at Federal 
Agencies GAO-05-218G (Washington, D.C.: September 2005).

GAO's Mission: 

The Government Accountability Office, the audit, evaluation, and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. Government Accountability Office: 
441 G Street NW, Room LM: 
Washington, DC 20548: 

To order by Phone: 
Voice: (202) 512-6000: 
TDD: (202) 512-2537: 
Fax: (202) 512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Gloria Jarmon, Managing Director, JarmonG@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, DC 20548: 

Public Affairs: 

Susan Becker, Acting Manager, BeckerS@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, DC 20548: