This is the accessible text file for GAO report number GAO-07-278 
entitled 'Homeland Security: Planned Expenditures for U.S. Visitor and 
Immigrant Status Program Need to Be Adequately Defined and Justified' 
which was released on February 14, 2007. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Report to Congressional Committees: 

February 2007: 

Homeland Security: 

Planned Expenditures for U.S. Visitor and Immigrant Status Program Need 
to Be Adequately Defined and Justified: 

GAO-07-278: 

GAO Highlights: 

Highlights of GAO-07-278, a report to congressional committees 

Why GAO Did This Study: 

The Department of Homeland Security (DHS) has established a program—the 
U.S. Visitor and Immigrant Status Indicator Technology (US-VISIT)—to 
collect, maintain, and share information, including biometric 
identifiers, on selected foreign nationals who travel to the United 
States. By congressional mandate, DHS is to develop and submit for 
approval an expenditure plan for US-VISIT that satisfies certain 
conditions, including being reviewed by GAO. GAO was required to 
determine if the plan satisfied these conditions, follow up on 
recommendations related to the expenditure plan, and provide any other 
observations. To address the mandate, GAO assessed plans against 
federal guidelines and industry standards and interviewed the 
appropriate DHS officials. 

What GAO Found: 

The US-VISIT expenditure plan, related program documentation, and 
program officials’ statements satisfied or partially satisfied each of 
the legislative conditions required by the Department of Homeland 
Security Appropriations Act, 2006. For example, they satisfied the 
condition that the agency provide certification that an independent 
verification and validation agent is currently under contract for the 
program and partially satisfied the condition that US-VISIT comply with 
DHS’s enterprise architecture. 

DHS also completed or partially completed each of GAO’s prior 
expenditure plan-related recommendations. For example, the department 
completed recommendations that it provide an expenditure plan to the 
Senate and House Appropriations Subcommittees on Homeland Security 
before obligating restricted fiscal year funds and that it identify and 
disclose management reserve funding in those plans. However, DHS only 
partially completed recommendations that the plan fully disclose how 
the US-VISIT acquisition is being managed and that it fully disclose US-
VISIT’s cost, schedule, capabilities, and benefits. 

GAO identified several additional areas of concern. First, DHS has not 
adequately defined and justified its proposed fiscal year 2006 
expenditures for pilot and demonstration projects aimed at collecting 
information on persons exiting the country at air, sea, and land 
borders. Second, DHS has continued to invest in US-VISIT without a 
clearly defined operational context that includes explicit 
relationships with related border security and immigration enforcement 
initiatives. Third, US-VISIT program management costs have risen 
sharply, while costs for development have decreased, without any 
accompanying explanation of the reasons. 

Overall, the US-VISIT fiscal year 2006 expenditure plan and other 
available program documentation do not provide a sufficient basis for 
Congress to exercise effective oversight of the program and to hold the 
department accountable for results. For proper oversight and 
accountability to occur, it is essential that DHS increase US-VISIT 
program transparency and accountability by justifying planned 
investments on the basis of adequate definition and disclosure of 
planned expenditures, timelines, capabilities, and benefits, and by 
effectively measuring and reporting progress against each. It is also 
essential for DHS to fully satisfy each of the conditions legislated by 
Congress, because doing so will minimize the program’s exposure to 
risk. 

What GAO Recommends: 

GAO is recommending that the Secretary of DHS direct the US-VISIT 
program director to increase program transparency and accountability by 
defining and justifying planned investments and effectively measuring 
and reporting on their progress and to determine and mitigate risks 
associated with not fully satisfying legislative conditions and report 
these risks to DHS senior leadership and to the appropriate 
congressional committees. DHS agreed with GAO’s findings and 
recommendations. 

[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-07-278]. 

To view the full product, including the scope and methodology, click on 
the link above. For more information, contact Randolph C. Hite at (202) 
512-3439 or hiter@gao.gov. 

[End of section] 

Contents: 

Letter: 

Compliance with Legislative Conditions: 

Status of Open Recommendations: 

Observations on the Expenditure Plan and Management of US-VISIT: 

Conclusions: 

Recommendations for Executive Action: 

Agency Comments: 

Appendixes: 

Appendix I: Briefing to the Staffs of the Subcommittees on Homeland 
Security, Senate and House Committees on Appropriations: 

Appendix II: Comments from the Department of Homeland Security: 

Appendix III: GAO Contact and Staff Acknowledgments: 

Abbreviations: 

a-ID: automated identification: 

ADIS: Arrival Departure Information System: 

AIDMS: Automated Identification Management System: 

APIS: Advance Passenger Information System: 

CBP: Customs and Border Protection: 

CLAIMS 3: Computer Linked Application Information Management System 3: 

CMMI: Capability Maturity Model Integration: 

DHS: Department of Homeland Security: 

EA: enterprise architecture: 

EVM: earned value management: 

FEA: Federal Enterprise Architecture: 

FFMS: Federal Financial Management System: 

IAFIS: Integrated Automated Fingerprint Identification System: 

IBIS: Interagency Border Inspection System: 

IDENT: Automated Biometric Identification System: 

IRB: Investment Review Board: 

OMB: Office of Management and Budget: 

POE: port of entry: 

RFID: radio frequency identification: 

SEI: Software Engineering Institute: 

SEVIS: Student and Exchange Visitor Information System: 

TECS: Treasury Enforcement Communications System: 

US-VISIT: U.S. Visitor and Immigrant Status Indicator Technology: 

February 14, 2007: 

The Honorable Robert C. Byrd: 
Chairman: 
The Honorable Thad Cochran: 
Ranking Minority Member: 
Subcommittee on Homeland Security: 
Committee on Appropriations: 
United States Senate: 

The Honorable David E. Price: 
Chairman: 
The Honorable Harold Rogers: 
Ranking Minority Member: 
Subcommittee on Homeland Security: 
Committee on Appropriations: 
House of Representatives: 

The Department of Homeland Security (DHS) submitted to Congress in 
August 2006 its fiscal year 2006 expenditure plan for the U.S. Visitor 
and Immigrant Status Indicator Technology (US-VISIT) program in 
compliance with the Department of Homeland Security Appropriations Act, 
2006.[Footnote 1] US-VISIT is a governmentwide program to collect, 
maintain, and share information on foreign nationals who enter and exit 
the United States. The program's goals are to enhance the security of 
U.S. citizens and visitors, facilitate legitimate trade and travel, 
ensure the integrity of the U.S. immigration system, and protect the 
privacy of visitors to the United States. As required by the 
appropriations act, we reviewed US-VISIT's fiscal year 2006 expenditure 
plan. Our objectives were to (1) determine whether the expenditure plan 
satisfies legislative conditions specified in the appropriations act, 
(2) determine the status of our open recommendations pertaining to the 
US-VISIT expenditure plan, and (3) provide observations about the 
expenditure plan and DHS's management of US-VISIT. 

On November 13, 2006, we briefed the staffs of the Senate and House 
Appropriations Subcommittees on Homeland Security on the results of our 
review. This report transmits these results. The full briefing, 
including our scope and methodology, is reprinted in appendix I. 

Compliance with Legislative Conditions: 

The US-VISIT expenditure plan, including related program documentation 
and program officials' statements, satisfies or partially satisfies 
each of the legislative conditions. The expenditure plan partially 
satisfies the legislative conditions that it (1) meet the capital 
planning and investment control review requirements established by the 
Office of Management and Budget (OMB), including OMB Circular A-11, 
part 7; (2) comply with DHS's enterprise architecture; and (3) comply 
with federal acquisition rules, requirements, guidelines, and systems 
acquisition management practices. In addition, the plan and related 
documentation satisfy the legislative conditions that (1) DHS certify 
that an independent verification and validation agent is currently 
under contract for the program; (2) the plan be reviewed and approved 
by DHS's Investment Review Board, the Secretary of Homeland Security, 
and OMB; and (3) the plan be reviewed by GAO. 

Status of Open Recommendations: 

DHS has completed or has partially completed all of the remaining 
recommendations contained in our prior reports on expenditure plans. 
Each recommendation, along with its current status, is summarized in 
this section. 

* Ensure that future expenditure plans are provided to DHS's Senate and 
House Appropriations Subcommittees on Homeland Security in advance of 
US-VISIT funds being obligated. 

DHS has completed this recommendation by providing the fiscal year 2006 
plan to the Senate and House Appropriations Subcommittees on Homeland 
Security on August 10, 2006. 

* Ensure that all future US-VISIT expenditure plans identify and 
disclose management reserve funding. 

DHS has completed this recommendation by specifying management reserve 
funding of $13 million in the fiscal year 2006 plan. 

* Ensure that future expenditure plans fully disclose how the US-VISIT 
acquisition is being managed. 

The department has partially completed this recommendation. The fiscal 
year 2006 expenditure plan describes a range of key acquisition 
management activities and control areas, such as configuration 
management and testing. However, the plan's descriptions do not fully 
disclose challenges that the US-VISIT program faces in how it is 
managing acquisition activities. 

* Develop a plan, including explicit tasks and milestones, for 
implementing all of our open recommendations and report on this 
progress, including reasons for delays, in all future US-VISIT 
expenditure plans. 

The department has partially completed this recommendation. The fiscal 
year 2006 expenditure plan lists most of our recommendations and 
describes DHS efforts to address them. However, the plan does not 
provide future tasks or milestones for more than half of our 
recommendations and is missing four recommendations altogether. 

* Ensure that future expenditure plans fully disclose US-VISIT system 
capabilities, schedule, cost, and benefits to be delivered. 

The department has partially completed this recommendation. The fiscal 
year 2006 expenditure plan discloses some system capabilities, 
schedule, cost, and benefits. However, capability information is 
largely described as activities to be performed, rather than 
capabilities to be delivered. Also, in many cases, cost information is 
not provided at a sufficient level of detail for oversight. 
Furthermore, the plan does not explicitly link performance measures to 
program benefits. Finally, the plan does not include performance 
measures related to exit processing, even though the plan's stated 
goals and cited benefits include immigration system integrity, which 
requires an effective exit processing capability. As a result, the plan 
does not provide sufficient information on capabilities, schedule, 
cost, and benefits to fully support congressional oversight and promote 
department accountability. 

* Fully and explicitly disclose in all future expenditure plans how 
well DHS is progressing against the commitments that it made in prior 
expenditure plans. 

The department has partially completed this recommendation. The fiscal 
year 2006 expenditure plan describes progress against some, but not 
all, commitments in the fiscal year 2005 expenditure plan. As a result, 
the plan does not provide sufficient disclosure of program performance 
to support congressional oversight and promote department 
accountability. 

Observations on the Expenditure Plan and Management of US-VISIT: 

Our observations raise concerns about the lack of definition and 
justification for planned investments in several aspects of the US- 
VISIT program. An overview of each observation follows. 

* Observation 1: DHS has not adequately defined and justified its 
proposed fiscal year 2006 expenditures in exit pilots and demonstration 
projects. Federal legislation requires that DHS develop the capability 
to collect information on persons exiting the country at 
borders.[Footnote 2] Having a cost-effective exit capability is 
essential for US-VISIT to accomplish its stated strategic goals, such 
as enhancing the security of U.S. citizens and visitors and ensuring 
the integrity of the immigration system. Over the last 3 years, DHS has 
devoted considerable time and resources to establishing an operational 
exit capability at land, air, and sea ports of entry through several 
pilot and demonstration efforts. However, these efforts have raised 
concerns and highlighted limitations, particularly with respect to land 
ports of entry. For example, successful reading of traveler's 
information occurred at below-acceptable rates and was based on 
technologies that are not fully reliable. Notwithstanding these issues, 
the fiscal year 2006 expenditure plan proposes investing another $33.5 
million to continue operation of air and sea exit pilots and allocates 
carryover of $21.5 million in fiscal year 2005 funds for land exit 
demonstration activities without adequately justifying continuing these 
investments. As a result, we concluded that it was unclear whether 
these investments will produce value that is commensurate with costs 
and risks. In its comments on a draft of this report, DHS stated that 
it has since terminated the land exit demonstration. 

* Observation 2: DHS continues to invest in US-VISIT without a clearly 
defined operational context that includes explicit relationships with 
related border security and immigration enforcement initiatives. In 
2003, we recommended that DHS clarify the operational context[Footnote 
3] in which US-VISIT is to operate, including, among other things, 
related initiatives.[Footnote 4] However, DHS continues to pursue US- 
VISIT without having this operational context. Exacerbating this 
situation is that DHS has recently launched other major programs, 
including the Secure Border and Western Hemisphere Travel Initiatives, 
but it has not adequately defined the relationships between US-VISIT 
and each of these programs. Clearly defining the dependencies among US- 
VISIT and related programs is important because there is commonality 
among the strategic goals of these programs and the operational 
environments in which they are to function. Despite these dependencies, 
neither the fiscal year 2006 expenditure plan nor any other available 
program documentation addresses these relationships or how they will be 
managed. As a result, we concluded that DHS runs the risk of defining 
and implementing the US-VISIT strategic solution in a way that does not 
optimize departmentwide performance and results. 

* Observation 3: DHS has not adequately justified increases in, and 
disclosed the scope and nature of, program management-related fiscal 
year 2006 expenditures. 

US-VISIT's planned investment in program management-related activities 
has risen steadily over the last 4 years, while planned investment in 
the development of new program capabilities has correspondingly 
declined. The fiscal year 2006 expenditure plan proposes spending $126 
million on program management-related costs, or $1.35 on program 
management-related activities for each dollar spent on developing new 
US-VISIT capabilities. The expenditure plan does not explain the 
reasons for this recent growth or otherwise justify the sizeable 
proposed investment in program management and operations on the basis 
of measurable expected value. Moreover, the plan does not adequately 
describe the range of program management and operations activities. As 
a result, we concluded that it was unclear whether the planned 
investment in program management-related activities represents the best 
use of limited resources. In its comments on a draft of this report, 
DHS stated that it has since provided a revised version of the 
expenditure plan that clarifies program management-related spending to 
its appropriations committees. 

Conclusions: 

The legislatively mandated expenditure plan requirement for US-VISIT is 
a congressional oversight mechanism aimed at ensuring that planned 
expenditures are justified, performance against plans is measured, and 
accountability for results is established. To the extent that the US- 
VISIT expenditure plan and related program documentation do not 
adequately disclose program information on what is to be accomplished 
by when and what it will cost to do so, Congress' ability to make 
informed US-VISIT investment decisions on the basis of justified 
expenditures and measured performance is restricted. 

The fiscal year 2006 expenditure plan, combined with other available 
program documentation and program officials' statements, does not 
provide sufficient justification for all planned US-VISIT expenditures, 
nor does it permit progress against program commitments to be 
adequately measured and disclosed. Although three of the six stated 
legislative conditions for the expenditure plan are fully satisfied, 
the other three have gaps that, while they are intended to be addressed 
in the future, limit DHS's ability to manage the program today. 
Moreover, four of our six prior recommendations aimed at fully defining 
and disclosing program commitments and managing for results have been 
only partially implemented and completed. 

Compounding these issues is the lack of definition and disclosure of 
key aspects of US-VISIT's future. In particular, the program's long- 
term strategy and vision have remained unknown because DHS has yet to 
approve the US-VISIT strategic plan. Equally unknown at this time is a 
viable exit solution and the relationships among US-VISIT and other 
recent border security and immigration enforcement programs, such as 
the Secure Border Initiative. The absence of definition and clarity in 
these areas is significant because US-VISIT's ability to meet its 
strategic goals depends in large part on these key aspects. 

Notwithstanding this lack of definition, disclosure, and thus certainty 
about the justification for planned expenditures and the ability to 
measure performance and results, US-VISIT program management costs have 
risen sharply without any accompanying explanation for the reasons. 
Compounding these problems is that critical areas of program 
management, such as acquisition management, are also largely undefined 
in terms of when and at what costs improvements can be expected. 

Overall, the US-VISIT fiscal year 2006 expenditure plan and other 
available program documentation do not provide a sufficient basis for 
Congress to exercise effective oversight of the program and to hold DHS 
accountable for results. For proper oversight and accountability to 
occur, it is essential that DHS increase US-VISIT program transparency 
and accountability by (1) justifying planned investments on the basis 
of adequate definition and disclosure of planned expenditures, 
timelines, capabilities, and benefits and (2) effectively measuring and 
reporting progress against each investment. 

Recommendations for Executive Action: 

To ensure that US-VISIT is better defined and justified and that our 
prior recommendations aimed at instilling greater results-oriented 
performance management and accountability in the program are fully 
implemented, we recommend that the Secretary of DHS direct the US-VISIT 
Acting Program Director to take the following four actions: 

* Report regularly to the Secretary and to the DHS authorization and 
appropriations committees on the range of program risks associated with 
not having fully satisfied all expenditure plan legislative conditions, 
reasons why they were not satisfied, and steps being taken to mitigate 
these risks. 

* Limit planned expenditures for exit pilots and demonstration projects 
until such investments are economically justified and until each 
investment has a well-defined evaluation plan. The projects should be 
justified on the basis of costs, benefits, and risks, and the 
evaluation plans should define what is to be achieved and should 
include a plan of action and milestones and measures for demonstrating 
achievement of pilot and project goals and desired outcomes. 

* Work with the DHS Enterprise Architecture Board to identify and 
mitigate program risks associated with investing in new US-VISIT 
capabilities in the absence of a DHS-wide operational and technological 
context for the program. These risks should reflect the absence of 
fully defined relationships and dependencies with related border 
security and immigration enforcement programs. 

* Limit planned expenditures for program management-related activities 
until such investments are economically justified and have well-defined 
plans detailing what is to be achieved, include a plan of action and 
milestones, and should include measures for demonstrating progress and 
achievement of desired outcomes. The investments should be justified on 
the basis of costs, benefits, and risks. 

Agency Comments: 

In written comments on a draft of this report, signed by the Director, 
Departmental GAO/IG Liaison Office (reprinted in app. II), DHS agreed 
with our findings and recommendations and described actions taken or 
under way to address them. DHS also provided technical comments, which 
we have incorporated into our report as appropriate. 

We are sending copies of this report to the Chairmen and Ranking 
Minority Members of other Senate and House committees and subcommittees 
that have authorization and oversight responsibilities for homeland 
security. We are also sending copies to the Secretary of Homeland 
Security, Secretary of State, and the Director of OMB. Copies of this 
report will also be available at no charge on our Web site at 
[Hyperlink, http://www.gao.gov]. 

If you or your staffs have any questions on matters discussed in this 
report, please contact me at (202) 512-3439 or at hiter@gao.gov. 
Contact points for our Offices of Congressional Relations and Public 
Affairs may be found on the last page of this report. GAO staff who 
have made significant contributions to this report are listed in 
appendix III. 

Signed by: 

Randolph C. Hite: 
Director, Information Technology Architecture and Systems Issues: 

[End of section] 

Appendix I: Briefing to the Staffs of the Subcommittees on Homeland 
Security, Senate and House Committees on Appropriations: 

Homeland Security: Planned Expenditures for U.S. Visitor and Immigrant 
Status Program Need to Be Adequately Defined and Justified: 

Briefing to the Staffs of the Subcommittees on Homeland Security Senate 
and House Committees on Appropriations: 

November 13, 2006: 

Briefing Overview: 

Introduction: 
Objectives: 
Results in Brief: 
Background: 
Results: 
* Legislative Conditions: 
* Status of Open Recommendations: 
* Observations: 
Conclusions: 

Recommendations for Executive Action: 

Attachment 1. Scope and Methodology: 

Attachment 2. Related Products List: 

Attachment 3. Detailed Description of US-VISIT Program Office: 

Attachment 4. Detailed Description of Increments and Component Systems: 

Introduction: 

The U.S. Visitor and Immigrant Status Indicator Technology (US-VISIT) 
program of the Department of Homeland Security (DHS) is a 
governmentwide program to collect, maintain, and share information on 
foreign nationals. The goals of US-VISIT are to: 

enhance the security of U.S. citizens and visitors,  

facilitate legitimate travel and trade, 

ensure the integrity of the U.S. immigration system, and: 

protect the privacy of our visitors. 

The US-VISIT program involves the interdependent application of people, 
processes, technology, and facilities. 

[See PDF for image] 

Sources: GAO analysis of US-VISIT data, Nova Development Corp. 
(clipart). 

[End of figure] 

The Department of Homeland Security Appropriations Act, 2006[Footnote 
5], states that DHS may not obligate $159,658,000 of the $340 
million[Footnote 6] appropriated for the US-VISIT project until the 
Senate and House Committees on Appropriations receive and approve a 
plan for expenditure that: 

meets the capital planning and investment control review requirements 
established by the Office of Management and Budget (OMB), including 
Circular A-11, part 7[Footnote 7]; 

complies with DHS's enterprise architecture; 

complies with the acquisition rules, requirements, guidelines, and 
systems acquisition management practices of the federal government; 

includes a certification by the DHS Chief Information Officer that an 
independent verification and validation agent is currently under 
contract for the project; 

is reviewed and approved by the DHS Investment Review Board (IRB), the 
Secretary of Homeland Security, and OMB; and: 

is reviewed by GAO. 

On August 10, 2006, DHS submitted its fiscal year 2006 expenditure plan 
for $336.6 million to the House and Senate Appropriations Subcommittees 
on Homeland Security. 

Objectives: 

Our objectives were to: 

1. determine whether the US-VISIT fiscal year 2006 expenditure plan 
satisfies the legislative conditions, 

2. determine the status of the six open recommendations pertaining to 
the US-VISIT expenditure plan,[Footnote 8] and: 

3. provide observations about the expenditure plan and management of 
the program. 

We conducted our work at US-VISIT offices in Arlington, Virginia from 
August 2006 through November 2006 in accordance with generally accepted 
government auditing standards. Details of our scope and methodology are 
described in attachment 1. 

Results in Brief: Objective 1 Legislative Conditions: 

Fiscal Year 2006 US-VISIT Expenditure Plan's Satisfaction of 
Legislative Conditions: 

Legislative conditions: Meets the capital planning and investment 
control review requirements established by OMB, including OMB A-11, 
part 7; 
Partially satisfies[A]: X; 
Satisfies[B]: Empty]. 

Legislative conditions: Complies with the DHS enterprise architecture; 
Partially satisfies[A]: X; 
Satisfies[B]: [Empty]. 

Legislative conditions: Complies with the acquisition rules, 
requirements, guidelines, and systems acquisition management practices 
of the federal government; 
Partially satisfies[A]: X; 
Satisfies[B]: [Empty]. 

Legislative conditions: Includes a certification by the DHS Chief 
Information Officer that an independent verification and validation 
agent is currently under contract for the program; 
Partially satisfies[A]: [Empty]; 
Satisfies[B]: X. 

Legislative conditions: Is reviewed and approved by the DHS IRB, the 
Secretary of Homeland Security, and OMB; 
Partially satisfies[A]: [Empty]; 
Satisfies[B]: X. 

Legislative conditions: Is reviewed by GAO; 
Partially satisfies[A]: [Empty]; 
Satisfies[B]: X. 

Source: GAO. 

[A] Satisfies or provides for satisfying some, but not all, key aspects 
of the condition that we reviewed. 

[B] Satisfies or provides for satisfying every aspect of the condition 
that we reviewed. 

[End of table] 

Results in Brief: Objective 2 Open Recommendations: 

Status of Actions to Implement Open Recommendations Specific to the 
Expenditure Plan: 

Partially; completed. 

Open recommendations: Ensure that future expenditure plans are provided 
to the department's House and Senate Appropriations Subcommittees on 
Homeland Security in advance of US-VISIT funds being obligated; 
Partially complete[C]: [Empty]; 
Complete[D]: x. 

Open recommendations: Ensure that all future US-VISIT expenditure plans 
identify and disclose management reserve funding; 
Partially complete[C]: [Empty]; 
Complete[D]: x. 

Open recommendations: Ensure that future expenditure plans fully 
disclose how the US-VISIT acquisition is being managed; 
Partially complete[C]: X; 
Complete[D]: [Empty]. 

Develop a plan for implementing all our open recommendations and report 
on this progress, including reasons for delays, in all future US-VISIT 
expenditure plans; 
Partially complete[C]: X; 
Complete[D]: [Empty]. 

Open recommendations: Ensure that future expenditure plans fully 
disclose US-VISIT system capabilities, schedule, cost, and benefits to 
be delivered; 
Partially complete[C]: X; 
Complete[D]: [Empty]. 

Fully and explicitly disclose in all future expenditure plans how well 
DHS is progressing against the commitments that it made in prior 
expenditure plans; 
Partially complete[C]: X; 
Complete[D]: [Empty]. 

Source: GAO. 

[C] A recommendation is partially complete when documentation indicates 
that some, but not all, actions needed to implement it have been taken. 

[D] A recommendation is complete when documentation demonstrates that 
it had been fully addressed. 

[End of table] 

Results in Brief: Objective 3: 

Observation Summary: 

DHS has not adequately defined and justified its proposed fiscal year 
2006 expenditures in exit pilots and demonstration projects. Without 
adequately defining and justifying exit pilot investments, it is 
unclear that they will produce value commensurate with costs and risks. 

DHS has yet to define and justify US-VISIT within an enterprisewide 
operational and technological context that includes explicitly defined 
linkages and dependencies with related border security and immigration 
enforcement initiatives. Without such context, US-VISIT runs the risk 
of being defined and implemented in a way that suboptimizes DHS-wide 
performance and results. 

DHS has not adequately disclosed and justified its investment in and 
the scope and nature of US-VISIT program management-related fiscal year 
2006 expenditures. Without disclosing and justifying its proposed 
investment in program management-related efforts, it is unclear whether 
such a large increase in spending represents the best use of limited 
resources. 

Results in Brief: Recommendations and Agency Comments: 

To ensure that US-VISIT is better defined and justified, we made 
recommendations to the DHS Secretary aimed at increasing satisfaction 
of the legislative conditions, limiting investment in exit pilots and 
projects until certain activities have been completed, reducing risks 
associated with the lack of operational and technological context for 
the program and limiting investment in program management-related 
activities until certain steps have been taken. 

In commenting on a draft of this briefing, US-VISIT program officials 
including the Acting Director, agreed with our findings, and said that 
our conclusions and recommendations were fair. 

Background US-VISIT Overview: 

The US-VISIT program is a multi-agency effort intended to enhance the 
security of U.S. citizens and visitors, facilitate legitimate travel 
and trade, ensure the integrity of the U.S. immigration system, and 
protect the privacy of our visitors. US-VISIT is to accomplish these 
things by: 

collecting, maintaining, and sharing information on certain foreign 
nationals who enter and exit the United States; 

identifying foreign nationals who (1) have overstayed or violated the 
terms of their admission; (2) can receive, extend, or adjust their 
immigration status; or (3) should be apprehended or detained by law 
enforcement officials; 

detecting fraudulent travel documents, verifying traveler identity, and 
determining traveler admissibility through the use of biometrics; and: 

facilitating information sharing and coordination within the 
immigration and border management community. 

US-VISIT Program Office: 

Organizational Structure and Functional Responsibilities[Footnote 9] 

[See PDF for image] 

Source: US-VISIT. 

[End of figure] 

Background: 

Acquisition Strategy: 

DHS plans to deliver US-VISIT capability in four major increments. 

Increments 1 through 3 are interim, or temporary, solutions that focus 
on building interfaces among existing (legacy) systems; enhancing the 
capabilities of these systems; deploying these systems to air, sea, and 
land ports of entry (POEs); and modifying POE facilities. These 
increments largely involve placing task orders against existing 
contracts. 

Increment 4 is to be a series of incremental releases, or mission 
capability enhancements, that are to deliver long-term strategic 
capabilities for meeting program goals. 

In May 2004, DHS awarded an indefinite-delivery/indefinite- 
quantity[Footnote 10] prime contract to Accenture and its partners for, 
among other things, delivering Increment 4.[FOOTNOTE 11]

Background: 

Description and Status of Increments: 

Increment 1: 

Increment 1 was intended to establish entry and exit capabilities at 
air and sea POEs by December 31, 2003. 

Increment 1 air and sea entry capabilities were deployed on January 5, 
2004 at 115 airports and 14 seaports for individuals requiring 
nonimmigrant visas to enter the United States.[Footnote 12] These 
capabilities include the collection and matching of biographic 
information, biometric data (two digital index finger scans) and a 
digital photograph for selected foreign nationals. 

An Increment 1 air and sea exit device for collecting biometric data 
was deployed to one airport and one seaport in January 2004 on a pilot 
basis. Subsequently, this pilot was expanded to 12 airports and 2 
seaports and several exit alternatives, including: 

Enhanced kiosk - A self-service device (includes a multi-lingual, touch-
screen interface, document scanner, finger scanner, digital camera, and 
receipt printer) that captures a digital photograph and fingerprint and 
prints out an encoded receipt. 

Mobile device - A hand-held device operated by a workstation 
attendant[Footnote 13] (includes a document scanner, finger scanner, 
digital camera, and receipt printer) that captures a digital photograph 
and fingerprint. 

Validator - A hand-held device operated by a workstation attendant that 
captures a digital photograph and fingerprint and then matches the 
captured photograph and fingerprint to the ones originally captured via 
the kiosk and encoded in the receipt. 

This pilot was completed in May 2005; it established the technical 
feasibility of a biometric exit solution at air and sea POEs. However, 
it identified issues that limited the operational effectiveness of the 
solution. 

The fiscal year 2006 expenditure plan allocated $33.5 million for air 
and sea exit pilots. According to program officials, they are now 
developing a plan for deploying a comprehensive, affordable exit 
solution; no time frame has been established for this plan being 
approved. Meanwhile, US-VISIT plans to conduct a second pilot phase at 
air and sea POEs that will involve multiple operational scenarios, such 
as: 

* repositioning the kiosks, 

* integrating biometric exit into airport check-in processes, 

* integrating biometric exit into existing airline processes, 

integrating biometric exit into Transportation Security Administration 
screening checkpoints, and: 

* enhancing the use of Immigration and Customs Enforcement programs 
intended for enforcement, such as screening of targeted flights at 
selected airports. 

Increment 2: 

Increment 2 was originally to extend US-VISIT entry and exit 
capabilities to the 50 busiest land POEs by December 31, 2004. 
Subsequently, the increment was divided into three parts-2A, 213, and 
2C. 

* Increment 2A was to establish the entry capability at land, sea, and 
air POEs to biometrically authenticate machine-readable visas and other 
travel and entry documents issued by Department of State (State) and 
DHS to foreign nationals by October 26, 2005.[Footnote 14] It was also 
to enable DHS and State to read biometrically enabled passports from 
visa waiver countries (e-Passports) by October 26, 2006.[Footnote 15] 

The capability to authenticate machine-readable visas and other travel 
and entry documents issued by State and DHS was deployed to all POEs on 
October 23, 2005. The capability to read e-Passports was deployed to 24 
POEs on October 26, 2006, and is to be deployed to an additional 9 POEs 
by November 14, 2006. According to DHS, these 33 POEs account for about 
97 percent of all travelers who enter the country with e-Passports. 
Remaining POEs are to receive equipment over the subsequent months. The 
fiscal year 2006 expenditure plan allocates $15.4 million to Increment 
2A. 

* Increment 213 was to include extending the Increment 1 entry solution 
to the 50 busiest land POEs, including redesigning the process for 
issuing a handwritten Form I-94[Footnote 16] to enable the electronic 
capture of biographic, biometric (unless the traveler is 
exempt),[Footnote 17]  and related travel documentation for arriving 
travelers in secondary inspection. This capability was deployed to the 
50 busiest land POEs as of December 29, 2004. 

Increment 2C was to demonstrate the feasibility of using passive radio 
frequency identification (RFID) technology[Footnote 18] to record 
travelers' entry and exit via a unique ID number tag embedded in the 
Form I-94 and to provide the Customs and Border Protection (CBP) 
officers in pedestrian lanes with biographic, biometric, and watch list 
data. The pilot is currently deployed at five land POEs and includes 
two proof-of-concept phases. 

* The proof-of-concept was initiated in August 2005, and initial 
results were reported in January 2006. These results showed that there 
were problems that would affect the ability to implement an RFID land 
border solution. This was subsequently termed Phase 1 and is still 
ongoing, using $21.5 million in funds carried over from fiscal year 
2005. 

* Phase 2 of the proof-of-concept is to begin in April 2007. The plan 
for Phase 2 states that it will expand Phase 1 by providing CBP 
officers in both pedestrian and vehicle lanes with additional 
biographic, biometric, and watch list data to determine a traveler's 
admissibility. After Phase 2 is completed, next steps in deploying this 
capability to land POEs are to be determined. According to the US-VISIT 
Director of Implementation, the schedule for completing Increment 2C 
has not yet been determined. 

Increment 3: 

Increment 3 was to extend Increment 213 entry capabilities to 104 land 
POEs by December 31, 2005. It was essentially completed as of December 
19, 2005.[Footnote 19]  

Increment 4: 

The fiscal year 2005 and preceding year expenditure plans have 
described Increment 4 as the yet-to-be-defined, strategic solution for 
the US-VISIT program. Program officials stated in 2005 that Increment 4 
would likely consist of a series of releases that provided a range of 
capability enhancements to support an overall DHS vision for 
immigration and border management operations. The fiscal year 2005 US- 
VISIT expenditure plan included $21 million for these activities, 
including improved immigration and border management identity and 
verification; improved cooperation across federal, state, and local 
agencies through improved access to foreign national data; and enhanced 
communications, management, and collaboration across the border 
management community.  

The fiscal year 2006 expenditure plan defines Increment 4 to be US- 
VISIT's migration to the use of 10 fingerprints in identifying an 
individual and the development of interoperability between US-VISIT's 
Automated Biometric Identification System (IDENT) and the Federal 
Bureau of Investigation's Integrated Automated Fingerprint 
Identification System (IAFIS). 

The fiscal year 2006 plan allocates $44.5 million to these activities, 
including evaluation and testing of industry prototypes for a new 10- 
fingerprint scanner, associated facilities and engineering support, and 
related modifications to the systems used to store the fingerprint data 
and conduct fingerprint scan matches. In addition, an interim Data 
Sharing Model has been deployed as an interim solution to increase the 
biometric data shared between agencies, establish information sharing 
processes following a positive biometric identification, and to 
establish cooperative strategies for full information sharing. 

According to the Director of Implementation, Increment 4 is further 
defined in the US-VISIT Strategic Plan. However, the Acting Program 
Director told us that this plan has not yet been approved and thus has 
not been released. 

Background: 

Increments 1, 2B and 3 Systems Overview[Footnote 20] 

Systems Diagram of US-VISIT for Increment 1 (air and sea entry) and 
Increments 213 and 3 (land entry): 

[See PDF for image] 

Sources: GAO analysis of US-VISIT data, Nova Development Corp. 
(clipart). 

[End of figure] 

Background: 

Increments 1 B and 2C Systems Overview[Footnote 21] 

Systems Diagram of US-VISIT Increment 1 B (air and sea exit) and 
Increment 2C (land entry and exit): 

[See PDF for image] 

Source: GAO analysis of US-VISIT data. 

[End of figure] 

Background: 

Chronology of Expenditure Plans: 

Fiscal year: 2002; 
Date submitted: 11/15/2002; 
Funds appropriated: $13,300,000; 
Funds requested: $13,300,000; 
Funds released to date: $13,300,000. 

Fiscal year: 2003; 
Date submitted: 06/05/2003; 
Funds appropriated: $362,000,000; 
Funds requested: $375,000,000; 
Funds released to date: $367,000,000[Footnote 22]. 

Fiscal year: 2004; 
Date submitted: 01/ 27/2004; 
Funds appropriated: $330,000,000; 
Funds requested: $330,000,000; 
Funds released to date: $330,000,000. 

Fiscal year: 2005; 
Date submitted: 10/19/2004; 
Funds appropriated: $340,000,000; 
Funds requested: $340,000,000; 
Funds released to date: $340,000,000. 

Fiscal year: 2006; 
Date submitted: 08/10/2006; 
Funds appropriated: $336,600,000; 
Funds requested: $336,600,000; 
Funds released to date: $178,540,000. 

Fiscal year: 2007; 
Date submitted: TBD; 
Funds appropriated: $362,494,000; 
Funds requested: TBD; 
Funds released to date: $162,494,000. 

Total; 
Funds appropriated: $1,744,394,000; 
Funds requested: $1,394,900,000; 
Funds released to date: $1,391,334,000. 

[End of table] 

Background: 

Summary of 2006 Expenditure Plan: 

Area of expenditure (see next slides for descriptions): Increment 1 - 
Entry/exit (air and sea POEs); 
Amount: $33,500,000. 

Area of expenditure (see next slides for descriptions): Increment 2A - 
U.S. travel documents issued to non-citizens and e- Passports; 
Amount: 15,400,000. 

Area of expenditure (see next slides for descriptions): Increment 2B - 
Entry/land border - 50 busiest POEs; 
Amount: 0. 

Area of expenditure (see next slides for descriptions): Increment 2C - 
Automated ID (RFID) - land border POEs; 
Amount: 0. 

Area of expenditure (see next slides for descriptions): Increment 3 - 
Entry/remaining land border POEs; 
Amount: 0. 

Area of expenditure (see next slides for descriptions): Increment 4 - 
Modernization and expansion of systems and capabilities; 
Amount: 44,500,000. 

Area of expenditure (see next slides for descriptions): Operations and 
maintenance (increments 1-3); 
Amount: 104,200,000. 

Area of expenditure (see next slides for descriptions): Program 
management and operations - government; 
Amount: 37,000,000. 

Area of expenditure (see next slides for descriptions): Program 
management and operations - contractor support; 
Amount: 89,000,000. 

Area of expenditure (see next slides for descriptions): Management 
reserve; 
Amount: 13,000,000. 

Total; 
Amount: $336,600,000. 

Source: GAO, based on an analysis of DHS data. 

[End of table] 

Increment 1 - Entry/exit: Includes continued testing of deployment 
options for the implementation of an exit screening program at air, 
sea, and land ports, as well as supporting the current 14 POEs where 
the exit pilots are in place. 

Increment 2A - U.S. travel documents issued to non-citizens and e- 
Passports: Includes continued systems design, development, testing, 
procurement, and deployment of e-Passport readers. 

Increment 4 - Modernization and expansion of systems and capabilities: 
Includes implementing the 10-fingerprint scanners; related systems 
interoperability; associated facilities and engineering support; and 
systems architecture, engineering and integration, and design. 

Operations and maintenance: Includes operations and maintenance of 
Increment 1, 2, and 3 systems, including technical, application, 
system, network, and infrastructure support costs. 

Program management and operations - government: Includes the government 
salaries and benefits for 115 government program office positions 
necessary to manage and operate the program, including relocation 
costs, personnel security checks, and training. 

Program management and operations - contractor support: Includes the 
program office support contractors. 

Management reserve: Includes funds allocated to accommodate unknown 
timing and magnitude of risks. 

Objective 1: Legislative Conditions Condition 1: 

The US-VISIT expenditure plan, related program documentation, and 
program officials' statements satisfies or provides for satisfying (in 
part or total) each of the legislative conditions. 

Condition 1. The plan, including related program documentation and 
program officials' statements, partially satisfies or provides for 
satisfying the capital planning and investment control review 
requirements established by OMB, including OMB Circular A-11, part 7, 
which establishes policy for planning, budgeting, acquisition, and 
management of federal capital assets. 

The table that follows provides examples of the results of our 
analysis, including areas in which the A-11 requirements have been and 
have yet to be fully satisfied, as well as an area in which we have 
ongoing work to more closely examine the quality of program 
documentation and practices. Given that the A-11 requirements are 
intended to minimize a program's exposure to risk, permit performance 
measurement and oversight, and promote accountability, any areas in 
which the program falls short of the requirements reduce the chances of 
delivering cost-effective capabilities and measurable results on time 
and within budget. 

Objective 1: Legislative Conditions Condition 1: 

Examples of A-11 Conditions: Provide a brief description of the 
investment and its status in the capital planning and investment 
control review, including major assumptions made about the investment; 
Results of our analysis: The expenditure plan and other documentation 
provide a description of the US-VISIT investment and its status in the 
DHS capital planning and investment control process. In particular, US-
VISIT is in the capability development and demonstration phase of the 
process, having received IRB approval in August 2004 to begin this 
phase. According to program officials, they have followed DHS’s 
evolving capital planning and investment control process and will 
continue to do so. Further, the plan and related documents identify 
program assumptions. For example, the OMB exhibit 300 submission states 
that existing systems and processes do not enable a unified entry and 
exit decision support workflow supported by interoperable systems. 

Examples of A-11 Conditions: Provide a summary of the investment’s risk 
assessment, including how 19 OMB-identified risk elements are being 
addressed; 
Results of our analysis: The US-VISIT Enterprise Risk Assessment was 
approved in December 2005. It identified an inventory of risks, 
including the likelihood of occurrence, and the potential impact and 
recommended controls for each. The Risk Management Plan, which was 
approved in September 2005, is being updated and the new plan is due in 
early 2007. Risks are monitored monthly by program management and 
stakeholders. Both the OMB exhibit 300 budget submission and the Risk 
Management Plan address the 19 risk elements required by OMB. 

Examples of A-11 Conditions: Demonstrates that the investment is 
included in the agency’s enterprise architecture and capital planning 
and investment control process.  Illustrates agency’s capability to 
align the investment to the Federal Enterprise Architecture (FEA); 
Results of our analysis: The plan does not describe US-VISIT’s 
activities in regard to the DHS enterprise architecture. Moreover, the 
most recent review of program compliance with the DHS enterprise 
architecture was in August 2004 and since then, both US-VISIT and the 
DHS architecture have changed.  With regard to the FEA, the US-VISIT 
Exhibit 300 budget submission states that the US-VISIT program is 
included in the DHS enterprise architecture, and contains tables that 
satisfy OMB’s requirement for listing the FEA business areas, lines, 
and sub-functions supported, FEA service domains, types, and components 
supported, and FEA technical service areas, categories, and standards 
supported. US-VISIT’s architecture alignment is discussed further under 
the legislative condition 2 section of this briefing. With respect to 
the CPIC process, and as noted above, US-VISIT is in the capability 
development and demonstration phase in DHS’ capital planning and 
investment control review process, and we were told that an IRB review, 
to include architectural alignment, is scheduled for November 2006. 

Examples of A-11 Conditions: Provides a description of an investment's 
security and privacy issues.  Summarizes the agency's ability to manage 
security at the system or application level.  Demonstrates compliance 
with the certification and accreditation processes, as well as the 
mitigation of IT security weaknesses; 
Results of our analysis: As we previously reported, US-VISIT’s 2004 
security plan and privacy impact assessments generally satisfied OMB 
and the National Institute of Standards and Technology security 
guidance. Further, the expenditure plan states that all of the US-VISIT 
component systems have been certified and accredited and given full 
authority to operate. However, the 2004 security plan preceded the US-
VISIT risk assessment, which was not completed until December 2005, and 
the security plan was not updated to reflect this risk assessment. 
According to US-VISIT officials, they intend to develop a security 
strategy by the end of 2006 that reflects the risk assessment. 
Additionally, we previously reported that issues raised in the privacy 
impact assessment had not been fully addressed in system 
documentation.  We have ongoing work to evaluate the quality of the US-
VISIT security and privacy documents and practices.  

Examples of A-11 Conditions: Provides a summary of the investment’s 
status in accomplishing baseline cost and schedule goals through the 
use of an earned value management (EVM) system or operational analysis, 
depending on the life-cycle stage; 
Results of our analysis: The program is currently relying on the prime 
contractor’s EVM system to manage the prime contractor’s progress 
against cost and schedule goals and the fiscal year 2006 expenditure 
plan states that the program office assessed the prime contractor’s EVM 
system against relevant standards in early fiscal year 2006. However, 
this EVM system was self-certified by the prime in December 2003 as 
meeting established standards, and OMB requires that agencies verify 
contractor self-certifications. The program office has yet to do this, 
although program officials told us that they plan to retain the 
services of another contractor to perform this validation. Further, our 
review of the integrated baseline review, which agencies are required 
by OMB to complete to ensure that the EVM program baseline is accurate, 
showed that this baseline review did not address key baseline 
considerations, such as cost and schedule risks. The fiscal year 2006 
expenditure plan also states that all US-VISIT contractors will be 
required to perform EVM. According to US-VISIT officials, this 
requirement will be met in accordance with DHS guidelines, for all 
contracts after October 1, 2006.

Source: OMB criteria and GAO analysis of DHS documentation. 

[End of table] 

Objective 1: Legislative Conditions Condition 2: 

Condition 2. The plan, including related program documentation and 
program officials' statements, partially provides for satisfying the 
condition that it comply with DHS's enterprise architecture (EA). 

According to federal guidelines and best practices, investment 
compliance with an EA is essential for ensuring that an organization's 
investment in new and existing systems is defined, designed, and 
implemented in a way that promotes integration and interoperability and 
minimizes overlap and redundancy, thus optimizing enterprisewide 
efficiency and effectiveness. A compliance determination is not a one- 
time event that occurs when an investment begins, but is, rather, a 
series of determinations that occur throughout an investment's life 
cycle as changes to both the EA and the investment's architecture are 
made. 

The DHS Enterprise Architecture Board, supported by the Enterprise 
Architecture Center of Excellence, is responsible for ensuring that 
projects demonstrate adequate technical and strategic compliance with 
the department's EA. 

The DHS Enterprise Architecture Board has not reviewed US-VISIT 
architecture compliance for more than 2 years. Specifically, in August 
2004, this board reviewed US-VISIT's architectural alignment with some 
aspects of the DHS EA, and it recommended that US-VISIT be given 
conditional approval to proceed.[Footnote 23]  

As we previously reported,[Footnote 24] this August 2004 architectural 
compliance determination did not fully satisfy the legislative 
condition for several reasons. 

DHS's determination was based on version 1.0 of the EA, which was 
missing, in part or in whole, all the key elements expected in a well- 
defined architecture, such as a description of business processes, 
information flows among these processes, and security rules associated 
with the information flows. 

DHS did not provide sufficient documentation to allow us to understand 
the methodology and criteria for architecture compliance or to verify 
analysis justifying the conditional approval. 

Since August 2004, both US-VISIT and the EA have changed. For example, 
additional functionality, such as the IDENT/IAFIS interoperability and 
expansion of DENT to collect ten rather than two prints, has been 
added. Also, two new versions of the DHS EA have been issued since 
August 2004. 

In the absence of an architecture compliance review over the past 2 
years, US-VISIT officials told us they have taken other steps to 
maintain compliance. These steps include: 

submitting their technical baseline of existing hardware and software 
to the EA Center for Excellence for inclusion in the DHS EA; 

submitting technology insertion requests for new equipment planned for 
US-VISIT, such as RFID technology, to the EA Center of Excellence to be 
reviewed for compliance and inclusion in the DHS EA, and: 

documenting US-VISIT alignment with the business and services models of 
the Federal Enterprise Architecture (FEA) reference models. 

In addition, US-VISIT officials told us that they recently requested an 
alignment review for November 2006. According to them, 2 years have 
passed since the last review because they were waiting until changes to 
DHS's capital planning and investment control process were complete 
before seeking a review. 

US-VISIT officials said that key alignment efforts since the last 
architecture compliance review are documented in the program's fiscal 
year 2007 Exhibit 300 budget submission. Specifically, it included: 

tables listing the FEA business, service, and technical reference model 
components that US-VISIT supports, 

a discussion of issues regarding data used or planned for use in US- 
VISIT, including data types, sources, limitations, and privacy 
concerns, including the recognition that US-VISIT's data have not been 
fully defined, and: 

a commitment to develop a strategy for maintaining future alignment 
with the DHS EA. 

Until DHS demonstrates, through verifiable documentation and 
methodologically-based analysis, that US-VISIT is aligned with a well- 
defined DHS enterprise architecture, the program will remain at risk of 
being defined and implemented in a way that does not support optimized 
departmentwide operations, performance, and achievement of strategic 
goals and outcomes. 

Objective 1: Legislative Conditions Condition 3: 

Condition 3. The plan, including related program documentation and 
program officials' statements, partially provides for satisfying the 
condition that it comply with the acquisition rules, requirements, 
guidelines, and systems acquisition management practices of the federal 
government. 

Federal acquisition rules, requirements, guidelines, and management 
practices provide an acquisition management framework that is based on 
the use of rigorous and disciplined processes for planning, managing, 
and controlling the acquisition of IT resources.[Footnote 25] These 
acquisition management processes are embodied in published best 
practices models, such as the Software Engineering Institute (SEI) 
Capability Maturity Models®. These models explicitly define, among 
other things, acquisition process management controls that are 
recognized hallmarks of successful organizations and that, if 
implemented effectively, can greatly increase the chances of acquiring 
software-intensive systems that provide promised capabilities on time 
and within budget. 

We reported in September 2003[Footnote 26] that the program office had 
not defined key acquisition management controls to support the 
acquisition of US- VISIT, and therefore its efforts to acquire, deploy, 
operate, and maintain system capabilities were at risk of not meeting 
system requirements and benefit expectations on time and within budget. 

Subsequently, the program adopted the SEI Capability Maturity Model 
Integration[Footnote 27] (CMMI®) to guide its efforts to employ 
effective acquisition management practices and approved an acquisition 
management process improvement plan dated May 16, 2005. This plan is 
divided into two parts: 

* Phase 1 (2005-2006): The goal for this phase was to achieve a CMMI® 
level 2 capability rating from SEI by October 2006. To accomplish this, 
the program was to, among other things, define a strategy to implement 
acquisition management process improvements, establish a process 
improvement infrastructure (management steering group, enterprise 
process group, and process action teams), and conduct an independent 
CMMI® level 2 appraisal. 

* Phase 2 (2007-2011): The goals of this phase are to lower program 
costs and acquisition risks, shorten increment and overall schedules, 
reduce costs, and deliver better performing, higher quality products. 
To accomplish this, the program intends to build on the October 2006 
appraisal and address improvement opportunities, establish future 
organizational process improvement goals, and leverage and 
institutionalize processes and improvement activities across the 
program. 

In September 2005, US-VISIT completed an initial assessment of 13 key 
acquisition process areas, and this assessment revealed a number of 
weaknesses across the areas. In light of this, US-VISIT updated its 
acquisition management process improvement plan. According to the 
update, while the program had implemented some of the required 
practices, many other practices were not being performed to the extent 
required by CMMI. Accordingly, the updated plan adopted a 2-year focus 
as follows. 

2006: The update narrows the scope of the process improvement 
activities in this year to six of the CMMI process areas--project 
planning, project monitoring and control, requirements management, risk 
management, configuration management, and product and process quality 
assurance--and focuses on two US-VISIT projects--Increment 2A and 
Unique Identity. According to the update, the 2006 goal is to enhance 
capabilities in those six process areas in order to conduct an 
independent CMMI assessment in October 2006. 

2007: The update provides for addressing the weaknesses found in the 
October 2006 assessment plus two additional process areas related to 
CMMI level 2 (supplier agreement management, and measurement and 
analysis). Further, the update states that the program will look for 
any additional CMMI level 2 and 3 process areas that would be 
beneficial and affordable. These efforts are to be complete by October 
2007. 

In May 2006, the program conducted a second internal assessment of the 
six key process areas. According to the results of this assessment, 
improvements were made, but weaknesses remained in all six. Among the 
cited weaknesses are: 

A number of key acquisition management documents were not adequately 
prepared and processes were not sufficiently defined, including those 
related to systems development, budget and finance, facilities, and 
strategic planning (e.g., product work flow among organizational units 
was unclear and not documented, and roles, responsibilities, and 
assignments for performing work tasks and activities were not 
adequately defined and documented). 

Policies, process descriptions, and templates were lacking for 
requirements development and management. 

Roles, responsibilities, work products, expectations, resources, and 
accountability of external stakeholder organizations were not well 
defined. 

Evidence that the program management plan was used for managing the 
program was limited. 

Evidence that dependencies in its Integrated Master Plan/Integrated 
Master Schedule were complete, accurate, and validated was limited. 

Measurement controls were under development but were not yet complete. 

Because of the significance of these weaknesses, program officials 
recently decided to postpone indefinitely the planned October 2006 
independent appraisal. Instead, they told us that they intend to 
perform quarterly internal assessments until the results show that they 
can pass an independent appraisal. A revised target date for the 
program's external appraisal has not been set. The program's readiness 
for an appraisal is to be reassessed by March 2007. 

Notwithstanding these weaknesses, program officials told us that their 
self-assessments show that they have made incremental progress in 
implementing the 113 practices associated with the six key process (see 
next slide). 

U.S. VISIT CMMI Status Number: 

[See PDF for image] 

Sources: GAO analysis of DHS data. 

[End of figure] 

The acquisition management weaknesses in the six key process areas are 
exacerbated by weaknesses in other process areas. For example, we 
recently reported[Footnote 28] that the US-VISIT contract tracking and 
oversight process suffers from a number of weaknesses. Specifically, 
the program had not effectively overseen US-VISIT-related contract work 
performed on its behalf by other DHS and non-DHS agencies, and these 
agencies did not always establish and implement the full range of 
controls associated with effective management of contractor activities. 
Further, neither the program office nor the other agencies had 
implemented effective financial controls.[Footnote 29] 

The program agreed with our recommendations for correcting these 
weaknesses and stated that steps were either under way or planned to 
implement them. 

US-VISIT officials attribute their slow progress to the magnitude of 
the effort needed to achieve CMMI® level 2 capabilities. Further, they 
said that there is a limit to the amount of change that the program can 
handle at one time. Until the program addresses these and other 
acquisition management weaknesses, it will remain at risk of not 
delivering cost-effective system applications and measurable results on 
time and on budget. 

Objective 1: Legislative Conditions Condition 4: 

Condition 4. The plan satisfies the condition that it include a 
certification by the DHS Chief Information Officer that an independent 
verification and validation agent is currently under contract for the 
project. 

On June 5, 2006, the DHS Deputy Chief Information Officer certified in 
writing that an independent verification and validation agent was under 
contract for US-VISIT. 

According to the certification memorandum: 

the agent is fully qualified and has demonstrated experience in 
conducting independent verification and validation activities for 
programs of comparable complexity; 

the agent's statement of work is clear with respect to expected tasks 
and is in full conformance with the applicable standard; and: 

the agent's technical approach is consistent with the statement of 
work. 

Objective 1: Legislative Conditions Condition 5: 

Condition 5. The plan, including related program documentation and 
program officials' statements, satisfies the requirement that it be 
reviewed and approved by the DHS IRB, the Secretary of Homeland 
Security, and OMB. 

* The DHS Deputy Secretary, who is also the chair of the I RB, approved 
the fiscal year 2006 expenditure plan on June 21, 2006, and: 

* OMB approved the plan on August 7, 2006. 

Objective 1: Legislative Conditions Condition 6: 

Condition 6. The plan satisfies the requirement that it be reviewed by 
GAO. Our review was completed on November 13, 2006. 

Objective 2: Open Recommendations Recommendation 1: 

The US-VISIT expenditure plan, related program documentation, and 
program officials' statements, address or provide for addressing (in 
part or total) each of our recommendations. 

Recommendation: Ensure that future expenditure plans are provided to 
DHS's House and Senate Appropriations Subcommittees on Homeland 
Security in advance of US-VISIT restricted funds being obligated. 

Status: Complete: 

The fiscal year 2006 Department of Homeland Security Appropriations Act 
provides $340 million in fiscal year 2006 funds for the US-VISIT 
program.[Footnote 30] In addition, the act states that $159,658,000 of 
this amount may not be obligated for US-VISIT until the Appropriations 
Committees receive and approve a plan that meets each of the previously 
cited legislative conditions. OMB subsequently instructed US-VISIT to 
reduce this number to $158,060,000, as part of the governmentwide 
budget rescission. 

On August 10, 2006, DHS provided its fiscal year 2006 expenditure plan 
to the Senate and House Appropriations Subcommittees on Homeland 
Security. As of September 30, 2006, the US-VISIT program reported that 
$77,992,260 of fiscal year 2006 funds had been obligated and that 
$98,741,239 had been expended, leaving an unobligated balance of 
$159,866,501. After application of the rescission, the unobligated 
balance is $1,806,501 greater than the original amount restricted from 
obligation by the appropriations legislation. 

As we recently reported, the system that US-VISIT uses to manage its 
finances (U.S. Immigration and Customs Enforcement's Federal Financial 
Management System (FFMS)) has reliability issues.[Footnote 31] In light 
of these issues, the US-VISIT Budget Office has begun tracking program 
obligations and expenditures separately using a spreadsheet and 
comparing this spreadsheet to the information in the FFMS. Based on a 
review of this spreadsheet, there is reasonable assurance that the US- 
VISIT obligations being reported by FFMS are accurate. 

This is the third consecutive expenditure plan that DHS has provided 
the House and Senate Appropriations Subcommittees on Homeland Security 
in advance of obligating restricted US-VISIT funds. 

Objective 2: Open Recommendations Recommendation 2: 

Recommendation: Ensure that all future US-VISIT expenditure plans 
identify and disclose management reserve funding. 

Status: Complete: 

The fiscal year 2006 expenditure plan specified management reserve 
funding of $13 million to accommodate unknown timing and magnitude of 
risk. This amount is about 3.9 percent of the 2006 plan's total 
funding. 

This is the third consecutive expenditure plan in which management 
reserve funding has been identified and disclosed. 

Objective 2: Open Recommendations Recommendation 3: 

Recommendation: Ensure that future expenditure plans fully disclose how 
the US-VISIT acquisition is being managed. 

Status: Partially complete: 

The 2006 expenditure plan describes a range of key acquisition 
management activities and control areas. These include: 

* governance and organizational structures, 

* human capital management, 

* stakeholder management, 

* test management, 

* system capacity management, 

* configuration management, and: 

* independent verification and validation. 

However, the plan's descriptions do not fully disclose challenges that 
the US-VISIT program faces in how it is managing acquisition 
activities, for example, it does not disclose the progress in 
addressing acquisition management weaknesses and achieving process 
maturity goals that is discussed in the legislative conditions section 
of this briefing. 

Objective 2: Open Recommendations Recommendation 4: 

Recommendation: Develop a plan, including explicit tasks and 
milestones, for implementing all our open recommendations and report 
progress against this plan, including reasons for delays, in all future 
US-VISIT expenditure plans. 

Status: Partially complete: 

The fiscal year 2006 expenditure plan lists most of our recommendations 
and describes DHS efforts to address them. However, the plan does not 
provide future tasks or milestones for more than half of our 
recommendations, and is missing four recommendations altogether. The 
missing recommendations are: 

Ensure that future expenditure plans are provided to DHS's House and 
Senate Appropriations Subcommittees on Homeland Security in advance of 
US-VISIT funds being obligated. 

Ensure that future expenditure plans fully disclose US-VISIT system 
capabilities, schedule, cost, and benefits to be delivered. 

Ensure that all future US-VISIT expenditure plans identify and disclose 
management reserve funding. 

Fully and explicitly disclose in all future expenditure plans how well 
DHS is progressing against the commitments that it made in prior 
expenditure plans. 

Objective 2: Open Recommendations Recommendation 5: 

Recommendation: Ensure that future expenditure plans fully disclose US- 
VISIT system capabilities, schedule, cost, and benefits to be 
delivered. 

Status: Partially complete: 

The fiscal year 2006 expenditure plan discloses some system 
capabilities, schedules, costs, and benefits, but important information 
to fully support congressional oversight and promote department 
accountability is missing. 

Capabilities: 

The fiscal year 2006 expenditure plan provides information relative to 
each increment. However, this information is largely in terms of 
general descriptions of activities to be performed, rather than 
capabilities to be delivered. Examples of such general descriptions 
are: 

* Increment 2A - Complete and execute test plans to support an 
international joint live operational test with Visa Waiver Program 
countries. 

* Increment 2C - Continue to develop, test, and integrate the US-VISIT 
systems that support the proof of concept. 

* Increment 3 - Upgrade land POE technology, infrastructure, and 
facilities. 

* Increment 4 - Continue to assure environmental compliance, traffic, 
and operational impact modeling, geospatial data development, power 
utilization studies, and special studies. 

Schedule: 

The fiscal year 2006 expenditure plan includes specific dates for some 
broadly defined planned capabilities. For example, the plan states 
that: 

* Increment 2A e-Passport reader deployment is scheduled for October 
26, 2006. 

* The Increment 4 interim data sharing database is scheduled to be 
deployed on September 3, 2006. 

For other capabilities, no dates are provided. For example, the plan 
states that Increment 2C's proof of concept phase will be completed "in 
this fiscal year." Further, the plan does not provide a commitment date 
for completing the Increment 1 exit pilot at air and sea POEs, or for 
beginning deployment of an exit solution to the remaining POEs. 

Costs: 

The fiscal year 2006 plan identifies each increment's estimated costs 
and associates the estimated cost with fiscal year funding. In some 
cases, meaningful detail is given to understand how the funds will be 
used. However, in many cases, costs are not decomposed to a level that 
would permit such understanding and oversight. For example, the plan 
states that: 

* $33.5 million of fiscal year 2006 funds will be spent on Increment 1 
to support air and sea exit pilots at 14 locations and to develop an 
exit plan; however, the funds are not allocated between the two 
activities. 

* $26.7 million of fiscal year 2006 funds will be spent on Increment 4 
for 10-print transition and IDENT/IAFIS interoperability; however, the 
funds are not allocated between the two activities or to major tasks 
and products under each activity, such as the iDSM. 

Benefits: 

The fiscal year 2006 expenditure plan cites benefits associated with 
the increments. However, the benefits are very broadly stated. Examples 
of incremental benefits are as follows: 

* Increment 2A - Prevent terrorist attacks on the US. 

* Increment 2A - Ensure the integrity of immigration system. 

* Increment 2C - Improve the current ability to monitor overstays. 

* Increment 2C - Protect the privacy of travelers. 

* Increment 2C - Help to address the Western Hemisphere Travel 
Initiative. 

* Increment 4 - Give law enforcement and immigration officials access 
to crucial information. 

The plan also separately describes US-VISIT performance measures. 
Specifically, it cites seven performance measures and provides the 
actual fiscal year 2005 performance data for each. Examples of 
performance measures include: 

ratio of adverse actions to total biometric watch list hits at POEs 
and: 

number of biometric watch list hits for visa applicants processed at 
consular offices. 

However, the plan does not include fiscal year 2006 performance targets 
for three of the seven performance measures. Moreover, the plan does 
not explicitly link these measures to program benefits. Finally, the 
plan does not include any measures related to exit processing, even 
though the plan's stated goals and cited benefits include immigration 
system integrity, which requires an effective exit processing 
capability. 

Program officials told us that they face challenges in measuring 
accrual of benefits. Specifically, 

Performance measures are limited to items for which they have 
performance data, and such data is spotty. As a result, not all 
benefits associated with program increments have performance measures. 
As additional system capabilities are implemented, such as 10- 
fingerprint scanning and IDENT/IAFIS interoperability, program 
officials said that they will develop additional performance measures. 

Not all US-VISIT performance data are reliable. As a result, the 
program has created a Data Integrity Group to improve data 
completeness, accuracy, and currency. 

Not all performance measures are under the control of the US-VISIT 
program because US-VISIT is a collection of different systems that are 
managed by different organizational entities. As a first step towards 
addressing this problem, US-VISIT recently began working with Customs 
and Border Protection to develop performance measures that go beyond US-
VISIT to include other aspects of the nation's immigration system. 
According to program officials, this effort was initiated in September 
2006; timeframes for completing it have not been established. 

According to program officials, some US-VISIT performance measures were 
excluded from the expenditure plan. The US-VISIT program has developed 
a quarterly performance measures report that includes all externally 
reported performance measures, the fiscal year 2005 performance 
baselines, the fiscal year 2006 targets, and the actual performance 
during fiscal year 2006 by quarter. The program officials also stated 
that this report has been provided to congressional committees. 

Objective 2: Open Recommendations Recommendation 6: 

Recommendation: Fully and explicitly disclose in all future expenditure 
plans how well DHS is progressing against the commitments that it made 
in prior expenditure plans. 

Status: Partially complete: 

The fiscal year 2006 expenditure plan describes progress against some, 
but not all, commitments in the fiscal year 2005 expenditure plan, and 
thus does not provide sufficient disclosure of program performance to 
support congressional oversight and promote department accountability. 

Capabilities: 

The expenditure plan describes progress in achieving some system 
capabilities. For example, the fiscal year 2005 expenditure plan 
committed to implementing entry functionality at the remaining 115 land 
POEs as part of Increment 3. The fiscal year 2006 plan reported that 
this capability was deployed to 105 POEs, and explained that the 
remaining 10 POEs did not receive this functionality because they do 
not process travelers who are subject to US-VISIT, or they are not 
capable of supporting the necessary US-VISIT infrastructure (e.g., do 
not have the telecommunications infrastructure needed for US-VISIT). 

However, progress made against a number of other important capability 
commitments is not fully and explicitly disclosed. For example, the 
2005 expenditure plan stated that the prime contractor would begin 
integrating the long-term Increment 4 strategy into the interim US- 
VISIT system's environment and the overall DHS enterprise architecture, 
and that US-VISIT and the prime contractor would work with the 
stakeholder community to identify opportunities for delivery of long- 
term capabilities under Increment 4. However, the fiscal year 2006 plan 
does not discuss progress or accomplishments relative to these 
commitments. 

Schedule: 

The expenditure plan identifies progress in meeting most of the 
schedule commitments. For example, the fiscal year 2005 plan committed 
to providing all POEs with the capability to allow comparison of 
biometric travel documents (e-Passports) by October 26, 2005. The 
fiscal year 2006 expenditure plan discusses how this deadline was moved 
by legislation to October 26, 2006. 

However, progress against schedule commitments is not addressed in all 
cases. For example, the 2005 expenditure plan committed to begin 
deploying the most effective exit alternative for capturing biometrics 
at air and sea POEs during fiscal year 2005. In contrast, the 2006 
expenditure plan states that the exit pilots will continue throughout 
fiscal year 2006 and does not address whether the fiscal year 2005 
schedule deployment commitment was met. 

Costs: 

The expenditure plan cites progress against some cost commitments 
relative to US-VISIT increments. For example, the fiscal year 2006 plan 
states that: 

$33.1 million of the $54.8 million estimated cost for Increment 2C in 
fiscal year 2005 was expended or obligated during that fiscal year, and 
$21.7 million was carried over to fiscal year 2006 and: 

all of the $21.4 million cost estimate for Increment 4 in fiscal year 
2005 was expended or obligated during that fiscal year. 

However, the fiscal year 2006 plan did not report progress against 
fiscal year 2005 cost commitments relative to: 

operations and maintenance ($86 million estimate), 

program management and operations ($83 million estimate), and: 

management reserve ($23 million estimate). 

Benefits: 

As we have previously reported,[Footnote 32] the fiscal year 2005 plan 
identified several generic benefits and associated them with the 
various increments. The fiscal year 2006 plan describes accomplishments 
that can be linked to most, but not all, of these benefits. 

For example, the previous plan cited an Increment 1 benefit as "Prevent 
entry of high-threat or inadmissible individuals through improved and/ 
or advanced access to data prior to the foreign national's arrival." In 
the fiscal year 2006 plan, DHS reports the cumulative number of people 
who were subject to adverse actions or denied entry to the United 
States since Increment 1 became operational (about 2,100 persons). 
However, since the fiscal year 2005 plan did not associate a 
performance target with this specific performance measure, the degree 
of progress is not clear. 

Moreover, the fiscal year 2006 plan does not report any performance 
data that can be linked to a number of benefit commitments made in the 
fiscal year 2005 plan. For example, progress against the following 
benefits is not addressed. 

Increment 1: Improved enforcement of immigration laws through improved 
data accuracy and completeness. 

Increment 2A: Improved accuracy and timeliness of the determination of 
foreign nationals' admissibility. 

Increment 2B: Improved facilitation of legitimate travel and trade at 
land POEs through improved timeliness and accuracy of determination of 
traveler status. 

Increment 4: 

* Improved immigration and border management identity and verification. 

* Improved cooperation across federal, state, and local agencies 
through improved access to foreign national data. 

* Enhanced communication, management, and collaboration across the 
border management community. 

The fiscal year 2006 expenditure plan also does not address all 
performance measures cited in the 2005 plan. Specifically, the 2005 
plan included 11 measures. In contrast, the 2006 plan lists 7 measures, 
4 of which are similar, but not identical to, some of the 11 measures 
in the 2005 plan. This means that several of the 2005 plan's measures 
are not addressed in the 2006 plan. Moreover, and as the following 
example illustrates, even in cases of similar performance measures, the 
fiscal year 2006 plan does not adequately describe progress in meeting 
commitments. 

The fiscal year 2005 expenditure plan cited a performance measurement 
of "Pre-entry watch list hits on biometrically enabled visa 
applications." The fiscal year 2006 plan cites the performance measure 
of "Number of biometric watch list hits for visa applicants processed 
at consular offices." According to the latter plan, in fiscal year 2005 
there were 897 such hits; however, neither plan cites a performance 
target against which to gauge progress, assuming that the two 
performance measures mean the same thing. 

Objective 3: Observations Exit Definition and Justification: 

Observation 1: DHS has not adequately defined and justified its 
proposed fiscal year 2006 investment in exit pilots and demonstration 
projects. 

Having a cost effective exit capability is essential for US-VISIT to 
accomplish its stated strategic goals, such as enhancing the security 
of U.S. citizens and visitors and ensuring the integrity of the 
immigration system. This exit capability is also required by 
law.[Footnote 33] 

Over the last 3 years, DHS has devoted considerable time and resources 
toward establishing an operational exit capability at land, air, and 
sea POEs. For example, in fiscal years 2003 and 2004 the US-VISIT 
program allocated a total of $79 million to evaluating alternative air 
and sea exit solutions, and the fiscal year 2005 expenditure plan 
committed $32 million to conducting air and sea exit pilots and $51 
million for conducting a land exit pilot. Notwithstanding this 
considerable investment of time and resources, the US-VISIT program 
still does not have either an operational exit capability or a viable 
exit solution to deploy. 

Moreover, US-VISIT exit pilot and concept demonstration reports have 
raised concerns and limitations, particularly with respect to land 
POEs. According to land exit pilot and demonstration reports: 

Successful reading of information on the RFID tags occurred at below 
acceptable levels. 

High-powered RFID readers could cause RFID tags to be read incorrectly. 

Other land POE exit solutions rely on leading edge technologies that 
are inherently risky. 

Notwithstanding these results, the fiscal year 2006 expenditure plan 
proposes investing another $33.5 million to continue air and sea exit 
pilot and demonstration activities, and the program is carrying over 
$21.5 million from fiscal year 2005 to continue the land exit pilot. 
However, 

Neither the plan nor other exit-related program documentation 
adequately defines what these efforts entail or what they will 
accomplish. In particular, the plan and other exit-related program 
documentation merely state that $33.5 million will be used to continue 
air and sea exit pilots and demonstrations while a comprehensive exit 
solution is developed. They do not adequately describe measurable 
outcomes (benefits and results) from the pilot or demonstration 
efforts, or related cost, schedule, and capability commitments that 
will be met. 

Further, while the plan and other exit-related documentation do not 
allocate any current funding to the land exit demonstration projects 
using RFID, they allocate carryover from fiscal year 2005 of $21.5 
million to continue this effort. The documents do not adequately 
describe measurable outcomes (benefits and results) from the pilot and 
demonstration efforts, and related cost, schedule, and capability 
commitments that will be met. 

The plan does not recognize the challenges revealed from prior exit 
efforts, nor does it show how proposed exit investments address these 
challenges. For example, the plan does not address the low read rates 
observed in the pilot or the problems with cross reading and system 
downtime. 

The plan allocates more funding for continuing the air and sea exit 
pilot and demonstration efforts ($33.5 million) than the prior year's 
plan said would be needed to fully deploy an operational air and sea 
exit solution ($32 million). 

According to US-VISIT officials, the pilots are being continued to 
maintain a presence intended to provide a deterrent effect at exit 
locations. They are also to be used to gather additional data, which 
officials said could help support planning for a comprehensive exit 
solution. 

Without adequately defining and justifying exit pilot investments in 
the context of what has already been accomplished and learned from past 
demonstration projects and what new outcomes and results will be 
accomplished when, and at what cost, it is unclear that planned exit 
investments will produce value commensurate with costs and risks. As a 
result, these investments are neither adequately defined nor justified. 

GAO Objective 3: Observations US-VISIT Defined without Operational 
Context: 

Observation 2: DHS continues to invest in US-VISIT without a clearly 
defined operational context that includes explicit relationships with 
related border security and immigration enforcement initiatives. 

As we have previously reported, it is important that US-VISIT be 
developed and deployed within an operational context (e.g. enterprise 
architecture) that defines, among other things, applicable policies, 
rules, standards, and related initiatives.[Footnote 34] Without such a 
context to provide a common frame of reference to guide and constrain 
both US- VISIT and other border security and immigration enforcement 
initiatives, we concluded that DHS risks investing in programs and 
systems that are duplicative, are not interoperable, and do not 
optimize enterprisewide mission operations. As a result, we recommended 
in 2003 that DHS clarify the operational context in which US-VISIT is 
to operate. Since then, we have reported on weaknesses with the DHS 
enterprise architecture and have made recommendations for improving 
it.[Footnote 35] We currently have work under way to examine the latest 
version of the architecture. 

Over the last 3 years, DHS has continued to pursue US-VISIT (both in 
terms of deploying interfaces between and enhancements to existing 
systems, and in defining a longer-term, strategic US-VISIT solution) 
without producing the program's operational context. Exacerbating this 
situation is the fact that DHS has recently launched other major 
programs, but has not adequately defined the relationships among US- 
VISIT and each of these programs. For example, 

Secure Border Initiative, which is a multi-year plan to secure the 
borders and reduce illegal immigration by installing state-of-the-art 
surveillance technologies along the border, increasing border security 
personnel, and ensuring information access to DHS personnel at and 
between POEs. 

Western Hemisphere Travel Initiative, which DHS states will provide the 
means to implement the provisions of the Intelligence Reform and 
Terrorism Prevention Act of 2004[Footnote 36] requiring citizens of the 
United States, Canada, Bermuda, and Mexico to have a designated 
document that establishes the bearer's identity and citizenship to 
enter or re-enter the United States. 

Clearly defining the dependencies among US-VISIT and programs like 
Secure Border Initiative and Western Hemisphere Travel Initiative is 
important because there is commonality among the strategic goals of 
these programs and in the operational environments in which they are to 
function. For example, both US-VISIT and Secure Border Initiative share 
the goal of securing the ports of entry. Moreover, there is overlap in 
the data that each is to produce and use. For example, both US-VISIT 
and Western Hemisphere Travel Initiative will require identification 
data for travelers at POEs. 

Despite these dependencies, neither the fiscal year 2006 US-VISIT 
expenditure plan nor any other available US-VISIT program documentation 
addresses these relationships or how they will be managed. Further, 
according to a memo dated March 6, 2006, from the DHS Joint 
Requirements Council, the US-VISIT strategic plan did not provide 
evidence of sufficient coordination between US-VISIT and the other 
entities involved in border security and immigration efforts. The 
council's recommendation was that the strategic plan not be approved 
until greater coordination between US-VISIT and other components was 
addressed. 

However, according to the acting director, there are a number of 
efforts under way to coordinate with other entities, such as with CBP 
on RFID, with the Coast Guard on development of a mobile biometric 
reader, and with State on standards for document readers. Further, the 
acting director stated that the strategic plan is to be approved in 
November 2006 and submitted to Congress in December 2006. 

Without a clear, complete, transparent, and understood definition 
around how related programs and initiatives interact, US-VISIT and 
other border security and immigration enforcement programs run the risk 
of being defined and implemented in a way that suboptimizes DHS-wide 
performance and results. 

Objective 3: Observations Program Management-Related Costs: 

Observation 3: DHS has not adequately justified increases in, and 
disclosed the scope and nature of, program management-related fiscal 
year 2006 expenditures. 

Program management is an important and integral aspect of any system 
acquisition program. Our recommendations to DHS aimed at strengthening 
US-VISIT program management are grounded in our research, OMB 
requirements, and recognized best practices relative to the importance 
of strong program management capabilities. The importance of program 
management, however, does not in and of itself justify any level of 
investment in such activities. Rather, such investment in program 
management capabilities should be viewed the same as investment in any 
program capability, meaning the scope, nature, size, and value of the 
investment should be disclosed and justified in relation to the size 
and significance of the acquisition activities being performed. 

US-VISIT's planned investment in program management-related activities 
has risen steadily over the last 4 years, while planned investment in 
development of new program capabilities has correspondingly declined 
(see chart on next page). Specifically, 

The fiscal year 2003 expenditure plan provided $30 million for program 
management and operations. In contrast, the fiscal year 2006 plan 
provides $126 million for such program management-related functions (an 
increase of $96 million). This amount includes a $43 million increase 
(52 percent) over fiscal year 2005 funding levels. 

The fiscal year 2003 expenditure plan provided about $325 million for 
new development efforts. In contrast, the fiscal year 2006 plan 
provides $93 million for new development. 

This means that the fiscal year 2006 plan is proposing to expend $33 
million more for program management and operations than it is for new 
development. 

U.S. VISIT Breakdown of Planned Expenditures As a Dollar Amount for FY 
2002 thru FY 2006[A]: 

[See PDF for image] 

Source: GAO analysis of DHS data. 

[A] According to US-VISIT program officials, actual cost information 
for program management and operations cannot be readily provided due to 
limitations in their financial management system. 

[End of figure] 

The increase in planned program management-related expenditures is more 
pronounced if it is viewed as a percentage of planned development 
expenditures (see chart on next page). Specifically, 

Planned program management-related expenditures represented about 9 
percent of planned development in fiscal year 2003, but represents 
about 135 percent of fiscal year 2006 development. 

Planned program management-related expenditures as a percentage of new 
development increased sharply between fiscal years 2005 and 2006 (56 
percent to 135 percent). 

This means that the fiscal year 2006 expenditure plan proposes spending 
about $1.35 on program management-related activities for each dollar 
spent on developing new US-VISIT capability. 

U.S.-VISIT Planned Expenditures for Program Management and Operations 
as a Percentage of Development for FY 2002 thru FY 2006[A]: 

[See PDF for Image] 

Source: GAO analysis of DHS data. 

[A] According to US-VISIT program officials, actual cost information 
for program management and operations cannot be readily provided due to 
limitations in their financial management system. 

[End of figure] 

The expenditure plan does not explain the reasons for this recent 
growth or otherwise justify the sizeable proposed investment in program 
management and operations on the basis of measurable expected value. 
Moreover, the plan does not adequately describe the range of program 
management and operations activities. 

US-VISIT program officials told us that the DHS Acting Undersecretary 
for Management recently raised concerns about the large amount of 
program management and operations funding in the expenditure plan. They 
also said that they plan to address this issue by carefully 
distinguishing between expenditures that are purely program management 
and those that are development or operations and maintenance. 

Without disclosing and justifying its proposed investment in program 
management-related efforts, it is unclear whether such a large increase 
in spending represents the best use of limited resources. 

Conclusions: 

The legislatively mandated expenditure plan requirement for US-VISIT is 
a congressional oversight mechanism aimed at ensuring that planned 
expenditures are justified, performance against plans is measured, and 
accountability for results is established. To the extent that the US- 
VISIT expenditure plan and related program documentation do not 
adequately disclose program information on what is to be accomplished 
by when, and what it will cost to do so, the Congress's ability to make 
informed US-VISIT investment decisions based on justified expenditures 
and measured performance is restricted. 

The fiscal year 2006 expenditure plan, combined with other available 
program documentation and program officials' statements, does not 
provide sufficient justification for all planned US-VISIT expenditures 
nor does it permit progress against program commitments to be 
adequately measured and disclosed. While three of the six stated 
legislative conditions for the expenditure plan are fully satisfied, 
the other three have gaps that, while they are intended to be addressed 
at some future point, limit the department's ability to manage the 
program today. Moreover, four of our six prior recommendations aimed at 
fully defining and disclosing program commitments and managing for 
results have been only partially implemented and completed. 

Compounding the above is the lack of definition and disclosure of key 
aspects of US-VISIT's future. In particular, the program's long-term 
strategy and vision have remained unknown as the department has yet to 
approve the US-VISIT strategic plan. Equally unknown at this time is a 
viable exit solution and the relationships among US-VISIT and other 
recent border security and immigration enforcement programs, like 
Secure Border Initiative. The absence of definition and clarity in 
these areas is significant because US-VISIT's ability to meet its 
strategic goals depends in large part on these key aspects. 

Notwithstanding this lack of definition, disclosure, and thus, 
certainty about the justification for planned expenditures and the 
ability to measure performance and results, US-VISIT program management 
costs have risen sharply without any accompanying explanation for the 
reasons. Compounding this problem is that critical areas of program 
management, such as acquisition management, are also largely undefined 
in terms of when and at what costs improvements can be expected. 

All told, this means that the US-VISIT fiscal year 2006 expenditure 
plan and other available program documentation do not provide 
sufficient basis for the Congress to exercise effective oversight of 
the program and to hold the department accountable for results. For 
proper oversight and accountability to occur, it is essential that DHS 
increase US-VISIT program transparency and accountability by justifying 
planned investments on the basis of adequate definition and disclosure 
of planned expenditures, timelines, capabilities, and benefits, and by 
effectively measuring and reporting progress against each. 

Recommendations for Executive Action: 

To ensure that US-VISIT is better defined and justified, and that our 
prior recommendations aimed at instilling greater results-oriented 
performance management and accountability in the program are fully 
implemented, we are making four recommendations. 

We recommend that the Secretary of DHS direct the US-VISIT Acting 
Program Director to report regularly to the Secretary and to the DHS 
authorization and appropriations committees on the range of program 
risks associated with not having fully satisfied all expenditure plan 
legislative conditions, reasons why they are not satisfied, and steps 
being taken to mitigate these risks. 

In addition, we recommend that the Secretary direct the US-VISIT Acting 
Director to: 

Limit planned expenditures for exit pilots and demonstration projects 
until such investments are economically justified and until each 
investment has a well-defined evaluation plan. The projects should be 
justified on the basis of costs, benefits, and risks, and the 
evaluation plans should define what is to be achieved, include a plan 
of action and milestones, and measures for demonstrating achievement of 
pilot and project goals and desired outcomes. 

Work with the DHS Enterprise Architecture Board to identify and 
mitigate program risks associated with investing in new US-VISIT 
capabilities in the absence of a DHS-wide operational and technological 
context for the program. These risks should reflect the absence of 
fully defined relationships and dependencies with related border 
security and immigration enforcement programs. 

Limit planned expenditures for program management-related activities 
until such investments are economically justified and have well-defined 
plans detailing what is to be achieved, include a plan of action and 
milestones, and should include measures for demonstrating progress and 
achievement of desired outcomes. The investments should be justified on 
the basis of costs, benefits, and risks. 

Agency Comments: 

We provided this briefing to, and discussed its contents with, US-VISIT 
program officials, including the Acting Director. In commenting on a 
draft of this briefing, US-VISIT program officials agreed with our 
findings, and said that our conclusions and recommendations were fair. 
They also provided technical comments on the briefing, which we have 
incorporated into the briefing as appropriate. 

Attachment 1 Scope and Methodology: 

To accomplish our first objective, 

we reviewed the fiscal year 2006 plan and other available program 
documentation related to each condition. In doing so, we examined not 
only completed actions and steps, but also planned actions and steps, 
including program officials' stated commitments to perform such 
activities and steps. More specifically, we: 

compared the information in US-VISIT's fiscal year 2006 Exhibit 300 
budget submission and related documentation to capital planning 
guidance (OMB A-11 part 7) to determine whether the information 
complies with the capital planning and investment controls, 

assessed US-VISIT against criteria in DHS's Investment Review Process 
to determine whether the US-VISIT program could demonstrate compliance 
with the DHS enterprise architecture, 

assessed US-VISIT's software improvement program to determine the 
progress made in developing acquisition processes that meet industry 
standards, 

reviewed documentation to determine whether an independent verification 
and validation agent was currently under contract, and: 

reviewed documentation to determine whether the expenditure plan 
received the required certification and approvals. 

To accomplish our second objective, we: 

* examined funding obligations reports and prior work on US-VISIT 
financial systems data reliability to assess the reliability of 
obligation data, and: 

* interviewed the Budget Director to determine what compensating 
controls were in place over the US-VISIT budget control document, 
including what individuals were allowed data entry access to the 
document, how often the document was reconciled with the financial 
system, and how discrepancies with the financial system were reconciled 
to determine whether these procedures provide US-VISIT with reasonable 
assurance that the obligations reported by the financial system were 
accurate. 

We also analyzed the plan to determine if it: 

* identified and disclosed management reserve funding; 

* disclosed key aspects of how the acquisition is being managed, 
including management areas that our prior reports on US-VISIT 
identified as important but missing (e.g., governance structure, 
organizational structure, human capital, systems configuration, and 
system capacity); 

* discussed steps and timetables for implementing all open GAO 
recommendations including reasons for any delays encountered in 
implementing the tasks; 

* contained measurable descriptions of system capabilities, benefits, 
costs, and schedule; and: 

* described actual progress against commitments for system 
capabilities, benefits, cost, and schedule from the fiscal year 2005 
spend plan. 

To accomplish our third objective, we reviewed the fiscal year 2006 
plan and other available program documentation related to each of the 
following areas. In doing so, we examined completed and planned actions 
and steps, including program officials' stated commitments to perform 
them. More specifically, we reviewed efforts to: 

* define and implement an exit strategy for air, sea, and land, 

* define the relationships between US-VISIT and other border security 
initiatives, and: 

* program management costs. 

For DHS-provided data that our reporting commitments did not permit us 
to substantiate, we have made appropriate attribution indicating the 
data's source. 

We conducted our work at US-VISIT program offices in Arlington, 
Virginia, from August 2006 through November 2006, in accordance with 
generally accepted government auditing standards. 

Attachment 2 Related Products List: 

Related Products List: 

Homeland Security: Contract Management and Oversight for Visitor and 
Immigrant Status Program Need to Be Strengthened. GAO-06-404. 
Washington, D.C.: June 9, 2006. 

Homeland Security: Progress Continues, but Challenges Remain on 
Department's Management of Information Technology. GAO-06-598T. 
Washington, D.C.: March 29, 2006. 

Homeland Security: Recommendations to Improve Management of Key Border 
Security Program Need to be Implemented. GAO-06-296. Washington, D.C.: 
February 14, 2006. 

Homeland Security: Visitor and Immigrant Status Program Operating, but 
Management Improvements Are Still Needed. GAO-06-318T. Washington, 
D.C.: January 25, 2006. 

Information Security. Department of Homeland Security Needs to Fully 
Implement Its Security Program. GAO-05-700. Washington, D.C.: June 17, 
2005. 

Information Technology. Customs Automated Commercial Environment 
Program Progressing, but Need for Management Improvements Continues. 
GAO-05-267. Washington, D.C.: March 14, 2005. 

Homeland Security: Some Progress Made, but Many Challenges Remain on 
U.S. Visitor and Immigrant Status Indicator Technology Program. GAO-05- 
202. Washington, D.C.: February 23, 2005. 

Border Security. State Department Rollout of Biometric Visas on 
Schedule, but Guidance Is Lagging. GAO-04-1001. Washington, D. C.: 
September 9, 2004. 

Border Security. Joint, Coordinated Actions by State and DHS Needed to 
Guide Biometric Visas and Related Programs. GAO-04-1080T. Washington, 
D.C.: September 9, 2004. 

Homeland Security: First Phase of Visitor and Immigration Status 
Program Operating, but Improvements Needed. GAO-04-586. Washington, 
D.C.: May 11, 2004. 

Homeland Security: Risks Facing Key Border and Transportation Security 
Program Need to Be Addressed. GAO-04-569T. Washington, D.C.: March 18, 
2004. 

Homeland Security: Risks Facing Key Border and Transportation Security 
Program Need to Be Addressed. GAO-03-1083. Washington, D.C.: September 
19, 2003. 

Information Technology. Homeland Security Needs to Improve Entry Exit 
System Expenditure Planning. GAO-03-563. Washington, D.C.: June 9, 
2003. 

Attachment 3: 

Detailed Description of US-VISIT Program: 

The US-VISIT program consists of nine organizations and uses contractor 
support services in several areas. The roles and responsibilities of 
each of the nine organizations include the following: 

Chief Strategist is responsible for developing and maintaining the 
strategic vision and related documentation, transition plan, and 
business case. 

Budget and Financial Management is responsible for establishing the 
program's cost estimates; analysis; and expenditure management 
policies, processes, and procedures that are required to implement and 
support the program by ensuring proper fiscal planning and execution of 
the budget and expenditures. 

Mission Operations Management is responsible for developing business 
and operational requirements based on strategic direction provided by 
the Chief Strategist. 

Outreach Management is responsible for enhancing awareness of the US- 
VISIT requirements among foreign nationals, key domestic audiences, and 
internal stakeholders by coordinating outreach to media, third parties, 
key influencers, Members of Congress, and the traveling public. 

Information Technology Management is responsible for developing 
technical requirements based on strategic direction provided by the 
Chief Strategist and business requirements developed by Mission 
Operations Management. 

Implementation Management is responsible for developing accurate, 
measurable schedules and cost estimates for the delivery of mission 
systems and capabilities. 

Acquisition and Program Management is responsible for establishing and 
managing the execution of program acquisition and management policies, 
plans, processes, and procedures. 

Administration and Training is responsible for developing and 
administering a human capital plan that includes recruiting, hiring, 
training, and retaining a diverse workforce with the competencies 
necessary to accomplish the mission. 

Facilities and Engineering Management is responsible for establishing 
facilities and environmental policies, procedures, processes, and 
guidance required to implement and support the program office. 

The program uses contractor support services in the following six 
subject matter areas: 

Facilities and Infrastructure - provides the infrastructure and 
facilities support necessary for current and anticipated future staff 
for task orders awarded under the prime contract. 

Program-Level Management-defines the activities required to support the 
prime contractor's program management office, including quality 
management, task order control, acquisition support, and integrated 
planning and scheduling. 

Program-Level Engineering - assures integration across incremental 
development of US-VISIT systems and maintains interoperability and 
performance goals. 

Data Management Support-analyzes data for errors and omissions, 
corrects data, reports changes to the appropriate system of record 
owners, and provides reports. 

Data Management and Governance - provides support in the implementation 
of data management architecture and transition and sequencing plans, 
conducts an assessment of the current data governance structure and 
provides a recommendation for the future data governance structure, 
including a data governance plan. 

Mission Operations Data Integrity Improvements - determines possible 
ways to automate some of the data feeds from legacy systems, making the 
data more reliable. 

Attachment 4: Detailed Description of Increments and Component Systems: 

Below is a discussion of the processes underlying each increment and 
the systems that provide information to US-VISIT. 

Increment 1 processes -Increment 1 includes the following five 
processes at air and sea ports of entry (POEs): pre-entry, entry, 
status management, exit, and analysis, which are depicted in the 
graphic below. 

[See PDF for image] 

Sources: GAO analysis of US-VISIT data, Nova Development Corp. 
(clipart). 

[End of figure] 

Pre-entry process: 

Pre-entry processing begins with initial petitions for visas, grants of 
visa status, or the issuance of travel documentation. When a foreign 
national applies for a visa at a U.S. consulate, biographic and 
biometric data are collected and shared with border management 
agencies. The biometric data (i.e., fingerprint scan of the right and 
left index fingers) are transmitted from the Department of State 
(State) to the Department of Homeland Security (DHS), where the 
fingerprints are run against the Automated Biometric Identification 
System (IDENT) to verify identity and to run a check against the 
biometric watch list. The results of the biometric check are 
transmitted back to State. A "hit" response prevents State's system 
from printing a visa for the applicant until the information is cleared 
by a consular officer. 

Pre-entry also includes transmission by commercial air and sea carriers 
of crew and passenger manifests before arriving in the United 
States.[Footnote 37] These manifests are transmitted through the 
Advance Passenger Information System (APIS). The APIS lists are run 
against the biographic lookout system and identify those arrivals who 
have biometric data available. 

In addition, POEs review the APIS list in order to identify foreign 
nationals who need to be scrutinized more closely. 

Entry process: 

When the foreign national arrives at a primary POE inspection booth, 
the inspector, using a document reader, scans the machine-readable 
travel documents. APIS returns any existing records on the foreign 
national to the US-VISIT workstation screen, including manifest data 
matches and biographic lookout hits. When a match is found in the 
manifest data, the foreign national's name is highlighted and outlined 
on the manifest data portion of the screen. 

Biographic information, such as name and date of birth, is displayed on 
the bottom half of the computer screen, as well as the photograph from 
State's Consular Consolidated Database. The inspector at the booth 
scans the foreign national's fingerprints (left and right index 
fingers) and takes a digital photograph. This information is forwarded 
to the IDENT database, where it is checked against stored fingerprints 
in the IDENT lookout database. 

If no prints are currently in IDENT, the foreign national is enrolled 
in US-VISIT (i.e., biographic and biometric data are entered). If the 
foreign national's fingerprints are already in IDENT, the system 
performs a match (a comparison of the fingerprint taken during the 
primary inspection to the one on file) to confirm that the person 
submitting the fingerprints is the person on file. If the system finds 
a mismatch of fingerprints or a watch list hit, the foreign national is 
sent to an inspection booth for further screening or processing. 

While the system is checking the fingerprints, the inspector questions 
the foreign national about the purpose of his or her travel and length 
of stay. The inspector adds the class of admission and duration of stay 
information into the Treasury Enforcement Communications Systems 
(TECS), and stamps the "admit until" date on the Form I-94. 

If the foreign national is ultimately determined to be inadmissible, 
the person is detained, lookouts are posted in the databases, and 
appropriate actions are taken. 

Within 2 hours after a flight lands and all passengers have been 
processed, TECS is to send the Arrival Departure Information System 
(ADIS) the records showing the class of admission and the "admit until" 
dates that were modified by the inspector. 

Status management process: 

The status management process manages the foreign national's temporary 
presence in the United States, including the adjudication of benefits 
applications and investigations into possible violations of immigration 
regulations. 

Commercial air and sea carriers transmit departure manifests 
electronically for each departing passenger. These manifests are 
transmitted through APIS and shared with ADIS. ADIS matches entry and 
exit manifest data to ensure that each record showing a foreign 
national entering the United States is matched with a record showing 
the foreign national exiting the United States. 

ADIS also provides the ability to run queries on foreign nationals who 
have entry information but no corresponding exit information. 

ADIS receives status information from the Computer Linked Application 
Information Management System and the Student and Exchange Visitor 
Information System on foreign nationals. 

Exit process: 

The exit process includes the carriers' electronic submission of 
departure manifest data to APIS. This biographic information is passed 
to ADIS, where it is matched against entry information. At the 14 POEs 
where the exit solution is being implemented, the departure is 
processed by one of three exit methods. Within each port, one or more 
of three exit methods may be used. 

The three alternatives are: 

enhanced kiosk: 

mobile device: 

validator: 

Enhanced kiosk: The traveler approaches a kiosk for departure 
processing. At the kiosk, the traveler, guided by a workstation 
attendant if needed, scans the machine-readable travel documents, 
provides electronic fingerprints, and has a digital photograph taken. 
An encoded receipt is printed to provide documentation of compliance 
with the exit process and to assist in compliance on the traveler's 
next attempted entry to the country. After the receipt prints, the 
traveler proceeds to his/her departure gate. At the conclusion of the 
transaction, the collected information is transmitted to IDENT. 

Mobile device: At the departure gate, and just before the traveler 
boards the departure craft, a workstation attendant scans the machine- 
readable travel documents, scans the traveler's fingerprints (right and 
left index fingers), and takes a digital photograph. A receipt is 
printed to provide documentation of compliance with the exit process 
and to assist in compliance on the traveler's next attempted entry into 
the country. The workstation attendant provides the receipt to the 
traveler, and the traveler then boards the departure craft. The device 
wirelessly transmits the captured data in real time to IDENT via the 
Transportation Security Administration's Data Operations Center. 

Validator: Using the enhanced kiosk, the traveler, guided by a 
workstation attendant if needed, scans the machine-readable travel 
documents, provides electronic fingerprints, and has a digital 
photograph taken. 

As with the enhanced kiosk, a receipt is printed to provide 
documentation of compliance with the exit process and to assist in 
compliance on the traveler's next attempted entry to the country. 
However, this receipt has biometrics (i.e., the traveler's fingerprints 
and photograph) embedded on the receipt. At the conclusion of the 
transaction, the collected information is transmitted to IDENT. 

The traveler presents his or her receipt to the workstation attendant 
at the gate or departure area, who scans the receipt using a mobile 
device. The traveler's identity is verified against the biometric data 
embedded on the receipt. Once the traveler's identity is verified, he 
or she is allowed to board the departure craft. The captured data are 
not transmitted in real time back to IDENT. Instead, the data collected 
on the mobile device are periodically uploaded through the kiosk to 
IDENT. 

Analysis: 

An ongoing analysis capability is to provide for the continuous 
screening against watch lists of individuals enrolled in US-VISIT for 
appropriate reporting and action. As more entry and exit information 
becomes available, it is to be used to analyze traffic volume and 
patterns as well as to perform risk assessments. The analysis is to be 
used to support resource and staffing projections across the POEs, 
strategic planning for integrated border management analysis performed 
by the intelligence community, and determination of travel use levels 
and expedited traveler programs. 

[See PDF for image] 

[End of figure] 

Increment 2B and Increment 3 processes -: 

Increments 2B and 3 deployed US-VISIT entry processing capabilities to 
land POEs. These two increments are similar to Increment 1 (air and sea 
POEs), with several noteworthy differences. 

No advance passenger information is available to the inspector before 
the traveler arrives for inspection. 

Travelers subject to US-VISIT are processed at secondary inspection, 
rather than at primary inspection. 

Inspectors' workstations use a single screen, which eliminates the need 
to switch between the TECS and IDENT screens. 

Form I-94 data are captured electronically. The form is populated by 
data obtained when the machine-readable zone of the travel document is 
swiped. If visa information about the traveler exists in the Datashare 
database,[Footnote 38] it is used to populate the form. Fields that 
cannot be populated electronically are manually entered. A copy of the 
completed form is printed and given to the traveler for use upon exit. 

No electronic exit information is captured. 

Increment 2C process -: 

Increment 2C enhances operating capabilities at land POEs through the 
use of Form I-94s, which contain radio frequency chips that are capable 
of being read automatically, passively, and remotely at land POEs 
during entry and exit. 

Increment 2C processes are being piloted at five land POEs in two proof 
of concept phases. 

In both phases of the pilot: 

* travelers receive Form 1-94s upon first entry, which contain radio 
frequency tags containing a unique number used to identify the tag with 
the person, known as an automated identification (a-I D); and: 

* on exit and later re-entries, radio frequency identification readers 
detect the tag passing through the POE in all vehicle and pedestrian 
lanes and record the event in the Automated Identification Management 
System (AIDMS), described below. 

In Phase 1: 

* Only in the pedestrian primary inspection lanes: 

- upon remote reading of the a-ID, a biographic watch list check is 
automatically performed and presented to the CBP officer and: 

- upon manual scan of the a-ID, the biographic data, photograph, and 
information regarding the status of a-ID is presented to the CBP 
officer. 

In Phase 2: 

* In the pedestrian primary inspection lanes: 

- in addition to capabilities of Phase 1, upon manual scan of the a-ID, 
the CBP officer will receive additional information regarding the 
traveler's admissibility. 

* In the vehicle primary inspection lanes, upon remote reading of the a-
ID, the system will automatically: 

- perform a biographic watch list check and present the results to the 
CBP officer; 

- present biographic data, photograph, and information regarding the 
status of a-I D to the CBP officer; 

- present additional information regarding the traveler to the CBP 
officer regarding admissibility; and: 

- associate the traveler's data with the vehicle's license plate data. 

* Upon exit from either pedestrian or vehicle lanes: 

- upon remote reading of the a-ID, a real-time biographic watch list 
query, including biometric watch list status, will be automatically 
performed. 

Component systems: 

US-VISIT Increments 1 through 3 include the interfacing and integration 
of existing systems and, with Increment 2C, the creation of a new 
system. The three main existing systems are as follows: 

Arrival Departure Information System (ADIS) stores: 

* noncitizen traveler arrival and departure data received from air and 
sea carrier manifests, 

* arrival data captured by CBP officers at air and sea POEs, 

* Form I-94 issuance data captured by CBP officers at Increment 2B land 
POEs, 

* departure information captured at US-VISIT biometric departure pilot 
(air and sea) locations, 

* pedestrian arrival information and pedestrian and vehicle departure 
information captured at Increment 2C POE locations, and: 

* status update information provided by the Student and Exchange 
Visitor Information System (SEVIS) and the Computer Linked Application 
Information Management System (CLAIMS 3) (described below). 

ADIS provides record matching, query, and reporting functions. 

The passenger processing component of the Treasury Enforcement 
Communications Systems (TECS) includes two systems: 

* Advance Passenger Information System (APIS) captures arrival and 
departure manifest information provided by air and sea carriers, and: 

* Interagency Border Inspection System (IBIS) maintains lookout data 
and interfaces with other agencies' databases. 

CBP officers use these data as part of the admission process. The 
results of the admission decision are recorded in TECS and ADIS. 

The Automated Biometric Identification System (IDENT) collects and 
stores biometric data on foreign visitors, including data such as: 

* Federal Bureau of Investigation information[Footnote 39] on all known 
and suspected terrorists, selected wanted persons (foreign-born, 
unknown place of birth, previously arrested by DHS), and previous 
criminal histories for high-risk countries; 

* DHS Immigration and Customs Enforcement information on deported 
felons and sexual registrants; and: 

* DHS information on previous criminal histories and previous IDENT 
enrollments. 

The new system developed for Increment 2C, the Automated Identification 
Management System, is a collection of systems that manages data 
collected through the automatic scan of radio frequency chips in the 
Form I-94s through antennas and readers installed at the five land POEs 
included in the pilot. 

It maintains four categories of records: 

Traveler identification information such as the traveler's unique radio 
frequency identification number and data received from TECS such as the 
traveler's complete name, date of birth, and travel document type, 
number, date and country of issuance. 

Radio frequency identification tag related information such as the tag 
number and status (e.g. active, returned, seized, lost, stolen, 
damaged, etc.) 

Tag read event information such as the date, time and location of a 
read event and the direction of the border crossing (entry or exit). 

Border crossing history, which consists of the composition of 
information from the other three categories of information into a 
border crossing event that is communicated to other DHS systems such as 
TECS and ADIS. 

US-VISIT also exchanges biographic information with other DHS systems, 
including SEVIS and CLAIMS 3: 

SEVIS is a system that contains information on foreign students and: 

CLAIMS 3 is a system that contains information on foreign nationals who 
request benefits, such as change of status or extension of stay. 

Some of the systems involved in US-VISIT, such as IDENT and AIDMS, are 
managed by the program office, while some systems are managed by other 
organizational entities within DHS. For example: 

TECS is managed by CBP, 

SEVIS is managed by Immigration and Customs Enforcement, 

CLAIMS 3 is under United States Citizenship and Immigration Services, 
and: 

ADIS is jointly managed by CBP and US-VISIT. 

US-VISIT also interfaces with other, non-DHS systems for relevant 
purposes, including watch list[Footnote 40] (i.e. lookout) updates and 
checks to determine whether a visa applicant has previously applied for 
a visa or currently has a valid U.S. visa. In particular, US-VISIT 
receives biographic and biometric information from State's Consular 
Consolidated Database as part of the visa application process, and 
returns fingerscan information and watch list changes. 

[End of section] 

Appendix II: Comments from the Department of Homeland Security: 

U.S. Department of Homeland Security: 
Washington, DC 20528: 

January 19, 2007: 

Mr. Randolph C. Hite: 
Director: 
Information Technology Architecture and Systems Issues: 
U.S. Government Accountability Office: 
441 G Street, NW: 
Washington, D.C. 20548: 

Dear Mr. Hite: 

Thank you for the opportunity to review the draft report entitled 
Homeland Security: Planned Expenditures for U.S Visitor and Immigrant 
Status Program Need to Be Adequately Defined and Justified (GAO-07- 
278). As with prior reports that your office has issued regarding US- 
VISIT, there are many areas with which we agree, and the 
recommendations have made US-VISIT a stronger program. We concur with 
the report recommendations and the need for improvement. Overall, the 
report's findings will help US-VISIT to continue making its already 
highly successful and valuable contributions to the enhanced security. 
of the United States. We believe, however, that some of GAO's 
statements regarding US-VISIT's Fiscal Year 2006 Expenditure Plan need 
to be modified or otherwise clarified. 

In the draft report addressed to the Committees on Appropriations, GAO 
in discussing its first observation (page 5) states that, 
"Notwithstanding these issues, the fiscal year 2006 expenditure plan 
proposes investing another $33.5 million to continue air and sea exit 
pilots and allocates carryover of $21.5 million in fiscal year 2005 
funds for land exit demonstration activities, without adequately 
justifying continuing these investments. " The $33.5 million in funding 
for air and sea exit pilot operations was initially requested to 
support the current operations while expanding to additional locations. 
The GAO report outlines the $33.5 million as an investment, but it is 
more accurately depicted as continuing operations, as well as an 
investment. Currently, the Department of Homeland Security (DHS) has 
determined that portions of the funding will support current pilot 
operations, while exploring a more comprehensive exit strategy. It 
should be noted that we are not carrying over $21.5 million from FY 
2005 funds for use on Increment 2C (RFID). We are using a small portion 
of these funds ($1.2 million) for 2C shutdown and closeout, while the 
remaining funds will be considered for reprogramming. 

In discussing the third observation (pages 5-6), GAO states that, "DHS 
has not adequately justified increases in, and disclosed the scope and 
nature of, program management-related fiscal year 2006 expenditures. US-
VISIT's planned investment in program management-related activities has 
risen steadily over the last 4 years, while planned investment in the 
development of new program capabilities has similarly declined . The 
expenditure plan does not explain the reasons for this recent growth or 
otherwise justify the sizeable proposed investment in program 
management and operations on the basis of measurable expected value. " 
US-VISIT officials understand and share the concerns about the 
appearance of growth in program management and contract support costs, 
and regret that the initial Fiscal Year 2006 Expenditure Plan 
submission lacked sufficient detail and clarity. A revised plan signed 
by the Secretary of the Department of Homeland Security was submitted 
on January 16, 2007 to the Committees on Appropriations to show how the 
cost growth is more accurately attributed to operations, program and 
project activities directly related to implementation of homeland 
security measures. 

In Attachment I, Briefing to the Staffs of the Subcommittees on 
Homeland Security, Committee on Appropriations, page 22 (Background - 
Description and Status of Increments), GAO states that, "The proof-of- 
concept was initiated in August 2005, and initial results were reported 
in January 2006 These results showed that there were problems that 
would affect the ability to implement an RFID land border solution. 
This was subsequently termed Phase 1 and is still ongoing, using $21.5 
million in funds carried over from fiscal year 2005." Termination of 
the Increment 2C pilot (RFID) began in November 2006. 

GAO states in Attachment 1, page 74 (Objective 3: Observations, Exit 
Definition and Justification) that "Further, while the plan and other 
exit-related documentation do not allocate any current funding to the 
land exit demonstration projects using RFID, they allocate carryover 
from fiscal year 2005 of $21.5 million to continue this effort. " As 
previously noted, US-VISIT officials will not carry over $21.5 million 
from Fiscal Year 2005 funds for use on RFID (2C). US-VISIT officials 
will use $1.2 million of the $21.5 million FY 2005 carryover funds for 
2C shutdown and closeout, while the remaining funds will be considered 
for reprogramming. 

Sincerely, 

Signed by: 

Steven J. Pecinovsky: 
Director, Departmental GAO/OIG Liaison Office: 

[End of section] 

Appendix III: GAO Contact and Staff Acknowledgments: 

GAO Contact: 

Randolph C. Hite, (202) 512-3439: 

Staff Acknowledgments: 

In addition to the individual named above, Tonia Johnson (Assistant 
Director), Eric Costello, Deborah Davis, Neil Doherty, Nancy Glover, 
David Hinchman, Jamelyn Payan, Scott Pettis, and Daniel Wexler made key 
contributions to this report. 

(310633): 

FOOTNOTES 

[1] Pub. L. No. 109-90 (Oct. 18, 2005). 

[2] Immigration and Naturalization Service Data Management Improvement 
Act of 2000, Pub. L. No. 106-215, 114 Stat. 337, codified at 8 U.S.C. § 
1365a(b). 

[3] The operational context defines, among other things, applicable 
policies, rules, standards, and related initiatives. It also provides a 
common frame of reference to guide and constrain both US-VISIT and 
other border security and immigration enforcement initiatives. 

[4] GAO, Homeland Security: Efforts Under Way to Develop Enterprise 
Architecture, but Much Work Remains, GAO-04-777 (Washington, D.C.: Aug. 
6, 2004). 

[5]Pub. L.109-90 (Oct. 18, 2005). 

[6] The appropriated amount was subsequently reduced to $336.6 million 
by a governmentwide 1 percent rescission, Pub. L. 109-148 (Dec. 30, 
2005), and OMB instructed US-VISIT to reduce the amount that could not 
be obligated to $158,060,000. 

[7] 0 MB Circular A-11 establishes policy for planning, budgeting, 
acquisition, and management of federal capital assets. 

[8] Our reports on US-VISIT expenditure plans have resulted in 24 
recommendations, six of which pertain to the US-VISIT expenditure plan 
and 18 of which pertain to the US-VISIT program. Earlier this year, we 
reported on the status of the 18 recommendations pertaining to the US- 
VISIT program. See GAO-06-296, Homeland Security. Recommendations to 
Improve Management of Key Border Security Program Need to Be 
Implemented, (Washington, D.C.: Feb. 14, 2006). For a full list of US- 
VISIT related GAO reports, see attachment 2. 

[9] See attachment 3 for more details. 

[10] An indefinite-delivery/indefinite-quantity contract provides for 
an indefinite quantity, within stated limits, of supplies or services 
during a fixed period of time. The government schedules deliveries or 
performance by placing orders with the contractor. 

[11] Accenture's partners include, among others, Raytheon Company, the 
Titan Corporation, and SRA International, Inc. 

[12] On September 30, 2004, US-VISIT expanded biometric entry 
procedures to include individuals from visa waiver countries applying 
for admission. 

[13] Workstation attendants also assist travelers in using the kiosk. 

[14] Legislation requiring the installation of software and equipment 
at POEs to authenticate machine-readable visas and travel documents 
established a deadline of October 26, 2004 (Pub. L. 107-173, (May 14, 
2002)), but this date was subsequently changed (Pub. L. 108-299 (Aug.9, 
2004)). 

[15] Legislation requiring Visa Waiver Program countries to issue e- 
Passports originally established a deadline of October 26, 2004 (Pub. 
L. 107-173, (May 14, 2002)), but this date was subsequently changed 
(Pub. L. 108-299 (Aug. 9, 2004)). Subsequently, DHS and State obtained 
an agreement with the appropriate congressional committee to change 
this date to October 26, 2006. 

[16] Form I-94s are used to record a foreign national's entry into the 
United States. The form has two parts-arrival and departure-containing 
a unique number for the purposes of recording and matching the arrival 
and departure records of nonimmigrants. 

[17] For example, diplomats and persons under the age of 14 or over the 
age of 79 are exempt from US-VISIT requirements. 

[18] Radio frequency technology relies on proximity cards and card 
readers. Radio frequency devices read the information contained on the 
card when the card is passed near the device. The information can 
contain personal identification of the cardholder. 

[19] At one POE, these capabilities were deployed by December 19, 2005, 
but were not fully operational until January 7, 2006, because of a 
telephone company strike that prevented the installation of a T-1 line. 

[20] For details on the processes underlying each increment and systems 
supplying information to US-VISIT, see attachment 4. 

[21] For details on the processes underlying each increment and systems 
supplying information to US-VISIT, see attachment 4. 

[22] In fiscal year 2003, the approved expenditure plan was for $375 
million, but the appropriated amount was for $362 million. The 
difference of $13 million was to have been made up through user fees 
from Immigration and Customs Enforcement. However, only $5 million in 
user fees was provided to the US-VISIT program, for a total of $367 
million. 

[23] Provided that the program office resubmit documentation upon 
approval of the US-VISIT strategic plan, which, at that time, was 
anticipated to be in January 2005. 

[24] GAO, Homeland Security. Some Progress Made, but Many Challenges 
Remain on U.S. Visitor and Immigrant Status Indicator Technology 
Program, GAO-05-202 (Washington, D.C.: Feb. 23, 2005). 

[25] See, for example, the Clinger-Cohen Act of 1996 (P.L. 104-106), 
OMB Circular A-130, and the Federal Acquisition Regulation. 

[26] GAO, Homeland Security. Risks Facing Border and Transportation 
Security Program Need to be Addressed, GAO-03-1083 (Washington D.C.: 
Sept. 19, 2003). 

[27] The CMMI® ranks organizational maturity according to five levels. 
Maturity levels 2 through 5 require verifiable existence and use of 
certain key process areas. 

[28] GAO, Homeland Security. Contract Management and Oversight for 
Visitor and Immigrant Status Program Need to Be Strengthened, GAO-06- 
404 (Washington, D.C.: June 9, 2006). 

[29] Financial controls are practices to provide accurate, reliable, 
and timely accounting for billings and expenditures. 

[30] The appropriated amount was subsequently reduced to $336.6 million 
by a governmentwide 1 percent rescission. Pub. L. 109-90 (Oct. 18, 
2005) and Pub. L. 109-148 (Dec. 30, 2005). 

[31] GAO-06-404, June 9, 2006. 

[32] GAO-05-202. 

[33] Immigration and Naturalization Service Data Management Improvement 
Act of 2000, P.L. 106-215, 114 Stat. 337, codified at 8 U.S.C. § 
1365a(b); Intelligence Reform and Terrorism Prevention Act of 2004, 
P.L. 108-458, codified at 8 U.S.C § 1365b(d). 

[34] GAO-03-1083. 

[35] GAO, Homeland Security. Efforts Under Way to Develop Enterprise 
Architecture, but Much Work Remains, GAO-04-777 (Washington, D.C.: Aug. 
6, 2004): 

[36] pub. L. No. 108-458, § 7209, 118 Stat. 3638, 3823 (2004). 

[37] Pub. L. 107-173 (May 14, 2002). 

[38] Datashare includes a data extract from State's Consular 
Consolidated Database system and includes the visa photograph, 
biographical data, and the fingerprint identification number assigned 
when a nonimmigrant applies for a visa. 

[39] Information from the Federal Bureau of Investigation includes 
fingerprints from the Integrated Automated Fingerprint Identification 
System. 

[40] Watch list data sources include DHS's Customs and Border 
Protection and Immigration and Customs Enforcement; the Federal Bureau 
of Investigation; legacy DHS systems; the U.S. Secret Service; the U.S. 
Coast Guard; the Internal Revenue Service; the Drug Enforcement Agency; 
the Bureau of Alcohol, Tobacco, & Firearms; the U.S. Marshals Service; 
the U.S. Office of Foreign Asset Control; the National Guard; the 
Treasury Inspector General; the U.S. Department of Agriculture; the 
Department of Defense Inspector General; the Royal Canadian Mounted 
Police; the U.S. State Department; Interpol; the Food and Drug 
Administration; the Financial Crimes Enforcement Network; the Bureau of 
Engraving and Printing; and the Department of Justice Office of Special 
Investigations. 

GAO's Mission: 

The Government Accountability Office, the investigative arm of 
Congress, exists to support Congress in meeting its constitutional 
responsibilities and to help improve the performance and accountability 
of the federal government for the American people. GAO examines the use 
of public funds; evaluates federal programs and policies; and provides 
analyses, recommendations, and other assistance to help Congress make 
informed oversight, policy, and funding decisions. GAO's commitment to 
good government is reflected in its core values of accountability, 
integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through the Internet. GAO's Web site ( www.gao.gov ) contains 
abstracts and full-text files of current reports and testimony and an 
expanding archive of older products. The Web site features a search 
engine to help you locate documents using key words and phrases. You 
can print these documents in their entirety, including charts and other 
graphics. 

Each day, GAO issues a list of newly released reports, testimony, and 
correspondence. GAO posts this list, known as "Today's Reports," on its 
Web site daily. The list contains links to the full-text document 
files. To have GAO e-mail this list to you every afternoon, go to 
www.gao.gov and select "Subscribe to e-mail alerts" under the "Order 
GAO Products" heading. 

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. Government Accountability Office 

441 G Street NW, Room LM 

Washington, D.C. 20548: 

To order by Phone: 

Voice: (202) 512-6000: 

TDD: (202) 512-2537: 

Fax: (202) 512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: www.gao.gov/fraudnet/fraudnet.htm 

E-mail: fraudnet@gao.gov 

Automated answering system: (800) 424-5454 or (202) 512-7470: 

Public Affairs: 

Jeff Nelligan, managing director, 

NelliganJ@gao.gov 

(202) 512-4800 

U.S. Government Accountability Office, 

441 G Street NW, Room 7149 

Washington, D.C. 20548: